Rules on Standards for Evacuation, Fire Protection, and Structures of Buildings
291033 · 2026-10-06
Article 1 (Purpose) The purpose of this Rule is to establish technical standards regarding evacuation, fire prevention, etc. of buildings pursuant to Articles 49, 50, 50-2, 51, 52, 52-4, 53, and 64 of the Building Act. <Amended July 22, 2005; April 7, 2010; Jan. 6, 2012; Aug. 6, 2019; Oct. 24, 2019>
Article 2 (Water-Resistant Materials) In subparagraph 6 of Article 2 of the Enforcement Decree of the Building Act (hereinafter referred to as the "Decree"), the term "materials prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to brick, natural stone, artificial stone, concrete, asphalt, ceramic materials, glass, and other similar water-resistant building materials. <Amended July 22, 2005; March 14, 2008; March 23, 2013; August 6, 2019>
Article 3 (Fire-resistant Structure) In subparagraph 7 of Article 2 of the Enforcement Decree, the term "structure conforming to standards prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to any of the following: <Amended 2000.6.3, 2005.7.22, 2006.6.29, 2008.3.14, 2008.7.21, 2010.4.7, 2013.3.23, 2019.8.6, 2021.8.27, 2021.12.23>
1. In the case of walls, any of the following items
a. Reinforced concrete or steel-reinforced concrete structures with a thickness of 10 centimeters or more
b. A structure having a steel frame and covering both sides with wire mesh mortar at least 4 centimeters thick (limited to those with a non-combustible substrate; hereinafter the same applies in this Article) or concrete blocks, bricks, or stone at least 5 centimeters thick.
c. Concrete block, brick, or stone structures reinforced with steel, wherein the thickness of the concrete blocks, etc. covering the steel is 5 centimeters or more.
D. Brickwork with a thickness of 19 centimeters or more
E. Lightweight cellular concrete panels or lightweight cellular concrete blocks cured with high-temperature and high-pressure steam, having a thickness of 10 centimeters or more
2. In the case of non-load-bearing walls among exterior walls, notwithstanding Subparagraph 1, any of the following:
a. Reinforced concrete or steel-reinforced concrete structures with a thickness of 7 centimeters or more
b. A structure having a steel frame and both sides covered with wire mesh mortar at least 3 centimeters thick, or concrete blocks, bricks, or stone at least 4 centimeters thick.
c. Concrete block, brick, or stone structures reinforced with steel, wherein the thickness of the concrete blocks, etc. covering the steel is 4 centimeters or more.
D. Plain concrete, concrete block, brick, or stone structures with a thickness of 7 centimeters or more
3. In the case of columns, those with a smaller diameter of 25 centimeters or more that fall under any of the following subparagraphs. However, if high-strength concrete (referring to concrete with a design standard strength of 50 MPa or more; hereinafter the same applies in this Article) is used, it must comply with the management standards for fire resistance performance of high-strength concrete prescribed and notified by the Minister of Land, Infrastructure and Transport.
A. Reinforced concrete structure or steel-reinforced concrete structure
b. Steel frames covered with wire mesh mortar at least 6 centimeters thick (5 centimeters when using lightweight aggregate) or concrete blocks, bricks, or stone at least 7 centimeters thick
c. Steel frames covered with concrete at least 5 centimeters thick
4. In the case of floors, any of the following items
a. Reinforced concrete or steel-reinforced concrete structures with a thickness of 10 centimeters or more
b. Concrete block, brick, or stone structures reinforced with steel, wherein the thickness of the concrete blocks, etc. covering the steel is 5 centimeters or more
C. Steel with both sides covered with wire mesh mortar or concrete at least 5 centimeters thick
5. In the case of beams (including roof trusses), any of the following shall apply. However, if high-strength concrete is used, it must comply with the management standards for fire resistance performance of high-strength concrete prescribed and notified by the Minister of Land, Infrastructure and Transport.
A. Reinforced concrete structure or steel-reinforced concrete structure
b. Steel frames covered with wire mesh mortar at least 6 centimeters thick (5 centimeters when using lightweight aggregate) or concrete at least 5 centimeters thick
c. Steel-framed roof trusses (limited to those with a height of 4 meters or more from the floor to the lower part) that have no ceiling directly underneath or have a ceiling made of non-combustible material
6. In the case of a roof, any of the following items
A. Reinforced concrete structure or steel-reinforced concrete structure
B. Steel-reinforced concrete block, brick, or stone masonry
c. Glass blocks reinforced with steel or wired glass (referring to thick plate glass with a wire mesh inserted)
7. In the case of stairs, any of the following items
A. Reinforced concrete structure or steel-reinforced concrete structure
B. Plain concrete, concrete block, brick, or stone structure
C. Steel-reinforced concrete block, brick, or stone masonry
D. Steel Frame Structure
8. The head of the Korea Institute of Construction Technology (hereinafter referred to as the "President of the Korea Institute of Construction Technology"), established pursuant to Article 8 of the "Act on the Establishment, Operation, and Promotion of Government-funded Research Institutions, etc. in the Science and Technology Field," shall determine that the results of quality testing conducted in accordance with the method prescribed and notified by the Minister of Land, Infrastructure and Transport shall conform to the performance standards set forth in Annex 1.
9. Anything falling under any of the following items that the President of the Korea Institute of Construction Technology recognizes as conforming to standards approved by the Minister of Land, Infrastructure and Transport
A. Those conforming to fire-resistant structural standards recognized by the President of the Korea Institute of Construction Technology
B. A structure capable of verifying the performance of a fire-resistant structure in accordance with a performance design recognized by the President of the Korea Institute of Construction Technology.
