Article 1 (Purpose) The purpose of this ruleis to prescribe matters delegated by the National Heritage Impact Assessment Act and the Enforcement Decree of the same Act , as well as matters necessary for the implementation thereof.
Article 2 (Request for Prior Impact Consultation) ① In Article 3, Paragraph 1 of the Enforcement Decree of the National Heritage Impact Assessment Act (hereinafter referred to as the “Decree”), the term “request for prior impact consultation prescribed by the Ordinance of the Ministry of Culture, Sports and Tourism” refers to the request for prior impact consultation in Form No. 1 of the attached document.
② In Article 3 , Paragraph 1 of the Enforcement Decree, “documents prescribed by the Ordinance of the Ministry of Culture, Sports and Tourism” refers to the documents in each of the following subparagraphs.
1. Development Plan (Draft)
2. Internal Review Form for Prior Impact Consultation (Attachment No. 2)
Article 3 (Timing of Impact Assessment) The specific timing for the implementation of the impact assessment pursuant to Article 9, Paragraph 1 of the National Heritage Impact Assessment Act (hereinafter referred to as the “Act”) is as set forth in Attached Table 1 .
Article 4 (Method and Procedure for Impact Assessment) ①In accordance with Article 10, Paragraph 1 of the Act , the impact assessment performed by the National Heritage Impact Assessment Agency under Article 20 of the Act (hereinafter referred to as the “Assessment Agency”) shall be carried out according to the classifications in each of the following subparagraphs.
1. Construction work falling under Article 9, Paragraph 1 , Subparagraph 1 or 3 of the Act : Surface survey to confirm whether buried heritage is distributed in the area of the relevant construction work (hereinafter referred to as “surface survey”)
2. Construction work carried out in a buried heritage preservation area pursuant to Article 9 , Paragraph 1, Subparagraph 2 of the Act , or construction work carried out in an area where buried heritage is judged to be distributed based on the results of a surface survey pursuant to Subparagraph 1 of this Paragraph: an evaluation of which of the following conservation measures is necessary in relation to the said construction work (hereinafter referred to as “Preservation Area Evaluation”)
a. Preservation in Status: Preserving all or part of buried heritage in its current state on-site.
B. Observation Survey: An expert related to buried heritage [in the case of a person under Paragraph 3, Subparagraph 1, limited to cases where the head of a buried heritage investigation agency pursuant to Article 24 of the Act on the Protection and Investigation of Buried Heritage (hereinafter referred to as the “Buried Heritage Investigation Agency”) has consented] confirming at the site whether buried heritage has been unearthed and whether excavation work can proceed following such unearthment when excavation work is carried out during the construction period.
C. Excavation: Any of the following
1) Detailed Excavation Survey: An excavation survey conducted by obtaining an excavation permit pursuant to the proviso of Article 11, Paragraph 1 of the Act on the Protection and Investigation of Buried Heritage, covering the entire area within the construction site that is a buried heritage preservation area or an area where buried heritage is judged to be distributed based on surface survey results (hereinafter referred to as “Buried Heritage Preservation Area, etc.” in this paragraph ) .
2) Trial Excavation: An excavation survey conducted within a scope of 10 percent or less of the area containing buried heritage, etc., within the construction site, after obtaining an excavation permit pursuant to the proviso of Article 11, Paragraph 1 of the Act on the Protection and Investigation of Buried Heritage.
3) Sample Survey: To determine whether to conduct a detailed excavation or an exploratory excavation, a sample survey of the types and distribution of buried heritage is conducted within a scope of no more than 2 percent of the area containing buried heritage within the construction site.
3. Construction projects subject to impact assessment under Article 9 , Paragraph 1 of the Act , carried out in the historical and cultural environment preservation area of a National Designated Heritage: Review of the following matters in relation to the said construction project (hereinafter referred to as “Impact Review”)
a. Matters concerning whether the relevant construction work exceeds the scope of specific conduct standards notified pursuant to Article 13, Paragraph 5 of the Act on the Preservation and Utilization of Cultural Heritage or Article 10, Paragraph 4 of the Act on the Preservation and Utilization of Natural Heritage (hereinafter referred to as “conduct standards”)
B. Matters concerning whether the implementation of the relevant construction work constitutes an act that is likely to affect the preservation of the National Designated Heritage.
