송ㆍ변전설비 주변지역의 보상 및 지원에 관한 법률 시행규칙
278937 · 2025-10-01
Ministry of Climate, Energy and Environment ( Power Grid Policy Division ), 044-203-5124
Article 1 (Purpose) The purpose of this ruleis to prescribe matters delegated by the Act on Compensation and Support for Areas Surrounding Transmission and Substation Facilities and the Enforcement Decree of the same Act , as well as matters necessary for the implementation thereof.
Article 2 (Determination of the Scope of Areas Surrounding Transmission and Substation Facilities) ①In accordance with Article 2, Paragraph 3 of the Enforcement Decree of the Act on Compensation and Support for Areas Surrounding Transmission and Substation Facilities (hereinafter referred to as the “Decree”),, it shall submit aRequest for Determination of Areas Surrounding Transmission and Substation Facilities in Form No. 1 of the Appendix to the Minister of Climate, Energy and Environment, attaching a List of Households Requesting Determination in Form No. 2 of the Appendix. <Amended Oct. 1, 2025>
② In accordance with Article 2, Paragraph 4 of the Enforcement Decree , if residents intend to submit an opinion regarding the determination of the scope of the area surrounding transmission and substation facilities, they must submit to the business operator an opinion form on the area surrounding transmission and substation facilities in Form No. 1 of the attached document, with the list of households requesting the determination in Form No. 2 of the attached document attached.
③ If a business operator receives a written opinion pursuant to Paragraph 2, it shall send it to the Minister of Climate, Energy and Environment within three months from the date of receipt. <Amended Oct. 1, 2025>
④ Upon receiving a request pursuant to Paragraph 1, the Minister of Climate, Energy and Environment shall determine the scope of the area surrounding the transmission and substation facilities following deliberation by the Surrounding Area Support Deliberation Committee (hereinafter referred to as the “Deliberation Committee”) pursuant to Article 6, Paragraph 1 of the Act on Compensation and Support for Areas Surrounding Transmission and Substation Facilities (hereinafter referred to as the “Act”), and notify the business operator of the result without delay. <Amended Oct. 1, 2025>
⑤ If the business operator receives a notice pursuant to Paragraph 4, it shall notify the residents of the relevant area of the results without delay.
Article 3 (Forms for Land and Housing Specifications) ①The land specification pursuant to Article 3, Paragraph 3, Subparagraph 2 of the Enforcement Decree shall be in the form of Annex 3 .
② The housing specifications pursuant to Article 3 , Paragraph 3, Subparagraph 3 of the Enforcement Decree shall be in the form of Attached Form No. 4 .
Article 4 (Forms for Notification of Compensation Plan, etc.) ① When a business operatornotifies the contents of a plan for consultation and support under each of the following subparagraphs (hereinafter referred to as the “Compensation Plan”) pursuant to the main text of the part other than each subparagraph of Article 4, Paragraph 2 of the Enforcement Decree, the operator shall provide such notification by attaching the Claim Form for Property Compensation, Housing Purchase, or Support for Housing Environment Improvement Costs (Form No. 6 ) to the Guide for Claiming Property Compensation, Housing Purchase, or Support for Housing Environment Improvement Costs (Form No. 5). <Amended July 4, 2023>
1. Negotiation of the amount of property compensation pursuant to Article 4, Paragraph 2 of the Act
2. Consultation on housing purchase pursuant to Article 5 , Paragraph 3 of the Act
3. Support for housing environment improvement costs pursuant to Article 5, Paragraph 1, Subparagraph 2 of the Act
② If a person referred to in Subparagraph 1 or 2 of Article 4 , Paragraph 2 of the Enforcement Decree intends to claim property compensation, purchase of a house, or support for residential environment improvement costs, they shall submit a Claim for Property Compensation, Purchase of a House, or Support for Residential Environment Improvement Costs in the form of Annex 6 to the business operator. In this case, when claiming the purchase of a house, the documents specified in each of the following subparagraphs must be attached. <Amended July 4, 2023; July 30, 2024>
1. One copy of the owner's seal certificate or confirmation of signature.
2. One copy of documents proving ownership and other rights
③ Notwithstanding the latter part of Paragraph 2, if a business operator can verify the documents in each subparagraph of Paragraph 2 through the joint use of administrative information pursuant to Article 36 Paragraph 1 of the Electronic Government Act , and the person requesting the verification consents to such verification, the relevant documents may not be submitted.
