Article 1 (Purpose) The purpose of this rule is to prescribe matters delegated by the Urban Development Act and the Enforcement Decree of the Urban Development Act, and matters necessary for their implementation.
Article 2 (Roads) In Article 2, Paragraph 1, Subparagraph 2, Item (b) of the Enforcement Decree of the Urban Development Act (hereinafter referred to as the “Decree”), the term “roads prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport” refers to roads falling under Subparagraphs (a) and ( b) of Article 9, Subparagraph 3 of the Rules on the Determination, Structure and Installation Standards of Urban Planning Facilities . <Amended Mar. 23, 2013>
Article 3 (Criteria for Designation of Urban Development Zones) The criteria for designation of urban development zones pursuant to Article 2, Paragraphs 4 and 5 of the Enforcement Decree are as set forth in Table 1 .
Article 4 Deleted <June 30, 2010>
Article 5 (Request for Designation of Urban Development Zone) When a Mayor (excluding the Mayor of a large city with a population of 500,000 or more, excluding Seoul Metropolitan City and a Metropolitan City pursuant to Article 175 of the Local Autonomy Act ; hereinafter referred to as “Mayor of a large city”), County Governor, or District Head (referring to the head of an autonomous district; hereinafter the same applies) requests the designation of an urban development zone pursuant to Article 3, Paragraph 4 of the Urban Development Act (hereinafter referred to as the “Act”), they shall submit a request for designation of an urban development zone in the form of Annex 3 to the Special City Mayor, Metropolitan City Mayor, Provincial Governor, or Special Self-Governing Provincial Governor (hereinafter referred to as the “City/Provincial Governor”), attaching the documents and drawings specified in each of the following subparagraphs. In this case, the City/Provincial Governor shall verify the cadastral map and forest map through the joint use of administrative information pursuant to Article 36, Paragraph 1 of the Electronic Government Act . <Amended Mar. 30, 2012; Apr. 13, 2012; Dec. 29, 2017>
1. Urban Development Zone Survey Form ( Attachment No. 2)
2. Documents regarding land area and consent of land owners pursuant to Article 4, Paragraph 4 of the Act (applicable only to areas where the land reallocation method is applied)
3. Documents concerning the contents of the development plan pursuant to Article 5, Paragraph 1 of the Act . However, in cases where a development plan is established after the designation of an urban development zone pursuant to the proviso to Article 4 , Paragraph 1 of the Act , documents containing the matters specified in each subparagraph of Article 9, Paragraph 1 of the Enforcement Decree and an environmental review report (applicable only to cases where an urban development zone is designated within a green space area or in an area outside an urban area, and in cases where a strategic environmental impact assessment has been conducted pursuant to the Environmental Impact Assessment Act , it refers to the strategic environmental impact assessment report).
4. Documents regarding basic investigation, etc. pursuant to Article 6 of the Act
5. Results of hearing opinions from residents and relevant experts, etc. pursuant to Article 7, Paragraph 1 of the Act and written review opinions thereon
6. Documents regarding land area and landowner's consent pursuant to Article 11 , Paragraph 6 of the Act
7. Location map at a scale of 1:25,000 or 1:50,000
8. Topographic maps with a scale of 1:1,000 to 1:5,000 indicating the boundaries of the urban development zone and documents stating the reasons for establishing the boundaries
9. The results of consultation with the City, County, or District Urban Planning Committee pursuant to Article 113, Paragraph 2 of the Act on Planning and Utilization of National Land and the written review opinion thereon ( excluding cases where consultation with the City, County, or District Urban Planning Committee was not conducted pursuant to the proviso of Article 5 of the Enforcement Decree)
10. Documents necessary for the determination of an urban or county management plan under Article 9 (2) of the Act
11. Survey data on the current status of incorporated farmland and forest land
[Wholly Amended June 30, 2010]
Article 6 (Register of Designated Urban Development Zones) ① A person designating an urban development zone pursuant to Article 3 of the Act (hereinafter referred to as the “designating authority”) shall , when designating an urban development zone pursuant to the same Article, prepare and manage a register of designated urban development zones in the form of Annex 4 .
② The urban development zone designation register referred to in Paragraph 1 shall be prepared and managed using a method that enables electronic processing, unless there is a special reason why electronic processing is impossible.
Article 7 (Consent Forms, etc.) ① The consent form, withdrawal of consent form, and consent form for designation of a representative pursuant to Article 6, Paragraph 6 of the Enforcement Decree shall be in accordance with Forms No. 5 , No. 6 , and No. 7 of the Attached Forms , respectively . <Amended Mar. 30, 2012>
② The withdrawal of consent under paragraph (1) shall be submitted to the implementer or prospective implementer by content-certified mail under Article 25 (1) 4 (a) of the Enforcement Rule of the Postal Service Act.
Article 8 Deleted <December 30, 2011>
Article 9 (Matters to be included in the development plan) The term “matters prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport” in Article 8, Paragraph 1, Subparagraph 14 of the Enforcement Decree refers to the following matters:
1. Elderly Welfare Facility Planning
2. Disaster Prevention Plan
3. Crime Prevention Plan
[Wholly Amended Sep. 10, 2013]
Article 10 (Contents of Basic Survey) In Article 10, Paragraph 1, Subparagraph 6 of the Enforcement Decree, “other matters prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport” refers to the matters in each of the following subparagraphs. <Amended Mar. 23, 2013>
1. Current Status of Cultural Heritage Distribution
2. Current Status of Park and Green Space Distribution
3. Current environmental conditions required for the preparation of the environmental review report (applicable only when designating an urban development zone within a green space area or outside an urban area)
Article 10-2 (Documents to be Submitted Upon Request for Consultation for Designation of Urban Development Zone) In Article 14-2, Paragraph 2 of the Enforcement Decree, the term “documents prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport” refers to the documents and drawings under Article 5 , Subparagraphs 1 , 3, 4 , 5 , and 7 through 11. <Amended Mar. 23, 2013>
[This Article was newly established on June 30, 2010.]
Article 11 (Details of Land) ① In Subparagraph 7 of Article 15, Paragraph 1 of the Enforcement Decree, the term “details of land prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport” refers to matters concerning the location, lot number, land category, area (in cases where part of a single parcel is included in an urban development zone, the total area of the said parcel and the area of the land incorporated into the urban development zone), and the landowner. <Amended Mar. 23, 2013>
② The details of the land pursuant to Paragraph 1 shall be in accordance with Form No. 7-2 of the Attached Form .
[This Article was newly established on March 30, 2012.]
Article 12 (Simplified Structures) In Article 16, Paragraph 3, Subparagraph 1 of the Enforcement Decree, the term “simplified structures prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport” refers to the structures set forth in each of the following subparagraphs. <Amended Mar. 23, 2013>
1. Vinyl greenhouse
2. Sericulture farm
3. Drying facilities for agricultural, forestry, and fishery products such as chili peppers, leaf tobacco, and seaweed
4. Mushroom cultivation facility
5. Seedling nursery
6. Compost bin
7. Threshing ground
8. Other structures similar to those in subparagraphs 1 through 7, designated by the Minister of Land, Infrastructure and Transport and announced in the Official Gazette
Article 13 (Standards for Management Soundness) In Article 18 , Paragraph 4 , Subparagraph 2 , the main text of Paragraph 5 of the Enforcement Decree , and Paragraph 6, Subparagraph 3 of the Enforcement Decree, the term “standards prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport” refers to those that meet the requirements of each of the following subparagraphs. <Amended July 18, 2012; March 23, 2013; October 12, 2021>
1. It must be a corporation that has not incurred a net loss for the relevant year on the income statement disclosed pursuant to Article 23, Paragraph 5 of the Act on External Audits of Corporations, etc., as of the date of application for designation as an urban development project implementer. In this case, if the income statement for the relevant year has not been disclosed, the income statement of the preceding year shall be used.
