분산에너지 활성화 특별법 시행규칙
283831 · 2026-03-03
Ministry of Climate, Energy and Environment ( Distributed Energy Division ), 044-203-3926
Article 1 (Purpose) The purpose of this ruleis to prescribe matters delegated by the Special Act on the Promotion of Distributed Energy and the Enforcement Decree of the same Act , as well as matters necessary for the implementation thereof.
Article 2 (Requirements for Power Generation Facilities for Distributed Energy Production) In subparagraph 4 of Article 2 of the Enforcement Decree, “requirements prescribed by the Ordinance of the Ministry of Climate, Energy and Environment, such as proximity to energy-using areas” refers to the requirements of each of the following subparagraphs. <Amended Oct. 1, 2025>
1. It shall be connected to a substation via a transmission line within 15 kilometers in length.
2. The capacity of the substation connected pursuant to Subparagraph 1 (referring to the combined capacity if there are two or more substations) shall be greater than the capacity of the relevant power generation facility.
3. The production of electricity shall not have a negative impact on the reliability of the power system and the quality of electricity of electrical facilities, such as transmission and distribution lines and substations, connected for the power supply to energy-consuming areas.
Article 3 (Registration and Amendment Registration, etc. of Distributed Energy Business) ① Any person who intends to register a distributed energy business pursuant to Article 8, Paragraph 1 of the Act shall submit an application for registration or amendment registration of a distributed energy business in the form of Annex No. 1 , attaching the documents set forth in each of the following subparagraphs, to the Minister of Climate, Energy and Environment (in cases where the Minister of Climate, Energy and Environment has entrusted the relevant duties pursuant to Article 62 of the Act and Article 54 of the Enforcement Decree, this refersto the entrusted agency; hereinafter the same applies in Articles 4 and 6 ). <Amended Oct. 1, 2025>
1. Documents proving compliance with the registration standards set forth in Annex 1 of the Enforcement Decree
2. Distributed Energy Business Plan (must include the business name, business details, preparation period, planned business commencement date, and financial management plan)
3. Certificate of Corporate Registration (applicable only to corporations)
4. Certificate of Business Registration (referring to a certificate of business registration excluding the Resident Registration Number)
② If an application under Paragraph 1 does not fall under any of the subparagraphs of Article 8, Paragraph 3 of the Act, the Minister of Climate, Energy and Environment shall issue a Distributed Energy Business Registration Certificate in the form of Annex 2 to the relevant applicant . <Amended Oct. 1, 2025>
③ In the event that a distributed energy business operator intends to register a change pursuant to Article 8, Paragraph 4 of the Act, the operator shall submit an application for registration or change of registration of a distributed energy business in the form of Annex No. 1, attached with documents proving the changes, to the Minister of Climate, Energy and Environment within 30 days from the date on which the matters specified in each subparagraph of Article 8 , Paragraph 2 of the Enforcement Decree are changed. <Amended Oct. 1, 2025>
Article 4 (Reporting of Succession to Status of Distributed Energy Business Operator) A person who has succeeded to the status of a distributed energy business operator pursuant to Article 9, Paragraph 1 of the Act shall report to the Minister of Climate, Energy and Environment by attaching the documents classified according to each of the following subparagraphs to the Report on Succession to Status of Distributed Energy Business Operator in Annex 3. <Amended Oct. 1, 2025>
1. In the case of the acquisition of a distributed energy business: Copy of the transfer and acquisition agreement
2. In the case of inheritance of a distributed energy business: A family relationship certificate pursuant to Article 15, Paragraph 1, Subparagraph 1 of the Act on Registration of Family Relations, etc. , and documents proving heirship
3. In the case of a corporate merger or division: Documents proving the succession to the status of a distributed energy business operator, such as a copy of the merger agreement
Article 5 (Considerations for Calculating Mandatory Installation Quantities) In Article 13, Paragraph 3, Subparagraph 5 of the Act, “matters prescribed by the Ordinance of the Ministry of Climate, Energy and Environment” refers to regional electricity supply and demand conditions. <Amended Oct. 1, 2025>
Article 6 (Submission of Calculation Results for Mandatory Distributed Energy Installation Quantity) In accordance with Article 13, Paragraph 4 of the Act, mandatory installers shall submit a distributed energy facility installation plan containing the calculation results for the mandatory installation quantity to the Minister of Climate, Energy and Environment by the submission deadline specified in Article 20, Paragraph 4 and Annex 1 of the Enforcement Decree of the Energy Rationalization Act . <Amended Oct. 1, 2025>
Article 7 (Disconnection of Distribution Network) ① A distribution business operator may disconnect a distribution network in any of the following cases pursuant to Article 16, Paragraph 4, Subparagraphs 1 and 2 of the Act.
