집단에너지사업법 시행규칙
279009 · 2025-10-01
Ministry of Climate, Energy and Environment ( Heat Industry Innovation Division ), 044-203-5142
Article 1 (Purpose) The purpose of this Rule is to prescribe matters delegated by the Integrated Energy Supply Act and the Enforcement Decree of the same Act, as well as matters necessary for their implementation. <Amended Sep. 3, 1999>
Article 2 (Classification of Heat Supply Facilities) Among the supply facilities referred to in subparagraph 6 of Article 2 of the Integrated Energy Supply Act (hereinafter referred to as the “Act”), the supply facilities for the production, transportation, or distribution of heat (hereinafter referred to as “heat supply facilities”) shall be classified as follows. <Amended Sep. 3, 1999; Oct. 13, 2015; Jan. 21, 2022>
1. Heat source facilities: Equipment and auxiliary equipment for heating or cooling water, steam, or other heat transfer media, including the facilities specified in each of the following items:
a. Heat generating equipment [boilers, turbines (referring to machines that obtain rotational force by causing high-pressure liquid or gas to strike the blades of a rotor; hereinafter the same applies), generators, incinerators, etc.]
b. Heat pumps
c. Refrigeration equipment
d. Heat exchangers (excluding heat transport facilities)
e. Thermal storage tanks
f. Other equipment related to heat production
2. Heat transport facilities: Equipment and auxiliary equipment for transporting or distributing water, steam, or other heat transfer media, including the facilities specified in each of the following items:
a. Heat transmission pipes ( excluding piping within heat source facilities and usage facilities under Article 2 , Item 7 of the Act )
b. Circulation pumps
c. Heat exchangers (only those installed in the middle of heat transport pipes for heat exchange between heat source facilities) and their internal piping
d. Other facilities related to the transportation or distribution of heat
Article 3 (Scope of Development Projects Subject to Consultation and Timing of Consultation Requests, etc.) (1) Pursuant to Article 4 of the Act and Article 5 of the Enforcement Decree of the Integrated Energy Supply Act (hereinafter referred to as the “Decree”), development projects subject to consultation with the Minister of Climate, Energy and Environment shall be projects involving the construction of 10,000 or more housing units or projects whose development areas meet any of the following criteria. <Amended Feb. 19, 2002; Mar. 3, 2008; Mar. 23, 2013; Nov. 18, 2016; Oct. 1, 2025>
1. For projects falling under Article 5(1)1 and 2 of the Decree: projects with a development area of at least 600,000 square meters.
2. For projects falling under Article 5(1)3 and 4 of the Decree: projects with a development area of at least 300,000 square meters.
(2) Any person who intends to consult on the feasibility of supplying integrated energy pursuant to paragraph (1) shall request consultation from the Minister of Climate, Energy and Environment by submitting the documents specified in each of the following subparagraphs. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
1. Plan for the development project
2. Location map of the development project area and land use plan map
3. Data specified in Attached Table 1
(3) The timing for requesting consultation under paragraph (2) shall be as specified in Attached Table 2.
[Wholly Amended Sep. 3, 1999]
Article 4 (Notification of Consultation Results, etc.) (1) When the Minister of Climate, Energy and Environment receives a request for consultation on the feasibility of supplying integrated energy pursuant to Article 4 of the Act, the Minister shall notify the results of the consultation within 20 days. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
(2) When notifying the results of consultation on the feasibility of supplying integrated energy under paragraph (1), the Minister of Climate, Energy and Environment may, if deemed necessary, recommend that the person requesting consultation take measures considered necessary for the supply of integrated energy, such as adjusting or supplementing the development project plan. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
[Wholly Amended Sep. 3, 1999]
Article 5 (Application for Permission to Newly Establish, etc., Heat Production Facilities) (1) A person who intends to obtain a permit for newly establishing, re-establishing, or extending heat production facilities, or an amended permit for such activities, pursuant to Article 6(1) of the Act shall submit an application in Form No. 1 attached hereto, together with the following documents, to the Minister of Climate, Energy and Environment. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
1. A location map of the heat production facilities to be newly established, re-established, or extended.
2. A list of equipment for the heat production facilities to be newly established, re-established, or extended.
3. A statement of reasons for newly establishing, re-establishing, or extending the heat production facilities.
4. Where the applicant intends to change any permitted matters, a statement of reasons for the change.
② The Minister of Climate, Energy and Environment who receives an application under Paragraph 1 shall verify the Certificate of Corporate Registration (applicable only to corporations) through the joint use of administrative information pursuant to Article 36 , Paragraph 1 of the Electronic Government Act . <Amended Mar. 25, 2011; Mar. 23, 2013; Oct. 1, 2025>
(3) Upon receiving an application for a permit or amended permit under paragraph (1), the Minister of Climate, Energy and Environment shall provide an opportunity to submit opinions to the person who has obtained a business license under Article 9(1) of the Act in the area to be supplied in which the relevant heat production facility is located. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
[This Article was newly established on Dec. 13, 2006.]
Article 6 Deleted <September 3, 1999>
Article 7 (Application for Business Permit, etc.) (1) A person who intends to obtain a business permit pursuant to Article 9(1) of the Act shall submit an application for a permit in Form No. 2 attached hereto, together with the following documents, to the Minister of Climate, Energy and Environment. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
1. Business Plan
2. Resume of the applicant (in the case of a corporation, an executive thereof, or in the case of a corporation in the process of being established, a person who is to become an executive thereof). However, this shall not apply if the applicant is a corporation established under a special law (hereinafter referred to as a “special corporation”).