2. In the case of a trustee, it must be a corporation that has not received necessary measures from the Financial Services Commission to ensure management soundness pursuant to Article 31, Paragraph 4 of the Capital Market and Financial Investment Business Act . However, this shall not apply if measures to ensure management soundness have been completed.
Article 14 (Application for Designation of Implementer, etc.) ① The application for designation of a project implementer pursuant to the main text of Article 19, Paragraph 1 of the Enforcement Decree shall be in accordance with Form No. 8 of the Attached Form .
② The application form pursuant to Paragraph 1 shall be accompanied by the documents and drawings of each of the following subparagraphs.
1. Business Plan
2. Funding Plan
3. Documents that can verify whether it falls under any of the subparagraphs of Article 11, Paragraph 1 of the Act
4. Documents that can verify whether it falls under any of the subparagraphs of Article 11, Paragraph 2 of the Act
5. Bylaws, Articles of Incorporation, or Implementing Regulations
6. Location map at a scale of 1:25,000 or 1:50,000
③ When the designating authority designates an implementer of an urban development project (hereinafter referred to as the “implementer”) pursuant to Article 11, Paragraph 1 of the Act , it shall issue a certificate of designation of implementer in the form of Annex 9 to the applicant and prepare and manage a register of designations of implementer in the form of Annex 10 .
④ Pursuant to Article 11, Paragraph 5 of the Act , if a person falling under Subparagraphs 2 through 11 of Paragraph 1 of the same Article proposes the designation of an urban development zone, the designating authority may designate such proposer as the implementing entity with priority. In this case, among persons falling under Subparagraph 7 of Paragraph 1 of the Act , landowners who are corporations must comply with the standards under Subparagraph 1 of Article 13 .
⑤ Unless there is a special reason why electronic processing is impossible, the register of designated implementers under Paragraph 3 shall be prepared and managed in a manner that enables electronic processing.
Article 15 (Proposal for Designation of Urban Development Zone) A person who intends to propose the designation of an urban development zone pursuant to Article 23, Paragraph 1 of the Enforcement Decree shall submit a proposal for the designation of an urban development zone in the form of Annex 11 , attaching the documents and drawings specified in each of the following subparagraphs, to the Minister of Land, Infrastructure and Transport, the Governor of a Special Self-Governing Province, the Mayor, the County Governor, or the District Head. In this case, the Governor of a Special Self-Governing Province, the Mayor, the County Governor, or the District Head shall verify the cadastral map and forest map through the joint use of administrative information pursuant to Article 36, Paragraph 1 of the Electronic Government Act. <Amended Mar. 26, 2009; June 30, 2010; Mar. 23, 2013>
1. The documents and drawings under Article 5, subparagraphs 1 through 4 and 6 through 8.
2. Deleted <March 26, 2009>
3. Survey data on the current status of incorporated farmland and forest land
Article 16 (Application for Extension of Application Period for Approval of Implementation Plan) If an implementing entity deems it necessary to extend the application period for approval of an implementation plan pursuant to the proviso of Article 24 of the Enforcement Decree, it shall submit an application for extension of the application period for approval of an urban development project implementation plan ( Form No. 12) to the designating authority through the Mayor (excluding the mayor of a large city), County Governor, or District Head, attaching the documents and drawings specified in each of the following subparagraphs. However, if the designating authority is the Minister of Land, Infrastructure and Transport, the Governor of a Special Self-Governing Province, or the mayor of a large city, the application may be submitted directly to the Minister of Land, Infrastructure and Transport, the Governor of a Special Self-Governing Province, or the Mayor of a metropolitan city. <Amended Mar. 23, 2013>
1. Statement of Reasons for Extension of Approval Application Period
2. Location map at a scale of 1:25,000 or 1:50,000
Article 17 (Consent Forms, etc.) The consent forms pursuant to Article 25, Paragraph 2 of the Enforcement Decree shall be in accordance with the classifications in each of the following subparagraphs, and the consent form for withdrawal of consent and the consent form for designation of a representative shall be in accordance with Form No. 6 and Form No. 7 of the Attached Form, respectively.
1. Consent to Designation of Urban Development Project Implementer Pursuant to Article 11, Paragraph 2, Subparagraph 3 of the Act : Form No. 12-2
2. Consent Form for Proposal of Designation of Urban Development Zone Pursuant to Article 11, Paragraph 6 of the Act : Attached Form No. 12-3
[Wholly Amended Mar. 30, 2012]
Article 18 (Rates of entrustment fees) The rates of entrustment fees pursuant to Article 12, Paragraph 3 of the Act are as set forth in Attached Table 2 .
Article 19 (Application for Approval of Trust Agreement) In cases where an implementing entity intends to obtain approval for a trust agreement concerning an urban development project pursuant to Article 28, Paragraph 1 of the Enforcement Decree, it shall submit an application for approval of a trust agreement in the form of Annex 13 to the designating authority, attaching the documents and drawings specified in each of the following subparagraphs. <Amended Dec. 30, 2016>
1. Business Plan
2. Funding Plan
3. Documents verifying whether the requirements under Article 18 , Paragraph 5 of the Enforcement Decree have been met
4. Location Map
Article 19-2 (Consent form for application for approval of establishment of association, etc.) The consent form for the application for approval of establishment of an association pursuant to Article 13 , Paragraph 3 of the Act shall be in accordance with Form No. 13-2 of the Attached Form, and the withdrawal of consent for the said consent and the consent form for the designation of a representative pursuant to Article 32 , Paragraph 3 of the Enforcement Decree shall be in accordance with Form No. 6 of the Attached Form and Form No. 7 of the Attached Form, respectively .
[This Article was newly established on March 30, 2012.]
Article 20 (Application for Approval of Implementation Plan) ① When an implementing entity (excluding cases where the designating authority is the implementing entity) intends to obtain approval for an implementation plan pursuant to Article 17, Paragraph 2 of the Act , it shall submit to the designating authority an application for approval of an urban development project implementation plan in the form of Annex 14, attaching the documents and drawings specified in each of the following subparagraphs. <Amended Dec. 31, 2008; Mar. 30, 2012; Jan. 27, 2016; Dec. 30, 2016; Jan. 21, 2022>
1. Project Cost and Financing Plan (including annual investment plan)
2. Specifications of existing factories or buildings, etc. to be retained
3. Compensation plan (including relocation measures)
4. Business entrustment or trust plan
5. Surveys and drawings of public facilities newly installed or existing public facilities resulting from the implementation of an urban development project ( applicable only where the implementing entity is a person falling under subparagraphs 1 through 4 of Article 11 , Paragraph 1 of the Act )
6. Appraisal reports from two or more appraisal firms, etc. regarding property of the State or a local government whose use is discontinued due to the implementation of an urban development project ( only applicable where the implementing entity is a person falling under subparagraphs 5 through 11 of Article 11 , Paragraph 1 of the Act )
7. A list and drawings of public facilities newly installed as part of an urban development project and a calculation of the installation costs ( only applicable if the implementing entity falls under subparagraphs 5 through 11 of Article 11, Paragraph 1 of the Act ). In this case, if the land required for the installation of the new public facilities and the land on which the existing public facilities are installed are the same land, only the installation costs excluding the land price shall be calculated.
8. Relevant documents and drawings necessary for the determination of the city/county management plan (including district unit plan)
9. Various impact assessment reports, such as environmental impact assessment, traffic impact assessment, and disaster impact assessment
10. Documents required for consultation with the heads of relevant administrative agencies pursuant to Article 19 , Paragraph 2 of the Act
11. Location Map
12. Plan drawings and schematic drawings
② In cases where the designating authority has granted approval for an implementation plan for an urban development project pursuant to Article 17, Paragraph 2 of the Act , it shall prepare and manage the urban development project implementation plan approval register in the form of Annex 15 .
