Article 1 (Purpose) The purpose of this Rule is to prescribe matters delegated by the Oil Pipeline Safety Control Act and the Enforcement Decree of the same Act, as well as matters necessary for the implementation thereof. <Amended Dec. 16, 2021>
Article 2 (Subjects of Approval for Construction Plans, etc.) ① Installation works for oil pipelines requiring approval of a construction plan pursuant to the provisions of the main clause of Article 3, Paragraph 1 of the Oil Pipeline Safety Control Act (hereinafter referred to as the “Act”) are as follows: <Amended Sep. 28, 2002; Dec. 16, 2021>
1. Installation work for oil pipelines (including pipe joints and valves; hereinafter the same applies)
2. Installation work for storage tanks
3. Installation work for oil supply booster pumps
4. Installation work for cathodic protection equipment, operating status monitoring devices, and pressure safety devices
5. Installation work for buildings or structures necessary for the operation of the oil pipeline
② In the proviso to Article 3, Paragraph 1 of the Act , the term “minor work prescribed by the Ordinance of the Ministry of Trade and Industry” refers to work involving the additional installation of an operating status monitoring device or a pressure safety device on an oil pipeline, or the alteration of their location. <Amended Sep. 28, 2002; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
③ Minor changes to construction plans subject to reporting pursuant to the proviso of Article 3 , Paragraph 3 of the Act are as follows: <Amended Sep. 28, 2002>
1. Change within the range of one-tenth of the length of the oil pipeline
2. Changes within the range of one-tenth of the storage tank capacity
3. Change within the range of one-tenth of the oil supply booster pump capacity (based on flow rate)
4. Change in the type and location of the operating status monitoring device or pressure safety device
5. Changes within the scope of one-tenth of the total floor area of buildings or structures necessary for the operation of the oil pipeline
Article 3 (Application for Approval of Construction Plan, etc.) ① A person who intends to obtain approval for a construction plan for oil pipeline installation work or a change thereof pursuant to the provisions of the main clause of Article 3, Paragraph 1 and the main clause of Paragraph 3 of the Act shall submit an application in the form of Annex No. 1, attached with the documents set forth in each of the following subparagraphs, to the Minister of Trade and Industry. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
1. Construction plan and attached documents prepared in accordance with the instructions in Attached Table 1
2. Construction Schedule
3. Documents stating the reason for the change (limited to cases where the construction plan is changed)
② When the Minister of Trade and Industry grants an authorization pursuant to the provisions of the main clause of Article 3, Paragraph 1 of the Act , or grants an authorization for change pursuant to the provisions of the main clause of Article 3, Paragraph 3 of the Act , he/she shall issue an authorization or an authorization for change in the form of attached Form No. 1-2. <Newly added Sep. 28, 2002; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
[Title amended Sep. 28, 2002]
Article 4 (Notification of Construction Plan, etc.) ① Any person who intends to report oil pipeline installation work pursuant to the provisions of the proviso to Article 3, Paragraph 1 of the Act shall submit a report in the form of Annex No. 2, attached with a statement of reasons for the work, to the Minister of Trade and Industry within 30 days after the completion of work requiring urgency, such as disaster recovery work, and before the commencement of work for other works. <Amended Sep. 28, 2002; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
② Any person who intends to report a change to minor matters of a construction plan pursuant to the provisions of the proviso to Article 3, Paragraph 3 of the Act shall submit a report in the form of Annex 2 to the Minister of Trade and Industry. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
③ When the Minister of Trade and Industry receives a report pursuant to the proviso of Article 3, Paragraph 1 of the Act or a report of change pursuant to the proviso of Article 3, Paragraph 3 of the Act , he /she shall issue a Certificate of Report or a Certificate of Report of Change in the form of Annex 2-2 . <Newly added Sep. 28, 2002; Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
Article 5 (Technical Standards for Oil Pipeline Installation Works) The technical standards for oil pipeline installation works pursuant to the provisions of Article 3, Paragraph 2 of the Act are as follows:
1. General Technical Standards for Oil Pipeline Installation Works: Appendix 2
2. Technical Standards for Seismic Design of Oil Pipeline Installation Works: Appendix 2-2
[Wholly Amended Sep. 28, 2002]
Article 6 (Review of Construction Plan) The Korea Gas Safety Corporation (hereinafter referred to as the “Corporation”) pursuant to Article 28 of the High Pressure Gas Safety Management Act shall, upon receiving a request for review of a construction plan pursuant to Article 3, Paragraph 1 of the Enforcement Decree of the Oil Pipeline Safety Control Act (hereinafter referred to as the “Decree”), prepare a written opinion on the review and submit it to the Minister of Trade and Industry within 30 days. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
Article 7 (Application for Completion Inspection, etc.) ① When an oil pipeline installer intends to undergo a completion inspection pursuant to the provisions of Article 5, Paragraph 1 of the Act , he/she shall submit an application for inspection in the form of Annex 3 to the Minister of Trade and Industry. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
② Any person who wishes to undergo an inspection for use pursuant to the provisions of Article 5, Paragraph 3 of the Act shall submit an application in the form of Annex 3 to the Minister of Trade and Industry, attaching a statement of reasons for intending to use a portion of the oil pipeline. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
Article 8 (Methods of Completion Inspection and Use Inspection, etc.) ① The timing and methods of completion inspection and use inspection pursuant to the provisions of Article 5 , Paragraph 1 and Paragraph 3 of the Act shall be as set forth in Attached Table 3 .