② The business plan under Paragraph 1, Item 1 must include the details and required documents specified in Attached Table 3 .
(3) Upon receiving an application for a business license under paragraph (1), the Minister of Climate, Energy and Environment shall select the applicant to be granted a business license, taking into consideration the licensing criteria under Article 9(2) of the Act and the licensing criteria under Article 7(5) and (6) of the Electric Power Business Act. In this case, the Minister may determine and publicly notify detailed criteria and procedures for selecting applicants for business licenses. <Amended Oct. 28, 2024; Oct. 1, 2025>
(4) When the Minister of Climate, Energy and Environment receives an application for a business license under paragraph (1), the Minister may seek the opinion of the head of the local government having jurisdiction over the relevant supplied district regarding the installation of heat source facilities. <Newly Inserted Dec. 13, 2006; Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
[Title amended Sep. 3, 1999]
Article 8 (Application for an Amended License, etc.) (1) The matters for which a person who has obtained a business license (hereinafter referred to as the “business operator”) is required to obtain an amended license pursuant to the latter part of Article 9(1) of the Act are as follows. <Amended Jun. 21, 1993; Sep. 3, 1999; Dec. 31, 2008>
1. Reduction of a heat supply area (only where the heat demand of the area to be reduced is at least 20 percent of the heat demand of the area for which a business license or amended license has been obtained).
2. Increase in a heat supply area (only where the heat demand of the area to be added is at least 20 percent of the heat demand of the area for which a business license or amended license has been obtained).
3. Change in the installation location or type of heat-generating equipment.
4. Change in the capacity of heat-generating equipment (only where the change is at least 20 percent of the capacity approved under the original or amended license).
5. Change to heat transmission pipes (only where the change is at least 20 percent of the total length and maximum diameter approved under the original or amended license).
(2) Any person who intends to obtain an amended license pursuant to the latter part of Article 9(1) of the Act shall submit an application for an amended license in Form No. 3 attached hereto, together with the following documents, to the Minister of Climate, Energy and Environment. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
1. Statement of Reason for Change
2. Business Plan
3. Business license certificate
(3) The business plan referred to in paragraph (2)2 shall include the particulars and supporting documents specified in Attached Table 3.
Article 9 (Notification of Changes to Matters Not Requiring an Amended License) Any person who intends to change any matter for which a business license has been obtained under Article 9(1) of the Act and that falls under any of the following subparagraphs shall report the change to the Minister of Climate, Energy and Environment by submitting a report in Form No. 4 attached hereto, together with the business license certificate. Provided, That in the case of subparagraph 3, the report shall be filed within 30 days from the date of change. <Amended Sep. 3, 1999; Mar. 3, 2008; Dec. 31, 2008; Mar. 23, 2013; Oct. 1, 2025>
1. Increase in a heat supply area (only where the heat demand of the area to be added is less than 20 percent of the heat demand of the area for which a business license or amended license has been obtained).
1-2. Reduction of a heat supply area (only where the heat demand of the area to be reduced is less than 20 percent of the heat demand of the area for which a business license or amended license has been obtained).
2. Change in the capacity of heat-generating equipment (only where the change is less than 20 percent of the capacity approved under the original or amended license).
3. Change in the business operator’s business name, location, or representative.
[Wholly Amended June 21, 1993]
Article 10 (Business License Certificate) (1) When the Minister of Climate, Energy and Environment grants a business license or amended license pursuant to Article 9(1) of the Act, the Minister shall issue to the applicant a business license certificate in Form No. 5 attached hereto. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
(2) When any of the following cases applies, the Minister of Climate, Energy and Environment shall enter the relevant change in the section for recording changes on the business license certificate under paragraph (1) and issue the certificate to the applicant. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
1. When the Minister receives a report on a change to a matter that does not require an amended license pursuant to Article 9.
2. When the Minister receives a report on succession to the business pursuant to Article 12(3) of the Act.
3. When the Minister grants permission to suspend or close the business pursuant to Article 14(1) of the Act.
4. When the Minister receives a report on resumption of business pursuant to Article 14(3) of the Act.
Article 11 Deleted <September 3, 1999>
Article 12 (Report on Succession to a Business) Any person who intends to report succession to a business pursuant to Article 12(3) of the Act shall submit a report in Form No. 7 attached hereto, together with the following documents, to the Minister of Climate, Energy and Environment. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
1. Documents confirming the fact of succession
2. A resume of the successor (if the successor is a corporation, the resume of its executive; or, if the successor is a corporation being established, the resume of the person who will become its executive). Provided, That this shall not apply where the successor is a special corporation.
3. Business License
4. A 1:50,000 topographic map showing the boundaries of the supplied districts of the transferor and transferee, and a document describing an overview of the supply facilities transferred to the transferee (limited to cases where part of the business is transferred).