③ The urban development project implementation plan approval register referred to in Paragraph 2 shall be prepared and managed in a manner that enables electronic processing, unless there is a special reason why electronic processing is impossible.
Article 21 (Minor Changes to Implementation Plan) In the proviso to Article 17, Paragraph 4 of the Act , the term “minor matters prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport” refers to the matters set forth in each of the following subparagraphs. <Amended Oct. 15, 2010; Dec. 30, 2011; Mar. 30, 2012; Apr. 13, 2012; Mar. 23, 2013; Oct. 12, 2021>
1. Deleted <December 30, 2011>
2. Deleted <December 30, 2011>
3. Correction of project implementation area due to errors, omissions, etc., within the scope where there is no change in the project implementation area
4. Reduction of area within the range of 10% of the project implementation area
5. Increase or decrease in project costs within the range of 10% of the total project cost
6. Changes in site area, etc., of each of the following items to reflect the results of cadastral surveying pursuant to Article 2, Subparagraph 4 of the Act on the Establishment and Management of Spatial Information, etc.
a. Urban development zone
b. Land designated under the land use plan pursuant to Article 5 (1) 7 of the Act
c. Urban or county planning facilities
7. Change of a city or county management plan (excluding district unit plans) falling under any of the subparagraphs of Article 25, Paragraph 3 of the Enforcement Decree of the National Land Planning and Utilization Act
8. A change to a district unit plan falling under any of the subparagraphs of Article 25, Paragraph 4 of the Enforcement Decree of the National Land Planning and Utilization Act
9. Changes to related permits, licenses, etc. deemed pursuant to Article 19, Paragraph 1 of the Act (limited to cases designated as minor changes in relevant laws and regulations)
Article 22 (Payment of Construction Supervision Fees) When a supervisor pursuant to Article 20, Paragraph 2 of the Act applies for payment of construction supervision fees , the implementing entity shall verify the appropriateness thereof in accordance with the contract concluded between the parties and pay the construction supervision fees. In this case, the implementing entity shall pay the construction supervision fees within 14 days from the date of application.
Article 22-2 (Consent to Use and Expropriation of Land, etc.) The consent to use and expropriation of land pursuant to Article 22 , Paragraph 1 of the Act and Article 44 of the Enforcement Decree shall be in accordance with Form No. 14-2 of the Appendix, and the consent to withdraw consent and the consent to designate a representative shall be in accordance with Form No. 6 and Form No. 7 of the Appendix, respectively .
[This Article was newly established on March 30, 2012.]
Article 23 (Standards for Land Supply by Private Contract) ① In Article 57, Paragraph 3, Subparagraph 3 of the Enforcement Decree, the term “area prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport” refers to 330 square meters. <Amended Mar. 23, 2013; Dec. 29, 2017>
② The standards and area for the supply of developed land by private contract pursuant to Article 57, Paragraph 5, Subparagraph 3 of the Enforcement Decree shall be as set forth in Attached Table 3. However, if the volume of developed land requested for supply exceeds the area planned in the supply plan for developed land, etc. submitted to the designating authority pursuant to Article 26 of the Act , the method of lottery shall apply. <Amended Dec. 29, 2017>
Article 24 (Selection of Special Design Development Implementer) ① In the event that the Implementer solicits applications for persons to be supplied with land by private contract pursuant to Article 57 , Paragraph 5, Subparagraph 6 of the Enforcement Decree (hereinafter referred to as the “Special Design Development Implementer,” including corporations scheduled for establishment), it shall publish the matters of each of the following subparagraphs at least once each in a daily newspaper with nationwide or relevant regional distribution areas and on an internet homepage. In this case, the application period shall be at least 90 days.
1. Current Status of Land Subject to Open Call
2. Eligibility and Competition Schedule
3. Other matters deemed necessary by the implementer
② The implementing entity shall select a special design development implementing entity through an evaluation by the selection review committee. In this case, specific operational measures, such as the distribution of evaluation materials and the method of selecting review committee members, must be established to ensure a fair evaluation.
③ When constituting the Selection Deliberation Committee pursuant to Paragraph 2, the following criteria shall be followed:
1. Members must be experts in their respective fields.
2. At least half of the committee members shall be persons who are not employees of the implementer.
3. It shall be formed on or after the day before the deliberation. However, if the day before the deliberation is a Saturday or a public holiday pursuant to the “Regulations on Public Holidays for Government Offices,” it may be formed on the day before.
④ Other matters necessary for the composition of the selection review committee, evaluation criteria, selection method, conclusion of agreement, etc. shall be determined by the implementing entity, and the evaluation criteria shall be disclosed to the general public.
[Wholly Amended Jan. 31, 2025]
Article 24-2 (Supply of Land to Special Design Development Implementers) When an implementing entity supplies land to a special design development implementer, it shall take into consideration sound urban development and balanced regional development, etc. However, the area of land supplied in commercial areas shall not exceed 50 percent of the total area of commercial areas in the relevant urban development zone (excluding public land that cannot be sold to the general public pursuant to Article 57 , Paragraph 5, Subparagraph 1 of the Enforcement Decree).
[This Article Newly Inserted Jan. 31, 2025]
Article 25 (Supply Price of Developed Land, etc.) In Subparagraph 6 of Article 58, Paragraph 1 of the Enforcement Decree, the phrase “other infrastructure facilities prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport pursuant to Subparagraph 6 of Article 2 of the Act on Planning and Utilization of National Land ” refers to the facilities listed in each of the following subparagraphs that are directly installed by an administrative agency in accordance with the same Act . <Amended Oct. 15, 2010; Mar. 23, 2013>
1. Deleted <June 30, 2010>
2. Market
3. Bus terminal
4. General medical facilities
5. Broadcasting and telecommunications facilities ( limited to facilities directly installed by the State in cases where the implementing entity falls under any of subparagraphs 1 through 4 of Article 11 of the Act )
Article 26 (Contents to be Included in the Land Reallocation Plan) ① The land reallocation design pursuant to Article 28, Paragraph 1, Subparagraph 1 of the Act (hereinafter referred to as the “land reallocation design”) shall be accompanied by a planned land reallocation map with a scale of at least 1:1200, a comparison map before and after reallocation, a map indicating surplus or deficit areas, and a map indicating evaluation unit prices before and after reallocation. <Amended Mar. 30, 2012>
② When preparing the details of land subject to liquidation pursuant to Article 28, Paragraph 1 , Subparagraph 3 of the Act , the implementing agency shall also determine the area of entitlement (hereinafter referred to as “area of entitlement”) pursuant to the latter part of Article 62, Paragraph 1 of the Enforcement Decree , even for land excluded from the scope of land reallocation pursuant to Articles 30 and 31 of the Act . <Amended Mar. 30, 2012>
③ In Article 28, Paragraph 1, Subparagraph 6 of the Act , “matters prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport” refers to the matters in each of the following subparagraphs. <Newly added Mar. 30, 2012; Mar. 23, 2013>
1. Income and Expenditure Plan
2. Average burden rate and proportionality rate and their calculation statements ( limited to cases where land reallocation is designed using the valuation method pursuant to Article 27, Paragraph 3 )
3. Architectural plan (limited to cases where three-dimensional land reallocation is implemented)
4. Results of deliberation by the Land Valuation Council pursuant to Article 28 , Paragraph 3 of the Act
④ The average burden rate and proportionality rate under Paragraph 3, Subparagraph 2 shall be calculated according to the formulas in each of the following subparagraphs. <Newly added Mar. 30, 2012>
1. Average burden rate
2. Proportionality rate
⑤ The value of rights under Paragraph 4, Subparagraph 1 shall be calculated as follows. <Newly added Mar. 30, 2012>
Article 27 (Standards for Land Reallocation Plans) ① When the implementing agencyprepares a land reallocation plan pursuant to Article 28, Paragraph 1 of the Act (hereinafter referred to as the “Land Reallocation Plan”), it shall prepare the plan separately for each land reallocation planning zone (referring to the scope of an urban development zone where an urban development project is implemented using the land reallocation method; and in cases where an urban development zone is divided into two or more project implementation districts pursuant to Article 5, Paragraph 1, Subparagraph 3 of the Act, it refers to each of the divided project implementation districts; hereinafter the same applies), and shall comprehensively consider matters approved for the implementation plan, the degree of urbanization within the land reallocation planning zone, the actual land use status, and economic value, etc. <Amended Mar. 30, 2012>
② The methods of land reallocation shall be classified as follows: <Amended Mar. 30, 2012>
1. Planar Land Reallocation: A method of transferring rights to the land prior to reallocation to land created through an urban development project.