④ When a business operator allows inspection of a compensation plan in accordance with the first part of Article 4, Paragraph 3 of the Enforcement Decree , the business operator shall prepare a compensation plan inspection register in the form of Annex 7 .
⑤ Landowners, etc. who intend to raise an objection regarding the compensation plan pursuant to Article 4 , Paragraph 4 of the Enforcement Decree shall submit an objection application form in Annex 8 to the business operator.
Article 5 (Change of Minor Matters) In the proviso to Article 4, Paragraph 8 of the Enforcement Decree, the phrase “where minor matters prescribed by the Ordinance of the Ministry of Climate, Energy and Environment are changed” refers to any of the following cases: <Amended July 4, 2023; Oct 1, 2025>
1. Where the relevant change does not entail a change in the location or area of the ground transmission line
2. Cases where the location or area of the above-ground transmission line has changed but does not entail a change in the property compensation area or the claim area, such as for the purchase of housing.
Article 6 (Forms for Request for Compensation Negotiation, etc.) ①The request for compensation negotiation pursuant to the main text of the part other than each subparagraph of Article 5, Paragraph 1 of the Enforcement Decree shall be in the form of Annex No. 9 .
② The land survey, housing survey, and consultation history report pursuant to Article 5, Paragraph 5 of the Enforcement Decree shall be in accordance with the classifications in each of the following subparagraphs.
1. Land Survey: Attached Form No. 10
2. Housing Survey: Attached Form No. 11
3. Report on the Circumstances of Consultation: Attached Form No. 12
Article 7 (Procedures and Methods for Valuation of Land) ① For the valuation of land value pursuant to Article 7, Paragraph 1, Subparagraph 2 of the Enforcement Decree, a business operator may receive a recommendation for an appraisal business operator (referring to an appraisal business operator pursuant to Article 2, Subparagraph 9 of the Act on Public Announcement of Real Estate Prices and Appraisal , hereinafter referred to as “appraisal business operator”) from the Mayor of a Special City, Metropolitan City, Special Self-Governing City, Province, or Special Self-Governing Province where the land subject to valuation is located.
② With respect to the procedures for land valuation and standards for calculating the amount of property compensation pursuant to Article 7, Paragraph 2 of the Enforcement Decree, the provisions of Article 16 , Article 17 , Paragraphs 1, 2, 4 and 5, Articles 18 through 20 , and Articles 22 through 24 of the Enforcement Rules of the Act on Acquisition and Compensation of Land, etc. for Public Projects shall apply mutatis mutandis.
③ In addition to the matters prescribed in Paragraph 1, detailed matters necessary for the recommendation and selection, etc. of appraisal business operators shall be determined and announced by the Minister of Climate, Energy and Environment . <Amended Oct. 1, 2025>
Article 8 (Subjects of Request for Purchase of Housing) In Article 10, Paragraph 1, Subparagraph 5 of the Enforcement Decree, the term “unauthorized residential buildings falling under the standards prescribed by the Ordinance of the Ministry of Climate, Energy and Environment” refers to unauthorized buildings deemed to be lawful buildings pursuant to Article 5, Paragraphs 1 and 2 of the Addenda to the Partial Amendment to the Enforcement Rule of the Act on the Acquisition and Compensation of Land, etc. for Public Projects, Decree No. 344 of the Ministry of Construction and Transportation (limited to cases of residential use). <Amended Oct. 1, 2025>
Article 9 (Compensation for Housing Relocation Expenses and Movable Property Relocation Expenses) Articles 54 and 55 of the Enforcement Rules of the Act on Acquisition and Compensation of Land, etc. for Public Projects shall apply mutatis mutandis to the compensation for housing relocation expenses and movable property relocation expenses pursuant to Article 10 , Paragraph 3 of the Enforcement Decree . In this case, the phrase “at the time of the public notice of project recognition, etc. or at the time of the public notice, etc. under relevant laws and regulations for public projects ” in the main clause and proviso of Article 54 , Paragraph 2 of the Enforcement Rules of the Act on Acquisition and Compensation of Land, etc. forshall be deemed to be “at the time of the public notice of the compensation plan pursuant to Article 4 , Paragraph 7 of the Enforcement Decree”.