Article 13 Deleted <September 3, 1999>
Article 14 Deleted <September 3, 1999>
Article 15 (Application for Permission to Suspend or Close Business) A person who intends to obtain permission to suspend or close a business pursuant to Article 14(1) of the Act shall submit an application for permission in Form No. 10 attached hereto, together with the following documents, to the Minister of Climate, Energy and Environment. Provided, That where the entire business is to be suspended or closed, only the documents specified in subparagraphs 1 and 5 may be attached. <Amended Mar. 23, 2013; Jan. 21, 2022; Oct. 1, 2025>
1. Statement of Reasons for Suspension or Closure
2. A 1:50,000 topographic map showing the boundaries of the supplied district of the business to be suspended or closed.
3. Document outlining the supply facilities of the business that is temporarily or permanently closed
4. Projected income and expenditure statements by fiscal year for 5 years following suspension or closure
5. Business license certificate
[Wholly Amended Oct. 5, 2012]
Article 16 (Application for Approval of Dissolution of a Corporation) Any person who intends to obtain approval for the dissolution of a corporation pursuant to Article 14(2) of the Act shall submit an application for approval in Form No. 11 attached hereto, together with the following documents, to the Minister of Climate, Energy and Environment. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
1. Statement of Reasons for Dissolution
2. Documents confirming the resolution for dissolution or the consent of all members to the dissolution
3. Business license certificate
Article 17 (Notification of Resumption of Business) Any person who intends to report the resumption of business pursuant to Article 14(3) of the Act shall submit a report in Form No. 12 attached hereto to the Minister of Climate, Energy and Environment within 30 days from the date of resumption. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
[Wholly Amended Sep. 3, 1999]
Article 18 (Types of Violations Subject to Surcharges and Amounts of Surcharges) (1) The types of violations subject to surcharges under Article 15(3) of the Act and the amounts of surcharges according to the type and severity of the violation shall be as specified in Attached Table 3-2.
(2) The Minister of Climate, Energy and Environment may, taking into consideration the severity and frequency of a violation, increase or reduce the surcharge under paragraph (1) by up to one-half. Provided, That even where the surcharge is increased, the total amount shall not exceed KRW 20 million. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
[Wholly Amended Sep. 3, 1999]
Article 18-2 (Imposition and Payment of Surcharges) (1) When the Minister of Climate, Energy and Environment intends to impose a surcharge pursuant to Article 15(3) of the Act, the Minister shall notify the person liable for payment in writing, specifying the type of violation, the amount of the surcharge, and other relevant matters. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
(2) Any person who receives a notice to pay a surcharge under paragraph (1) shall pay the surcharge to the designated receiving institution within 20 days. <Amended Dec. 12, 2023>
(3) The receiving institution that receives payment of a surcharge pursuant to paragraph (2) shall issue a receipt to the payer.
(4) When a receiving institution collects a surcharge pursuant to paragraph (2), it shall promptly notify the Minister of Climate, Energy and Environment of that fact. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
[This Article was newly established on Sep. 3, 1999.]
Article 18-3 (Criteria for Calculating Contributions and Method of Imposition, etc.) (1) The contribution under Article 16-2(1) of the Act shall be calculated by multiplying the chargeable unit for each use by the standard unit price per unit.
(2) Where a business operator intends to impose a contribution on a user pursuant to Article 16-2(1) of the Act, the business operator shall notify the user in writing of the amount of the contribution, the details of its calculation, the method of payment, and the payment deadline.
(3) A user who objects to a contribution payment notice under paragraph (2) may file an objection with the business operator, and the business operator shall notify the user who filed the objection of the result within 20 days from the date of receipt of the objection.
(4) Where a user fails to pay the contribution under paragraph (2) in full by the payment deadline, the business operator shall calculate and collect a late payment charge equal to 25/100,000 of the overdue contribution for each day of delay.
[This Article Newly Inserted Aug. 8, 2025]
Article 19 (Matters to Be Included in Supply Regulations) Supply regulations under Article 17(1) of the Act shall include the following matters. <Amended Aug. 8, 2025>
1. Supply area
2. Types of supply
3. Temperature and pressure of the supplied heat or voltage and frequency of the supplied electricity
4. Fees
5. Share of construction costs for supply facilities pursuant to Article 16-2 , Paragraph 1 of the Act
6. In cases other than Subparagraphs 4 and 5 where the user under Article 2, Subparagraph 4 of the Act (hereinafter referred to as the “User”) bears any burden, the details thereof and the amount or method of determining the amount thereof
7. Method of measuring supplied heat/heat quantity or supplied power/electricity quantity and method of adjusting charges
8. The demarcation point of responsibility for the supply of integrated energy.
9. Where restrictions are imposed on the method of using integrated energy or on the use of machinery, equipment, etc., the details of such restrictions.
10. In addition to the matters under subparagraphs 1 through 9, where there are matters concerning the conditions for supplying integrated energy or the responsibilities of the business operator and users, the details of such matters.
11. Effective Date
Article 20 (Reporting of Supply Regulations, etc.) Any person who intends to report supply regulations or a change thereto pursuant to Article 17(1) of the Act shall submit a report in Form No. 13 attached hereto, together with the following documents, to the Minister of Climate, Energy and Environment. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Jan. 21, 2022; Aug. 8, 2025; Oct. 1, 2025>
1. Draft Supply Regulations
2. Explanatory statement regarding the basis for calculation or method of determining fees or other amounts borne by the user, and projected statements of income and expenditure for each fiscal year for five years following the effective date of the supply regulations
3. Where the applicant intends to amend the supply regulations, a statement of reasons for the amendment.
4. Where the basis for calculating charges or the method of determining other amounts borne by users is to be amended, an explanatory statement regarding the amendment and projected income and expenditure statements for each fiscal year for five years after the effective date of the amended supply regulations.