1. When it is determined that a distributed energy business operator modifies, alters, damages, or manipulates electrical facilities, thereby having a significant impact on securing the security and stability of the distribution network
2. Cases where it is difficult to protect the interests of distributed energy business operators or electricity users other than by disconnecting the distribution network
3. Other cases where the distribution business operator deems it necessary to disconnect the distribution network to ensure the security and stability of the distribution network
② If a distribution business operator blocks a distribution network connection pursuant to Article 16, Paragraph 4 of the Act, it shall notify the distributed energy business operator of the reason and grounds for such blockage within 30 days of the blockage and disclose the details through the distribution business operator's internet homepage.
Article 8 (Stable Operation of Power System and Establishment of Coordination System) Distribution business operators and the Korea Power Exchange shall, pursuant to Article 17, Paragraph 5 of the Act , mutually share information,such as operational plans for the power system, that is deemed necessary for the stable operation of the power system as determined and notified by the Minister of Climate, Energy and Environment . <Amended Oct. 1, 2025>
Article 9 (Survey on the Status of Distributed Energy and Plans for Distribution Network Expansion and Operation, etc.) ① If a distribution business operator has conducted a survey on the status of
② A distribution business operator shall submit a distribution network expansion plan and an operation plan to the Minister of Climate, Energy and Environment within six months after conducting a fact-finding survey pursuant to the first part of Article 18, Paragraph 1 of the Act. <Amended Oct. 1, 2025>
③ The distribution network expansion plan and operation plan submitted by a distribution business operator to the Minister of Climate, Energy and Environment pursuant to the first part of Article 18, Paragraph 1 of the Act shall include the matters in each of the following subparagraphs. The same shall apply when intending to change the distribution network expansion plan and operation plan pursuant to the latter part of Article 18, Paragraph 1 of the Act. <Amended Oct. 1, 2025>
1. A plan of at least five years regarding the method of distribution network expansion, the timing of expansion, and the installation areas for related facilities
2. A plan of five years or more regarding distribution network operation
3. Other matters deemed necessary by the Minister of Climate, Energy and Environment
④ In the latter part of Article 18, Paragraph 2 of the Act, “special reasons prescribed by the Ordinance of the Ministry of Climate, Energy and Environment” refers to unavoidable reasons, such as natural disasters, that make it impossible to implement distribution network expansion plans and operation plans. <Amended Oct. 1, 2025>
Article 10 (Notification of Matters Requiring Improvement, etc.) In accordance with Article 24, Paragraph 5 of the Act, if, as a result of reviewing the report on the assessment of power system impact pursuant to Article 28, Paragraph 1 of the Enforcement Decree (hereinafter referred to as the “Power System Impact Assessment Report”), there are matters falling under any of the subparagraphs of Article 24, Paragraph 5 of the Act, the Minister of Climate, Energy and Environment shall notify the business operator pursuant to Article 27, Paragraph 1, Subparagraph 1 of the Enforcement Decree (hereinafter referred to as the “System Impact Business Operator”) of the results of the review of the Power System Impact Assessment Report, including the contents of each of the following subparagraphs. <Amended Oct. 1, 2025>
1. Contents regarding the adjustment of the project area among projects or project plans subject to power system impact assessment pursuant to Article 24, Paragraph 1 of the Act (hereinafter referred to as “project plans, etc.”)
2. Details regarding the timing of electricity usage in business plans, etc.
3. Other matters determined and notified by the Minister of Climate, Energy and Environment to minimize the impact on the power system
Article 11 (Documents to be Submitted Following Succession of Obligations) A grid impact business operator who has succeeded to the obligations to perform pursuant to Article 28, Paragraph 1 of the Act shall submit a Notification of Succession of Obligations to Perform Grid Impact Business (Form No. 4) to the Minister of Climate, Energy and Environment within 15 days from the date the cause for succession occurred. <Amended Oct. 1, 2025>
Article 12 (Verification of whether obligations to perform have been fulfilled) The investigation and verification results report pursuant to Article 29, Paragraph 3 of the Act shall be in the form of Annex 5 .