② The Minister of Trade and Industry shall issue a Certificate of Inspection in the form of Annex 4 to any person who has passed the completion inspection and the use inspection . <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
Article 9 (Application for Authorization of Safety Management Regulations, etc.) ① When an oil pipeline installer or oil pipeline manager (hereinafter referred to as “Oil Pipeline Installer, etc.”) intends to obtain authorization for safety management regulations pursuant to the provisions of the first part of Article 6, Paragraph 1 of the Act , they shall submit an application for authorization in the form of Annex No. 5 , attaching a draft of the safety management regulations, to the Minister of Trade and Industry. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
② When an oil pipeline installer, etc. intends to obtain authorization for a change to safety management regulations pursuant to the provisions of the latter part of Article 6, Paragraph 1 of the Act , they shall submit an application for authorization for change in the form of Annex 5 to the Minister of Trade and Industry, attaching the documents set forth in each of the following subparagraphs. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
1. Proposed Amendment to Safety Management Regulations
2. Statement of Reason for Change
Article 10 (Review of Safety Management Regulations, etc.) When the Corporation receives a request for a review of safety management regulations pursuant to Article 3, Paragraph 2 of the Enforcement Decree, it shall review whether the draft safety management regulations in question comply with the standards set forth in Annex 4 , and then prepare a written opinion on the review and submit it to the Minister of Trade and Industry within 15 days from the date of receiving the request. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
Article 11 (Verification of Compliance with Safety Management Regulations) The Minister of Trade and Industry shall verify compliance with safety management regulations pursuant to Article 6 , Paragraph 3 of the Act when conducting a safety inspection pursuant to Article 8 of the Act . <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
Article 12 (Reporting of Appointment of Safety Manager, etc.) ① The appointment period for a successor safety manager pursuant to the provisions of Article 7, Paragraph 2 of the Act shall be within 30 days from the date the predecessor is dismissed or retires.
② In Article 7, Paragraph 3 of the Act , the term “period prescribed by the Ordinance of the Ministry of Trade and Industry” means 15 days. <Amended Mar. 23, 2013; Oct. 1, 2025>
③ The report on the appointment of a safety manager pursuant to the provisions of Article 7, Paragraph 3 of the Act shall be in accordance with Form No. 6 of the Attached Form .
Article 13 (Duties of Safety Manager) A safety manager shall record the details of safety management duties performed in accordance with the provisions of Article 5 of the Enforcement Decree and maintain and preserve them for one year after the end of the fiscal year.
Article 14 (Subjects, Standards, and Methods, etc. of Safety Inspection) ① The subjects and periods of safety inspection pursuant to Article 8, Paragraph 1 of the Act shall be as follows: <Amended Oct. 1, 2025>
1. Subjects of Safety Inspection: Oil pipeline piping, safety equipment, and storage tanks
2. Safety Inspection Period: To be received every two years starting from the year of completion inspection. However, in the following cases, safety inspections may be conducted at any time.
a. In the event of an accident at an oil pipeline facility
b. In the event that any other cause determined by the Minister of Trade and Industry occurs
② The standards for safety inspections pursuant to Article 8 , Paragraph 1 of the Act are as set forth in Table 5 .