C. Matters concerning measures to eliminate or mitigate the impact in cases where the execution of the relevant construction work is an act that is likely to affect the preservation of a National Designated Heritage.
② Notwithstanding Paragraph 1, Subparagraphs 1 and 2, if the implementing entity of a construction project proves that the project falls under any of the following subparagraphs, it shall be deemed that a surface survey and an assessment of the preserved area have been conducted.
1. Construction work carried out in an area where geological strata containing artifacts or remains have already been damaged due to cutting or excavation.
2. Construction work carried out in areas where reclamation of public waters, dredging of rivers or seabeds, or extraction of aggregates and minerals has already taken place.
3. Construction work carried out in reclaimed areas to the extent that the topography prior to reclamation is not damaged.
4. Planting, felling, or thinning of trees and bamboo carried out in existing forest areas
③ The evaluation of a heritage site shall be conducted by obtaining the opinions of at least two experts in buried heritage affiliated with different institutions, among those who have obtained a degree related to the excavation and investigation of buried heritage and fall under any of the following subparagraphs.
1. Persons currently serving as a survey team leader, principal investigator, or investigator at a buried heritage survey institution
2. Faculty members currently or formerly employed as assistant professors or higher at schools pursuant to Article 2 of the Higher Education Act
3. Research curators or curators currently employed at the institutions listed in each of the following subparagraphs
a. National museums or public museums pursuant to Article 3, Paragraph 1 , Subparagraph 1 or 2 of the Museum and Art Gallery Promotion Act
B. National Institute of Cultural Heritage or National Maritime Heritage Research
C. Science museums pursuant to Article 2, Subparagraph 1 of the Act on the Establishment, Operation, and Promotion of Science Museums
4. A member of the committee or an expert member falling under any of the following subparagraphs
a. Cultural Heritage Committee or City/Provincial Cultural Heritage Committee pursuant to Article 8 or Article 71 of the Act on the Preservation and Utilization of Cultural Heritage
B. Natural Heritage Committee or City/Provincial Natural Heritage Committee pursuant to Article 7-2 or Article 41-2 of the Act on the Preservation and Utilization of Natural Heritage
④ If construction work carried out in a preservation area for the historical and cultural environment of a nationally designated heritage exceeds the scope of the activity standards, the opinions of at least three experts related to the historical and cultural environment belonging to different institutions who fall under any of the following subparagraphs must be heard (the number of persons falling under subparagraph 2 shall not exceed one, and at least one person falling under subparagraph 3 must be included). In this case, the experts related to the historical and cultural environment must be persons not affiliated with the institution carrying out the construction work.
1. Faculty members holding the rank of Assistant Professor or higher in departments related to national heritage at schools pursuant to Article 2 of the Higher Education Act
2. Research curators, research fellows, or professional career officers of Group Na or higher responsible for national heritage affairs
3. Persons falling under Paragraph 3, Subparagraph 4
⑤ In addition to the matters specified in paragraphs 1 through 4, necessary matters concerning the methods and procedures for impact assessment, etc. shall be determined and announced by the Administrator of the National Heritage Administration .
Article 5 (Preparation of Diagnosis Report) ① A diagnosis institution shall prepare a report on the results of the impact diagnosis pursuant to Article 11, Paragraph 1 of the Act (hereinafter referred to as the “diagnosis report”) in accordance with the classifications in each of the following subparagraphs.