10. That which the President of the Korea Institute of Construction Technology recognizes in accordance with the recognition standards established pursuant to Article 27, Paragraph 1
Article 4 (Fire-resistant Structure) In subparagraph 8 of Article 2 of the Enforcement Decree, the term "structure conforming to standards prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to any of the following: <Amended 2005.7.22, 2008.3.14, 2010.4.7, 2013.3.23, 2019.8.6, 2022.2.10>
1. Wire mesh mortar with a coating thickness of 2 centimeters or more
2. Cement mortar or plaster applied over a gypsum board, with a total thickness of 2.5 centimeters or more
3. Tiles attached over cement mortar with a total thickness of 2.5 centimeters or more
4. Delete <2010.4.7>
5. Delete <2010.4.7>
6. Earthen wall facing the hearth
7. Items corresponding to Fire Resistance Class 2 or higher as a result of testing in accordance with Korean Industrial Standards pursuant to the Industrial Standardization Act (hereinafter referred to as "Korean Industrial Standards")
Article 5 (Flame-retardant Materials) In Subparagraph 9 of Article 2 of the Enforcement Decree, "materials conforming to standards prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to materials that, as a result of testing in accordance with Korean Industrial Standards, satisfy the performance standards for flame-retardant materials prescribed and notified by the Minister of Land, Infrastructure and Transport regarding gas toxicity, heat release rate, etc. <Amended 2005.7.22, 2006.6.29, 2008.3.14, 2013.3.23, 2019.8.6, 2022.2.10>
Article 6 (Non-combustible Materials) In subparagraph 10 of Article 2 of the Enforcement Decree, the term "materials conforming to the standards prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to any of the following: <Amended 2000.6.3, 2004.10.4, 2005.7.22, 2006.6.29, 2008.3.14, 2013.3.23, 2014.5.22, 2019.8.6, 2022.2.10>
1. Concrete, stone, brick, roof tile, steel, aluminum, glass, cement mortar, and lime. In this case, if plastering materials such as cement mortar or lime are used, they shall be limited to those having a thickness equal to or greater than that specified in the Standard Specifications for Building Construction enacted pursuant to Article 44, Paragraph 1, Subparagraph 2 of the Construction Technology Promotion Act.
2. That the mass loss rate, etc., as a result of testing in accordance with Korean Industrial Standards, satisfies the performance standards for non-combustible materials prescribed and notified by the Minister of Land, Infrastructure and Transport
3. Other non-combustible materials similar to those in Subparagraph 1, as recognized by the Minister of Land, Infrastructure and Transport. However, this excludes cases where the material in Subparagraph 1 is composed of a composite material and a non-combustible material.
Article 7 (Semi-noncombustible Materials) In Subparagraph 11 of Article 2 of the Enforcement Decree, the term "materials conforming to standards prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to materials that, as a result of testing in accordance with Korean Industrial Standards, satisfy the performance standards for semi-noncombustible materials prescribed and notified by the Minister of Land, Infrastructure and Transport regarding gas toxicity, heat release rate, etc. <Amended 2005.7.22, 2006.6.29, 2008.3.14, 2013.3.23, 2019.8.6, 2022.2.10>
Article 7-2 (Installation Works for Finishing Materials Subject to Assignment of Assistant Architects) In the first part of Article 19, Paragraph 7 of the Enforcement Decree, the phrase "cases prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to cases where insulation materials other than non-combustible, semi-non-combustible, or flame-retardant materials are used pursuant to Article 24, Paragraph 3, and said insulation materials are exposed to the outside air.
[This Article Newly Established 2021.9.3]
Article 8 (Installation Standards for Direct Stairs)
① In the proviso to Article 34, Paragraph 1 of the Enforcement Decree, the term "factory prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to a factory manufacturing semiconductors, display panels, and secondary batteries. <Newly added Apr. 7, 2010; Mar. 23, 2013; Aug. 6, 2019; Sep. 19, 2025>
② When installing two or more direct staircases pursuant to Article 34, Paragraph 2 of the Enforcement Decree, they must comply with the standards of each of the following subparagraphs. <Amended Aug. 6, 2019>
1. The shortest straight-line distance between the entrances of the two furthest direct staircases (referring to the shortest walking distance between entrances if the corridor connecting the direct staircases is partitioned by a fire compartment from another part of the building) shall be at least half of the maximum diagonal distance of the building plan. However, if sprinklers or other similar automatic fire extinguishing systems are installed, it shall be at least one-third.
2. Install a passageway, such as a corridor connected to the living room, between each direct staircase.
Article 8-2 (Standards for Installation of Evacuation Safety Zones)
① An evacuation safety zone established pursuant to Paragraphs 3 and 4 of Article 34 of the Enforcement Decree (hereinafter referred to as the "Evacuation Safety Zone") shall occupy one floor of the relevant building as an evacuation space and may be installed on the same floor as a space for installing building facilities, such as machine rooms, boiler rooms, and electrical rooms, to the extent that it does not hinder evacuation. In this case, the Evacuation Safety Zone shall be partitioned from the space where building facilities are installed by a fire-resistant structure. <Amended Jan. 6, 2012>
② Special evacuation staircases connected to evacuation safety zones shall be installed in a structure that allows access to upper and lower floors via the evacuation safety zone.
③ The structure and facilities of evacuation safety zones shall comply with the standards of each of the following subparagraphs. <Amended 2012.1.6, 2014.11.19, 2017.7.26, 2019.8.6, 2024.8.26>
1. The floor immediately below and above the evacuation safety zone shall be equipped with insulation materials that comply with the standards prescribed and notified by the Minister of Land, Infrastructure and Transport pursuant to Article 15, Paragraph 1 of the "Act on Support for the Creation of Green Buildings." In this case, the standards for the ceiling or roof of the living room on the top floor shall apply mutatis mutandis to the floor of the living room on the bottom floor, and the standards for the floor of the living room on the bottom floor shall apply mutatis mutandis to the floor of the top floor.
2. Interior finishing materials of evacuation safety zones shall be installed using non-combustible materials.
3. Stairs leading from the interior of the building to the evacuation safety zone shall be installed as special evacuation stairs.
4. Emergency elevators shall be installed in a structure that allows boarding and alighting in the evacuation safety zone.