[Title amended Sep. 3, 1999]
Article 20-2 Deleted <Mar. 25, 2011>
Article 21 (Matters to be Included in Contract for Supply) A contract for supply pursuant to the provisions of Article 19, Paragraph 1 of the Act shall include the following matters:
1. Fees and Calculation Method
2. Temperature, pressure, and other supply conditions of the heat supplied
3. Matters concerning the responsibilities of the contracting parties and the method of bearing costs for work related to the supply of heat
[Wholly Amended Sep. 3, 1999]
Article 22 (Business Operators Subject to the Obligation to Accumulate Construction Costs for Supply Facilities, etc.) (1) Business operators required to accumulate, as construction costs for supply facilities, an amount equivalent to the depreciation expenses for supply facilities acquired with amounts contributed by users pursuant to Article 20-3(1) of the Act (hereinafter referred to as “depreciation expenses for supply facilities”) shall be those whose fees collected from users include such depreciation expenses. <Amended Aug. 8, 2025>
(2) Where the undistributed retained earnings of a business operator under paragraph (1) for the relevant business year are less than the depreciation expenses for supply facilities, the business operator may carry over the shortfall and accumulate it as undistributed retained earnings for the following business year.
[This Article was newly established on Feb. 19, 2002.]
Article 23 Deleted <September 3, 1999>
Article 24 Deleted <September 3, 1999>
Article 25 (Application for Approval of Construction Plans, etc.) (1) The term “construction prescribed by Ordinance of the Ministry of Climate, Energy and Environment” in Article 22(1) of the Act refers to construction specified in the column for matters requiring approval in Attached Table 4. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
(2) Any person who intends to obtain approval or amended approval of a construction plan pursuant to Article 22(1) of the Act shall submit an application for approval in Form No. 16 attached hereto, together with the following documents, to the Minister of Climate, Energy and Environment. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
1. Document outlining the project overview
2. Construction Plan
3. Where the construction plan for which approval is sought includes any matter falling under the subparagraphs of Article 49(1) of the Act, the documents required when applying for permits, licenses, etc. or requesting consultation under each relevant Act.
4. Where the construction plan is to be amended, a statement of reasons for the amendment.
5. Deleted <September 3, 1999>
(3) The construction plan referred to in paragraph (2)2 shall include the particulars and supporting documents specified in Attached Table 5.
Article 26 (Reporting of Minor Works, etc.) (1) The term “minor works prescribed by Ordinance of the Ministry of Climate, Energy and Environment” in Article 22(2) of the Act refers to works specified in the column for matters to be reported in Attached Table 4. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
(2) Any person who intends to report minor works, disaster recovery works, or other urgent works pursuant to Article 22(2) of the Act shall submit a report in Form No. 17 attached hereto, together with a statement of the details of the works, to the Minister of Climate, Energy and Environment. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
(3) The statement of the details of the works referred to in paragraph (2) shall include the particulars and supporting documents specified in Attached Table 5.
Article 27 Deleted <September 3, 1999>
Article 28 (Subjects of Pre-use Inspection, etc.) ① Supply facilities subject to inspection pursuant to the provisions of the main text of Article 23, Paragraph 1 of the Act (hereinafter referred to as “pre-use inspection”) shall be supply facilities excluding those listed in each of the following subparagraphs. <Amended Mar. 25, 2011>
1. Equipment subject to inspection pursuant to Article 39 of the Energy Use Rationalization Act
2. Heat supply facilities subject to self-inspection pursuant to the provisions of Paragraph 2
② The facilities subject to self-inspection pursuant to the proviso of Article 23, Paragraph 1 of the Act (hereinafter referred to as “self-inspection”) are as follows:
1. Heat supply facilities resulting from disaster recovery work or other urgent installation or modification work
2. Facilities under subparagraph 1(f) and subparagraph 2(c) of Article 2.
3. Heat supply facilities used temporarily for testing
4. Heat supply facilities used temporarily due to the special need to test other heat supply facilities
(3) Where a business operator conducts a self-inspection of the heat supply facilities referred to in paragraph (2)1, 3, or 4, the business operator shall submit the inspection records to the Korea Energy Agency under Article 45 of the Energy Use Rationalization Act (hereinafter referred to as the “Korea Energy Agency”). Provided, That this shall not apply where the facilities have undergone a pre-use inspection by the Korea Energy Agency. <Amended Mar. 25, 2011; Aug. 5, 2020>
[Wholly Amended Sep. 3, 1999]
Article 29 (Timing of Pre-use Inspection) The timing for receiving a pre-use inspection is as follows: <Amended Sep. 3, 1999; Aug. 5, 2020>
1. In the case of construction of heat source facilities, when commissioning can be performed
2. In the case of construction of heat transport facilities, welding inspections, hydrostatic pressure tests, and insulation-thickness inspections shall be conducted for each zone or section when possible; provided, That where heat transport facilities are to be buried underground, such inspections shall be conducted before burial at a location designated by the Korea Energy Agency.
Article 30 (Application for Pre-use Inspection) Any person who intends to undergo a pre-use inspection shall submit an application for inspection in Form No. 19 attached hereto, together with the documents prescribed by the Minister of Climate, Energy and Environment, to the Korea Energy Agency. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Aug. 5, 2020; Oct. 1, 2025>
Article 31 (Subjects of Periodic Inspection) Heat supply facilities subject to inspection pursuant to the provisions of Article 23, Paragraph 3 of the Act (hereinafter referred to as “periodic inspection”) shall be heat supply facilities operated and maintained by a business operator. However, equipment subject to inspection under Article 39 of the Energy Rationalization Act shall be excluded. <Amended Sep. 3, 1999; Mar. 25, 2011>
Article 32 (Application for Periodic Inspection) (1) Any person who intends to undergo a periodic inspection shall submit an application for inspection in Form No. 20 attached hereto, together with the documents prescribed by the Minister of Climate, Energy and Environment, to the Korea Energy Agency. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Aug. 5, 2020; Oct. 1, 2025>
② An application for inspection pursuant to the provisions of Paragraph 1 must be made at least 20 days before the expiration of the validity period pursuant to the provisions of Article 33 .