1. Cases where an indicator survey was conducted
A. Contents of the literature review on the history, archaeology, folklore, geology, and natural environment of the region
B. Details of the field survey regarding artifact sites, archaeological remains, folklore, ancient buildings (including modern buildings), geology, and the natural environment of the relevant area
C. Existence of buried heritage and the negative impact of the construction project on the buried heritage
D. Opinion of the diagnostic institution
2. Cases where a heritage area assessment has been conducted
A. Maps and Areas of Buried Heritage Preservation Zones, etc.
B. Preservation measures pursuant to each item of Article 4, Paragraph 1, Subparagraph 2
C. Negative impact of the relevant construction work on buried heritage and measures for removal and mitigation thereof
D. Opinion of the diagnostic institution
3. Cases where an impact review has been conducted
a. In cases where the relevant construction work exceeds the scope of the activity standards, the expert review opinion regarding the historical and cultural environment ( Form No. 3)
B. Negative impact of the relevant construction work on the historical and cultural environment of the National Designated Heritage and measures for its removal and mitigation
C. Opinion of the diagnostic institution
4. Cases where surface surveys and preservation area assessments are deemed to have been conducted
a. Any of the reasons falling under any of the subparagraphs of Article 4, Paragraph 2
B. Opinion of the diagnostic institution
② The following documents must be attached to the diagnostic report:
1. Location map of the planned project area with a scale of 1:10,000 or larger
2. Construction work plan (including materials that allow identification of changes in topography and the ground, such as excavation and construction)
3. In the case of Paragraph 1, Subparagraph 4, materials capable of proving a reason falling under any of the subparagraphs of Article 4, Paragraph 2
③ In addition to the matters prescribed in Paragraphs 1 and 2, matters necessary for the preparation of the diagnostic report shall be determined and announced by the Administrator of the National Heritage Administration .
Article 6 (Submission of Diagnosis Report, etc.) ① The implementing entity of a construction project that has conducted an impact diagnosis shall,in accordance with Article 11, Paragraph 1 of the Act , submit the diagnosis report attached to the report of completion of impact diagnosis in Form No. 4 of the attached document to the mayor of a special self-governing city, governor of a special self-governing province, mayor, county head, or district head having jurisdiction over the area (the district head refers to the head of a self-governing district, hereinafter referred to as “mayor, county head, or district head”) and the head of the National Heritage Administration within 30 days from the date the impact diagnosis is completed.
② The Administrator of the National Heritage Administration may disclose the diagnostic report and attached documents with the consent of the person holding the rights to the work.
Article 7 (Review of the Appropriateness of a Diagnostic Report) ① When the Administrator of the National Heritage Administration or the Mayor of a Special City, Metropolitan City, Special Self-Governing City, or Governor of a Province or Special Self-Governing Province (hereinafter referred to as “Mayor or Governor”) reviews the appropriateness of a diagnostic report pursuant to Article 11, Paragraph 3 of the Act , they shall consider the following matters:
1. Appropriateness of the impact assessment method
2. Whether there is a negative impact on the preservation of buried heritage or nationally designated heritage.
3. Validity of preservation measures for buried heritage or protection plans for the historical and cultural environment of nationally designated heritage
4. Other matters related to the preservation of buried heritage or nationally designated heritage that the Administrator of the National Heritage Administration deems necessary and announces through public notice.
② The Administrator of the National Heritage Administration may hear the opinions of the mayor, county governor, or district head having jurisdiction over the relevant area regarding the diagnosis report if necessary to review the appropriateness of the diagnosis report pursuant to Article 11, Paragraph 3 of the Act.
Article 8 (Notification of Review Results of Diagnostic Report) When the Administrator of the National Heritage Administration or the Mayor or Provincial Governor notifies the review results of a diagnostic report pursuant to Article 13, Paragraph 1 of the Act , they shall do so in accordance with the classifications in each of the following subparagraphs.
