소프트웨어 진흥법 시행규칙
271031 · 2025-04-30
Ministry of Science and ICT ( Software Policy Division ), 044-202-6324
Ministry of Science and ICT ( Software Industry Division ), 044-202-6334
Article 1 (Purpose) The purpose of this rule is to prescribe matters delegated by the Software Promotion Act and the Enforcement Decree of the same Act , and matters necessary for the implementation thereof.
Article 2 (Application for Designation of Software Promotion Facility, etc.) ① The application form for designation of a software promotion facility pursuant to Article 9, Paragraph 2 of the Enforcement Decree of the Software Promotion Act (hereinafter referred to as the “Decree”) is as in Form No. 1 of the Attached Form .
② The Minister of Science and ICT, upon receiving an application for designation as a software promotion facility pursuant to Article 9, Paragraph 2 of the Enforcement Decree, shall verify the documents listed in each of the following subparagraphs through the joint use of administrative information pursuant to Article 36, Paragraph 1 of the Electronic Government Act . However, if the applicant (including local governments; hereinafter the same applies in this Article and Article 3 ) does not consent to the verification, the relevant documents must be attached.
1. Land (Forest) Register and Building Register
2. Certificate of Corporate Registration and Certificate of Building Registration
③ When the Minister of Science and ICT designates a software promotion facility pursuant to Article 11, Paragraph 3 of the Software Promotion Act (hereinafter referred to as the “Act”), he/she shall issue a software promotion facility designation certificate in the form of Annex 2 to the applicant.
④ The provisions of Paragraphs 1 through 3 shall apply mutatis mutandis to the change of designation of a software promotion facility. In this case, the “application for designation” shall be deemed the “application for change of designation.”
Article 3 (Application for Designation of Software Promotion Complex, etc.) ① The application form for designation of a software promotion complex pursuant to Article 12, Paragraph 2 of the Enforcement Decree shall be in accordance with Form No. 3 of the Attached Form .
② The Minister of Science and ICT, upon receiving an application for designation of a software promotion complex pursuant to Article 12, Paragraph 2 of the Enforcement Decree, shall verify the documents listed in each of the following subparagraphs through the joint use of administrative information pursuant to Article 36, Paragraph 1 of the Electronic Government Act . However, if the applicant does not consent to the verification, the relevant documents must be attached.
1. Land (Forest) Register, Building Register, and Land Use Planning Information
2. Certificate of Corporate Registration, Certificate of Building Registration, and Certificate of Land Registration
③ When the Minister of Science and ICT designates a software promotion complex pursuant to Article 12, Paragraph 1 of the Act , he/she shall issue a software promotion complex designation certificate in the form of Annex 4 to the applicant.
④ The provisions of Paragraphs 1 through 3 shall apply mutatis mutandis to the change of designation of a Software Promotion Complex. In this case, the “application for designation” shall be deemed the “application for change of designation.”
Article 4 (Application Procedure for Software Quality Certification) Pursuant to Article 15, Paragraph 1 of the Enforcement Decree, any person who intends to apply for software quality certification pursuant to Article 20, Paragraph 1 of the Act (hereinafter referred to as “software quality certification”) shall submit the software quality certification application form in Annex 5, along with the documents specified in each of the following subparagraphs and the software to be certified, to the head of the software quality certification body pursuant to Article 20, Paragraph 2 of the Act (hereinafter referred to as the “software quality certification body”).
1. Product Description
2. User Manual
3. Other documents required for software quality certification as determined and announced by the Minister of Science and ICT
Article 5 (Software Quality Certification Grades and Quality Certification Marks) ① Software quality certification grades are classified into Grade 1 and Grade 2.
② The software quality certification marks pursuant to Article 15 , Paragraph 2 of the Enforcement Decree are as shown in Attached Table 1 .
Article 6 (Issuance of Software Quality Certification, etc.) ① When the head of a software quality certification body receives an application for software quality certification pursuant to Article 4, if he or she recognizes that the software meets the software quality certification standards pursuant to Article 17 of the Enforcement Decree , he or she shall issue a software quality certification certificate in Attached Form No. 6 to the applicant.
