지능형전력망의 구축 및 이용촉진에 관한 법률 시행규칙
289269 · 2026-09-18
Ministry of Climate, Energy and Environment ( Distributed Energy Division ), 044-203-3923
Article 1 (Purpose) The purpose of this ruleis to prescribe matters delegated by the Act on Promotion of Establishment and Use of Intelligent Power Grids and the Enforcement Decree of the same Act , and matters necessary for the implementation thereof.
Article 2 (Intelligent Grid Technology) In Article 2, Subparagraph 4 of the Act on the Promotion of Establishment and Use of Intelligent Grids (hereinafter referred to as the “Act”), the phrase “technology concerning the establishment and use of intelligent grids as prescribed by the Ordinance of the Ministry of Climate, Energy and Environment” means any of the following subparagraphs. <Amended Mar. 23, 2013; July 9, 2015; Oct. 1, 2025; Aug. 31, 2026>
1. Technology that utilizes information and communication technology, etc., to improve the efficiency of power demand management and power trading, or to enhance the stability, security, and operational efficiency of intelligent power grids.
2. A technology that improves energy efficiency by inducing rational electricity usage by electricity users through the exchange of intelligent power grid information.
3. Technology for establishing and operating electric vehicle charging infrastructure or improving the stability of related intelligent power grids
4. Technology for stably connecting renewable energy pursuant to Article 2, Subparagraph 2 of the “ Act on Promotion of Development, Utilization, and Dissemination of Renewable Energy,” energy utilized in fuel cells, etc., pursuant to Article 2, Subparagraphs 6 and 11 of the “Act on Promotion of Hydrogen Economy and Hydrogen Safety Management,” and hydrogen energy to an intelligent power grid.
Article 3 (Application for Registration, etc. by Intelligent Power Grid Operators) ① The application form for registration (change of registration) of an intelligent power grid operator pursuant to Article 8 , Paragraph 1 and Article 9 , Paragraph 1 of the Enforcement Decree of the Act on Promotion of Establishment and Use of Intelligent Power Grids ( hereinafter referred to as the “Decree”) shall be as Form No. 1 attached hereto .
② The application for registration (or change of registration) under Paragraph 1 shall be accompanied by the documents specified in each of the following subparagraphs (in the case of change of registration, only the changed documents among those submitted at the time of the registration application). In this case, the head of the Intelligent Power Grid Association (hereinafter referred to as the “Association President”) who has received the application pursuant to Article 12 of the Act and Subparagraph 2 of Article 19 of the Enforcement Decree shall verify the Certificate of Corporate Registration (only applicable if the applicant is a corporation), the Business Registration Certificate, and the National Technical Qualification Certificate under the National Technical Qualification Act through the joint use of administrative information pursuant to Article 36 , Paragraph 1 of the Electronic Government Act; and if the applicant does not consent to the verification of the Business Registration Certificate or the National Technical Qualification Certificate under the National Technical Qualification Act through the joint use of administrative information , a copy of the relevant documents shall be attached. <Amended Jan. 16, 2015>
1. Deleted <2015. 1. 16.>
2. Documents proving capital ( applicable only to intelligent power grid infrastructure construction business operators pursuant to Article 8 , Paragraph 2 and Annex 1 of the Enforcement Decree)
3. Other documents proving compliance with the registration standards and scope of business of an intelligent power grid business operator pursuant to Article 8 , Paragraph 2 of the Enforcement Decree
③ In cases where the Minister of Climate, Energy and Environment grants registration pursuant to Article 8, Paragraph 3 of the Enforcement Decree , the President of the Association may issue the Intelligent Power Grid Business Operator Registration Certificate in the form of Annex 2 to the applicant. <Amended Mar. 23, 2013; Oct. 1, 2025>
④ A person who has been issued a registration certificate pursuant to Paragraph 3 may apply to the President of the Association for reissuance of the registration certificate if the certificate is lost or becomes worn out and unusable. In this case, when applying for reissuance because the certificate has become worn out and unusable, the registration certificate must be attached.
⑤ The President of the Association who receives an application for reissuance of a registration certificate pursuant to Paragraph 4 shall reissue the registration certificate after confirming that the applicant is a registered intelligent power grid operator.