5. Install at least one water tap for drinking water supply in the evacuation safety zone and install lighting facilities powered by a backup power source.
6. Install alarm and communication facilities capable of emergency contact with the management office or disaster prevention center, etc.
7. The area shall be equal to or greater than the area calculated according to the standards set forth in Attached Table 1-2
8. The height of the evacuation safety zone shall be 2.1 meters or more
9. Install smoke exhaust facilities (hereinafter referred to as "smoke exhaust facilities") in accordance with Article 14 of the "Rules on Standards for Building Facilities, etc."
10. Be equipped with other facilities for firefighting and disaster management as prescribed by the Commissioner of the National Fire Agency
[This Article Newly Established 2010.4.7]
Article 9 (Structure of Evacuation Stairs and Special Evacuation Stairs)
① In accordance with the main text of the part other than the subparagraphs of Article 35, Paragraph 1 of the Enforcement Decree, direct staircases leading from a floor of 5 stories or higher or a floor of 2 basement levels or lower to an evacuation floor or ground level (in the case of a building with 1 basement level, including stairs on the 1st basement level directly connected to a direct staircase leading from a floor of 5 stories or higher to an evacuation floor or ground level) shall be installed as evacuation staircases or special evacuation staircases. <Amended Aug. 6, 2019>
② The structure of escape stairs and special escape stairs pursuant to Paragraph 1 shall comply with the standards of each of the following subparagraphs. <Amended 2000.6.3, 2003.1.6, 2005.7.22, 2010.4.7, 2012.1.6, 2019.8.6, 2021.3.26, 2024.11.15>
1. Structure of escape stairs installed inside a building
a. Stairwells shall be partitioned from other parts of the building by fire-resistant walls, excluding windows, doorways, and other openings (hereinafter referred to as "windows, etc.").
B. The finish (including the base for the finish) of the parts of the stairwell facing the interior (referring to all parts facing the interior, such as floors and ceilings) shall be made of non-combustible materials.
C. Lighting facilities powered by a backup power source shall be installed in the stairwells.
D. Windows, etc. facing the outside of the stairwell (excluding fixed windows with wired glass, each with an area of 1 square meter or less) shall be installed at a distance of 2 meters or more from windows, etc. installed in other parts of the building.
E. Windows, etc. in stairwells facing the interior of the building (excluding doorways) shall be fixed windows with wired glass, and their area shall each be 1 square meter or less.
F. The effective width of an entrance leading from the interior of a building to a stairwell shall be at least 0.9 meters, and such entrance shall be equipped with a 60-minute+ fire door as defined in Article 64, Paragraph 1, Subparagraph 1 of the Enforcement Decree (hereinafter referred to as "60-minute+ fire door") or a 60-minute fire door as defined in Subparagraph 2 of the same Paragraph (hereinafter referred to as "60-minute fire door"), which can be opened in the direction of evacuation and is structured to remain closed at all times or to close automatically upon detecting smoke or flames caused by a fire. However, if it is not possible to construct a structure that closes automatically upon detecting smoke or flames, it may be constructed to close automatically upon detecting temperature.
d. Stairs shall be of fire-resistant construction and shall be directly connected to the evacuation floor or the ground floor.
2. Structure of escape stairs installed on the exterior of a building
a. Stairs shall be installed at a distance of at least 2 meters from windows, etc., other than the doorway leading to the stairs (excluding fixed windows with wired glass, each with an area of 1 square meter or less).
B. Install 60-minute+ fire doors or 60-minute fire doors at entrances leading to stairs from the interior of the building.
c. The effective width of the stairs shall be at least 0.9 meters.
D. Stairs shall be of fire-resistant construction and shall connect directly to the ground level
3. Structure of Special Evacuation Stairs
a. The interior of the building and the stairwell shall be connected through a balcony, or through a window with an area of 1 square meter or more that opens outward (limited to those installed at a height of 1 meter or more from the floor), or through an ancillary room with an area of 3 square meters or more equipped with a smoke exhaust system of a structure compliant with the provisions of Article 14 of the "Rules on Building Equipment Standards, etc."
B. Stairwells, balconies, and ancillary rooms (including ancillary rooms used as landings for emergency elevators pursuant to the provisions of Article 10, Subparagraph 2, Item A of the Rules on Building Equipment Standards, etc.) shall each be partitioned by fire-resistant walls, excluding windows, etc.
C. The finishes (including the substrate for the finish) of parts facing the interior of stairwells and ancillary rooms (referring to all parts facing the interior, such as floors and ceilings) shall be made of non-combustible materials.
D. Install lighting facilities powered by a backup power source in the stairwells
E. Windows, etc. facing the exterior of the building installed in stairwells, balconies, or ancillary rooms (excluding fixed windows with wired glass, each with an area of 1 square meter or less) shall be installed at a distance of 2 meters or more from windows, etc. installed in other parts of the building outside the stairwell, balcony, or ancillary room.
f. Windows, etc. facing the interior of the building shall not be installed in stairwells, except for parts adjacent to balconies or ancillary rooms.
d. Windows, etc. (excluding doorways) facing balconies or ancillary rooms in stairwells shall be fixed windows with wired glass, and their area shall each be 1 square meter or less.
H. Windows, etc. (excluding doorways) facing the interior of the building, excluding stairwells, shall not be installed in balconies and ancillary rooms.
J. Fire doors rated for 60 minutes or more, or fire doors rated for 60 minutes, shall be installed at entrances leading from the interior of the building to balconies or ancillary rooms, and fire doors rated for 60 minutes or more, fire doors rated for 60 minutes or less, or fire doors rated for 30 minutes as prescribed in Article 64, Paragraph 1, Subparagraph 3 of the Enforcement Decree shall be installed at entrances leading from balconies or ancillary rooms to stairwells. In this case, the fire doors shall be designed to remain closed at all times or to close automatically upon detecting smoke or flames caused by a fire; however, if it is not possible to design them to close automatically upon detecting smoke or flames, they may be designed to close automatically upon detecting temperature.
