재해위험 개선사업 및 이주대책에 관한 특별법 시행규칙
228725 · 2021-01-12
Ministry of the Interior and Safety ( Disaster Mitigation Division ), 044-205-5158
Article 1 (Purpose) The purpose of this ruleis to prescribe matters delegated by the Special Act on Disaster Risk Improvement Projects and Relocation Measures and the Enforcement Decree of the same Act , as well as matters necessary for the implementation thereof.
Article 2 (Application for Designation of Disaster Risk Improvement Project District) ① The application for designation of a disaster risk improvement project district pursuant to Article 4 of the Special Act on Disaster Risk Improvement Projects and Relocation Measures (hereinafter referred to as the “Act”)and Article 4 of the Enforcement Decree of the same Act (hereinafter referred to as the “Decree”) shall be in accordance with Form No. 1 attached hereto .
② The survey report indicating the status of buildings, land use, and infrastructure within the disaster risk improvement project district pursuant to Article 4, Paragraph 3, Subparagraph 2 of the Act shall be in accordance with Form No. 2 of the Attached Form .
Article 3 (Subjects of Review for Metropolitan Transportation System) In Subparagraph 5 of Article 4 of the Enforcement Decree, the term “area prescribed by the Ordinance of the Ministry of the Interior and Safety” refers to 1 million square meters. <Amended Aug. 24, 2009; Mar. 23, 2013; Nov. 19, 2014; Jul. 26, 2017>
Article 4 (Simplified Structures) Pursuant to Article 8, Paragraph 3, Subparagraph 2 of the Enforcement Decree, the term “simplified structures prescribed by the Ordinance of the Ministry of the Interior and Safety” that may be installed without the permission of the competent Mayor, County Governor, or Head of an autonomous district (hereinafter referred to as “Mayor or County Governor”) within a disaster risk improvement project district refers to any of the following: <Amended Aug. 24, 2009; Mar. 23, 2013; Nov. 19, 2014; Jul. 26, 2017; Dec. 29, 2017>
1. Vinyl greenhouse
2. Sericulture farm
3. Chili drying room
4. Tobacco Leaf Drying Station
5. Seaweed drying room
Article 5 (Reporting of Construction or Project Progress) ①When reporting the progress of construction or project to the competent mayor or county governor pursuant to Article 7 , Paragraph 3 of the Act and Article 8, Paragraph 4 of the Enforcement Decree, a report form in accordance with Form No. 3 of the Attached Form must be submitted along with the progress of the construction or project and the implementation plan.
② The documents indicating the progress of the construction or project under Paragraph 1 are as follows:
1. Documents proving permission and notification in accordance with relevant laws and regulations
2. Photos confirming the progress of the construction as of the reporting date
3. Construction or project-related documents, such as site plans (applicable only in cases of land alteration or extraction of soil, rock, or gravel)
4. Design documents (applicable only in cases of installing buildings or structures)
Article 6 (Agency for Disaster Risk Improvement Projects) ① Any business operator who intends to act on behalf of a part of a disaster risk improvement project pursuant to Article 9, Paragraph 2 of the Enforcement Decree shall submit to the project implementer a letter of intent to act on behalf of the disaster risk improvement project, containing the matters set forth in each of the following subparagraphs as prescribed by the Minister of the Interior and Safety. <Amended Nov. 19, 2014; Jul. 26, 2017>
1. Name (in the case of a corporation, the name of the corporation and the name of the representative) and address of the business operator carrying out the disaster risk improvement project
2. Name, location, and area of the project district where the disaster risk improvement project is to be carried out
3. Overview of the disaster risk improvement project implementation plan including the following items
A. Purpose of the Project
B. Types of Business
C. Project Implementation Period
② If a project implementer intends to have a disaster risk improvement project carried out on their behalf pursuant to Article 9, Paragraph 2 of the Enforcement Decree, they must enter into a written contract regarding the delegation of the disaster risk improvement project with a business operator carrying out site development or housing construction, etc.
③ The contents of the contract pursuant to Paragraph 2 shall specify the matters in each subparagraph of Paragraph 1 and the construction price, etc.