Article 10 (Calculation and Evaluation of Value of Housing Purchase or Housing Environment Improvement Costs) ① The provisions of Article 7 , Paragraphs 2 and 3 shall apply mutatis mutandis to the recommendation and selection, etc. of appraisal firms for the evaluation of the housing purchase value pursuant to Article 11, Paragraph 1 , Subparagraph 4 of the Enforcement Decree.
② Regarding the calculation standards and evaluation procedures, etc. for land, etc., for the calculation of the purchase price of a house pursuant to Article 11 , Paragraph 6 of the Enforcement Decree, Articles 22 through 29 , Article 34 , Articles 36 through 40 , and Article 58, Paragraph 1 of the Enforcement Rules of the Act on Acquisition and Compensation of Land, etc. for Public Projects shall apply mutatis mutandis.
③ In the first part of Article 11-2, Paragraph 1 of the Enforcement Decree, the term “ratio prescribed by the Ordinance of the Ministry of Climate, Energy and Environment” refers to 30 percent. <Newly added July 4, 2023; October 1, 2025>
[Title amended July 4, 2023]
Article 11 (Establishment and Amendment of Support Project Plan) ① The phrase “cases where an explanatory meeting cannot be held due to unavoidable circumstances prescribed by the Ordinance of the Ministry of Climate, Energy and Environment” in the proviso to Article 19, Paragraph 3 of the Enforcement Decree refers to any of the following cases: <Amended Oct. 1, 2025>
1. Cases where the briefing session cannot be held due to interference by stakeholders, etc.
2. Cases where an information session is held but cannot proceed normally due to interference by stakeholders, etc.
② In accordance with Article 19 , Paragraph 4 of the Enforcement Decree, if a person elected by the consent of a majority of residents in the area surrounding the transmission and substation facilities or residents in the area surrounding the transmission and substation facilities at the unit of Ri or Tong (hereinafter referred to as “basic administrative area”) intends to submit an opinion regarding the establishment of a support project plan for the area surrounding the transmission and substation facilities pursuant to Article 7 , Paragraph 1 of the Act (hereinafter referred to as the “support project plan”), they must submit their opinion regarding the matters, etc., of each subparagraph of Article 19 , Paragraph 2 of the Enforcement Decree in writing to the business operator.
③ In accordance with Article 19, Paragraph 5 of the Enforcement Decree, if a business operator intends to request a deliberation by the Deliberation Committee regarding a support project plan, it shall submit to the Minister of Climate, Energy and Environment an implementation plan for support projects in areas surrounding transmission and substation facilities in Form No. 13, attaching a unit project plan in Form No. 14. <Amended Oct. 1, 2025>
④ In the event that a business operator changes the support project plan pursuant to the main clause of Article 19, Paragraph 6 of the Enforcement Decree , it shall submit to the Minister of Climate, Energy and Environment the Statement of Changes to Support Projects for Areas Surrounding Transmission and Substation Facilities ( Form No. 15) , attaching the Statement of Changes to Unit Projects ( Form No. 16 ). <Amended Oct. 1, 2025>
⑤ In the proviso to Article 19, Paragraph 6 of the Enforcement Decree, “cases where minor matters prescribed by the Ordinance of the Ministry of Climate, Energy and Environment are changed” refers to any of the cases falling under any of the following subparagraphs. <Amended Oct. 1, 2025>
1. Cases where the type of support project for areas surrounding transmission and substation facilities pursuant to Article 8, Paragraph 1 of the Act is not changed, but the scale, location, or implementation period of the project is changed
2. Cases where regional support funds at the basic administrative district level remain unchanged, but a part of the support project plan is modified at the request of the relevant resident representative
Article 12 (Application for Electric Power Industry Infrastructure Fund) In accordance with Article 24, Paragraph 2 of the Enforcement Decree , if a business operator applies for the use of the Electric Power Industry Infrastructure Fund pursuant to Article 48 of the Electric Power Business Act, the operator shall submit the Application for Use of the Electric Power Industry Infrastructure Fund in the form of Annex 17 to the Minister of Climate, Energy and Environment. <Amended Oct. 1, 2025>
Article 13 (Submission of Results of Support Project Implementation) When an implementing entity submits the results of a support project pursuant to Article 29 of the Enforcement Decree, it shall submit the report on the results of the support project for areas surrounding transmission and substation facilities in Form No. 18, with the performance statement for each unit project in Form No. 19 attached.