D. Stairs shall be of a fire-resistant structure and shall be directly connected to the evacuation floor or the ground floor.
K. The effective width of the entrance shall be at least 0.9 meters, and it shall be able to open in the direction of evacuation.
③ Evacuation stairs or special evacuation stairs pursuant to the main text of the part other than the subparagraphs of Article 35, Paragraph 1 of the Enforcement Decree shall not be spiral stairs, and evacuation stairs or special evacuation stairs of a building required to install a rooftop plaza pursuant to Article 40 of the Enforcement Decree shall be installed to lead to the rooftop of the relevant building. In this case, the door leading to the rooftop shall be of a structure that opens in the direction of evacuation and shall not obstruct use during evacuation. <Amended Apr. 7, 2010, Aug. 6, 2019>
④ In Article 35, Paragraph 2 of the Enforcement Decree, the term "open-corridor type multi-unit dwelling" refers to a multi-unit dwelling with a structure in which one side of the corridor leading from the stairwell and elevator on each floor to each household is open to the outside air. <Newly added 2006.6.29, 2021.9.3>
Article 10 (Standards for Installation of Exits from Viewing Rooms, etc.)
① Doors used as exits to the outside from viewing rooms or assembly rooms of buildings falling under any of the subparagraphs of Article 38 of the Enforcement Decree shall not be inward-opening doors. <Amended Aug. 6, 2019>
② Pursuant to Article 38 of the Enforcement Decree, exits of individual viewing rooms in performance halls among cultural and assembly facilities (applicable only to those with a floor area of 300 square meters or more) shall be installed in compliance with the standards of each of the following subparagraphs. <Amended Aug. 6, 2019>
1. Install at least two locations per viewing room
2. The effective width of each outlet shall be at least 1.5 meters
3. The sum of the effective widths of individual viewing room exits shall be at least the width calculated at a rate of 0.6 meters for every 100 square meters of floor area of individual viewing rooms.
[Title Revised 2019.8.6]
Article 11 (Standards for Installation of Exits to the Outside of Buildings)
① In cases where an exit leading to the outside of a building is installed pursuant to the provisions of Article 39, Paragraph 1 of the Enforcement Decree, the walking distance from the stairs of the evacuation floor to the exit to the outside of the building (referring to the walking distance to the nearest exit; hereinafter the same) shall be no more than the distance prescribed in the provisions of Article 34, Paragraph 1 of the Enforcement Decree, and the walking distance from each part of a living room (excluding those with an entrance that does not hinder evacuation) to the exit to the outside of the building shall be no more than twice the distance prescribed in the provisions of Article 34, Paragraph 1 of the Enforcement Decree.
② Among buildings equipped with an exit leading to the outside pursuant to Article 39, Paragraph 1 of the Enforcement Decree, doors used as exits to the outside of buildings used for cultural and assembly facilities (excluding exhibition halls and zoos/botanical gardens), religious facilities, funeral homes, or entertainment facilities shall not be inward-opening doors. <Amended Apr. 7, 2010>
③ In cases where an exit leading to the outside of a building is installed pursuant to Article 39, Paragraph 1 of the Enforcement Decree, assembly halls or performance halls with a total floor area of viewing rooms of 300 square meters or more shall install at least two auxiliary exits or emergency exits in addition to the main exit. <Amended Aug. 6, 2019>
④ The sum of the effective widths of exits to the outside of the building installed on evacuation floors used for sales facilities shall be at least the width calculated at a rate of 0.6 meters for every 100 square meters of floor area for the relevant use on the floor with the maximum floor area for that use. <Amended 2010.4.7>
⑤ A ramp pursuant to Article 15, Paragraph 5 shall be installed in the passageway leading from the evacuation floor or the elevator landing of the evacuation floor to the outside of the building of any building falling under any of the following subparagraphs. <Amended 2010.4.7>
1. Among Class 1 neighborhood living facilities, community centers, police substations, police patrol units, fire stations, post offices, broadcasting stations, public health centers, public libraries, regional health insurance associations, and other similar facilities, wherein the total floor area used for the relevant purpose within the same building is less than 1,000 square meters
2. Among Class 1 neighborhood living facilities, village halls, village communal workshops, village communal marketplaces, substations, pumping stations, water purification plants, shelters, public restrooms, and other similar facilities
3. Sales facilities and transportation facilities with a gross floor area of 5,000 square meters or more
4. Schools among educational and research facilities
5. Among business facilities, buildings of state or local government offices and foreign diplomatic missions that do not fall under Class 1 Neighborhood Living Facilities
6. Buildings where elevators must be installed
6. In accordance with Article 49, Paragraph 1 of the Building Act (hereinafter referred to as the "Act"), safety glass must be used in doors leading to the outside of a building falling under any of the subparagraphs of Article 39, Paragraph 1 of the Enforcement Decree. <Newly added June 29, 2006, July 9, 2015>
Article 12 (Installation Standards for Revolving Doors) Revolving doors installed at the entrances of buildings pursuant to the provisions of Article 39, Paragraph 2 of the Enforcement Decree shall comply with the standards set forth in each of the following subparagraphs. <Amended Jul. 22, 2005>
1. Maintain a distance of at least 2 meters from stairs or escalators
2. Ensure the clearance specified in each of the following items between the revolving door, the door frame, and the floor, and fill the gaps using a combination of rubber and rubber felt, etc., to prevent damage to the body or objects.
A. The distance between the revolving door and the door frame is at least 5 centimeters
B. The distance between the revolving door and the floor is 3 centimeters or less
3. It shall be constructed to rotate in a consistent direction so as not to obstruct entry and exit.
4. The length from the central axis of the revolving door to the tip of the revolving door blade, including the gap between the revolving door and the door frame, shall be at least 140 centimeters.
5. The rotational speed of the revolving door shall not exceed 8 revolutions per minute.
6. Automatic revolving doors shall be constructed to stop using electronic detection devices, etc., in the event of impact or when a user is in a dangerous position.