② If the head of a software quality certification body receives an application for software quality certification pursuant to Article 4 and determines that the software does not meet the software quality certification standards pursuant to Article 17 of the Enforcement Decree , he/she shall notify the applicant of the results and details in writing.
Article 7 (Procedures for Designation of Software Quality Certification Institutions, etc.) ① Any person who intends to be designated as a software quality certification institution pursuant to Article 20, Paragraph 2 of the Act shall submit to the Minister of Science and ICT an application for designation as a software quality certification institution in the form of Annex 7 , attaching the documents listed in each of the following subparagraphs.
1. Specifications and operational plan regarding organization, professional personnel, testing facilities, technical capabilities, and certification procedures
2. Documents proving that the requirements of each subparagraph of Article 16 , Paragraph 1 of the Enforcement Decree and the detailed designation requirements for software quality certification bodies in Annex 2 have been met
② The Minister of Science and ICT who receives the application pursuant to Paragraph 1 shall verify the certificate of corporate registration through the joint use of administrative information pursuant to Article 36, Paragraph 1 of the Electronic Government Act .
③ If a software quality certification body intends to change software quality certification business, such as the software field subject to certification, it must submit an application for change of software quality certification business in the form of Annex 8 to the Minister of Science and ICT, attaching the documents specified in each subparagraph of Paragraph 1.
④ The matters that the Minister of Science and ICT must announce pursuant to Article 16, Paragraph 2 of the Enforcement Decree are as follows:
1. Name and address of the software quality certification body
2. Fields of Software Subject to Certification and Quality Certification Grades
3. Date of designation or date of revocation of designation of the software quality certification body
Article 8 (Application Procedure for Software Process Quality Certification) ① Any person who intends to apply for software process quality certification pursuant to Article 21, Paragraph 1 of the Act pursuant to Article 18, Paragraph 1 of the Enforcement Decree ( hereinafter referred to as “software process quality certification”) shall submit the application for software process quality certification in the form of Annex 9, along with a business description including the organizational chart, etc. of the software business operator subject to certification, to the head of the software quality certification body pursuant to Article 21, Paragraph 2 of the Act (hereinafter referred to as the “software process quality certification body”).
② The head of the software process quality certification body that receives the application form pursuant to Paragraph 1 shall verify the business registration certificate through the joint use of administrative information pursuant to Article 36, Paragraph 2 of the Electronic Government Act . However, if the applicant does not consent to the verification, the relevant documents must be attached.
Article 9 (Software Process Quality Certification Grades and Quality Certification Marks) ① Software process quality certification grades shall be classified from Grade 1 to Grade 3. <Amended Apr. 30, 2025>
② The software process quality certification mark pursuant to Article 18 , Paragraph 5 of the Enforcement Decree is as set forth in Attached Table 3. <Amended Oct. 17, 2023>
Article 10 (Issuance of Software Process Quality Certification, etc.) ① If the head of a software process quality certification body recognizes that a software business operator who has applied for software process quality certification pursuant to Article 8, Paragraph 1 satisfies the software process quality certification standards pursuant to Article 20, Paragraph 1 of the Enforcement Decree , he/she shall issue a software process quality certification in the form of Annex 10 to the applicant.
② If the head of a software process quality certification body determines that a software business operator who has applied for software process quality certification pursuant to Article 8 , Paragraph 1 does not meet the software process quality certification standards pursuant to Article 20, Paragraph 1 of the Enforcement Decree , he/she shall notify the applicant of the results and details in writing.
③ Any person who intends to extend the validity period of software process quality certification pursuant to Article 18 , Paragraph 2 of the Enforcement Decree shall submit an application for extension of the software process quality certification validity period in the form of Annex 11 to the head of the software process quality certification body, attaching performance data regarding activities carried out to maintain and improve software process quality. <Amended Oct. 17, 2023>
④ The head of the software process quality certification body that receives the application form pursuant to Paragraph 3 shall verify the business registration certificate through the joint use of administrative information pursuant to Article 36, Paragraph 2 of the Electronic Government Act . However, if the applicant does not consent to the verification, the business registration certificate must be attached.