2. Three-dimensional land reallocation: A method of transferring rights to land or buildings prior to reallocation (excluding unauthorized buildings) to subdivided buildings constructed as part of an urban development project, in accordance with Article 32 of the Act .
③ The land reallocation design shall, in principle, follow the appraisal method (referring to a method of determining reallocated land in proportion to the appraised value of land before and after the implementation of an urban development project; hereinafter the same applies); however, in cases where the movement of land resulting from the designation of reallocation is minor or involves simple maintenance of infrastructure, the area method (referring to a method of determining reallocated land based on the land and location prior to the implementation of an urban development project; hereinafter the same applies) may be applied. In such cases, the same method must be applied within a single land reallocation planning zone, and the appraisal method must be applied when implementing three-dimensional land reallocation. <Amended Mar. 30, 2012>
④ The location of the reallocation of land shall be determined by the implementing agency in consideration of the matters in each of the following subparagraphs. In this case, the reallocation of land or buildings must take place within the same land reallocation planning zone. <Amended Mar. 30, 2012>
1. Flat land reallocation: Determined by considering the use, holding period, location, value of rights, and size of liquidation amount of the land prior to reallocation.
2. Three-dimensional land reallocation: This shall be determined upon application by land owners, etc., but if there are two or more applications with the same content, it shall be determined by taking into consideration the holding period of the land or building prior to reallocation, the period of residence (limited to cases where housing is supplied), the value of rights, etc.
⑤ Every parcel of land within the land reallocation planning zone shall either be designated for land reallocation or, if excluded from land reallocation under Articles 30 and 31 of the Act, be subject to monetary settlement. In this case, land falling under any of the following subparagraphs shall be designated as reallocated land for another parcel. <Amended Mar. 30, 2012>
1. Land transferred to the implementing entity free of charge pursuant to Article 66, Paragraphs 1 and 2 of the Act
2. Land owned by the implementing entity (excluding land owned by an implementing entity other than the association for the purpose of receiving land reallocation)
⑥ Land [ including land shares corresponding to land use rights (limited to cases where they are ownership rights) pursuant to Article 2, Subparagraph 6 of the Act on Ownership and Management of Condominium Buildings ] or buildings (including parts of buildings corresponding to divided ownership rights pursuant to Article 2, Subparagraph 1 of the Act on Ownership and Management of Condominium Buildings ) shall be reallocated by parcel and by building. In this case, land and buildings owned by the same person belonging to a single site cannot be designated for three-dimensional reallocation separately. <Amended Mar. 30, 2012>
⑦ Where the planar land reallocation method is applied, buildings on the land prior to reallocation that have been relocated or removed at the time of the land reallocation disposition, or buildings on the land prior to reallocation that are not subject to three -dimensional land reallocation, shall be deemed obstacles, etc. pursuant to Article 38 of the Act , and compensation for loss shall be provided in accordance with Article 65 of the Act . <Newly added Mar. 30, 2012>
⑧ With respect to undersized land, etc. pursuant to Article 62 of the Enforcement Decree , the implementing agency may, upon receiving an application from two or more owners of land or buildings, designate the reallocated land as jointly owned on a single plot of land or subdivided building after reallocation. In this case, the person designated for reallocation may not be designated for another reallocation. <Newly added Mar. 30, 2012>
⑨ The implementing agency may designate reallocated land as jointly owned upon application by two or more landowners for land planned for the purpose of constructing a building falling under the Act on Ownership and Management of Condominium Buildings . <Newly added Mar. 30, 2012>
⑩ The implementing agency may designate a single plot of land or subdivided building after reallocation for two or more pre-reallocation plots or buildings owned by the same person. <Newly added Mar. 30, 2012>
⑪ The implementing agency may designate land reallocation for two or more lands after reallocation or subdivided buildings for a single parcel of land prior to reallocation (hereinafter referred to as “divided land reallocation”). In this case, the respective area of entitlement designated as divided land reallocation must be equal to or greater than the size of the substandard land pursuant to Article 62 of the Enforcement Decree. < Newly added Mar. 30, 2012>
⑫ Notwithstanding Paragraph 11, a land share corresponding to a right to use the land pursuant to Article 2, Subparagraph 6 of the Act on Ownership and Management of Condominium Buildings cannot be divided and reallocated. <Newly added Mar. 30, 2012>
⑬ When the implementing agency amends the land reallocation plan pursuant to Article 29, Paragraph 2 of the Act , it shall comply with the methods and standards in effect at the time of the original land reallocation plan. However, this shall not apply in cases where the original methods or standards cannot be followed due to reasons such as a change in the land reallocation plan area. <Amended Mar. 30, 2012>
⑭ Except for the matters prescribed in Paragraphs 1 through 12, the standards for the preparation of the land reallocation plan shall be determined by the bylaws, articles of incorporation, or enforcement rules as prescribed by the Minister of Land, Infrastructure and Transport . <Newly added Mar. 30, 2012; Mar. 23, 2013>
Article 27-2 (Appraisal Value of Land, etc. at the Time of Land Reallocation Design) ① The appraisal value of land and buildings applied at the time of the initial approval of the land reallocation plan shall be determined based on the time of approval and shall not be changed; the appraisal value of land and buildings after land reallocation may be changed only upon obtaining approval for a change in the land reallocation plan if the appraisal factors have changed due to a change in the implementation plan.
② When designing for land reallocation, the average burden rate pursuant to Article 26, Paragraph 4, Subparagraph 1 shall not exceed 50 percent. However, this may be exceeded if at least two-thirds of the total number of landowners in the land reallocation planning area consent (in cases where the implementing entity is a cooperative, this refers to cases where at least two-thirds of the total voting rights consent at a general meeting). <Amended July 18, 2012>
③ In addition to the matters prescribed in Paragraphs 1 and 2, matters necessary for the standards for land reallocation design shall be determined and announced by the Minister of Land, Infrastructure and Transport . <Amended Mar. 23, 2013>
[This Article was newly established on March 30, 2012.]
Article 28 (Criteria for Determining Reserved Land, etc.) ① Reserved land pursuant to Article 28, Paragraph 5 of the Act shall be determined in accordance with the approval of the implementation plan pursuant to Article 17 of the Act , provided that if an urban development zone is divided into two or more land reallocation plan zones, project costs and reserved land shall be determined for each land reallocation plan zone.
② Notwithstanding Paragraph 1, if an urban development project is implemented through combined development pursuant to Article 3-2, Paragraph 1 of the Act or through a mixed method pursuant to Article 43, Paragraph 1, Subparagraph 3 of the Enforcement Decree, or if necessary considering the scale of infrastructure, topographical conditions, project characteristics, etc., the proceeds from the sale of reserved land or project costs may be adjusted and distributed by land reallocation plan zone as stipulated in the bylaws, articles of incorporation, or enforcement regulations.