Article 13 (Notification of Change in Maintenance, Management, and Operation Methods, etc. of Self-Generating Facilities) ① A grid-affecting business operator who intends to report a change in a self-generating facility or the maintenance, management, and operation method thereof pursuant to Article 31, Paragraph 2 of the Act shall submit a Notification of Change in Maintenance, Management, and Operation Methods, etc. of Self-Generating Facilities in the Form No. 6 of the Appendix to the Minister of Climate, Energy and Environment, attaching materials capable of substantiating the reasons for the change. <Amended Oct. 1, 2025>
② The Minister of Climate, Energy and Environment who receives a notification of change pursuant to Paragraph 1 shall accept the notification if the contents of the change comply with the standards prescribed and notified by the Minister for the purpose of power system impact assessment, such as the prevention of overload of power facilities and the maintenance of appropriate voltage. <Amended Oct. 1, 2025>
③ If the Minister of Climate, Energy and Environment refuses to accept a notification of change under Paragraph 1, he/she shall notify the notifier of the fact of refusal and the reasons therefor in writing without delay. <Amended Oct. 1, 2025>
Article 14 (Application for Designation as an Agent for Power System Impact Assessment) ① In Article 31, Paragraph 1 of the Enforcement Decree, the phrase “a person who meets the requirements prescribed by the Ordinance of the Ministry of Climate, Energy and Environment, such as securing specialized personnel related to the power system” refers to an engineering business operator under Article 2, Subparagraph 4 of the Engineering Industry Promotion Act who possesses all of the personnel listed in each of the following subparagraphs. <Amended Oct. 1, 2025>
1. At least one person holding a Professional Engineer or a doctoral degree in the electrical field pursuant to the National Technical Qualifications Act .
2. Two or more engineers in the electrical field pursuant to the National Technical Qualifications Act
② Any person who intends to be designated as an agent for power system impact assessment pursuant to Article 31, Paragraph 2 of the Enforcement Decree shall submit an application for designation as an agent for power system impact assessment in the form of Annex 7 to the Minister of Climate, Energy and Environment. <Amended Oct. 1, 2025>
③ When the Minister of Climate, Energy and Environment designates an agent for power system impact assessment, he/ she shall issue a Certificate of Designation for Power System Impact Assessment Agent in the form of Annex 8. <Amended Oct. 1, 2025>
Article 15 (Application for Designation of Distributed Energy Specialized Area) The application for designation of a distributed energy specialized area pursuant to Article 32, Paragraph 1 of the Enforcement Decree shall be in accordance with Form No. 9 of the Attached Form .
Article 16 (Documents for Proposal of Distributed Energy Specialized Area Plan) Any private company or mayor, county governor, or district head (referring to the head of an autonomous district) who intends to propose a Distributed Energy Specialized Area Plan pursuant to Article 34 of the Act shall submit a draft Distributed Energy Specialized Area Plan containing the matters of each of the following subparagraphs to the mayor or provincial governor.
1. Name and address of the applicant (in the case of a corporation, the name and address of the corporation and the name and address of the representative)
2. Matters under each subparagraph of Article 35, Paragraph 1 of the Act
Article 17 (Electricity Supply in Distributed Energy Specialized Areas) ① A distributed energy business operator who has installed power generation facilities in a distributed energy specialized area shall, in accordance with Article 43, Paragraph 1 of the Act, install an electricity meter capable of measuring the amount of electricity supplied by time of day and verify the amount of electricity supplied when supplying electricity directly to users without passing through the electricity market within the distributed energy specialized area.