Article 11 (Procedures for Designation of Software Process Quality Certification Institutions, etc.) ① Any person who wishes to be designated as a software process quality certification institution shall submit to the Minister of Science and ICT an application for designation as a software process quality certification institution in the form of Annex 12 , attaching the documents listed in each of the following subparagraphs.
1. Specifications and operational plan regarding organization, professional personnel, technical capabilities, and certification procedures
2. Documents proving that the requirements of each subparagraph of Article 19 , Paragraph 1 of the Enforcement Decree and the detailed designation requirements for software process quality certification bodies set forth in Annex 4 have been met
② The Minister of Science and ICT who receives the application for designation under Paragraph 1 shall verify the certificate of corporate registration through the joint use of administrative information pursuant to Article 36, Paragraph 1 of the Electronic Government Act .
③ The matters that the Minister of Science and ICT must announce pursuant to Article 19, Paragraph 2 of the Enforcement Decree are as follows:
1. Name and location of the software process quality certification body
2. Date of designation or date of revocation of designation of the software process quality certification body
Article 12 (Procedures for Designation of Software Human Resources Training Institutions, etc.) ① Any person who intends to be designated as a software human resources training institution pursuant to Article 22, Paragraph 2 of the Act (hereinafter referred to as “software human resources training institution”) shall submit to the Minister of Science and ICT an application for designation as a software human resources training institution in the form of Annex 13 , attaching the documents listed in each of the following subparagraphs.
1. Articles of Incorporation
2. Status of Securing Faculty, Support Personnel, Facilities, and Equipment
3. Education plan including curriculum and content
4. Operating Expense Procurement Plan and Grant Usage Plan
5. Education Regulations
② The Minister of Science and ICT who receives the application form under Paragraph 1 shall verify the certificate of corporate registration through the joint use of administrative information pursuant to Article 36, Paragraph 1 of the Electronic Government Act .
③ The Minister of Science and ICT, upon receiving an application pursuant to Paragraph 1, shall verify whether the applicant meets the requirements for designation as a software personnel training institution under Annex 1 related to Article 23 , Paragraph 3 of the Enforcement Decree and issue a certificate of designation as a software personnel training institution in the form of Annex 14 to the applicant.
④ The matters that the Minister of Science and ICT must announce pursuant to Article 23, Paragraph 5 of the Enforcement Decree are as follows:
1. Name and location of designated software workforce training institutions
2. Date of designation or date of revocation of designation of the designated software workforce training institution
⑤ The head of a software personnel training institution shall issue a certificate of completion of education in the form of Annex 15 to persons who have received education and training (including retraining) pursuant to Article 23, Paragraph 1 of the Enforcement Decree .
Article 13 (Procedures for Verification of Software Engineer’s Career, etc.) ① A software engineer who wishes to receive management of records regarding their workplace, career, educational background, qualifications, etc. (hereinafter referred to as “career, etc.”) pursuant to Article 24 of the Act shall submit the following documents attached to the Application for Verification of Software Engineer’s Career, etc. in Form No. 16 of the Appendix to the agency performing maintenance and management duties regarding the software engineer’s career, etc. (hereinafter referred to as the “career management agency”).
1. Certificate of Work Experience ( Form No. 17) and Certificate of Technical Experience ( Form No. 18) confirmed by the Employer (Representative) or the Software Project Ordering Authority
2. National technical qualification certificate or private qualification certificate
3. Documents proving academic background, education, training, and awards
4. Other documents that can objectively prove work experience or changes in work experience
② The career management agency that receives the application form pursuant to Paragraph 1 shall verify the documents in each of the following subparagraphs through the joint use of administrative information pursuant to Article 36, Paragraph 2 of the Electronic Government Act . However, if the applicant does not consent to the verification, the relevant documents must be attached.
1. Certificate of Corporate Registration, Business Registration Certificate, or Certificate of Suspension or Closure
2. Proof of National Pension Subscriber Enrollment or Confirmation of Health Insurance Eligibility
3. Confirmation of National Technical Qualification Acquisition
4. Certificate of Alien Registration
③ The career management agency shall issue a software engineer career certificate in the form of Annex 19 if requested by a software engineer .