[Wholly Amended Mar. 30, 2012]
Article 29 (Standards for Area-Based Land Reallocation, etc.) ① In cases where the implementing agency has established a land reallocation plan based on area, it shall calculate the ratio of land burden borne by landowners within the land reallocation plan area for the urban development project (hereinafter referred to as the “land burden rate”) in accordance with the standards set forth in each of the following subparagraphs. <Amended Mar. 30, 2012>
1. Ensure an appropriate land burden rate by clearly determining the area of land for public facilities and calculating the reserve land by considering the fluctuation rate of land prices before and after land reallocation and the prices of neighboring land.
2. Land burden rates shall be calculated differentially for areas with high land utilization, such as existing urban areas and densely populated residential areas, and for areas with low land utilization, such as lowlands and forests; however, for residential areas where infrastructure such as roads and water and sewage systems has been in place prior to the project implementation, the land burden rate shall be minimized.
3. For land classified as paddy fields, dry fields, or forests but which has become building land due to actual changes in land use, and for land where public facilities such as roads have been donated or transferred to a local government free of charge, the land burden rate shall be calculated in consideration of the costs equivalent thereto.
② The average land burden rate of a land reallocation plan zone shall not exceed 50 percent. However, if the designating authority approves in consideration of the characteristics of the relevant land reallocation plan zone, it may be set up to 60 percent; additionally, if two-thirds or more of the total number of landowners in the land reallocation plan zone consent (in cases where the implementing entity is a cooperative, this refers to consent obtained by two-thirds or more of the total voting rights at a general meeting), it may be set exceeding 60 percent. <Amended Nov. 3, 2015>
③ The average land burden rate of the land reallocation plan area under Paragraph 2 shall be calculated according to the following formula. <Amended Mar. 30, 2012>
④ The implementing entity shall not change the land burden rate that imposes a burden on landowners, except in unavoidable cases during the implementation of the project.
⑤ When establishing a land reallocation plan based on area, the reallocated land shall be designated at the location of the land prior to reallocation. However, if the landowner consents, if the land prior to reallocation is designated as reserved land, or if necessary according to the land use plan, the reallocated land may be designated at a location different from the land prior to reallocation. <Newly added Mar. 30, 2012>
⑥ Main roads within a land reallocation plan zone that connect to the outside of the zone and have a width of 25 meters or more may be constructed if the landowner bears the cost of the road site and the competent local government subsidizes the construction costs. <Amended Mar. 30, 2012>
⑦ Except for the matters prescribed in Paragraphs 1 through 5, specific standards for area-based land reallocation plans shall be determined by the bylaws, articles of incorporation, or implementing regulations. <Newly added Mar. 30, 2012>
[Title amended Mar. 30, 2012]
Article 30 (Documents to Be Attached to Applications for Three-Dimensional Land Reallocation) A person applying for three-dimensional land reallocation under Article 62-2 (4) of the Enforcement Decree shall submit an application to the implementer together with the documents specified in the following subparagraphs.
1. Application for Three-Dimensional Land Reallocation
2. Deleted <December 29, 2017>
3. Certificate of registered matters regarding land or buildings owned prior to land reallocation
4. Other documents deemed necessary by the implementing agency for the application for three-dimensional land reallocation
[Wholly Amended Mar. 30, 2012]
Article 30-2 (Restrictions on Designation of Reallocation, etc.) ① In cases falling under any of the subparagraphs of Article 32-2, Paragraph 1 of the Act , the implementing entity may restrict the location, type, size, etc. of reallocated land as prescribed by the bylaws, articles of incorporation, or implementing regulations. In such cases, the implementing entity may not apply for three-dimensional reallocation of land or buildings exceeding the number of such land or buildings at the time of the reference date pursuant to Article 32-2, Paragraph 1 of the Act .
② Article 32-2, Paragraph 1, Subparagraphs 1 and 3 of the Act determine whether there is a restriction on land reallocation, etc., based on the date of registration received in the register under the Real Estate Registration Act for the division or transfer of the relevant land or housing, etc., and Article 32-2, Paragraph 1, Subparagraphs 2 and 4 of the Act determine whether there is a restriction on land reallocation, etc., based on the date of application for a building permit or a permit for change of use under the Building Act for the relevant building .
[This Article was newly established on March 30, 2012.]
Article 30-3 (Distribution of Remaining Units of Three-Dimensional Reallocation Land, etc.) The distribution of buildings remaining after supplying three-dimensional reallocation land pursuant to Article 62-3 of the Enforcement Decree shall be in accordance with the “Act on the Sale of Buildings” and the “Rules on the Supply of Housing.” However, buildings that are not subject to the application of the Act, the “Act on the Sale of Buildings,” and the “Rules on the Supply of Housing” may be distributed in accordance with the provisions of the bylaws, articles of incorporation, or enforcement regulations.
[This Article was newly established on March 30, 2012.]
Article 31 (Signs) The signs indicating the location of the planned land reallocation or reallocation pursuant to Article 39, Paragraph 2 of the Act are as shown in Attached Table 5 .
Article 32 (Application for Completion Inspection) If an implementing entity intends to undergo a completion inspection pursuant to Article 50, Paragraph 1 of the Act , it shall submit a Report on the Completion of Construction in the Form of Annex 16, attaching the documents and drawings specified in each of the following subparagraphs, to the designating authority through the Mayor (excluding the mayor of a large city), the County Governor, or the District Head. However, if the designating authority is the Minister of Land, Infrastructure and Transport, the Governor of a Special Self-Governing Province, or the mayor of a large city, the submission may be made directly to the Minister of Land, Infrastructure and Transport, the Governor of a Special Self-Governing Province, or the Mayor of a metropolitan city. <Amended Mar. 23, 2013>
1. Completion Report (including completion design documents and completion photographs)
2. Cadastral survey results issued by the Mayor, County Governor, or District Head
3. Documents and drawings necessary for consultation with the heads of relevant administrative agencies pursuant to Article 52 , Paragraph 3 of the Act
4. Statement of ownership and drawings of public facilities pursuant to Article 66 of the Act
5. Comparison map of old and new cadastral maps
Article 33 (Certificate of Completion Inspection) The certificate of completion inspection pursuant to Article 51, Paragraph 1 of the Act shall be in accordance with Form No. 17 of the Attached Form .
Article 34 (Permission for Use Before Completion) The application for permission for use before completion pursuant to Article 70 , Paragraph 1 of the Enforcement Decree shall be in accordance with Form No. 18 of the Attached Form .
Article 35 (Notice of Payment of Cost Burden) ① The notice of payment for cost burdens of local governments, cost burdens of public facility managers, and cost burdens for additionally installed facilities pursuant to Articles 56 through 58 of the Act shall be in accordance with Form No. 19 of the Attached Form .
② The payment notice referred to in Paragraph 1 shall be accompanied by a cost calculation statement regarding the installation of the relevant facility and a cost burden calculation statement, respectively.
Article 36 (Calculation of Costs for Additional Installation Facilities) The costs for additional installation facilities pursuant to Article 75, Paragraph 1 of the Enforcement Decree shall be the sum of construction costs, investigation costs, design costs, compensation costs, and other costs calculated according to the standards of Table 6 .
Article 37 (Keeping of Urban Development Bond Issuance Register, etc.) ① An agency handling affairs pursuant to Article 83, Paragraph 4 of the Enforcement Decree (hereinafter referred to as the “Urban Development Bond Agency”) shall keep an Urban Development Bond Issuance Register and record the matters set forth in each of the following subparagraphs. <Amended Dec. 29, 2017>
1. Name, date of birth, and address of the person who purchased the urban development bonds (hereinafter referred to as the “Purchaser”)
2. Amount of urban development bonds
3. Interest rates on urban development bonds
4. Issuance and Redemption Dates of Urban Development Bonds
② The agency handling urban development bonds shall report matters concerning the monthly sale and redemption of urban development bonds to the relevant mayor or provincial governor by the 20th of the following month.