Article 13 (Standards for Installation of Heliports and Structural Spaces)
① A heliport installed in a building pursuant to Article 40, Paragraph 4, Subparagraph 1 of the Enforcement Decree shall comply with the standards of each of the following subparagraphs. <Amended 2003.1.6, 2010.4.7, 2012.1.6, 2021.3.26>
1. The length and width of the helipad shall each be at least 22 meters. However, if the length and width of the rooftop floor of the building are each 22 meters or less, the length and width of the helipad may be reduced to 15 meters each.
2. No buildings, structures, landscaping facilities, railings, etc. that obstruct the take-off and landing of helicopters shall be installed within a radius of 12 meters from the center of the heliport.
3. The perimeter boundary line of the heliport shall be white, and the width of the line shall be 38 centimeters.
4. In the center of the helipad, a white "ⓗ" marker with a diameter of 8 meters shall be installed; the line width of the "H" marker shall be 38 centimeters, and the line width of the "○" marker shall be 60 centimeters.
5. Install an automatic emergency door opening and closing device (hereinafter referred to as "automatic emergency door opening and closing device") in accordance with the part other than each subparagraph of Article 40, Paragraph 3 of the Enforcement Decree on the entrance door leading to the helipad.
② In cases where a space capable of rescuing lives, etc. via helicopter is installed on a rooftop pursuant to Article 40, Paragraph 4, Subparagraph 1 of the Enforcement Decree, a rescue space with a diameter of at least 10 meters must be secured, and no buildings, structures, or railings that obstruct rescue activities shall be installed within the rescue space. In this case, the provisions of Paragraph 1, Subparagraphs 3 through 5 shall apply mutatis mutandis to the marking and installation standards, etc., of the rescue space. <Newly added Apr. 7, 2010; Jan. 6, 2012; Mar. 26, 2021>
③ Evacuation spaces installed pursuant to Article 40, Paragraph 4, Subparagraph 2 of the Enforcement Decree shall comply with the standards of each of the following subparagraphs. <Newly added 2012.1.6, 2021.3.26, 2024.11.15>
1. The area of the evacuation space shall be at least one-tenth of the horizontal projection area of the roof
2. It shall be connected to a special escape staircase or an escape staircase
3. Parts excluding doorways and windows shall be separated from other parts of the building by fire-resistant floors and walls.
4. Doorways shall have an effective width of at least 0.9 meters, and 60-minute+ fire doors or 60-minute fire doors shall be installed at such doorways.
4-2. Install an automatic emergency door opening and closing device on fire doors in accordance with Subparagraph 4.
5. Interior finishing materials shall be non-combustible materials
6. Install lighting fixtures that operate on backup power.
7. Install communication facilities capable of emergency contact with the management office, etc.
[Title Revised 2010.4.7]
Article 14 (Standards for Installation of Fire Compartments)
① Fire compartments installed in a building pursuant to the main text of the part other than each subparagraph of Article 46, Paragraph 1 of the Enforcement Decree shall comply with the standards of each of the following subparagraphs. <Amended Apr. 7, 2010; Aug. 6, 2019; Mar. 26, 2021>
1. Floors 10 stories or lower shall be partitioned at intervals of no more than 1,000 square meters of floor area (or 3,000 square meters of floor area if sprinklers or other similar automatic fire extinguishing systems are installed).
2. Each floor shall be partitioned. However, the ramp area directly connecting the first basement level to the ground level shall be excluded.
3. Floors of the 11th floor or higher shall be partitioned at intervals of no more than 200 square meters of floor area (600 square meters if sprinklers or other similar automatic fire extinguishing systems are installed). However, if the interior surfaces of walls and ceilings are finished with non-combustible materials, they shall be partitioned at intervals of no more than 500 square meters of floor area (1,500 square meters if sprinklers or other similar automatic fire extinguishing systems are installed).
4. In cases where a portion of a pilotis or other similar structure (only applicable if at least half of the wall area is an open space extending from the floor of that level to the underside of the floor above) is used as a parking lot, such portion shall be partitioned from other parts of the building.
② Fire compartments pursuant to Paragraph 1 shall be installed in accordance with the standards of each of the following subparagraphs. <Amended 2003.1.6, 2005.7.22, 2006.6.29, 2008.3.14, 2010.4.7, 2012.1.6, 2013.3.23, 2019.8.6, 2021.3.26, 2021.12.23, 2024.8.26, 2024.11.15, 2026.10.6>
1. 60-minute+ fire doors or 60-minute fire doors used as fire compartments pursuant to Article 46 of the Enforcement Decree shall be constructed to remain closed at all times or to close automatically upon detecting smoke or flames caused by a fire. However, if it is not possible to construct them to close automatically upon detecting smoke or flames, they may be constructed to close automatically upon detecting temperature.
2. In cases falling under any of the following subparagraphs, the relevant part shall be filled with a structure recognized for fire-resistant filling performance capable of withstanding a fire resistance time equal to or greater than the fire resistance time specified in Subparagraph 1 of Annex 1 (referring to the fire resistance time applied to constituent members filled with a structure recognized for fire-resistant filling performance).
a. Where a penetration occurs due to a water supply pipe, distribution pipe, or other pipe or wire, etc. penetrating a fire compartment
B. Where joints occur between walls and walls, walls and floors, or floors and floors of a fire compartment
C. In cases where a joint occurs between a fire compartment and an exterior wall
D. In cases where other gaps occur in the fire compartment
3. Where the air duct of a ventilation, heating, or cooling facility penetrates a fire compartment, a damper conforming to the standards of each of the following subparagraphs shall be installed at the penetrating portion or in a portion adjacent thereto. However, this shall not apply to semiconductor factory buildings where sprinkler heads are installed around the air duct penetrating a fire compartment.
a. It shall be constructed to automatically close upon detecting smoke or flames caused by a fire. However, in areas where smoke is constantly generated, such as kitchens, it may be constructed to automatically close upon detecting temperature.