Article 33 (Validity Period of Inspection) ① The validity period of pre-use inspections and self-inspections shall be one year. <Amended Sep. 3, 1999>
② The validity period of a periodic inspection shall be one year. However, in cases falling under any of the following subparagraphs, the Korea Energy Agency may determine a separate validity period. <Amended Sep. 3, 1999; Aug. 5, 2020>
1. Cases where it is deemed difficult to conduct an inspection due to a disaster or other unavoidable circumstances
2. Cases where it is deemed unnecessary to conduct regular inspections in light of the situation in which the facility is used as a heat supply facility for emergencies
Article 34 (Standards for Inspection, etc.) The standards and methods for pre-use inspections, periodic inspections, and self-inspections shall be as follows: <Amended June 21, 1993; September 3, 1999; March 3, 2008; March 23, 2013; October 1, 2025>
1. The heat supply facility shall comply with the technical standards under Article 21 of the Act .
2. Heat source facilities and heat transport facilities shall be inspected separately, and the inspection shall be conducted in accordance with the methods prescribed by the Minister of Climate, Energy and Environment to ensure the safety of heat supply facilities.
Article 35 (Issuance of Inspection Certificates, etc.) (1) An inspection certificate under Article 23(4) of the Act shall be issued in Form No. 21 attached hereto.
(2) The Korea Energy Agency shall notify the applicant of the inspection results in Form No. 22 attached hereto where heat supply facilities fail an inspection under Article 23(1) or (3) of the Act, and shall report that fact to the Minister of Climate, Energy and Environment. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Aug. 5, 2020; Oct. 1, 2025>
(3) An application for reinspection of heat supply facilities that have failed an inspection shall be made using Form No. 19 or Form No. 20 attached hereto, as applicable.
Article 36 (Safety Diagnosis Agencies) (1) The term “agency prescribed by Ordinance of the Ministry of Climate, Energy and Environment” in Article 23-2(1) of the Act refers to any of the following agencies. <Amended Oct. 1, 2025>
1. Korea Energy Agency
2. An institution designated by the Minister of Climate, Energy and Environment that possesses the personnel, equipment, and capital necessary for safety inspections.
(2) The requirements and procedures for designating a safety diagnosis agency under paragraph (1)2, and other necessary matters, shall be determined and publicly notified by the Minister of Climate, Energy and Environment. <Amended Oct. 1, 2025>
[This Article Newly Inserted Aug. 5, 2020]
Article 37 (Inspection of Heat-using Facilities) (1) When a business operator inspects a facility for the use of heat (hereinafter referred to as a “heat-using facility”) pursuant to Article 25(1) of the Act, the business operator may request the user to submit the following documents.
1. Documents specifying the equipment specifications of the heat-using facility and its installation drawings.
2. Instruction Manual for Operation Control Equipment
3. Other documents deemed necessary for the inspection
(2) A business operator shall record the following matters concerning inspections conducted pursuant to Article 25(1) of the Act and retain those records for three years. <Amended Sep. 3, 1999>
1. Name of the user (in the case of a corporation, its name and the name of its representative) and address
2. Date of inspection
3. Results of inspection
4. Deleted <September 3, 1999>
5. Deleted <September 3, 1999>
6. Name of the inspector
(3) A business operator shall issue to the user an inspection completion certificate in Form No. 23 attached hereto for any heat-using facility that has passed an inspection pursuant to Article 25(1) of the Act.
Article 38 (Inspection Standards, etc.) The standards for inspections under Article 25(1) of the Act shall be the technical standards under Article 21 of the Act, and the methods, procedures, and other necessary matters for inspections shall be determined by the business operator.
Article 39 (Matters to be Included in Safety Management Regulations) The safety management regulations pursuant to Article 27, Paragraph 1 of the Act shall include the following matters: <Amended Sep. 3, 1999>
1. Matters concerning the duties of persons engaged in work related to the construction, maintenance, or operation of heat supply facilities and the organizations responsible for such work
2. Matters concerning persons performing safety management duties for each workplace of supply facilities
3. Matters concerning safety training for persons engaged in the construction, maintenance, and operation of heat supply facilities
4. Matters concerning inspections, checks, and other examinations for safety management regarding the construction, maintenance, and operation of heat supply facilities, and records thereof
5. Matters concerning the operation of heat supply facilities and prevention of hazards
6. Matters concerning preservation methods in the event that the operation of heat supply facilities is suspended for a considerable period
7. Matters concerning the method of heat transmission pipe construction
8. Matters concerning the designation of the site manager for heat transmission pipe construction and the site safety management system
9. Matters concerning the protection and operation of heat transmission pipes when other construction is underway in the vicinity of the location where the heat transmission pipes are installed
10. Matters concerning measures to be taken in the event of a disaster or other emergency
11. Matters concerning measures against violators in cases where persons engaged in the construction, maintenance, and operation of heat supply facilities violate safety management regulations
12. Matters necessary for safety management regarding the construction, maintenance, and operation of other heat supply facilities
Article 40 (Reporting of Safety Management Regulations, etc.) (1) Any person who intends to report safety management regulations or a change thereto pursuant to Article 27(1) of the Act shall submit a report in Form No. 24 attached hereto, together with the following documents, to the Minister of Climate, Energy and Environment. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
1. Safety Management Regulations
2. Where the safety management regulations are amended, a statement of reasons for the amendment.
② Records regarding the implementation of safety management regulations shall be preserved for two years.