③ In the year in which a safety inspection is required under the main text of Paragraph 1, Subparagraph 2, if a detailed safety diagnosis under Article 8-2 of the Act is received, it shall be deemed that a safety inspection has been received.
[Wholly revised Dec. 16, 2021]
Article 15 (Procedure for Safety Inspection) ① When an oil pipeline installer, etc. intends to undergo a safety inspection pursuant to the provisions of Article 8, Paragraph 1 of the Act , they shall submit an application for safety inspection in the form of Annex 7 to the Minister of Trade and Industry. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
② The Minister of Trade and Industry shall issue a Certificate of Inspection in the form of Annex 4 to any person who has passed the safety inspection . <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
③ The Minister of Trade and Industry shall notify any person who has failed a safety inspection of the reasons for failure and the matters to be improved without delay. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
④ An oil pipeline installer, etc. who has received a notice of non-compliance pursuant to the provisions of Paragraph 3 shall improve the oil pipeline facilities and submit an application for re-inspection to the Minister of Trade and Industry within two months from the date of receiving the notice. <Amended Mar. 3, 2008; Mar. 23, 2013; Oct. 1, 2025>
Article 15-2 (Subjects, Standards, and Methods, etc., of Detailed Safety Diagnosis) ① In Article 8-2, Paragraph 1 of the Act , the term “oil pipeline prescribed by the Ordinance of the Ministry of Trade and Industry” refers to an oil pipeline for which 15 years or more have elapsed since the date on which the initial inspection certificate was received pursuant to Article 8 , Paragraph 2. <Amended Oct. 1, 2025>
② The timing of the precise safety diagnosis pursuant to Article 8-2, Paragraph 1 of the Act (hereinafter referred to as “precise safety diagnosis”) shall be as follows:
1. Initial Detailed Safety Diagnosis: The year in which 15 years have elapsed from the date the initial inspection certificate was received pursuant to Article 8, Paragraph 2.
2. Regular Detailed Safety Diagnosis: Every five years from the year in which the detailed safety diagnosis under Item 1 was received.
3. In cases where a detailed safety diagnosis cannot be conducted at the times specified in Subparagraphs 1 and 2 due to unavoidable reasons regarding pipeline operations: a time adjusted by the Korea Gas Safety Corporation
③ Specific standards and methods for detailed safety diagnosis pursuant to Article 8-2 , Paragraph 1 of the Act are as set forth in Table 7 .
[This Article Newly Inserted Dec. 16, 2021]
Article 15-3 (Procedures for Detailed Safety Diagnosis, etc.) ① Any person who intends to undergo a detailed safety diagnosis pursuant to Article 8-2, Paragraph 1 of the Act shall submit to the Korea Gas Safety Corporation, by attaching a detailed safety diagnosis plan to the application for a detailed safety diagnosis in Form No. 7-2 of the attached document, no later than 60 days before the date on which the detailed safety diagnosis is to be performed.
② Pursuant to Article 8-2, Paragraph 2 of the Act , the Korea Gas Safety Corporation shall report the results to the Minister of Trade and Industry within 30 days from the date the precise safety diagnosis is completed and notify the person who received the precise safety diagnosis. <Amended Oct. 1, 2025>
③ An oil pipeline installer, etc. who has received an order for measures pursuant to Article 8-2, Paragraph 3 of the Act shall take the measures set forth in each of the following subparagraphs. <Amended Oct. 1, 2025>
1. Prepare a plan of action and submit it to the Minister of Trade and Industry within 30 days from the date of receiving the order to take action.
2. After completing the measures pursuant to the action plan under Subparagraph 1, prepare a report on the results of the measures and submit it to the Minister of Trade and Industry and the Korea Gas Safety Corporation.