1. In cases where, as a result of reviewing the appropriateness of the diagnostic report pursuant to Article 11, Paragraph 3 of the Act , there is no concern that the relevant construction work will affect the preservation of buried heritage or nationally designated heritage: No impact
2. In cases where, as a result of reviewing the appropriateness of the diagnostic report pursuant to Article 11, Paragraph 3 of the Act , there is a concern that the relevant construction work may affect the preservation of buried heritage or nationally designated heritage: implement the following matters
a. Implementation of the measures listed in the relevant diagnostic report as necessary for the preservation of buried heritage among the preservation measures under each item of Article 4, Paragraph 1, Subparagraph 2, based on the results of the preservation area assessment (limited to cases where a preservation area assessment has been conducted)
B. Implementation of measures listed in the relevant diagnostic report as necessary to eliminate or mitigate negative impacts on the preservation of buried heritage or nationally designated heritage.
Article 9 (Implementation of Review Results of Diagnostic Report) An implementing entity of a construction project that has been notified of the review results pursuant to Article 8, subparagraph 2 shall report the results of such implementation to the Mayor, County Governor, District Head, and the Administrator of the National Heritage Administration in accordance with the classifications in each of the following subparagraphs pursuant to Article 13, paragraph 2 of the Act.
1. In the case where the matters under Article 8, Subparagraph 2, Item (a) have been fulfilled
A. Preservation in Status: Submit the following documents attached to the Report on Results of Buried Heritage Preservation Measures (Preservation in Status) ( Form No. 5 ).
1) Survey results
2) Photos of the preservation measures site
3) Future Management Plan
B. On-site Inspection: Submit the following documents attached to the Report on Results of Buried Heritage Preservation Measures (On-site Inspection) ( Form No. 6 ).
1) Location map of the observation survey area
2) Panoramic photo of the observation site
3) Photo of the observation survey scene
C. Excavation: Submit the following documents attached to the Report on Results of Buried Heritage Preservation Measures (Excavation) in Annex 7 .
1) Status of excavation survey (including survey overview, progress, and status of remains and artifacts)
2) List and photos of excavated buried heritage
2. In cases where the matters under Article 8, Subparagraph 2, Item ( b) have been implemented: Submit a revised construction plan (referring to a plan that confirms that the impact on the preservation of buried heritage or nationally designated heritage has been eliminated or reduced).
Article 10 (Inspection of Implementation and Measures) ① Pursuant to Article 16, Paragraph 1 of the Act , the Administrator of the National Heritage Administration, the Governor of a City or Province, or the Mayor, County Head, or District Head shall inspect whether the implementing entity of a construction project, having been notified of the results of the review pursuant to Article 8, Subparagraph 2 of this Rule, has implemented the matters listed in each subparagraph of the same subparagraph.
② In principle, the inspection of compliance matters pursuant to Article 16, Paragraph 1 of the Act shall be completed within 14 days from the date the results of compliance are received pursuant to Article 9 of this Rule. In this case, Saturdays, Sundays, public holidays under Article 2 of the Act on Public Holidays , and substitute public holidays under Article 3 of the same Act shall not be included in the period.
③ The Administrator of the National Heritage Administration may conduct an inspection of implementation matters pursuant to Article 16, Paragraph 1 of the Act by entrusting it to an agency or relevant expert pursuant to the latter part of Article 11, Paragraph 3 of the Act .
④ The order for measures pursuant to Article 16, Paragraph 2 of the Act shall be in accordance with the order for restoration, etc. in Form No. 8 of the Attached Form .
Article 11 (Subjects of Simplified Impact Assessment) The subjects of the simplified impact assessment pursuant to Article 17, Paragraph 1 of the Act are as follows:
1. Construction work carried out in a preservation area for the historical and cultural environment of a nationally designated heritage site for which an impact assessment pursuant to Article 9 of the Act has not been conducted.
2. Construction work carried out in a historical and cultural environment preservation area for municipal or provincial designated cultural heritage or cultural heritage materials pursuant to Article 2, Paragraph 3 , Subparagraph 2 or 3 of the Act on the Preservation and Utilization of Cultural Heritage
3. Construction work carried out in historical and cultural environment preservation areas for City/Provincial natural heritage or natural heritage materials pursuant to Article 2 , Subparagraph 4 or 4-2 of the Act on the Preservation and Utilization of Natural Heritage
Article 12 (Timing of Simplified Impact Assessment) The simplified impact assessment pursuant to Article 17, Paragraph 1 of the Act must be conducted before granting authorization, permission, etc. for the relevant construction work.