Article 38 (Early Redemption of Urban Development Bonds) ① Urban development bonds may not be redeemed early except in any of the following cases:
1. In cases where the permit or authorization that served as the reason for the purchase of the urban development bonds is revoked without fault attributable to the purchaser
2. Cases where the relevant contract is canceled without fault attributable to the person falling under Article 63, Paragraph 1, Subparagraph 1 of the Act
3. In cases where a person who is not obligated to purchase urban development bonds purchases them due to a mistake
4. Cases where the obligor of urban development bonds purchases urban development bonds in excess of the amount required to be purchased
② Any person who wishes to receive early redemption in accordance with each subparagraph of Paragraph 1 shall apply to the urban development bond handling agency by attaching documents proving any of the facts falling under each subparagraph of Paragraph 1, issued by the designating authority, local government, or implementing entity, to the application for early redemption of urban development bonds in the form of Annex 20.
Article 39 (Issuance of Purchase Certificate) ① When the head of an agency handling urban development bonds sells urban development bonds to a person falling under any of the subparagraphs of Article 63, Paragraph 1 of the Act , he/she shall sign and seal the urban development bond purchase certificate in Form No. 21 (hereinafter referred to as the “purchase certificate”) and issue it to the purchaser.
② The agency handling urban development bonds shall prepare and maintain a purchase certificate issuance ledger in the form of Annex 22 .
③ If there is an error or omission in the details of the purchase certificate, the purchaser must submit an application for correction of details of the purchase certificate of urban development bonds (Form No. 23) to the relevant urban development bond handling agency, attaching the purchase certificate.
④ When an agency handling urban development bonds receives an application for correction of the details pursuant to Paragraph 3, if there is an error or omission in the details of the purchase certificate, it shall correct it and, after stamping the purchase certificate with a mark of correction, issue it.
Article 40 (Reissuance of Purchase Certificate) ① A purchase certificate for urban development bonds shall not be reissued even if it is lost due to reasons such as destruction or theft. However, if the issuer of the relevant urban development bond confirms that the purchase certificate was not used for the purpose of purchasing the urban development bond, it may be reissued.
② A purchaser seeking reissuance of an urban development bond purchase certificate shall submit an application in attached Form No. 24 to the urban development bond handling agency together with a certificate of non-use of that purchase certificate in attached Form No. 25, issued by the person to whom the purchaser must submit the certificate (meaning a person who enters into a construction contract with a person obliged to purchase bonds under Article 63 (1) of the Act, approves an implementation plan for the person's urban development project, or permits a change in the form and quality of land; hereinafter referred to as the “recipient of the purchase certificate”). <Amended Dec. 29, 2017>
③ If the person receiving the purchase certificate has issued a certificate of non-use of the urban development bond purchase certificate pursuant to Paragraph 2, he/she shall record it in the Register of Certificates of Non-use of Urban Development Bond Purchase Certificates in the Attached Form No. 26. <Amended Dec. 29, 2017>
④ When an agency handling urban development bonds reissues a purchase certificate, it shall mark the upper right corner of the purchase certificate with a reissue mark and record it in the Urban Development Bond Purchase Certificate Reissuance Register in Form No. 27 .
Article 41 (Receipt of Purchase Certificate) ① The time at which the person receiving the purchase certificate must receive the purchase certificate from the purchaser is as follows: <Amended Dec. 29, 2017>
1. In the case of granting permission or authorization: When issuing documents proving that the relevant permission or authorization has been granted
2. When concluding a construction contract: When concluding a construction contract. However, if the construction period is 2 years or longer, a purchase certificate must be obtained when paying the price (in cases where the price is paid in installments, a purchase certificate corresponding to the installment amount).
② Upon receiving the purchase certificate, the person receiving it shall mark the purchase certificate with the cancellation seal of Form No. 28 and record the matters of each of the following subparagraphs in the Urban Development Bond Purchase Certificate Receipt Register of Form No. 29. <Amended Dec. 29, 2017>
1. Symbol and Number of Urban Development Bonds
2. Name and address of the buyer
3. Purpose of Purchase
4. Purchase price
③ The person receiving the purchase certificate shall keep the purchase certificate received from the purchaser separately for five years and shall present it upon request by the head of a local government, an agency handling urban development bonds, or other relevant agencies. <Amended Dec. 29, 2017>
④ Any person who wishes to be exempted from the purchase of urban development bonds pursuant to Table 1 of the Enforcement Decree shall submit an Application for Exemption from the Purchase of Urban Development Bonds (Form No. 30) to the person receiving the purchase certificate, attaching documents proving the grounds for the exemption. <Amended Dec. 29, 2017>
⑤ Upon receiving an application for exemption from the purchase of urban development bonds under paragraph (4), the recipient of the purchase certificate shall verify the applicant and the items for which exemption is sought and record them in the register of persons exempt from purchasing urban development bonds in attached Form No. 31. <Amended Dec. 29, 2017>
Article 42 (Identification and Permit) ① The identification and permit pursuant to Article 64, Paragraph 8 of the Act shall be in accordance with Form No. 32 and Form No. 33 of the Attached Form, respectively .
② The identification card pursuant to Article 74, Paragraph 3 of the Act shall be in accordance with Form No. 34 of the Attached Form .
Article 43 (Transfer and Storage of Related Documents) ① In cases where an implementing entity other than an administrative agency intends to transfer related documents to the Governor of a Special Self-Governing Province, Mayor, County Governor, or District Head pursuant to Article 72 , Paragraph 4 of the Act, it shall transfer the documents and drawings specified in each of the following subparagraphs within two months from the date of completion or termination of the urban development project. <Amended Mar. 30, 2012>
1. Approval of Implementation Plan
2. Documents related to bylaws, articles of incorporation, or implementing regulations
3. Documents and drawings related to land reallocation, such as land reallocation plans and dispositions
4. Related documents and drawings, such as construction design drawings
5. Documents concerning settlement payments
6. Documents related to the merger and dissolution of the partnership
7. Other general documents, related papers, and drawings
② The retention period for documents and drawings pursuant to Article 72, Paragraph 5 of the Act shall be 10 years for the documents and drawings under Subparagraphs 1 through 5 of Paragraph 1, and 5 years for the documents and drawings under Subparagraphs 6 and 7 of the same Paragraph. <Amended Dec. 29, 2017>
Article 44 (Subjects and Scope of Special Provisions, etc.) The criteria for applying special provisions pursuant to Article 85-3, Paragraph 2 of the Enforcement Decree are as set forth in Attached Table 7 .
[This Article was newly established on March 30, 2012.]
Article 45 (Review of Regulations) The Minister of Land, Infrastructure and Transport shall review the validity of the following matters every three years starting from January 1, 2017 (meaning before January 1 of every third year) and take measures such as improvements.
1. Area-based land reallocation standards pursuant to Article 29 , etc.
2. Cases where urban development bonds under Article 38 , Paragraph 1 may be redeemed early
[Wholly revised Dec. 30, 2016]
ADDENDA <Ministry of Land, Transport and Maritime Affairs Decree No. 53, Sep. 22, 2008>
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation. However, the amended provisions of Article 13, subparagraph 2 shall enter into force on February 4, 2009.
Article 2 (Transitional Measures Concerning Standards for Supply of Land by Private Contract) For areas where urban development zones have already been designated at the time of enforcement of the Partial Amendment to the Enforcement Rules of the Urban Development Act, Ministry of Construction and Transportation Decree No. 466, the former provisions shall apply notwithstanding the amended provisions of Item 1 (a) through (c) of Annex 3.