[This Article Newly Inserted Dec. 16, 2021]
Article 16 (Reporting on the Status of Appointment of Safety Managers) In reporting to the Minister of Trade and Industry the results of the processing of duties entrusted to the Corporation pursuant to the provisions of Article 6, Paragraph 2 of the Enforcement Decree, matters concerning the receipt of notifications regarding the appointment of safety managers shall be reported in accordance with Form No. 8 attached hereto within 10 days after the end of each half-year period . < Amended Mar. 3 , 2008; Mar. 23, 2013; Oct. 1, 2025>
Article 16-2 (Review of Regulations) The Minister of Trade and Industry shall review the validity of documents submitted at the time of an application for authorization regarding a construction plan or its modification pursuant to Article 3 every two years, starting from January 1, 2015 (meaning before January 1 of every second year), and take measures such as improvements. <Amended Oct. 1, 2025>
[This Article Newly Inserted Dec. 31, 2014]
Article 17 (Procedures for Collection of Administrative Fines) The Rules on the Handling of Revenue Collection Officers' Affairs shall apply mutatis mutandis to the procedures for the collection of administrative fines pursuant to the provisions of Article 7, Paragraph 4 of the Enforcement Decree. In this case, the notice of payment shall include the method of objection and the period for objection, etc.
ADDENDA <Ordinance of the Ministry of Commerce, Industry and Energy No. 82, Aug. 9, 1999>
① (Enforcement Date) This rule shall take effect on August 9, 1999.
② (Applicability to changes in facility standards) The amended provisions of Annex 2, item 2 (h) (2) of Annex 2 shall apply to oil pipeline facilities installed for the first time after the enforcement of this rule.
③ (Contents of Facility Management Plan) The matters to be included in the facility management plan pursuant to the provisions of Article 2, Paragraph 2 of the Addenda to the Act are as set forth in Attached Table 6.
④ (Review of Facility Management Plan) When the Corporation receives a request for review of a facility management plan pursuant to Article 2 of the Addenda to the Enforcement Decree, it shall prepare a review opinion within two months and submit it to the Minister of Commerce, Industry and Energy.
ADDENDA <Ordinance of the Ministry of Commerce, Industry and Energy No. 182, Sep. 28, 2002>
① (Enforcement Date) This Rule shall enter into force on the date of its promulgation. However, the amended provisions of Annex 2 and Annex 2-2 shall enter into force six months after the date of promulgation.
② (Applicability to the authorization of oil pipeline installation work) The amended provisions of Article 2, Paragraph 1, Item 5 shall apply to the installation work of a building or structure carried out for the first time after the enforcement of this rule.
③ (Applicability of technical standards for oil pipeline installation work) The amended provisions of Annex 2 (excluding subparagraph k of item 3) and Annex 2-2 shall apply to oil pipeline installation work and modification work carried out for the first time after the enforcement of this Rule. However, for modification work on oil pipelines installed before the enforcement of this Rule, where the length of the oil pipeline subject to modification work is 2 kilometers or less, the previous provisions shall apply.
④ (Transitional measures concerning the installation of seismic measuring instruments) For oil pipelines installed under the previous regulations at the time of enforcement of this rule that do not comply with the amended provisions of Item 3, Subparagraph k of Annex 2, seismic measuring instruments must be installed and operated in compliance with the amended provisions of Item 3, Subparagraph k of Annex 2 by the date six months have elapsed since the promulgation.
ADDENDA <Ordinance of the Ministry of Knowledge Economy No. 1, Mar. 3, 2008> (Enforcement Rule of the Organizational Structure of the Ministry of Knowledge Economy and Its Affiliated Agencies)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation.
Articles 2 through 4 omitted
Article 5 (Amendment of Other Laws) ① through ㉕ Omitted
㉖ The Enforcement Rules of the Oil Pipeline Safety Control Act are partially amended as follows.
In Article 2, Paragraph 2, “Ordinance of the Ministry of Commerce, Industry and Energy” shall be changed to “Ordinance of the Ministry of Knowledge Economy.”
In Article 3, Paragraphs 1 and 2; Article 4, Paragraphs 1, 2, and 3; Article 6; Article 7, Paragraphs 1 and 2; Article 8, Paragraph 2; Article 9, Paragraphs 1 and 2; Article 10; Article 11; Article 12, Paragraph 2; the proviso to Article 14, Subparagraph 3; Article 15, Paragraphs 1, 2, 3, and 4; and Article 16, “Minister of Commerce, Industry and Energy” shall be changed to “Minister of Knowledge Economy”.
Sections 27 through <64> omitted
ADDENDA <Ordinance of the Ministry of Knowledge Economy No. 271, Oct. 5, 2012> (Partial Amendment to the Enforcement Rules of the Act on Weights and Measures, etc. for the Improvement of Legal Forms)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation.