④ If a software engineer wishes to correct the contents of a software engineer career certificate issued by a career management agency, they must submit an application for correction of career verification in the form of Annex 20 to the career management agency, attaching documents that can objectively verify the matters to be corrected.
⑤ The fees pursuant to Article 24, Paragraph 4 of the Act are as set forth in Attached Table 5 .
⑥ Detailed matters concerning the maintenance and management of software technician careers, etc. pursuant to the provisions of paragraphs 1 through 5 shall be determined and announced by the Minister of Science and ICT .
Article 14 (Procedures for Approval of Subcontracting, etc.) ① In order for a software business operator to obtain approval from the head of a state agency, etc., for a case of subcontracting or further subcontracting (hereinafter referred to as “re-subcontracting”) pursuant to Article 51 , Paragraph 5 of the Act, the operator shall submit to the head of a state agency, etc., an application for approval of software business subcontracting or further subcontracting contract in the form of Annex 21 , attaching the documents specified in each of the following subparagraphs.
1. Copy of the draft subcontract or sub-subcontract agreement
2. Subcontract or sub-subcontract project execution plan (including subcontract amount calculation statement and project implementation schedule)
3. Self-Assessment Checklist for Determining the Appropriateness of Subcontracting Agreements
② The head of a state agency, etc., who receives an application pursuant to Paragraph 1 shall review the appropriateness of the subcontracting or sub-subcontracting and notify the applicant in writing of whether or not it is approved within 10 days. However, if there are unavoidable reasons, such as the review of appropriateness taking a considerable amount of time, the notification period may be extended only once within the range of 10 days, and the applicant shall be notified of the extended notification period without delay.
③ In order to manage and supervise compliance with subcontracting restriction regulations pursuant to Article 51, Paragraph 7 of the Act, the head of a national agency, etc., may request a software business operator who has received approval for subcontracting or re-subcontracting pursuant to Paragraph 5 of the same Article to submit a report on the status of compliance with software business subcontracting contracts in the form of Annex 22 , attaching the documents listed in each of the following subparagraphs.
1. Copy of the subcontract or sub-subcontract agreement
2. Documents proving compliance with subcontracting or sub-subcontracting contract requirements
④ Detailed matters concerning the approval procedures for subcontracting pursuant to the provisions of paragraphs 1 through 3 shall be determined and announced by the Minister of Science and ICT .
Article 15 (Procedures for Designation of Quality Performance Evaluation Testing Institutions, etc.) ① Any person who intends to be designated as a commercial software quality performance evaluation testing institution pursuant to Article 55, Paragraph 1 of the Act (hereinafter referred to as “Quality Performance Evaluation Testing Institution”) shall submit to the Minister of Science and ICT an application for designation as a software quality performance evaluation testing institution in the form of Annex 23 , attaching the documents listed in each of the following subparagraphs.
1. Documents proving that the requirements for designation as a quality performance evaluation testing institution pursuant to Annex 2 related to Article 49, Paragraph 1 of the Enforcement Decree and Annex 6 of these Rules have been met
2. Articles of Incorporation
3. Status of the institution and operation plan prepared in accordance with the preparation method specified in Attached Table 7
② The Minister of Science and ICT who receives the application form under Paragraph 1 shall verify the certificate of corporate registration through the joint use of administrative information pursuant to Article 36, Paragraph 1 of the Electronic Government Act .
③ The matters that the Minister of Science and ICT must announce pursuant to Article 49, Paragraph 2 of the Enforcement Decree are as follows:
1. Name and location of the designated quality performance evaluation testing institution
2. Fields of software subject to the commercial software quality and performance evaluation test pursuant to Article 55 , Paragraph 1 of the Act (hereinafter referred to as the “quality and performance evaluation test”)
3. Date of designation or date of revocation of designation of the designated quality performance evaluation testing institution
Article 16 (Request for Delegation of Quality Performance Evaluation Tests) In accordance with Article 51, Paragraph 1 of the Enforcement Decree, if the head of a national agency, etc. intends to request the delegation of quality performance evaluation tests, he/she must submit a request for delegation of software quality performance evaluation tests in the form of Annex 24 to the head of the quality performance evaluation test institution.