Article 41 Deleted <September 3, 1999>
Article 42 Deleted <September 3, 1999>
Article 43 (Electrical Facilities among Integrated Energy Facilities Subject to Safety Management under the Electric Power Business Act) In Article 48(2) of the Act, the term “electrical facilities prescribed by Ordinance of the Ministry of Climate, Energy and Environment” refers to turbines, generators, and transmission and distribution facilities. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
[Title amended Sep. 3, 1999]
Article 44 Deleted <September 3, 1999>
Article 45 (Fees) (1) Inspection fees under Article 52 of the Act shall be determined and publicly notified by the Minister of Climate, Energy and Environment, taking into account all costs required for inspection, including material costs and labor costs. <Amended Jun. 21, 1993; Sep. 3, 1999; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
② The fees under Paragraph 1 shall be paid to the Korea Energy Agency in cash. However, the Head of the Korea Energy Agency may allow such payment to be made by means of electronic money, electronic payment, etc., using an information and communications network. <Amended Feb. 2, 2005; Aug. 5, 2020>
③ If the Minister of Climate, Energy and Environment intends to determine the fees pursuant to Paragraph 1, he/she shall post the details thereon on the internet homepage of the Ministry of Climate, Energy and Environment for 30 days so as to collect opinions from interested parties. <Newly added Mar. 25, 2011; Mar. 23, 2013; Oct. 1, 2025>
④ When the Minister of Climate, Energy and Environment has determined the amount of the fee pursuant to Paragraph 1, he/she shall disclose said amount through the internet homepage of the Ministry of Climate, Energy and Environment. <Newly added Mar. 25, 2011; Mar. 23, 2013; Oct. 1, 2025>
Article 46 (Reporting on Results of Processing Entrusted Affairs) (1) A report on the results of processing entrusted affairs under Article 31 of the Enforcement Decree shall be made in Form No. 29 attached hereto.
② The report referred to in Paragraph 1 must be made by January 31 of the following year.
Article 47 (Review of Regulations) The Minister of Climate, Energy and Environment shall review the validity of each of the following matters every two years, based on the reference date specified for each matter (meaning until the day preceding the date corresponding to the reference date in every second year), and shall take measures such as improvement. <Amended Oct. 1, 2025>
1. Documents to be submitted with an application for a business license under Article 7(1) and (2), and particulars to be included in the business plan: January 1, 2015.
2. Matters requiring an amended license under Article 8 and documents to be submitted with an application for an amended license: January 1, 2015.
3. Documents to be submitted when reporting succession to an integrated energy business under Article 12: January 1, 2015.
4. Documents to be submitted when reporting supply regulations or amendments thereto under Article 20: January 1, 2015.
5. Works requiring approval of a construction plan under Article 25, and documents to be submitted when applying for approval or amended approval of a construction plan: January 1, 2015.
6. Documents to be submitted when reporting safety management regulations or amendments thereto under Article 40, and the period for retaining records: January 1, 2015.
[This Article Newly Inserted Dec. 31, 2014]
ADDENDA <Ministry of Energy and Resources Decree No. 126, June 15, 1992>
① (Enforcement Date) This rule shall take effect on June 15, 1992.
② (Transitional Measures concerning Reports on the Selection of Contractors for Heat Supply Facilities) A business operator who, at the time this Rule enters into force, has submitted a report on the appointment of a construction supervisor for heat supply facilities pursuant to Article 62 of the former Enforcement Rule of the Energy Use Rationalization Act shall be deemed to have filed a report on the selection of a contractor for heat supply facilities under Article 27(3).
③ (Transitional Measures concerning Fees) Until a public notice under Article 45(1) is issued, inspection fees shall be governed by the former Energy Use Rationalization Act.
ADDENDA <Ministry of Commerce, Industry and Energy Decree No. 9, June 21, 1993>
① (Enforcement Date) This rule shall take effect on the date of its promulgation.
② (Transitional Measures concerning Amended Business Licenses, etc.) Applications for an amended business license or amended approval filed under the former provisions before this Rule enters into force shall be governed by the former provisions.
ADDENDA <Ministry of Commerce, Industry and Energy Decree No. 88, Sep. 3, 1999>
① (Enforcement Date) This rule shall take effect on the date of its promulgation.
② (Applicability to Self-Inspection) The amended provisions of Article 28, Paragraph 2 shall apply to heat supply facilities installed for the first time after the enforcement of this Rule.
③ (Transitional measures regarding forms) Forms used under the previous regulations at the time of enforcement of this rule may be used together with the forms under this rule for three months from the date of enforcement of this rule.
ADDENDA <Ministry of Commerce, Industry and Energy Decree No. 155, Feb. 19, 2002>
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of Commerce, Industry and Energy Decree No. 254, Feb. 2, 2005> (Partial Amendment to the Enforcement Rules of the Act on Measurement, etc. for the Processing of Electronic Civil Petitions)
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of Commerce, Industry and Energy Decree No. 378, Dec. 13, 2006>
① (Enforcement Date) This rule shall take effect on the date of its promulgation.
② (Applicability to the Processing Period for Applications for Approval or Amended Approval of Construction Plans) The amended provisions concerning Form No. 16 shall apply to the first application for approval or amended approval of a construction plan filed after this Rule enters into force.
ADDENDA <Ministry of Knowledge Economy Decree No. 1, Mar. 3, 2008> (Enforcement Rule of the Organizational Structure of the Ministry of Knowledge Economy and Its Affiliated Agencies)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation.