Article 13 (Methods and Procedures for Simplified Impact Assessment, etc.) ① When a Mayor, County Governor, or District Head conducts a simplified impact assessment, they must obtainthe opinions of at least three experts in the history and cultural environment who belong to different agencies and fall under any of the subparagraphs of Article 4 , Paragraph 4 (the number of persons falling under subparagraph 2 of Article 4 , Paragraph 4 shall not exceed one, and at least one person falling under subparagraph 3 of the same paragraph must be included). In this case, the experts in the history and cultural environment must be persons who are not affiliated with the agency carrying out the relevant construction work.
② Notwithstanding Paragraph 1, when a mayor, county governor, or district head reviews whether the implementation of a construction project falls under the acts specified in Subparagraph C or D of Paragraph 2, Item 1 of the Enforcement Decree of the Act on the Preservation and Utilization of Cultural Heritage or Subparagraph 3 or 4 of Paragraph 4 of the Act on the Preservation and Utilization of Natural Heritage, they must hear the opinions of at least three persons, including at least one member or expert member falling under Subparagraph 4 of Paragraph 3 of Article 4 and at least one expert in a relevant field falling under any of the following subparagraphs.
1. A person currently serving as an assistant professor or higher in a department related to the fields of architecture, civil engineering, environment, urban planning, noise, vibration, air pollution, chemical substances, dust, or heat at a school pursuant to Article 2 of the Higher Education Act.
2. A person recommended by an academic society in the field referred to in Item 1
3. Persons affiliated with a research institution in the field specified in Subparagraph 1 who are currently employed as a researcher or higher.
③ The expert review opinions pursuant to Paragraphs 1 and 2 shall be in accordance with the brief impact diagnosis review opinion form in Annex 9 .
Article 14 (Decision on Simplified Impact Assessment) If at least half of the experts whose opinions were heard pursuant to Article 13, Paragraph 1 or 2 determine that the implementation of the relevant construction work falls underArticle 35 , Paragraph 1, Subparagraph 2 of the Act on the Preservation and Utilization of Cultural Heritage (including cases where it is applied mutatis mutandis pursuant to Article 74 of the same Act ) and Article 17, Paragraph 1 , Subparagraph 4 of the Act on the Preservation and Utilization of Natural Heritage (including cases where it is applied mutatis mutandis pursuant to Article 42 of the same Act ), the Mayor, County Governor, or District Head shall, pursuant to Article 18, Paragraph 1 of the Act , determine that there is a risk that the implementation of the relevant construction workdesignated cultural heritage pursuant to Article 2, Paragraph 3 of the Act on the Preservation and Utilization of Cultural Heritage and natural monuments, etc. pursuant to Article 2, Subparagraph 5 of the Act on the Preservation and Utilization of Natural Heritage.
Article 15 (Submission of Details of Results of Summary Impact Assessment Decisions) Pursuant to Article 18, Paragraph 3 of the Act , the Mayor, County Governor, or District Headshall submit the details of the results of the summary impact assessment decisions for each half-year period within one month after the end of each half-year period, according to the classifications in each of the following subparagraphs.
1. Details of the Decision Results on the Simplified Impact Assessment for the Historical and Cultural Environment Preservation Areas of Nationally Designated Heritage: Submitted to the Administrator of the National Heritage Administration
2. Details of the results of the simplified impact assessment for historical and cultural environment preservation areas of designated heritage, excluding national heritage: Submitted to the Mayor/Provincial Governor
Article 16 (Designation Criteria and Procedures for Professional Training Institutions) ① The designation criteria for professional training institutions pursuant to Article 24, Paragraph 4 of the Act are as follows:
1. The curriculum and educational content for training specialized personnel related to impact assessment, etc., shall be appropriate.