Article 7 (Application for Approval of Disaster Risk Improvement Project Plan) When applying for approval or modification of a disaster risk improvement project plan pursuant to Article 9 of the Act , the application form shall be in accordance with Form No. 4 of the Attached Form .
Article 8 (Application for Approval of Implementation Plan for Disaster Risk Improvement Project) When applying for approval or modification of an implementation plan for a disaster risk improvement project pursuant to Article 10 of the Act , the application form shall be in accordance with Form No. 5 of the Attached Form .
Article 9 (Documents Attached to the Implementation Plan for Disaster Risk Improvement Projects) The “other matters prescribed by the Ordinance of the Ministry of the Interior and Safety” to be included in the implementation plan for disaster risk improvement projects pursuant to Article 12, Paragraph 1, Subparagraph 9 of the Enforcement Decree shall refer to the matters in each of the following subparagraphs. <Amended Aug. 24, 2009; Mar. 23, 2013; Nov. 19, 2014; Jul. 26, 2017>
1. Matters concerning the attribution and replacement of public facilities and land, etc.
2. Matters concerning the plan for applying district-level flood defense standards pursuant to Article 18 of the Natural Disaster Countermeasures Act (to be submitted only if recommended by the Mayor or County Governor)
3. Matters concerning Type 1 district unit plans pursuant to Article 49 , Subparagraph 1 of the National Land Planning and Utilization Act ( applicable only to areas subject to designation as Type 1 district unit plans pursuant to Articles 49 through 51 of the National Land Planning and Utilization Act )
Article 10 (Application for Completion Inspection) The application for completion inspection for a disaster risk improvement project pursuant to Article 15 of the Enforcement Decree shall be in accordance with Form No. 6 of the Attached Form .
Article 11 (Certificate of Completion Inspection) The certificate of completion inspection pursuant to Article 13 , Paragraph 1 of the Act shall be in accordance with Form No. 7 of the Attached Form .
Article 12 (Identification for Entry into Others' Land) An identification indicating the authority to enter into, temporarily use, or alter other obstacles such as trees, soil, or stones on another person's land pursuant to Article 15, Paragraph 3 of the Act shall be in accordance with Form No. 8 of the Attached Form .
Article 13 (Inspection Official ID) The identification card indicating the authority of an official inspecting work related to disaster risk improvement projects pursuant to Article 31, Paragraph 2 of the Act shall be in accordance with Form No. 9 of the Attached Form .
Article 14 Deleted <January 12, 2021>
ADDENDA <Ministry of Government Administration and Home Affairs Decree No. 423, Feb. 1, 2008>
This rule shall take effect on February 4, 2008.
ADDENDA <Ministry of Public Administration and Security Decree No. 100, Aug. 24, 2009>
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of the Interior and Safety Decree No. 297, May 31, 2012> (Partial Amendment to the Enforcement Rules of the Act on the Management of Public Records, etc. for the Protection of Personal Information)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation.
Article 2 (Transitional Measures Regarding Amendment of Forms) Forms under the previous regulations at the time of enforcement of this rule may be used together with the forms under this rule until August 31, 2012.
ADDENDA <Ministry of Security and Public Administration Decree No. 3, Mar. 23, 2013> (Enforcement Rule for the Organization of the National Fire Agency and its Affiliated Agencies)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation.
Article 2 omitted
Article 3 (Amendment of Other Laws) ① through ⑩ Omitted
11. The Enforcement Rules of the Special Act on Disaster Risk Improvement Projects and Relocation Measures are partially amended as follows.
In Article 3, the part other than the numbered items of Article 4, and the part other than the numbered items of Article 9, “Ordinance of the Ministry of Public Administration and Security” shall be changed to “Ordinance of the Ministry of Safety and Security”.
12 Omitted
ADDENDA <Prime Minister's Decree No. 1105, Nov. 19, 2014> (Enforcement Rule for the Organization of the Ministry of Public Safety and Security and Its Affiliated Agencies)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation. However, among the Ministerial Ordinances amended pursuant to Article 6 of the Addenda, the parts amending Prime Ministerial Ordinances or Ministerial Ordinances that were promulgated prior to the enforcement of this Rule but whose effective date has not yet arrived shall enter into force on the respective effective dates of the said Prime Ministerial Ordinances or Ministerial Ordinances.