Article 2 (Transitional Measures Concerning the Revision of Forms) Forms in accordance with the previous regulations at the time of the enforcement of this Rule shall continue to be used, provided that the parts revised pursuant to this Rule are modified and used.
ADDENDA <Ordinance of the Ministry of Trade, Industry and Energy No. 1, Mar. 23, 2013> (Enforcement Rule of the Organizational Structure of the Ministry of Trade, Industry and Energy and its Affiliated Agencies)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation. <Proviso Omitted>
Articles 2 through 6 omitted
Article 7 (Amendment of Other Laws) ① through ㉘ omitted
㉙ Part of the Enforcement Rules of the Oil Pipeline Safety Control Act is amended as follows.
In Article 2, Paragraph 2, “Ordinance of the Ministry of Knowledge Economy” shall be changed to “Ordinance of the Ministry of Trade, Industry and Energy”.
In Article 3, Paragraph 1 (excluding the subparagraphs), Paragraph 2 of the same article, Paragraphs 1 through 3 of Article 4, Article 6, Paragraphs 1 and 2 of Article 7, Paragraph 2 of Article 8, Paragraph 1 of Article 9, Paragraph 2 (excluding the subparagraphs of the same article), Article 10, Article 11, the proviso to Subparagraph 3 of Article 14, Paragraphs 1 through 4 of Article 15, and Article 16, “Minister of Knowledge Economy” shall be changed to “Minister of Trade, Industry and Energy”.
In Article 12, Paragraph 2, “Ordinance of the Ministry of Commerce, Industry and Energy” shall be changed to “Ordinance of the Ministry of Trade, Industry and Energy.”
In Annex 2, item 3 (k) (2) (b), “Minister of Commerce, Industry and Energy” shall be changed to “Minister of Trade, Industry and Energy”.
In the first and second parts of Subparagraph 2(b) of Annex 3, “Minister of Commerce, Industry and Energy” shall be changed to “Minister of Trade, Industry and Energy” respectively.
In Form No. 1, Form No. 1-2, Form No. 2, Form No. 2-2, and Form No. 5, “Minister of Knowledge Economy” shall be changed to “Minister of Trade, Industry and Energy”.
In Forms No. 1, No. 2, and No. 5, “Ministry of Knowledge Economy” shall be changed to “Ministry of Trade, Industry and Energy”.
In Form No. 8 of the Attached Appendix, “Minister of Commerce, Industry and Energy” shall be changed to “Minister of Trade, Industry and Energy.”
Sections 30 through 63 are omitted.
ADDENDA <Ordinance of the Ministry of Trade, Industry and Energy No. 76, Aug. 4, 2014>
This rule shall take effect from the date of its promulgation.
ADDENDA <Ordinance of the Ministry of Trade, Industry and Energy No. 106, Dec. 31, 2014> (Partial Amendment to the Enforcement Rules of the High Pressure Gas Safety Management Act, etc. for Regulatory Reform, Including Setting Regulatory Review Periods)
This rule shall take effect on January 1, 2015.
ADDENDA <Ordinance of the Ministry of Trade, Industry and Energy No. 444, Dec. 16, 2021>
Article 1 (Enforcement Date) This rule shall enter into force on December 16, 2021.
Article 2 (Special provisions regarding the timing of detailed safety diagnoses) ① Pipeline installers, etc. managing oil pipelines for which the timing of the initial detailed safety diagnosis pursuant to the amended provisions of Article 15-2, Paragraph 2, Subparagraph 1 has passed at the time of enforcement of this Rule shall undergo a detailed safety inspection by December 16, 2026, in consultation with the Korea Gas Safety Corporation.
② An oil pipeline that has undergone a detailed safety diagnosis pursuant to Paragraph 1 shall be deemed to have undergone the initial detailed safety inspection pursuant to Article 15-2, Paragraph 2, Subparagraph 1.
Article 3 (Transitional Measures concerning Seismic Design Standards for Oil Pipeline Installation Works) Oil pipelines of oil pipeline installers who received authorization or filed a report in accordance with the former regulations at the time of the enforcement of this Rule shall be subject to the former regulations notwithstanding the amended provisions of Annex 2-2.
ADDENDA <Ordinance of the Ministry of Trade, Industry and Energy No. 448, Jan. 21, 2022> (Partial Amendment to 36 Ministry of Trade, Industry and Energy Decrees, including the Enforcement Rule of the High-Pressure Gas Safety Management Act)
This rule shall take effect from the date of its promulgation.