② In order to ensure a stable electricity supply to distributed energy business operators within a distributed energy specialized area, distributed energy business operators, distribution business operators, and other institutions deemed necessary by the Minister of Climate, Energy and Environment shall share the information set forth in each of the following subparagraphs. <Amended Oct. 1, 2025>
1. Hourly power supply volume of distributed energy providers
2. Electricity usage by time of day
3. Other matters deemed necessary by the Minister of Climate, Energy and Environment for the stable supply of electricity by distributed energy business operators
③ In addition to the matters prescribed in Paragraphs 1 and 2, detailed matters necessary for the supply of electricity by distributed energy business operators within distributed energy specialized areas pursuant to Article 43, Paragraph 1 of the Act shall be determined and announced by the Minister of Climate, Energy and Environment . <Amended Oct. 1, 2025>
Article 18 (Electricity Trading by Distributed Energy Business Operators and Electricity Sales Business Operators) In Article 43, Paragraph 2 of the Act, “reasons prescribed by the Ordinance of the Ministry of Climate, Energy and Environment, such as accidents” refers to any of the reasons falling under any of the following subparagraphs. <Amended Oct. 1, 2025; Mar. 3, 2026>
1. Cases where the amount of electricity produced by a distributed energy business operator falls short of the electricity user's demand or exceeds the demand.
2. When a distributed energy business operator is unable to supply electricity to a user due to any of the following reasons
a. Failure of supply facilities, communication facilities, etc. due to natural disasters or other similar causes
B. Periodic inspection and maintenance of power generation facilities
Article 19 (Training of Specialized Personnel) The term “matters prescribed by the Ordinance of the Ministry of Climate, Energy and Environment” in Article 49, Paragraph 1, Subparagraph 5 of the Act refers to the matters in each of the following subparagraphs. <Amended Oct. 1, 2025>
1. Implementation of online education on the development and dissemination of distributed energy
2. Establishment of a training institution for specialized technical personnel regarding the development and dissemination of distributed energy
Article 20 (Preparation of Statistics on Distributed Energy, etc.) ① The Minister of Climate, Energy and Environment may prepare statistics on distributed energy regarding the matters in each of the following subparagraphs pursuant to Article 50, Paragraph 1 of the Act. <Amended Oct. 1, 2025>
1. Current Status of Management and Personnel, etc. of Distributed Energy Business Operators
2. Matters concerning the supply status of distributed energy by type supplied by distributed energy business operators
3. Regional Supply Status of Distributed Energy
4. Matters related to the analysis of the economic ripple effects of distributed energy
5. Other matters deemed necessary by the Minister of Climate, Energy and Environment to promote the development and dissemination of distributed energy.
② Pursuant to Article 50, paragraph 2 of the Act, the Minister of Climate, Energy and Environment may have the Distributed Energy Promotion Center under Article 54, paragraph 1 of the Act perform the duties of compiling and managing statistics. <Amended Oct. 1, 2025>
③ The Distributed Energy Promotion Center, which performs the duties of compiling and managing statistics related to distributed energy pursuant to Paragraph 2, may request distribution business operators and the Korea Power Exchange to submit data necessary for compiling statistics on distributed energy.
Article 21 (International Cooperation, etc.) The term “projects prescribed by the Ordinance of the Ministry of Climate, Energy and Environment” pursuant to Article 51, Paragraph 1, Subparagraph 5 of the Act refers to any of the projects falling under any of the following subparagraphs. <Amended Oct. 1, 2025>
1. Survey and Research for International Cooperation in Distributed Energy Technology Development
2. Holding regular cooperation meetings with foreign government agencies
3. Demand Survey for Distributed Energy Technology Development Required for Overseas Expansion
Article 22 (Management Information, etc. of the Comprehensive Information Management System) ① The Minister of Climate, Energy and Environment may perform the following tasks for the establishment and operation of the Comprehensive Information Management System pursuant to Article 53, Paragraph 1 of the Act (hereinafter referred to as the “Comprehensive Information Management System”). <Amended Oct. 1, 2025>
1. Research and development and technical support for the establishment and operation of the integrated information management system
2. Promoting the joint use of information using the integrated information management system
3. Other matters deemed necessary by the Minister of Climate, Energy and Environment for the establishment and operation of the comprehensive information management system
② The Minister of Climate, Energy and Environment may establish and operate a consultative body composed of distributed energy experts and business operators for the efficient establishment and operation of the comprehensive information management system. <Amended Oct. 1, 2025>
③ Pursuant to Article 53, paragraph 2 of the Act, the Minister of Climate, Energy and Environment may have the Korea Energy Agency, established under Article 45 of the Energy Rationalization Act , perform duties concerning the establishment and operation of the Comprehensive Information Management System. <Amended Oct. 1, 2025>
Article 23 (Fees) The fees received from persons who intend to register a distributed energy business pursuant to Article 61 of the Actare as set forth in the attached table .