Articles 2 through 4 omitted
Article 5 (Amendment of Other Laws) ① through <55> Omitted
<56> The Enforcement Rule of the Integrated Energy Supply Act is partially amended as follows.
In Article 20-2(1)1 and Article 20-2(5), “Ministry of Commerce, Industry and Energy” shall each be changed to “Ministry of Knowledge Economy.”
In the main text of Article 3(1) and (2), Article 4(1) and (2), the main text of Article 5(1), Article 5(2) and (3), the main text of Article 7(1), Article 7(3) and (4), the main text of Article 8(2), the main text of Article 9, Article 10(1), the main text of Article 10(2), the main text of Article 12, the main text of Article 15, the main text of Article 16, Article 17, the main text of Article 18(2), Article 18-2(1) and (4), the main text of Article 20, the main text of Article 25(2), Article 26(2), Article 30, Article 32(1), subparagraph 2 of Article 34, Article 35(2), the main text of Article 40(1), and Article 45(1), (3) and (4), the term “Minister of Commerce, Industry and Energy” shall each be changed to “Minister of Knowledge Economy.”
In Article 25(1), Article 26(1), and Article 43, “Ordinance of the Ministry of Commerce, Industry and Energy” shall each be changed to “Ordinance of the Ministry of Knowledge Economy.”
In Article 20-2(1), “Vice Minister of Commerce, Industry and Energy” shall be changed to “Vice Minister of Knowledge Economy.”
In Article 20-2(1)1 and (2), “Ministry of Finance and Economy” shall each be changed to “Ministry of Strategy and Finance.”
In Article 20-2(1)2, “Minister of Finance and Economy” shall be changed to “Minister of Strategy and Finance.”
<57> through <64> omitted
ADDENDA <Ministry of Knowledge Economy Decree No. 50, Dec. 31, 2008>
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of Knowledge Economy Decree No. 105, Nov. 26, 2009> (Enforcement Rule of the Act on Promotion of Small and Medium Enterprises)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation.
Article 2 (Amendment of Other Laws) ① and ② Omitted
③ The Enforcement Rules of the Collective Energy Business Act are partially amended as follows.
In Attached Table 2, the term “pursuant to Article 20(1) of the Act on the Promotion of Small and Medium Enterprises and Encouragement of Purchase of Their Products” in subparagraph 3(d) of the column titled “Development Projects Subject to Consultation” and in the column titled “Timing of Requests for Consultation” shall each be changed to “pursuant to Article 20(1) of the Act on the Promotion of Small and Medium Enterprises.”
ADDENDA <Ministry of Knowledge Economy Decree No. 178, Mar. 25, 2011>
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of Knowledge Economy Decree No. 271, Oct. 5, 2012> (Partial Amendment to the Enforcement Rules of the Act on Weights and Measures, etc. for the Improvement of Legal Forms)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation.
Article 2 (Transitional Measures Concerning the Revision of Forms) Forms in accordance with the previous regulations at the time of the enforcement of this Rule shall continue to be used, provided that the parts revised pursuant to this Rule are modified and used.
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 1, Mar. 23, 2013> (Enforcement Rule of the Organizational Structure of the Ministry of Trade, Industry and Energy and its Affiliated Agencies)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation. <Proviso Omitted>
Articles 2 through 6 omitted
Article 7 (Amendment of Other Laws) ① through <55> Omitted
<56> The Enforcement Rule of the Integrated Energy Supply Act is partially amended as follows.
In the main text of Article 3(1) and (2), Article 4(1) and (2), the main text of Article 5(1), Article 5(2) and (3), the main text of Article 7(1), Article 7(3) and (4), the main text of Article 8(2), the main text of Article 9, Article 10(1), the main text of Article 10(2), the main text of Article 12, the main text of Article 15, the main text of Article 16, Article 17, the main text of Article 18(2), Article 18-2(1) and (4), the main text of Article 20, the main text of Article 25(2), Article 26(2), Article 30, Article 32(1), subparagraph 2 of Article 34, Article 35(2), the main text of Article 40(1), and Article 45(1), (3) and (4), “Minister of Knowledge Economy” shall each be changed to “Minister of Trade, Industry and Energy.”
In Article 25(1), Article 26(1), and Article 43, “Ordinance of the Ministry of Knowledge Economy” shall each be changed to “Ordinance of the Ministry of Trade, Industry and Energy.”
In Article 45(3) and (4), “Ministry of Knowledge Economy” shall each be changed to “Ministry of Trade, Industry and Energy.”
In Forms No. 1 through No. 4, the front page of Form No. 5, Form No. 7, Forms No. 10 through No. 13, Form No. 16, Form No. 17, Form No. 19, Form No. 20, and Form No. 24, “Minister of Knowledge Economy” shall each be changed to “Minister of Trade, Industry and Energy.”
In Forms No. 1 through No. 4, Form No. 7, Form No. 10, Form No. 11, Form No. 13, Form No. 16, Form No. 17, and Form No. 24, “Ministry of Knowledge Economy” shall each be changed to “Ministry of Trade, Industry and Energy.”
<57> through <63> omitted
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 106, Dec. 31, 2014> (Partial Amendment to the Enforcement Rules of the High Pressure Gas Safety Management Act, etc. for Regulatory Reform, Including Setting Regulatory Review Periods)
This rule shall take effect on January 1, 2015.