Article 3 (Transitional Measures Concerning the Effective Date) Until subparagraph 2 of Article 13 enters into force pursuant to the proviso of Article 1 of the Addenda, the said subparagraph shall be deemed to be stipulated as follows:
2. In the case of a trust company, it must be a corporation that has not received management improvement measures from the Financial Supervisory Commission pursuant to Article 24-3 of the Trust Business Act. However, this shall not apply if the management improvement measures have been completed.
Article 4 (Amendment of Other Laws) The "Rules on Housing Supply" are partially amended as follows.
In Article 19, Paragraph 3, Subparagraph 3, “pursuant to the provisions of Article 46, Paragraph 4, Subparagraph 3 of the Enforcement Decree of the Urban Development Act” shall be changed to “pursuant to Article 57, Paragraph 4, Subparagraph 3 of the Enforcement Decree of the Urban Development Act”.
Article 5 (Relationship with Other Laws and Regulations) Where, at the time of the enforcement of this Rule, other laws and regulations refer to the former "Enforcement Rules of the Urban Development Act" or its provisions, and there are corresponding provisions in this Rule, it shall be deemed that this Rule or the relevant provisions of this Rule have been referred to in place of the former provisions.
ADDENDA <Ministry of Land, Transport and Maritime Affairs Decree No. 83, Dec. 31, 2008> (Enforcement Rule of the Urban Traffic Management Promotion Act)
Article 1 (Enforcement Date) This rule shall enter into force on January 1, 2009.
Article 2 omitted
Article 3 (Amendment of Other Laws) ① and ② Omitted
③ The Enforcement Rules of the Urban Development Act are partially amended as follows.
In Article 20, Paragraph 1, Subparagraph 9, “traffic impact assessment” shall be changed to “traffic impact analysis and improvement measures.”
④ Omitted
ADDENDA <Ministry of Land, Transport and Maritime Affairs Decree No. 110, Mar. 26, 2009> (Partial Amendment to the Enforcement Rules of the Act on the Sale of Buildings, etc. for the Joint Use of Administrative Information and Document Reduction)
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of Land, Transport and Maritime Affairs Decree No. 256, June 30, 2010>
This rule shall take effect on June 30, 2010.
ADDENDA <Ministry of Land, Transport and Maritime Affairs Decree No. 297, Oct. 15, 2010>
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation.
Article 2 (Applicability to Changes in Supply Prices of Developed Land, etc.) The amended provisions of Article 25, subparagraph 5 shall apply to developed land, etc. for which a public notice or individual notification is made pursuant to Article 57, paragraph 3 of the Enforcement Decree or a private contract is concluded pursuant to Article 57, paragraph 4 of the same Decree for the first time after the enforcement of this Rule.
ADDENDA <Ministry of Land, Transport and Maritime Affairs Decree No. 349, Apr. 7, 2011> (Partial Amendment to the Enforcement Rules of the Construction Technology Management Act, etc. for Economic Revitalization and Relief of Public Inconveniences, etc.)
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of Land, Transport and Maritime Affairs Decree No. 428, Dec. 30, 2011>
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of Land, Transport and Maritime Affairs Decree No. 453, Mar. 30, 2012>
Article 1 (Enforcement Date) This Rule shall enter into force on April 1, 2012. However, the amended provisions of Article 20, Paragraph 1, Subparagraph 8 and Article 21, Subparagraph 7 shall enter into force on April 15, 2012, and the amended provisions of Article 5 shall enter into force on July 18, 2012.
Article 2 (Applicability to Consent Forms, etc.) The amended provisions of Articles 7, 17, 19-2, and 22-2 shall apply to consent forms, withdrawal of consent forms, and consent forms for the designation of a representative received after the enforcement of this Rule.
Article 3 (Applicability to Land Reallocation Plans, etc.) The amended provisions of Articles 26, 27, 27-2, 28 through 30, 30-2, and 30-3 shall apply from the time the first land reallocation plan is drawn up following the enforcement of this Rule.
ADDENDA <Ministry of Land, Transport and Maritime Affairs Decree No. 456, Apr. 13, 2012> (Enforcement Rule of the Act on Planning and Use of National Land)
Article 1 (Enforcement Date) This Rule shall enter into force on April 15, 2012. <Proviso Omitted>
Article 2 omitted
Article 3 (Amendment of Other Laws) ① through ⑨ Omitted
⑩ The Enforcement Rule of the Urban Development Act shall be partially amended as follows.
In Article 5, subparagraph 10, “urban management plan” shall be changed to “urban and county management plan”.
Article 21, subparagraph 6, item (c) shall be as follows.
c. Urban or county planning facilities
⑪ through ? Omitted
ADDENDA <Ministry of Land, Transport and Maritime Affairs Decree No. 498, July 18, 2012>
This rule shall take effect on July 18, 2012.
ADDENDA <Ministry of Land, Infrastructure and Transport Decree No. 1, Mar. 23, 2013> (Enforcement Rule of the Organizational Structure of the Ministry of Land, Infrastructure and Transport and its Affiliated Agencies)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation. <Proviso Omitted>
Articles 2 through 5 omitted
Article 6 (Amendment of Other Laws) ① through ㊻ Omitted
㊼ Part of the Enforcement Rules of the Urban Development Act is amended as follows.
In Article 2, Article 9, the part other than the numbered clauses of Article 10, Article 10-2, Article 11 Paragraph 1, the part other than the numbered clauses of Article 12, the part other than the numbered clauses of Article 13, the part other than the numbered clauses of Article 21, Article 23 Paragraph 1, the part other than the numbered clauses of Article 25, and the part other than the numbered clauses of Article 26 Paragraph 3, the term “Ordinance of the Ministry of Land, Transport and Maritime Affairs” shall be changed to “Ordinance of the Ministry of Land, Infrastructure and Transport”.
In Article 12, subparagraph 8; the first part of Article 15 excluding the subparagraphs; the proviso of Article 16 excluding the subparagraphs; Article 27, paragraph 14; Article 27-2, paragraph 3; and the proviso of Article 32 excluding the subparagraphs, “Minister of Land, Transport and Maritime Affairs” shall be changed to “Minister of Land, Infrastructure and Transport”.
In the section for processing agency (responsible department) on the back of Form No. 3, “Minister of Land, Transport and Maritime Affairs” in Forms No. 5, No. 9, No. 17, No. 19, and No. 34 shall be changed to “Minister of Land, Infrastructure and Transport” respectively.
In the front of Form No. 8, “Minister of Land, Transport and Maritime Affairs” shall be changed to “Minister of Land, Infrastructure and Transport,” and in the processing agency (responsible department) column on the back of the same form, “Ministry of Land, Transport and Maritime Affairs” shall be changed to “Ministry of Land, Infrastructure and Transport.”
In the front of Form No. 11, “Minister of Land, Transport and Maritime Affairs” shall be changed to “Minister of Land, Infrastructure and Transport,” and in the processing agency (responsible department) column on the back of the same form, “Ministry of Land, Transport and Maritime Affairs” shall be changed to “Ministry of Land, Infrastructure and Transport.”
In the front of Form No. 12, “Minister of Land, Transport and Maritime Affairs” shall be changed to “Minister of Land, Infrastructure and Transport,” and in the processing agency (responsible department) column on the back of the same form, “Ministry of Land, Transport and Maritime Affairs” shall be changed to “Ministry of Land, Infrastructure and Transport.”
In the front of Form No. 13, “Minister of Land, Transport and Maritime Affairs” shall be changed to “Minister of Land, Infrastructure and Transport,” and in the processing agency (responsible department) column on the back of the same form, “Ministry of Land, Transport and Maritime Affairs” shall be changed to “Ministry of Land, Infrastructure and Transport.”