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 561, June 14, 2024>
This rule will take effect on June 14, 2024.
ADDENDA <Ministry of Climate, Energy and Environment Decree No. 1, Oct. 1, 2025> (Enforcement Rule on the Organization of the Ministry of Climate, Energy and Environment and its Affiliated Agencies)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation. However, among the Ministerial Ordinances amended pursuant to Article 6 of the Addenda, the parts amending Ministerial Ordinances that were promulgated prior to the enforcement of this Rule but whose effective date has not yet arrived shall enter into force on the respective effective dates of those Ordinances.
Articles 2 through 5 omitted
Article 6 (Amendment of Other Laws) ① through ㉘ omitted
㉙ The Enforcement Rules of the Special Act on the Promotion of Distributed Energy are partially amended as follows.
In the part other than the numbered clauses of Article 2, Article 5, Article 9 Paragraph 4, the part other than the numbered clauses of Article 14 Paragraph 1, the part other than the numbered clauses of Article 18, the part other than the numbered clauses of Article 19, and the part other than the numbered clauses of Article 21, “Ordinance of the Ministry of Trade, Industry and Energy” shall be changed to “Ordinance of the Ministry of Climate, Energy and Environment”.
In Article 3, Paragraph 1 (excluding the numbered items), Paragraphs 2 and 3 of the same article, Article 4 (excluding the numbered items), Article 6, Article 8, Article 9, Paragraphs 1 and 2, the first part of Paragraph 3 of the same article (excluding the numbered items), and Subparagraph 3 of the same paragraph, Article 10 (excluding the numbered items), and Subparagraph 3 of the same article, Article 11, Article 13, Paragraphs 1 through 3, Article 14, Paragraphs 2 and 3, Article 17, Paragraph 2 (excluding the numbered items), Subparagraph 3 of the same paragraph, and Paragraph 3 of the same article, Article 20, Paragraph 1 (excluding the numbered items), Subparagraph 5 of the same paragraph, and Paragraph 2 of the same article, Article 22, Paragraph 1 (excluding the numbered items), Subparagraph 3 of the same paragraph, and Paragraphs 2 and 3 of the same article, “Minister of Trade, Industry and Energy” shall be changed to “Minister of Climate, Energy and Environment”.
In Forms No. 1 through No. 4 and Forms No. 6 through No. 9, “Minister of Trade, Industry and Energy” shall be changed to “Minister of Climate, Energy and Environment”.
In Form No. 1 and Form No. 3, “(Ministry of Trade, Industry and Energy)” shall be changed to “(Ministry of Climate, Energy and Environment)”.
In the processing procedure section of Form No. 6, Form No. 7, and Form No. 9, “Ministry of Trade, Industry and Energy” shall be changed to “Ministry of Climate, Energy and Environment”.
Omitted from 30 to <98>
ADDENDA <Ministry of Climate, Energy and Environment Decree No. 24, Mar. 3, 2026>
This rule shall take effect on March 3, 2026.
[Attached] Fees for Registration and Change of Registration of Distributed Energy Business Operators (Related to Article 23)
[Attachment Form No. 1] Application for Distributed Energy Business (Registration, Change of Registration)
[Attachment Form No. 2] Certificate of Registration for Distributed Energy Business (Storage Electricity Sales Business)
[Attachment Form No. 3] Report on Succession of Status as Distributed Energy Business Operator
[Attachment Form No. 4] Notification of Succession of Implementation Obligations for Grid Impact Projects
[Attachment Form No. 5] Report on the Results of Investigation and Verification of Compliance with Obligations
[Attachment Form No. 6] Notification of Change in Maintenance, Management, and Operation Methods, etc. of Self-Generating Facilities
[Attachment Form No. 7] Application for Designation of Power System Impact Assessment Agent
[Attachment Form No. 8] Designation of Power System Impact Assessment Agent
[Attachment Form No. 9] Application for Designation of Distributed Energy Specialized Zone