2. Adequate educational facilities and equipment shall be maintained. In this case, if the right to use educational facilities is secured through a lease agreement or a joint use agreement, the said educational facilities shall be deemed to be provided during the contract period.
3. Secure at least one professional instructor and at least one dedicated manager.
4. The operating expense financing plan must be feasible.
② When deciding whether to designate an institution for training professional personnel pursuant to Article 13, Paragraph 1 of the Enforcement Decree, the Administrator of the National Heritage Administration may consider the performance record of projects related to the training and education of professional personnel related to impact diagnosis, etc.
③ In Article 13, Paragraph 2 of the Enforcement Decree, “application for designation prescribed by the Ordinance of the Ministry of Culture, Sports and Tourism” refers to the application for designation of a professional personnel training institution in Form No. 10 of the Attached Form.
④ In Article 13, Paragraph 2 of the Enforcement Decree, “documents prescribed by the Ordinance of the Ministry of Culture, Sports and Tourism” refers to the documents listed in each of the following subparagraphs.
1. Education plan including curriculum and educational content
2. Data on the current status of securing educational facilities and equipment (including the relevant contract if the right to use the educational facilities has been secured through a lease agreement or joint use agreement)
4. Data on the Status of Securing Professional Faculty and Dedicated Managers
5. Performance record of projects related to the training and education of specialized personnel for impact assessment, etc. (only applicable if performance record exists)
6. Operating Expense Financing Plan
⑤ The Administrator of the National Heritage Administration, upon receiving an application for designation pursuant to Article 13, Paragraph 2 of the Enforcement Decree, shall verify the Certificate of Corporate Registration if the applicant is a corporation, and the Certificate of Business Registration (referring to a Certificate of Business Registration excluding the resident registration number) if the applicant is not a corporation, through the joint use of administrative information pursuant to Article 36, Paragraph 1 of the Electronic Government Act. However, if the applicant does not consent to the verification of the Certificate of Business Registration, the applicant must be required to attach the relevant document.
⑥ In Article 13, Paragraph 3 of the Enforcement Decree, the term “designation certificate prescribed by the Ordinance of the Ministry of Culture, Sports and Tourism” refers to the designation certificate for professional personnel training institutions in Form No. 11 of the Appendix .
Article 17 (Criteria for Revocation of Designation and Suspension of Business, etc.) The criteria for the revocation of designation and suspension of business of professional personnel training institutions pursuant to Article 24, Paragraph 3 of the Act are as set forth in Attached Table 2 .
ADDENDA <Ministry of Culture, Sports and Tourism Decree No. 586, Mar. 7, 2025>
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of Culture, Sports and Tourism Decree No. 617, Oct. 31, 2025> (Partial Amendment to the Enforcement Rules of the Act on Repair, etc. of National Heritage for the Change of Ministry Names, etc. Pursuant to the Amendment of the Government Organization Act)
This rule shall take effect from the date of its promulgation.
[Attached Table 1] Specific Timing for Impact Assessment (Related to Article 3)
[Appendix 2] Criteria for Revocation of Designation and Suspension of Operations of Professional Training Institutions (Related to Article 17)
[Attachment Form No. 1] Request for Prior Impact Consultation
[Attachment Form No. 2] Internal Review of Prior Impact Consultation
[Attachment Form No. 3] Expert Review Opinion on Historical and Cultural Environment
[Attachment Form No. 4] Report on Completion of Impact Assessment
[Attachment Form No. 5] Report on Results of Preservation Measures (Preservation in Current Condition) for Buried Heritage
[Attachment Form No. 6] Report on Results of Preservation Measures (Observation Survey) for Buried Heritage
[Attachment Form No. 7] Report on Results of Preservation Measures (Excavation Survey) for Buried Heritage
[Attachment Form No. 8] Order for Restoration, etc.
[Attachment Form No. 9] Review Opinion on Simplified Impact Assessment
[Attachment Form No. 10] Application for Designation as a Professional Training Institution