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 69, July 29, 2014>
Article 1 (Enforcement Date) This rule shall enter into force on July 29, 2014.
Article 2 (Applicability to the Calculation of Site Area for Unauthorized Buildings) Article 8 (referring to matters concerning the calculation of site area pursuant to Article 5, Paragraph 2 of the Addendum to the Partial Amendment to the Enforcement Rule of the Act on Acquisition and Compensation of Land, etc. for Public Projects, Ministry of Construction and Transportation Decree No. 344) shall apply from the time a compensation plan is announced in accordance with the main text of the part other than each subparagraph of Article 4, Paragraph 1 of the Enforcement Decree after the enforcement of this Rule.
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 514, July 4, 2023>
This rule will take effect on July 4, 2023.
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 568, July 30, 2024> (Ministry of Trade, Industry and Energy Decree on the Partial Amendment of Two Acts, Including the Enforcement Rule of the Act on Compensation and Support for Areas Surrounding Transmission and Substation Facilities for the Alleviation of Administrative Burdens on Citizens and Resolution of Inconveniences)
This rule shall take effect from the date of promulgation.
ADDENDA <Ministry of Climate, Energy and Environment Decree No. 1, Oct. 1, 2025> (Enforcement Rule on the Organization of the Ministry of Climate, Energy and Environment and its Affiliated Agencies)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation. However, among the Ministerial Ordinances amended pursuant to Article 6 of the Addenda, the parts amending Ministerial Ordinances that were promulgated prior to the enforcement of this Rule but whose effective date has not yet arrived shall enter into force on the respective effective dates of those Ordinances.
Articles 2 through 5 omitted
Article 6 (Amendment of Other Laws) ① through ㉟ omitted
㊱ The Enforcement Rules of the Act on Compensation and Support for Areas Surrounding Transmission and Substation Facilities are partially amended as follows.
In Article 2, Paragraphs 1, 3, and 4; Article 7, Paragraph 3; Article 11, Paragraphs 3 and 4; and Article 12, “Minister of Trade, Industry and Energy” shall be changed to “Minister of Climate, Energy and Environment”.
In the part other than the numbered clauses of Article 5, Article 8, Article 10 Paragraph 3, the part other than the numbered clauses of Article 11 Paragraph 1, and the part other than the numbered clauses of Article 11 Paragraph 5, the term “Ordinance of the Ministry of Trade, Industry and Energy” shall be changed to “Ordinance of the Ministry of Climate, Energy and Environment”.
In Forms No. 1, No. 13, No. 15, No. 17, and No. 18, “Minister of Trade, Industry and Energy” shall be changed to “Minister of Climate, Energy and Environment”.
Sections 24 through 98 omitted
[Attachment Form No. 1] Area Surrounding Transmission and Substation Facilities (Request for Decision, Statement of Opinion)
[Attachment Form No. 2] List of Households Requesting Decision
[Attachment Form No. 3] Land List
[Attachment Form No. 4] Housing Details
[Attachment Form No. 5] Guide to Claiming Property Compensation, Home Purchase, or Support for Housing Environment Improvement Costs
[Attachment Form No. 6] Invoice (Property Compensation, Housing Purchase, Support for Residential Environment Improvement Costs)
[Attachment Form No. 7] Compensation Plan Inspection Register
[Attachment Form No. 8] Objection Form
[Attachment Form No. 9] Request for Consultation on Property Compensation, etc.
[Attachment Form No. 10] Land Survey
[Attachment Form No. 11] Housing Survey
[Attachment Form No. 12] Report on the Circumstances of Consultation
[Attachment Form No. 13] Implementation Plan for Support Projects for Areas Surrounding Transmission and Substation Facilities
[Attachment Form No. 14] Unit Project Plan
[Attachment Form No. 15] Details of Changes to Support Projects for Areas Surrounding Transmission and Substation Facilities
[Attachment Form No. 16] Unit Project Change Statement
[Attachment Form No. 17] Application for Use of Electricity Industry Infrastructure Fund
[Attachment Form No. 18] Report on the Implementation Results of the Support Project for Areas Surrounding Transmission and Substation Facilities
[Attachment Form No. 19] Performance Statement by Unit Project