B. It shall comply with the standards for non-thermal insulation performance and smoke-retardant performance, etc., prescribed and notified by the Minister of Land, Infrastructure and Transport.
C. Delete <2019.8.6>
D. Delete <2019.8.6>
4. Automatic fire shutters installed pursuant to Article 46, Paragraph 1, Subparagraph 2 and Article 81, Paragraph 5, Subparagraph 5 of the Enforcement Decree shall satisfy all of the requirements of each of the following items. In this case, detailed matters concerning the structural and performance standards, etc., of automatic fire shutters shall be determined and notified by the Minister of Land, Infrastructure and Transport.
a. It shall be installed separately within 3 meters of a 60-minute+ fire door or a 60-minute fire door that allows for evacuation. However, this shall not apply in the case of installing a composite fire shutter (referring to an automatic fire shutter equipped with a fire door for evacuation).
B. It shall be capable of opening and closing by electric or manual means
C. Install either a flame detector or a smoke detector, and a heat detector.
D. It shall be a structure that partially closes upon detecting flames or smoke
E. It shall be a structure that completely closes when heat is detected.
③ In Article 46, Paragraph 1, Subparagraph 2 of the Enforcement Decree, the phrase "that which conforms to the standards prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to a matter for which the President of the Korea Institute of Construction Technology has recognized all of the following matters in accordance with the regulations prescribed and notified by the Minister of Land, Infrastructure and Transport. <Newly added Aug. 6, 2019; Mar. 26, 2021>
1. As a result of verifying the quality control status of the production plant, it shall comply with the standards prescribed and notified by the Minister of Land, Infrastructure and Transport
2. As a result of conducting quality tests on the product, it shall have secured non-thermal insulation fire resistance performance of at least 1 hour
④ The structure of downward-type escape routes (including covers, ladders, elevator-type escape devices, and alarm systems) pursuant to Article 46, Paragraph 5, Subparagraph 3 of the Enforcement Decree shall be installed in compliance with the standards of each of the following subparagraphs. <Newly added 2010.4.7, 2019.8.6, 2021.3.26, 2022.4.29>
1. The cover of the escape hatch (including the ladder, elevator-type escape device, or alarm system if the cover and the ladder, elevator-type escape device, or alarm system are integrated) shall possess non-thermal insulation fire resistance performance of at least 1 hour as a result of quality testing, and the effective opening of the escape hatch shall have a diameter of at least 60 centimeters.
2. The horizontal distance between escape routes on upper and lower floors shall be at least 15 centimeters.
3. The structure must be such that the escape door on the floor directly above cannot be opened from the floor below.
4. The ladder shall be no more than 50 centimeters long from the floor of the level immediately below.
5. It shall be structured so that an alarm sounds through the building management system, etc., if the cover is opened
6. Install lighting facilities powered by a backup power source in areas with escape routes.
⑤ Matters necessary for the fire-resistant filling method pursuant to Paragraph 2, Subparagraph 2 shall be determined and announced by the Minister of Land, Infrastructure and Transport. <Newly added 2012.1.6, 2013.3.23, 2019.8.6, 2021.3.26, 2024.8.26>
⑥ Pursuant to the proviso to Article 49, Paragraph 2 of the Act, additional facilities classified according to the following subparagraphs must be installed in the parts of warehouse facilities under Article 46, Paragraph 7 of the Enforcement Decree that fall under Subparagraph 2, Paragraph 2 of the same Article and are therefore exempt from or subject to a relaxed application of Article 46, Paragraph 1. <Newly added Apr. 29, 2022; Aug. 26, 2024>
1. In the case of openings: Equipment that meets the fire safety standards pursuant to Article 12, Paragraph 1 of the Act on the Installation and Management of Firefighting Facilities (hereinafter referred to as "fire safety standards" in this Article) and prevents the spread of fire by forming a water curtain
2. For areas other than openings: Sprinklers designed to extinguish fires early as equipment meeting fire safety standards
Article 14-2 (Evacuation Facilities, etc. in Complex Buildings) Pursuant to the proviso to Article 47, Paragraph 1 of the Enforcement Decree, if one or more of multi-unit housing, medical facilities, child-related facilities, or elderly welfare facilities (hereinafter referred to as "multi-unit housing, etc." in this Article) and one or more of entertainment facilities, hazardous materials storage and processing facilities, factories, or automobile repair shops (hereinafter referred to as "entertainment facilities, etc." in this Article) are to be installed together within the same building, they shall comply with the standards set forth in each of the following subparagraphs. <Amended July 22, 2005>
1. The entrances of multi-unit dwellings, etc. and the entrances of entertainment facilities, etc. shall be installed so that the walking distance between them is at least 30 meters.
2. Multi-unit dwellings, etc. (including passageways leading to said multi-unit dwellings, etc.) and entertainment facilities, etc. (including passageways leading to said entertainment facilities, etc.) shall be separated from each other by floors and walls made of fire-resistant structures.
3. Multi-unit dwellings, etc. and recreational facilities, etc. shall be arranged so as not to be adjacent to each other.
4. The main structural components of the building shall be of a fire-resistant structure
5. The finishes of the walls and ceilings of a living room facing the interior (excluding ceiling moldings, window sills, and other similar items; hereinafter the same applies in this Article) shall be made of non-combustible, semi-non-combustible, or flame-retardant materials, and the finishes of the walls and ceilings of the main corridor, staircase, and other passageway leading from the living room to the ground floor facing the interior shall be made of non-combustible or semi-non-combustible materials.
[This Article Newly Established 2003.1.6]
Article 15 (Standards for the Installation of Stairs)
① Stairs installed in a building pursuant to the provisions of Article 48 of the Enforcement Decree shall comply with the standards of each of the following subparagraphs. <Amended Apr. 7, 2010; Apr. 6, 2015; Oct. 6, 2026>
1. For stairs exceeding 3 meters in height, a landing with an effective width of at least 120 centimeters shall be installed at intervals of no more than 3 meters.