Articles 2 through 5 omitted
Article 6 (Amendment of Other Laws) ① through ㉘ omitted
㉙ The Enforcement Rules of the Special Act on Disaster Risk Improvement Projects and Relocation Measures are partially amended as follows.
In Article 3, the part other than the subparagraphs of Article 4, and the part other than the subparagraphs of Article 9, “Ordinance of the Ministry of Public Administration and Security” shall be changed to “Ordinance of the Prime Minister”.
In the part other than the subparagraphs of Article 6, Paragraph 1, “Commissioner of the National Fire Agency” shall be changed to “Minister of Public Safety and Security”.
In the front and back of Form No. 1 (Applicant and Processing Agency (Department in Charge) sections), the front and back of Form No. 4 (Processing Agency (Department in Charge) sections), the front and back of Form No. 5 (Processing Agency (Department in Charge) sections), the front of Form No. 6, Form No. 7, Form No. 8, and Form No. 9, “Commissioner of the National Fire Agency” shall be changed to “Minister of Public Safety and Security”.
In the back of Form No. 1, Form No. 4, Form No. 5, and Form No. 6, “National Fire Agency” shall be changed to “Ministry of Public Safety and Security”.
Omit items 30 through 46
ADDENDA <Prime Minister's Decree No. 1152, Mar. 30, 2015>
This rule shall take effect from the date of its promulgation.
ADDENDA <Prime Minister's Decree No. 1247, Jan. 27, 2016> (Partial Amendment to the Enforcement Rules of the Act on 119 Rescue and Emergency Medical Services, etc. for the Batch Amendment of Legal Forms)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation.
Article 2 (Transitional Measures Regarding Forms) Forms under the previous regulations at the time of enforcement of this rule may be used together with the forms under this rule for three months after enforcement of this rule.
ADDENDA <Ministry of the Interior and Safety Decree No. 1, July 26, 2017> (Enforcement Rule on the Organization of the Ministry of the Interior and Safety and its Affiliated Agencies)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation.
Articles 2 through 7 omitted
Article 8 (Amendment of Other Laws) ① through <60> Omitted
<61> The Enforcement Rules of the Special Act on Disaster Risk Improvement Projects and Relocation Measures are partially amended as follows.
In Article 3, the part other than the numbered items of Article 4, and the part other than the numbered items of Article 9, “Prime Minister’s Decree” shall be changed to “Ministry of the Interior and Safety Decree”.
In the part other than the subparagraphs of Article 6, Paragraph 1 and Article 14, “Minister of Public Safety and Security” shall be changed to “Minister of the Interior and Safety”.
In the front of Form No. 1 and the processing procedure column at the back of the same form, the front of Form No. 4 and the processing procedure column at the back of the same form, the front of Form No. 5 and the processing procedure column at the back of the same form, the front of Form No. 6, Form No. 7, Form No. 8, and Form No. 9, “Minister of Public Safety and Security” shall be changed to “Minister of the Interior and Safety”.
In the processing procedure section on the back of Form No. 1, Form No. 4, Form No. 5, and Form No. 6, “Ministry of Public Safety and Security” shall be changed to “Ministry of the Interior and Safety”.
<62> through <64> omitted
ADDENDA <Ministry of the Interior and Safety Decree No. 34, Dec. 29, 2017>
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of the Interior and Safety Decree No. 235, Jan. 12, 2021>
This rule shall take effect from the date of its promulgation.
[Attachment Form No. 1] Application for Designation of Disaster Risk Improvement Project District
[Attachment Form No. 2] Survey of Population, Buildings, Land Use, and Infrastructure Status within Disaster Risk Improvement Project District
[Attachment Form No. 3] Project (Construction) Progress Report
[Attachment Form No. 4] Application for Disaster Risk Improvement Project Plan (Approval, Change Approval)
[Attachment Form No. 5] Application for Implementation Plan (Approval, Approval of Change) for Disaster Risk Improvement Project
[Attachment Form No. 6] Application for Completion Inspection of Disaster Risk Improvement Project
[Attachment Form No. 7] Certificate of Completion Inspection
[Attachment Form No. 8] Certificate
[Attachment Form No. 9] Inspector ID Card