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 159, Oct. 13, 2015>
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 223, Nov. 18, 2016>
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 387, Aug. 5, 2020>
This rule will take effect on August 5, 2020.
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 448, Jan. 21, 2022> (Partial Amendment to 36 Ministry of Trade, Industry and Energy Decrees, including the Enforcement Rule of the High-Pressure Gas Safety Management Act)
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 533, Dec. 12, 2023> (Ministry of Trade, Industry and Energy Decree on the Partial Amendment of 7 Laws, Including the Enforcement Rule of the Weights and Measures Act, for the Revision of Regulations on Administrative Surcharges, etc.)
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 577, Oct. 28, 2024>
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of Trade, Industry and Energy Decree No. 612, Aug. 8, 2025>
This rule will take effect on August 28, 2025.
ADDENDA <Ordinance of the Ministry of Climate, Energy and Environment No. 1, October 1, 2025> (Enforcement Rule of the Organizational Structure of the Ministry of Climate, Energy and Environment and Its Affiliated Agencies)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation. However, among the Ministerial Ordinances amended pursuant to Article 6 of the Addenda, the parts amending Ministerial Ordinances that were promulgated prior to the enforcement of this Rule but whose effective date has not yet arrived shall enter into force on the respective effective dates of those Ordinances.
Articles 2 through 5 omitted
Article 6 (Amendment of Other Laws) ① through <71> Omitted
<72> The Enforcement Rule of the Integrated Energy Supply Act is partially amended as follows.
In the main text of Article 3(1) and (2), Article 4(1) and (2), the main text of Article 5(1), Article 5(2) and (3), the main text of Article 7(1), the first and second sentences of Article 7(3), Article 7(4), the main text of Article 8(2), the main text of Article 9, Article 10(1), the main text of Article 10(2), the main text of Article 12, the main text of Article 15, the main text of Article 16, Article 17, the main text of Article 18(2), Article 18-2(1) and (4), the main text of Article 20, the main text of Article 25(2), Article 26(2), Article 30, Article 32(1), subparagraph 2 of Article 34, Article 35(2), Article 36(1)2 and (2), the main text of Article 40(1), Article 45(1), (3) and (4), and the main text of Article 47, “Minister of Trade, Industry and Energy” shall each be changed to “Minister of Climate, Energy and Environment.”
In Article 25(1), Article 26(1), the main text of Article 36(1), and Article 43, “Ordinance of the Ministry of Trade, Industry and Energy” shall each be changed to “Ordinance of the Ministry of Climate, Energy and Environment.”
In Article 45(3) and (4), “Ministry of Trade, Industry and Energy” shall each be changed to “Ministry of Climate, Energy and Environment.”
In Forms No. 1 through No. 4, the front of Form No. 5, Form No. 7, Forms No. 10 through No. 13, Form No. 16, Form No. 17, the attached documents and fee sections of Form No. 19, the attached documents and fee sections of Form No. 20, and Form No. 24, “Minister of Trade, Industry and Energy” shall be changed to “Minister of Climate, Energy and Environment”.
In the processing procedure section of Form No. 1, Form No. 2, Form No. 3, Form No. 4, Form No. 7, Form No. 10, Form No. 11, Form No. 13, Form No. 16, Form No. 17, and Form No. 24, “Ministry of Trade, Industry and Energy” shall be changed to “Ministry of Climate, Energy and Environment”.
<73> through <98> omitted
[Attached Table 1] Materials to Be Submitted with a Request for Consultation on the Feasibility of Supplying Integrated Energy (Related to Article 3)
[Attached Table 2] Timing of Requests for Consultation on the Feasibility of Supplying Integrated Energy (Related to Article 3(3))
[Attached Table 3] Particulars and Supporting Documents Required for a Business Plan (Related to Article 7(2) and Article 8(3))
[Attached Table 3-2] Types of Violations Subject to Surcharges and Amounts of Surcharges (Related to Article 18(1))
[Attached Table 4] Matters for Approval or Notification of Construction Plan (Change) (Related to Article 25, Paragraph 1 and Article 26, Paragraph 1)
[Attached Table 5] Required Information and Attached Documents for Application for Approval or Notification of Construction Plan (Change) (Related to Article 25, Paragraph 3 and Article 26, Paragraph 3)
[Form No. 1] Application for a Permit (New Establishment, Re-establishment, or Extension) or an Amended Permit for Heat Production Facilities
[Form No. 2] Application for a Business License for an Integrated Energy Business
[Form No. 3] Application for an Amended Business License for an Integrated Energy Business
[Form No. 4] Report on Changes to Matters Covered by an Integrated Energy Business License
[Form No. 5] Integrated Energy Business (Business License, Amended Business License)
[Form No. 7] Report on Succession to an Integrated Energy Business
[Form No. 10] Application for Permission to Suspend or Close an Integrated Energy Business
[Form No. 11] Application for Approval of Dissolution of a Corporation
[Form No. 12] Report on Resumption of Business
[Form No. 13] Supply Regulations (Report, Report of Amendment)
[Form No. 16] Application for Approval or Amended Approval of a Construction Plan
[Form No. 17] Report on Minor Works, etc.
[Form No. 19] Application for Pre-use Inspection
[Form No. 20] Application for Periodic Inspection
[Form No. 21] Inspection Certificate for Heat Supply Facilities
[Form No. 22] Notice of Failure (Pre-use Inspection, Periodic Inspection)
[Form No. 23] Inspection Completion Certificate
[Form No. 24] Safety Management Regulations (Report, Report of Amendment)
[Form No. 29] Report on the Results of Entrusted Affairs Processing