2. Handrails (including walls or equivalents) shall be installed on both sides of stairs and landings exceeding 1 meter in height.
3. For stairs with a width exceeding 3 meters, handrails shall be installed in the middle of the stairs at intervals of no more than 3 meters in width. However, this shall not apply if the step height is 15 centimeters or less and the step width is 30 centimeters or more.
4. The effective height of the stairs (referring to the vertical height from the floor finish surface of the stairs to the lower finish surface of the superstructure) shall be 2.1 meters or more.
② When installing stairs in accordance with Paragraph 1, the dimensions of the width of the stairs and landings (limited to indoor stairs), the step height, and the step width shall comply with the standards of each of the following subparagraphs. In this case, the step width of a spiral staircase shall be measured at a position 30 centimeters from the end of the narrowest width. <Amended 2003.1.6, 2005.7.22, 2010.4.7, 2015.4.6, 2019.8.6, 2026.10.6>
1. In the case of stairs in elementary schools, the effective width of the stairs and landings shall be 150 centimeters or more, the step height shall be 16 centimeters or less, and the step width shall be 26 centimeters or more.
2. In the case of stairs in middle and high schools, the effective width of the stairs and landings shall be 150 centimeters or more, the step height shall be 18 centimeters or less, and the step width shall be 26 centimeters or more.
3. In the case of stairs in buildings used for cultural and assembly facilities (limited to performance halls, assembly halls, and viewing halls), sales facilities, or other similar purposes, the effective width of the stairs and landings shall be at least 120 centimeters.
4. In the case of stairs in a building other than those specified in Nos. 1 through 3, for a floor falling under any of the following subparagraphs, the effective width of the stairs and landings shall be at least 120 centimeters.
a. Where the floor to be installed is a ground floor: Where the total floor area of living spaces from the floor immediately above the relevant floor to the top floor (or the floor below it if there is an evacuation floor among the upper floors) is 200 square meters or more
B. In the case where the floor to be installed is a basement: If the total floor area of the basement living rooms is 100 square meters or more
5. In the case of other stairs, the effective width of the stairs and landings shall be at least 60 centimeters.
6. In the case of stairs installed in a workplace pursuant to the Industrial Safety and Health Act, they shall be of a structure prescribed by the Rules on Industrial Safety and Health Standards.
③ Handrails and flooring installed on main staircases, escape staircases, or special escape staircases of buildings used for the purposes of multi-unit housing (excluding dormitories), Class 1 neighborhood living facilities, Class 2 neighborhood living facilities, cultural and assembly facilities, religious facilities, sales facilities, transportation facilities, medical facilities, facilities for the elderly and children, office facilities, lodging facilities, entertainment facilities, or tourist and rest facilities shall be constructed to be safe for use by children and convenient for use by the elderly and persons with physical disabilities; in cases where there are walls on both sides and no handrails, handrails shall be installed. <Amended Apr. 7, 2010>
④ Handrails, walls, etc., and floor finishes pursuant to the provisions of Paragraph 3 shall be installed in accordance with the standards of each of the following subparagraphs. <Amended 2026.10.6>
1. The handle shall have a circular or elliptical cross-section with a maximum diameter of 3.2 centimeters or more and 3.8 centimeters or less.
2. The handrail shall be placed at least 5 centimeters away from the wall light, and the height from the stairs shall be 85 centimeters.
3. The handrail at the horizontal end of the stairs shall be installed so that it extends outward by at least 30 centimeters.
⑤ Ramps installed in place of stairs shall be installed in compliance with the standards of each of the following subparagraphs. <Amended Apr. 7, 2010, Oct. 6, 2026>
1. The slope shall not exceed 1:8
2. The surface shall be rough or finished with a non-slip material
3. The effective width of straight and bending sections of the ramp shall comply with the standards prescribed by the "Act on the Guarantee of Convenience Promotion for Persons with Disabilities, the Elderly, Pregnant Women, etc."
⑥ The provisions of each subparagraph of Paragraph 1 shall apply mutatis mutandis to the installation standards for ramps pursuant to the provisions of Paragraph 5. <Amended 2026.10.6>
⑦ Notwithstanding Paragraphs 1 and 2, in cases where a direct staircase leading to an evacuation floor or the ground is installed pursuant to the proviso of Article 34, Paragraph 4 of the Enforcement Decree, the effective width of the stairs and landings shall comply with the standards according to the classifications in each of the following subparagraphs. <Newly added Jan. 6, 2012; Apr. 6, 2015>
1. Multi-unit dwelling: 120 centimeters or more
2. Buildings other than multi-family housing: 150 centimeters or more
⑧ The provisions of Paragraphs 1 through 7 shall not apply to stairs used solely for special purposes, such as stairs for elevator machine rooms and stairs for watchtowers. <Amended Jan. 6, 2012>
Article 15-2 (Width and Installation Standards of Corridors)
① The effective width of a corridor installed in a building pursuant to the provisions of Article 48 of the Enforcement Decree shall be as shown in the following table.