Article 4 (Application for Certification, etc.) ① The subjects of application for certification pursuant to Article 15, Paragraph 1 of the Act are as follows:
1. Manufacturers of intelligent power grid equipment and products
2. Providers of intelligent power grid services
3. Building owner of a building where intelligent power grid equipment and products, etc. are installed
② Any person falling under any of the subparagraphs of Paragraph 1 who wishes to obtain certification shall submit an application for certification to the Minister of Climate, Energy and Environment or the head of a certification body, attaching documents, etc. proving compliance with the certification standards under Article 11 of the Enforcement Decree . <Amended Mar. 23, 2013; Oct. 1, 2025>
③ The Minister of Climate, Energy and Environment or the head of a certification body who has received an application for certification under Paragraph 2 shall issue a certificate to the applicant if they recognize that the contents of the application conform to the certification standards under Article 11 of the Enforcement Decree. <Amended Mar. 23, 2013; Oct. 1, 2025>
④ A person who has received certification pursuant to Article 15, Paragraph 1 of the Act may affix a certification mark indicating that the product or document, etc., has been certified.
⑤ Detailed matters necessary for certification, such as the application for certification under Paragraph 2, the certificate under Paragraph 3, and the certification mark under Paragraph 4, shall be determined and announced by the Minister of Climate, Energy and Environment. <Amended Mar. 23, 2013; Oct. 1, 2025>
Article 5 (Application for Designation as Certification Body, etc.) ①person who intends to be designated as a certification body pursuant to Article 16, Paragraph 1 of the Act shall submit to the Minister of Climate, Energy and Environment an application for designation as a certification body in the form of Annex 3 , attaching the documents specified in each of the following subparagraphs . In this case, the Minister of Climate, Energy and Environment who receives the application for designation shall verify the Certificate of Corporate Registration (only applicable if the applicant is a corporation) or the Certified Copy of the Representative's Resident Registration Record (only applicable if the applicant is not a corporation) through the joint use of administrative information pursuant to Article 36, Paragraph 1 of the Electronic Government Act; and if the applicant does not consent to the verification of the Certified Copy of the Resident Registration Record through the joint use of administrative information, the applicant shall be required to attach it. <Amended Mar. 23, 2013; Oct. 1, 2025>
1. Articles of Incorporation
2. Deleted <January 16, 2015>
3. Documents regarding the composition of the dedicated organization performing certification tasks and the status and experience of specialized personnel
4. Certification business regulations including certification procedures, etc.
5. Other documents proving compliance with the designation criteria for certification bodies pursuant to Article 12 of the Enforcement Decree
② Upon receiving an application for designation as a certification body pursuant to Paragraph 1, the Minister of Climate, Energy and Environment shall , if deemed to have complied with the criteria for designation as a certification body under Article 12 of the Enforcement Decree, issue a Certificate of Designation as a Certification Body in the form of Annex 4 to the applicant and publicize the fact. In this case, the Minister of Climate, Energy and Environment may conduct an on-site evaluation to verify compliance with the criteria for designation as a certification body. <Amended Mar. 23, 2013; Oct. 1, 2025>
Article 6 (Application for Designation of Support Agency, etc.) ①Any person who intends to be designated as a support agency for the promotion of the intelligent power grid industry pursuant to Article 19, Paragraph 1 of the Act (hereinafter referred to as the “Support Agency” ) shall submit to the Minister of Climate, Energy and Environment an application for designation as a support agency for the promotion of the intelligent power grid industry in the form of Annex 5, attaching the documents specified in each of the following subparagraphs. In this case, the Minister of Climate, Energy and Environment who receives the application for designation shall verify the Certificate of Corporate Registration (only applicable if the applicant is a corporation) or the Certified Copy of the Representative’s Resident Registration Record (only applicable if the applicant is not a corporation) through the joint use of administrative information pursuant to Article 36, Paragraph 1 of the Electronic Government Act; and if the applicant does not consent to the verification of the Certified Copy of the Resident Registration Record through the joint use of administrative information, the applicant shall be required to attach it. <Amended Mar. 23, 2013; Oct. 1, 2025>
1. Articles of Incorporation
2. Documents proving performance results pursuant to Article 14 , Subparagraph 2 of the Enforcement Decree
3. Documents regarding the composition of the dedicated organization and the current status and experience of specialized personnel pursuant to Article 14 , Subparagraph 3 of the Enforcement Decree
4. Other documents proving that the matters under Article 14 , Subparagraph 4 of the Enforcement Decree have been met
② Upon receiving an application for designation as a support agency pursuant to Paragraph 1, the Minister of Climate, Energy and Environment shall , if deemed to have complied with the criteria for designation as a support agency under Article 14 of the Enforcement Decree, issue a Certificate of Designation as a Support Agency for Intelligent Power Grid Industry Promotion in the form of Annex 6 to the applicant and publicize the fact. In this case, the Minister of Climate, Energy and Environment may conduct an on-site evaluation by establishing an evaluation plan that includes the purpose and method of evaluation, etc., to verify compliance with the criteria for designation as a support agency. <Amended Mar. 23, 2013; Jan. 16, 2015; Oct. 1, 2025>
Article 7 (Application for Mediation, etc.) ①The application for mediation pursuant to Article 15 , Paragraph 1 of the Enforcement Decree shall be in the form of Annex No. 7 .