In the front and back sections of Form No. 14, excluding the table above, replace “Minister of Land, Transport and Maritime Affairs” with “Minister of Land, Infrastructure and Transport”; in the processing agency (responsible department) column of the table above on the same page, replace “Ministry of Land, Transport and Maritime Affairs” with “Ministry of Land, Infrastructure and Transport” and “Minister of Land, Transport and Maritime Affairs” with “Minister of Land, Infrastructure and Transport”; and in the processing agency (responsible department) column of the table below on the same page, replace “Ministry of Land, Transport and Maritime Affairs” with “Ministry of Land, Infrastructure and Transport”.
In the front of Form No. 16, “Minister of Land, Transport and Maritime Affairs” shall be changed to “Minister of Land, Infrastructure and Transport,” and in the processing agency (responsible department) column on the back of the same form, “Ministry of Land, Transport and Maritime Affairs” shall be changed to “Ministry of Land, Infrastructure and Transport.”
In the front of Form No. 18, “Minister of Land, Transport and Maritime Affairs” shall be changed to “Minister of Land, Infrastructure and Transport,” and in the processing agency (responsible department) column on the back of the same form, “Ministry of Land, Transport and Maritime Affairs” shall be changed to “Ministry of Land, Infrastructure and Transport.”
Items 48 through 126 omitted
ADDENDA <Ministry of Land, Infrastructure and Transport Decree No. 26, Sep. 10, 2013>
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation.
Article 2 (Applicability to Matters to be Included in Development Plans) The amended provisions of Article 9 shall apply from the time a development plan is established pursuant to Article 4, Paragraph 1 of the Act after the enforcement of this Rule.
ADDENDA <Ministry of Land, Infrastructure and Transport Decree No. 169, Dec. 31, 2014> (Partial Amendment to the Enforcement Rules of the Act on the Sale of Buildings, etc. for the Establishment of Regulatory Review Periods, etc.)
This rule shall take effect on January 1, 2015.
ADDENDA <Ministry of Land, Infrastructure and Transport Decree No. 243, Nov. 3, 2015>
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation.
Article 2 (Applicability of Area-Based Land Reallocation Standards) The amended provisions of Article 29, Paragraph 2 shall apply from the time a land reallocation plan is first prepared after the enforcement of this Rule.
ADDENDA <Ministry of Land, Infrastructure and Transport Decree No. 282, Jan. 27, 2016> (Enforcement Rule of the Urban Traffic Management Promotion Act)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation.
Article 2 omitted
Article 3 (Amendment of Other Laws) ① and ② Omitted
③ The Enforcement Rules of the Urban Development Act are partially amended as follows.
In Article 20, Paragraph 1, Subparagraph 9, “traffic impact analysis and improvement measures” shall be changed to “traffic impact assessment”.
④ and ⑤ Omitted
Article 4 omitted
ADDENDA <Ministry of Land, Infrastructure and Transport Decree No. 382, Dec. 30, 2016> (Partial Amendment to the Enforcement Rules of the Act on Appraisal and Appraisers, etc. for the Establishment of Regulatory Review Periods, etc.)
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation. <Proviso Omitted>
Articles 2 through 4 omitted
ADDENDA <Ministry of Land, Infrastructure and Transport Decree No. 475, Dec. 29, 2017>
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of Land, Infrastructure and Transport Decree No. 896, Oct. 12, 2021>
This rule shall take effect from the date of its promulgation.
ADDENDA <Ministry of Land, Infrastructure and Transport Decree No. 1099, Jan. 21, 2022> (Enforcement Rule of the Act on Appraisal and Appraisers)
Article 1 (Enforcement Date) This rule shall enter into force on January 21, 2022.
Article 2 (Amendment of Other Laws) ① through ⑤ Omitted
⑥ Part of the Enforcement Rules of the Urban Development Act is amended as follows.
In Article 20, Paragraph 1, Subparagraph 6, “appraisal business operator” shall be changed to “appraisal corporation, etc.”
In Item 6 of the attached documents section on the front of Form No. 14, “appraisal business operator” shall be changed to “appraisal corporation, etc.”
⑦ through ⑫ omitted
ADDENDA <Ministry of Land, Infrastructure and Transport Decree No. 1446, Jan. 31, 2025>
This rule shall take effect from the date of its promulgation.
[Attachment 1] Criteria for Designation of Urban Development Zones (Related to Article 3)
[Annex 2] Rates of Entrustment Fees (Related to Article 18)
[Attached Table 3] Standards for Supply of Land and Area under Private Contract (Related to Article 23, Paragraph 2)
[Appendix 5] Signs for Indicating Land Reallocation, etc. (Related to Article 31)
[Appendix 6] Cost Calculation Standards (Related to Article 36)
[Appendix 7] Criteria for Application of Special Provisions (Related to Article 44)
[Attachment Form No. 2] Urban Development Zone Survey
[Attachment Form No. 3] Request for Designation of Urban Development Zone
[Attachment Form No. 4] Register of Designated Urban Development Zones
[Attachment Form No. 5] Consent Form for Urban Development Plan via Land Reallocation
[Attachment Form No. 6] Withdrawal of Consent
[Attachment Form No. 7] Consent Form for Designation of Representative
[Attachment Form No. 7-2] Land Details
[Attachment Form No. 8] Application for Designation of Urban Development Project Implementer
[Attached Form No. 9] Certificate of Designation of Urban Development Project Implementer
[Attachment Form No. 10] Register of Designated Urban Development Project Operators
[Attachment Form No. 11] Proposal for Designation of Urban Development Zone
[Attachment Form No. 12] Application for Extension of Application Period for Approval of Urban Development Project Implementation Plan
[Attachment Form No. 12-2] Consent Form for Designation of Urban Development Project Implementer
[Attachment Form No. 12-3] Consent Form for Proposal of Designation of Urban Development Zone
[Attachment Form No. 13] Application for Approval of Trust Agreement
[Attachment Form No. 13-2] Consent Form for Application for Approval of Association Establishment
[Attachment Form No. 14] Application for Approval of Urban Development Project Implementation Plan
[Attachment Form No. 14-2] Consent Form for Land Use and Expropriation
[Attachment Form No. 15] Register of Approved Implementation Plans for Urban Development Projects
[Attachment Form No. 16] Construction Completion Report
[Attachment Form No. 17] Certificate of Completion Inspection
[Attachment Form No. 18] Application for Permit of Use Before Completion
[Attachment Form No. 19] Notice of Payment of Cost Burden
[Attachment Form No. 20] Application for Early Redemption of Urban Development Bonds
[Attachment Form No. 21] Certificate of Purchase of Urban Development Bonds
[Attachment Form No. 22] Register of Issuance of Certificates of Purchase for Urban Development Bonds
[Attachment Form No. 23] Application for Correction of Details on Urban Development Bond Purchase Certificate
[Attachment Form No. 24] Application for Reissuance of Certificate of Purchase of Urban Development Bonds
[Attachment Form No. 25] Certificate of Non-Use of Urban Development Bond Purchase Certificate
[Attachment Form No. 26] Register of Issuance of Certificates of Unused Urban Development Bond Purchase Certificates
[Attachment Form No. 27] Register for the Reissuance of Urban Development Bond Purchase Certificates
[Attached Form No. 28] Cancellation Stamp for Urban Development Bond Purchase Certificate
[Attachment Form No. 29] Receipt Register for Urban Development Bond Purchase Certificates
[Attachment Form No. 30] Application for Exemption from Purchase of Urban Development Bonds
[Attachment Form No. 31] Record of Persons Exempt from Purchasing Urban Development Bonds
[Attached Form No. 32] Identification Card
[Attachment Form No. 33] Permit
[Attached Form No. 34] Identification Card