ADDENDA <Ordinance of the Ministry of Trade and Industry No. 1, Oct. 1, 2025> (Enforcement Rule of the Organizational Structure of the Ministry of Trade and Industry and Its Affiliated Agencies)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation. However, among the Ministerial Ordinances amended pursuant to Article 5 of the Addenda, the parts amending Ministerial Ordinances that were promulgated prior to the enforcement of this Rule but whose effective date has not yet arrived shall enter into force on the effective date of said Ministerial Ordinance.
Articles 2 through 4 omitted
Article 5 (Amendment of Other Laws) ① through ㉚ Omitted
31. The Enforcement Rules of the Oil Pipeline Safety Control Act are partially amended as follows.
In Article 2, Paragraph 2, Article 12, Paragraph 2, and Article 15-2, Paragraph 1, “Ordinance of the Ministry of Trade, Industry and Energy” shall be changed to “Ordinance of the Ministry of Trade and Industry”.
In Article 3, Paragraph 1 (excluding the subparagraphs), Paragraph 2 of the same article, Paragraphs 1 through 3 of Article 4, Article 6, Paragraphs 1 and 2 of Article 7, Paragraph 2 of Article 8, Paragraph 1 of Article 9, Paragraph 2 (excluding the subparagraphs of the same article), Article 10, Article 11, Article 14, Paragraph 1, Subparagraph 2 (b), Article 15, Paragraphs 1 through 4, Article 15-3, Paragraph 2, Subparagraphs 1 and 2 of Paragraph 3 of the same article, Article 16, and Article 16-2, “Minister of Trade, Industry and Energy” shall be changed to “Minister of Trade and Industry”.
In Annex 2, Item 3, Subparagraph k (2)(b), Annex 3, Subparagraph 2, Subparagraph b, the latter part, and Annex 7, Item 4, proviso, “Minister of Trade, Industry and Energy” shall be changed to “Minister of Trade and Industry”.
In Form No. 1, Form No. 1-2, Form No. 2, Form No. 2-2, Form No. 5, and Form No. 8, “Minister of Trade, Industry and Energy” shall be changed to “Minister of Trade and Industry”.
In the processing procedure section of Form No. 1, Form No. 2, and Form No. 5, “Ministry of Trade, Industry and Energy” shall be changed to “Ministry of Trade and Industry”.
Sections 32 through <54> omitted
[Annex 1] Guidelines for Preparing Construction Plans and Attached Documents (Related to Article 3, Item 1)
[Annex 2] General Technical Standards for Oil Pipeline Installation Works (Related to Article 5, Item 1)
[Annex 2-2] Technical Standards for Seismic Design of Oil Pipeline Installation Works (Related to Article 5, Subparagraph 2)
[Annex 3] Timing and Method of Completion Inspection and Use Inspection (Related to Article 8, Paragraph 1)
[Annex 4] Contents of Safety Management Regulations [Related to Article 10, Paragraph 1]
[Annex 5] Standards for Safety Inspection (Related to Article 14, Paragraph 2)
[Annex 6] Contents of the Facility Management Plan (Related to Paragraph 3 of the Addendum)
[Annex 7] Standards and Methods for Precision Safety Diagnosis of Oil Pipelines, etc. (Related to Article 15-2, Paragraph 3)
[Attachment Form No. 1] Application for Oil Pipeline Installation Construction Plan (Approval, Modification Approval)
[Attachment Form No. 1-2] Oil Pipeline Installation Construction Plan (Authorization, Authorization for Change)
[Attachment Form No. 2] Oil Pipeline Installation Construction Plan (Notification, Change Notification)
[Attachment Form No. 2-2] Certificate of Oil Pipeline Installation Construction Plan (Notification, Change Notification)
[Attachment Form No. 3] Application for (Completion Inspection, Use Inspection)
[Attachment Form No. 4] Certificate of Inspection (Completion, Use, Safety)
[Attachment Form No. 5] Application for Safety Management Regulations (Authorization, Authorization for Change)
[Attachment Form No. 6] Report on Appointment of Safety Manager
[Attachment Form No. 7] Application for Safety Inspection
[Attached Form No. 7-2] Application for Detailed Safety Diagnosis
[Attachment Form No. 8] Report on the Appointment of Safety Managers