Article 17 (Management of Performance, etc. of Software Business Operators) ① A software business operator may submit the application for management of general status of a software business operator in the form of Annex No. 25, pursuant to Article 58, Paragraph 1 of the Act, along with the documents listed in each of the following subparagraphs, to an institution performing the duties of maintaining and managing data on performance, etc. of a software business operator pursuant to Paragraph 2 of the same Article and Subparagraph 16 of Article 66, Paragraph 1 of the Enforcement Decree (hereinafter referred to as the “business operator performance management institution”).
1. Certificate of Confirmation of Middle-sized Enterprise ( applicable only if the software business operator is a middle-sized enterprise pursuant to Article 2, Subparagraph 1 of the Special Act on the Promotion of Growth and Strengthening of Competitiveness of Middle-sized Enterprises )
2. Other documents that can objectively prove performance or changes in performance
② The business performance management agency that receives the application form pursuant to Paragraph 1 shall verify the documents in each of the following subparagraphs through the joint use of administrative information pursuant to Article 36, Paragraph 2 of the Electronic Government Act . However, if the applicant does not consent to the verification, the relevant documents must be attached.
1. Certificate of Corporate Registration, Business Registration Certificate, Certificate of Suspension or Closure
2. Certificate of Financial Statements for the most recent year, Certificate of Value Added Tax Assessment Standard (applicable only to software businesses operating as sole proprietorships)
3. Certificate of Confirmation of Small and Medium Enterprise ( applicable only if the software business operator is a small and medium enterprise pursuant to Article 2 of the Framework Act on Small and Medium Enterprises )
③ If a software business operator who submitted an application under paragraph 1 wishes to have records of its performance of software projects maintained and managed, the operator shall submit an Application for Management of Software Project Performance Records in Attached Form No. 26, together with the following documents, to the business operator performance management agency.
1. Contract
2. Documents verifying software project performance
3. Other documents that can objectively prove the performance record of the applied software project
④ The business performance management agency shall issue the Software Business Operator General Status Management Confirmation Form No. 27 and the Software Business Performance Certificate Form No. 28 upon request by the software business operator .
⑤ The fees required for the maintenance and management of data such as performance records of software business operators pursuant to Article 58, Paragraph 2 of the Act are as set forth in Attached Table 8 .
⑥ Detailed matters concerning the maintenance and management of data on software business operator performance, etc., pursuant to the provisions of paragraphs 1 through 5 shall be determined and announced by the Minister of Science and ICT .
ADDENDA <Ministry of Science and ICT Decree No. 62, Dec. 23, 2020>
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation.
Article 2 (Transitional Measures Concerning Software Quality Certification) ① Software that received quality certification pursuant to the former Article 5 prior to December 28, 2015, the effective date of the Partial Amendment to the Enforcement Rules of the Software Industry Promotion Act by Decree No. 55 of the Ministry of Science, ICT and Future Planning, shall be deemed to have received a Grade 1 quality certification pursuant to Article 3-3 of the former Enforcement Rules of the Software Industry Promotion Act.
② Software quality certifications issued in accordance with the former Form No. 7 of the Annex prior to December 28, 2015, the effective date of the Partial Amendment to the Enforcement Rules of the Software Industry Promotion Act by Decree No. 55 of the Ministry of Science, ICT and Future Planning, shall be deemed to be software quality certifications issued in accordance with Form No. 7 of the former Enforcement Rules of the Software Industry Promotion Act (referring to a quality certification with a certification grade of Grade 1).
③ Software quality certificates issued in accordance with Form No. 7 of the former Enforcement Rule of the Software Industry Promotion Act between December 28, 2015 (the enforcement date of Ministry of Science, ICT and Future Planning Decree No. 55 partially amending the Enforcement Rule of the Software Industry Promotion Act) and the day before this Rule entered into force, shall be deemed to be software quality certificates issued in accordance with the amended provisions of Form No. 6.
④ A person who received a software quality certification in accordance with Form No. 7 of the former Enforcement Rule of the Software Industry Promotion Act prior to the enforcement of this Rule may apply to the head of the certification body to have it reissued as a software quality certification in accordance with the amended provisions of Form No. 6.