② In order for an intelligent power grid operator to request adjustment pursuant to Article 15 , Paragraph 1 of the Enforcement Decree , the following documents must be attached to the adjustment application form in Annex 7 .
1. Statement of the history of consultations between the parties (referring to the details of consultations between the parties by schedule from the time the mediation occurred until the time of application and the supporting documents)
2. Other objective materials that may be used as reference for the mediation of the mediation application case
Article 8 (Identification) The identification pursuant to Article 17, Paragraph 2 of the Enforcement Decree shall be in the form of Annex 8 .
Article 9 (Review of Regulations) The Minister of Climate, Energy and Environment shall review the validity of the matters set forth in each of the following subparagraphs every two years based on the reference dates specified in each of the following subparagraphs (meaning the period prior to the same date as the reference date of every second year) and take measures such as improvements. <Amended Oct. 1, 2025>
1. Documents to be submitted upon application for registration of an intelligent power grid operator pursuant to Article 3 : January 1, 2015
2. Documents to be submitted for the application for designation as a certification body pursuant to Article 5 : January 1, 2015
3. Documents to be submitted upon application for designation of a supporting institution pursuant to Article 6 : January 1, 2015
[This Article Newly Inserted Dec. 31, 2014]
ADDENDA <Ministry of Knowledge Economy Decree No. 211, Nov. 24, 2011>
This rule shall take effect on November 25, 2011.
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 1, Mar. 23, 2013> (Enforcement Rule of the Organizational Structure of the Ministry of Trade, Industry and Energy and its Affiliated Agencies)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation. <Proviso Omitted>
Articles 2 through 6 omitted
Article 7 (Amendment of Other Laws) ① through <51> Omitted
<52> The Enforcement Rules of the Act on the Promotion of Establishment and Use of Intelligent Power Grids are partially amended as follows.
In the part other than the subparagraphs of Article 2, “Ordinance of the Ministry of Knowledge Economy” shall be changed to “Ordinance of the Ministry of Trade, Industry and Energy.”
In Article 3, Paragraph 3; Article 4, Paragraphs 2, 3, and 5; the first and second parts of the part other than the subparagraphs of Article 5, Paragraph 1; the first and second parts of Paragraph 2 of the same article; the first and second parts of the part other than the subparagraphs of Article 6, Paragraph 1; and the first and second parts of Paragraph 2 of the same article, “Minister of Knowledge Economy” shall be changed to “Minister of Trade, Industry and Energy”.
In Forms No. 1, No. 3, and No. 5, “Ministry of Knowledge Economy” shall be changed to “Ministry of Trade, Industry and Energy”.
In Forms No. 2 through No. 8 of the Attached Forms, “Minister of Knowledge Economy” shall be changed to “Minister of Trade, Industry and Energy”.
<53> through <63> omitted
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 106, Dec. 31, 2014> (Partial Amendment to the Enforcement Rules of the High Pressure Gas Safety Management Act, etc. for Regulatory Reform, Including Setting Regulatory Review Periods)
This rule shall take effect on January 1, 2015.