Article 3 (Transitional Measures Concerning Software Process Quality Certification) ① A software process quality certification issued in accordance with the former Form No. 15 before December 28, 2015, the effective date of the Partial Amendment to the Enforcement Rules of the Software Industry Promotion Act by Decree No. 55 of the Ministry of Science, ICT and Future Planning, shall be deemed to be a software process quality certification issued in accordance with Form No. 15 of the former Enforcement Rules of the Software Industry Promotion Act.
② Software process quality certificates issued in accordance with Form No. 15 of the former Enforcement Rule of the Software Industry Promotion Act between December 28, 2015 (the enforcement date of Ministry of Science, ICT and Future Planning Decree No. 55 partially amending the Enforcement Rule of the Software Industry Promotion Act) and the day before this Rule entered into force, shall be deemed to be software process quality certificates issued in accordance with the amended provisions of Form No. 10.
③ A person who received a software process quality certification in accordance with Form No. 15 of the former Enforcement Rule of the Software Industry Promotion Act prior to the enforcement of this Rule may apply to the head of the software process quality certification body to have it reissued as a software process quality certification in accordance with the amended provisions of Form No. 10.
Article 4 (Transitional Measures Concerning Designation Certificates for Software Personnel Training Institutions) ① Designation certificates for software professional personnel training institutions issued prior to the enforcement of this Rule pursuant to Form No. 3 of the former Enforcement Rule of the Software Industry Promotion Act shall be deemed to be designation certificates for software personnel training institutions issued pursuant to the amended provisions of Form No. 14.
② A software professional training institution that received a designation certificate for software professional training institutions in accordance with Form No. 3 of the former Enforcement Rule of the Software Industry Promotion Act prior to the enforcement of this rule may apply to the Minister of Science and ICT to have it reissued as a designation certificate for software personnel training institutions in accordance with the amended provisions of Form No. 14.
Article 5 (Transitional Measures Concerning Certificates of Completion of Education) ① Certificates of completion of education issued prior to the enforcement of this Rule pursuant to Form No. 4 of the former Enforcement Rule of the Software Industry Promotion Act shall be deemed to be certificates of completion of education issued pursuant to the amended provisions of Form No. 15.
② A person who received a certificate of completion of education in accordance with Form No. 4 of the former Enforcement Rule of the Software Industry Promotion Act before the enforcement of this rule may apply to the head of a software personnel training institution to have the certificate of completion of education reissued in accordance with the amended provisions of Form No. 15.
Article 6 (Transitional Measures Concerning Certificates of Experience for Software Engineers) ① A Certificate of Experience for a Software Engineer issued prior to the enforcement of this Rule pursuant to Form No. 26 of the former Enforcement Rule of the Software Industry Promotion Act shall be deemed to be a Certificate of Experience for a Software Engineer issued pursuant to the amended provisions of Form No. 18.
② A software engineer who received a software engineer career certificate in accordance with Form No. 26 of the former Enforcement Rule of the Software Industry Promotion Act prior to the enforcement of this Rule may apply to the head of the career management agency to have the certificate reissued in accordance with the amended provisions of Form No. 20.
Article 7 (Transitional Measures Concerning Confirmation of General Status Management of Software Business Operators, etc.) ① A Confirmation of Registration of a Software Business Operator issued pursuant to Form No. 18 of the former Enforcement Rule of the Software Industry Promotion Act or a Confirmation of Software Business Performance issued pursuant to Form No. 19 of the same Rule prior to the enforcement of this Rule shall be deemed to be a Confirmation of General Status Management of a Software Business Operator issued pursuant to the amended provisions of Form No. 27 or a Certificate of Software Business Performance issued pursuant to the amended provisions of Form No. 28, respectively.
② Software business operators who received a software business operator registration confirmation certificate in accordance with Form No. 18 of the former Enforcement Rule of the Software Industry Promotion Act or a software business performance confirmation certificate in accordance with Form No. 19 of the same rule before the enforcement of this rule may apply to the head of the business operator performance management agency to have the certificate reissued in accordance with the revised provisions of Form No. 27 of the same rule or the software business performance certificate in accordance with the revised provisions of Form No. 28 of the same rule.