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 113, Jan. 16, 2015>
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 138, July 9, 2015> (Enforcement Rule of the Act on Promotion of Development, Utilization and Dissemination of New and Renewable Energy)
Article 1 (Enforcement Date) This Rule shall enter into force on July 29, 2015. <Proviso Omitted>
Article 2 (Amendment of Other Laws) ① Omitted
② The Enforcement Rules of the Act on the Promotion of Establishment and Use of Intelligent Power Grids are partially amended as follows:
In Article 2, subparagraph 4, “new energy and renewable energy prescribed in Article 2, subparagraph 1 of the Act on Promotion of Development, Use, and Dissemination of New and Renewable Energy” shall be changed to “new energy and renewable energy pursuant to subparagraphs 1 and 2 of the Act on Promotion of Development, Use, and Dissemination of New and Renewable Energy”.
ADDENDA <Ministry of Climate, Energy and Environment Decree No. 1, Oct. 1, 2025> (Enforcement Rule on the Organization of the Ministry of Climate, Energy and Environment and its Affiliated Agencies)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation. However, among the Ministerial Ordinances amended pursuant to Article 6 of the Addenda, the parts amending Ministerial Ordinances that were promulgated prior to the enforcement of this Rule but whose effective date has not yet arrived shall enter into force on the respective effective dates of those Ordinances.
Articles 2 through 5 omitted
Article 6 (Amendment of Other Laws) ① through <69> Omitted
<70> The Enforcement Rules of the Act on the Promotion of Establishment and Use of Intelligent Power Grids are partially amended as follows.
In the part other than the subparagraphs of Article 2, “Ordinance of the Ministry of Trade, Industry and Energy” shall be changed to “Ordinance of the Ministry of Climate, Energy and Environment”.
In Article 3, Paragraph 3; Article 4, Paragraphs 2, 3, and 5; the first and second parts of the part other than the numbered items of Article 5, Paragraph 1; the first and second parts of Paragraph 2 of the same article; the first and second parts of the part other than the numbered items of Article 6, Paragraph 1; the first and second parts of Paragraph 2 of the same article; and Article 9, the part other than the numbered items, “Minister of Trade, Industry and Energy” shall be changed to “Minister of Climate, Energy and Environment”.
In the processing procedure section of Form No. 1, Form No. 3, and Form No. 5, “Ministry of Trade, Industry and Energy” shall be changed to “Ministry of Climate, Energy and Environment”.
In the back of Forms No. 2, No. 3, No. 4, No. 5, No. 6, No. 7, and No. 8, “Minister of Trade, Industry and Energy” shall be changed to “Minister of Climate, Energy and Environment”.
<71> through <98> omitted
ADDENDA <Ministry of Climate, Energy and Environment Decree No. 56, Aug. 31, 2026> (Enforcement Rule of the Act on Promotion of Hydrogen Economy and Hydrogen Safety Management)
Article 1 (Enforcement Date) This rule shall enter into force on September 18, 2026.
Article 2 (Amendment of Other Laws) ① through ⑩ Omitted
11. Part of the Enforcement Rules of the Act on Promotion of Establishment and Use of Intelligent Power Grids is amended as follows.
In Article 2, subparagraph 4, “new energy and renewable energy pursuant to subparagraphs 1 and 2 of the Act on Promotion of Development, Utilization and Dissemination of New and Renewable Energy” shall be replaced with “renewable energy pursuant to Article 2, subparagraph 2 of the Act on Promotion of Development, Utilization and Dissemination of Renewable Energy and energy utilized in fuel cells, etc. and hydrogen energy pursuant to Article 2, subparagraphs 6 and 11 of the Act on Promotion of Hydrogen Economy and Hydrogen Safety Management.”
⑫ and ⑬ omitted
Article 3 Omitted
[Attachment Form No. 1] Application for Intelligent Power Grid Operator (Registration, Change of Registration)
[Attachment Form No. 2] Intelligent Power Grid Business Operator Registration Certificate
[Attachment Form No. 3] Application for Designation as a Certification Body
[Attachment Form No. 4] Certificate of Designation as a Certification Body
[Attachment Form No. 5] Application for Designation as a Support Agency for Intelligent Power Grid Industry Promotion
[Attachment Form No. 6] Designation Certificate for Intelligent Power Grid Industry Promotion Support Agency
[Attachment Form No. 7] Application for Mediation
[Attachment Form No. 8] Information Protection Compliance Confirmation Certificate