Article 8 (Amendment of Other Laws) Part of the Enforcement Rule of the Emergency Preparedness Resource Management Act under the jurisdiction of the Ministry of Science and ICT is amended as follows.
In Article 4, Paragraph 2, Subparagraph 3, “「Software Industry Promotion Act」” shall be changed to “「Software Promotion Act」”.
Article 9 (Relationship with Other Laws and Regulations) Where, at the time of the enforcement of this Rule, other laws and regulations cite the provisions of the former Enforcement Rule of the Software Industry Promotion Act, and there are corresponding provisions in this Rule, the relevant provisions of this Rule shall be deemed to have been cited in place of the former provisions.
ADDENDA <Ministry of Science and ICT Decree No. 115, Oct. 17, 2023>
This rule will take effect on October 19, 2023.
ADDENDA <Ministry of Science and ICT Decree No. 149, Apr. 30, 2025>
This rule shall take effect from the date of its promulgation.
[Appendix 1] Software Quality Certification Mark (Related to Article 5, Paragraph 2)
[Appendix 2] Detailed Designation Requirements for Software Quality Certification Bodies (Related to Article 7, Paragraph 1, Subparagraph 2)
[Appendix 3] Software Process Quality Certification Mark (Related to Article 9, Paragraph 2)
[Appendix 4] Detailed Designation Requirements for Software Process Quality Certification Bodies (Related to Article 11, Paragraph 1, Subparagraph 2)
[Attached Table 5] Maintenance and Management Fees Regarding Software Technicians' Experience, etc. (Related to Article 13, Paragraph 5)
[Appendix 6] Requirements for Designation of Quality Performance Evaluation Testing Institutions (Related to Article 15, Paragraph 1, Subparagraph 1)
[Attached Table 7] Method for Preparing the Agency Status and Operation Plan (Related to Article 15, Paragraph 1, Subparagraph 3)
[Appendix 8] Fees for Maintenance and Management of Data on Software Business Operator Performance, etc. (Related to Article 17, Paragraph 5)
[Attachment Form No. 1] Application for Software Promotion Facility (Designation, Change of Designation)
[Attachment Form No. 2] Designation of Software Promotion Facility
[Attachment Form No. 3] Application for Software Promotion Complex (Designation, Change of Designation)
[Attachment Form No. 4] Software Promotion Complex Designation Certificate
[Attachment Form No. 5] Software Quality Certification Application
[Attachment Form No. 6] Software Quality Certification Certificate
[Attachment Form No. 7] Application for Designation as a Software Quality Certification Agency
[Attachment Form No. 8] Application for Change of Software Quality Certification Services
[Attachment Form No. 9] Application for Software Process Quality Certification
[Attachment Form No. 10] Software Process Quality Certification Certificate
[Attachment Form No. 11] Application for Extension of Software Process Quality Certification Validity Period
[Attachment Form No. 12] Application for Designation as a Software Process Quality Certification Body
[Attachment Form No. 13] Application for Designation as a Software Manpower Training Institution
[Attachment Form No. 14] Designation Certificate for Software Manpower Training Institution
[Attachment Form No. 15] Certificate of Completion of Training
[Attachment Form No. 16] Application for Verification of Software Engineer Experience, etc. (New, Change)
[Attachment Form No. 17] Certificate of Work Experience
[Attachment Form No. 18] Technical Experience Verification Certificate
[Attachment Form No. 19] Software Engineer Career Certificate
[Attachment Form No. 20] Application for Correction of Career Verification
[Attachment Form No. 21] Application for Approval of Software Business (Subcontracting, Re-subcontracting) Contract
[Attachment Form No. 22] Report on Compliance with Software Business Subcontracting Agreements
[Attachment Form No. 23] Application for Designation as a Software Quality and Performance Evaluation Testing Agency
[Attachment Form No. 24] Request for Performance of Software Quality and Performance Evaluation Testing on Behalf of an Agency
[Attachment Form No. 25] Application for Management of Software Business Operator General Status (New, Change)
[Attachment Form No. 26] Application for Management of Software Project Performance Records (New, Change, Completed)
[Attachment Form No. 27] Confirmation of General Status Management for Software Business Operators
[Attachment Form No. 28] Certificate of Software Project Performance