<img src="http://www.law.go.kr/flDownload.do?flSeq=30607976" alt="img30607976" >
┌───────────────┬────────────┬──────┐
Classification Hallway with living rooms on both sides Other hallways
├───────────────┼────────────┼──────┤
Kindergarten/Elementary School 2.4 meters or more 1.8 meters or more
Middle School · High School
├───────────────┼────────────┼──────┤
Multi-unit housing · Officetel 1.8 meters or more 1.2 meters or more
├───────────────┼────────────┼──────┤
Floor area of the living room on the relevant floor is 1.5m or more (1.2m or more for medical facilities
If the total is 200 square meters or more, the corridor must be 1.8 meters or more)
└───────────────┴────────────┴──────┘
</img>
② Notwithstanding Paragraph 1, the effective width of corridors adjacent to viewing rooms or assembly rooms in cultural and assembly facilities (limited to performance halls, assembly halls, viewing halls, and exhibition halls), religious assembly halls among religious facilities, child-related facilities and elderly welfare facilities among facilities for the elderly and children, community training facilities among training facilities, and entertainment establishments and funeral homes among recreational facilities shall be the widths prescribed in each of the following subparagraphs. <Amended Apr. 7, 2010, Aug. 6, 2019>
1. In cases where the total floor area used for the relevant purpose on the relevant floor is less than 500 square meters, 1.5 meters or more
2. In cases where the total floor area used for the relevant purpose on the relevant floor is 500 square meters or more or less than 1,000 square meters, 1.8 meters or more
3. If the total floor area used for the relevant purpose on the relevant floor is 1,000 square meters or more, 2.4 meters or more
③ Corridors installed in performance halls among cultural and assembly facilities shall comply with the standards of each of the following subparagraphs. <Amended Aug. 6, 2019>
1. Corridors shall be installed on both sides and at the rear of individual viewing rooms in a performance hall (limited to cases where the floor area is 300 square meters or more).
2. In cases where two or more individual viewing rooms (limited to cases where the floor area is less than 300 square meters) are installed consecutively on a single floor, corridors shall be installed at the front and rear of the outer side of each viewing room.
④ In cases where a building falling under Article 37, Paragraph 1, Subparagraph 3 of the Enforcement Decree of the Special Act on Public Housing is to be converted to a quasi-residential building under Article 4 of the Enforcement Decree of the Housing Act pursuant to Article 19 of the Act, and all of the requirements of the following subparagraphs are met, the effective width of a corridor with living rooms on both sides within the converted building may be 1.5 meters or more, notwithstanding Paragraph 1. <Newly added 2021.10.15, 2026.10.6>
1. The purpose of the change of use must be to sell the relevant building to a public housing business operator intending to supply it as public purchase rental housing pursuant to Article 43, Paragraph 1 of the Special Act on Public Housing.
2. Two or more direct staircases shall be connected directly to the ground level
3. The effective width of the doorway leading from the interior of the building to the stairwell shall be at least 0.9 meters.
4. At the entrance referred to in Subparagraph 3, a fire door pursuant to Subparagraph 1 or 2 of Article 64, Paragraph 1 of the Enforcement Decree shall be installed so as to open in the direction of evacuation; provided that said fire door shall remain closed at all times or be structured to close automatically upon detecting smoke or flames caused by a fire. However, if it is not possible to make it structured to close automatically upon detecting smoke or flames, it may be structured to close automatically upon detecting temperature.
⑤ Notwithstanding Paragraph 1, in cases where the use of residential lodging facilities among lodging facilities (excluding cases where a building permit has been applied for with the effective width of a corridor with living rooms on both sides being 1.8 meters or more) is changed to an officetel among business facilities pursuant to Article 48, Paragraph 3 of the Enforcement Decree, the effective width of a corridor with living rooms on both sides within the officetel may be 1.5 meters or more. <Newly Added 2025.4.24>
[This Article Newly Established 2005.7.22]
Article 16 (Height of the living room)
① The ceiling of a living room installed pursuant to the provisions of Article 50 of the Ordinance (in cases where there is no ceiling, this refers to a beam, the underside of the floor slab of the floor immediately above, or other similar materials; hereinafter the same) shall have a height of 2.1 meters or more.
② Notwithstanding Paragraph 1, the height of the ceiling in a viewing room or assembly room with a floor area of 200 square meters or more in a building used for the purposes of a cultural and assembly facility (excluding exhibition halls and zoos/botanical gardens), religious facility, funeral home, or entertainment facility such as a nightclub shall be at least 4 meters (the height of the lower part of the balcony shall be 2.7 meters). However, this shall not apply if a mechanical ventilation system is installed. <Amended Apr. 7, 2010, Aug. 6, 2019>
Article 17 (Windows, etc. for Lighting and Ventilation)
① Pursuant to Article 51 of the Enforcement Decree, the area of windows, etc. installed in a living room for natural lighting shall be at least one-tenth of the floor area of the living room. However, this shall not apply if lighting devices with an illuminance equal to or greater than that specified in Annex 1-3 are installed according to the use of the living room. <Amended 2000.6.3, 2010.4.7, 2012.1.6>
② The area of windows, etc. installed in a living room for ventilation pursuant to the provisions of Article 51 of the Enforcement Decree shall be at least one-twentieth of the floor area of said living room. However, this shall not apply in cases where mechanical ventilation systems and centrally managed air conditioning systems are installed.
③ In applying the provisions of Paragraphs 1 and 2, two rooms partitioned by a sliding door that can be opened at any time shall be deemed as one room.
4. In Article 51, Paragraph 3 of the Enforcement Decree, the term "standards prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to handrails or other similar safety facilities for preventing falls that are 1.2 meters or higher in height. <Newly added Apr. 7, 2010; Mar. 23, 2013>
Article 18 (Moistureproofing for Living Rooms, etc.)
① Pursuant to the provisions of Article 52 of the Enforcement Decree, the height of the floor of a living room on the lowest floor of a building shall be at least 45 centimeters from the ground surface. However, this shall not apply in cases where measures for moisture prevention, such as installing a concrete floor on the ground surface, are taken.
② Pursuant to Article 52 of the Enforcement Decree, the floors of bathrooms or kitchens falling under any of the following subparagraphs, and the finishes of the interior walls up to a height of 1 meter from such floors, shall be made of water-resistant materials. <Amended Apr. 7, 2010; Aug. 27, 2021>
1. Bathrooms of bathhouses and kitchens of rest area restaurants among Class 1 neighborhood living facilities
2. Kitchens of general restaurants and rest area restaurants among Class 2 neighborhood living facilities and bathrooms of accommodation facilities
Article 18-2 (Standards for Firefighter Access Windows) The term "standards prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" in Article 49, Paragraph 3 of the Act refers to satisfying all of the requirements of each of the following subparagraphs. <Amended Aug. 26, 2024; Nov. 15, 2024; Sep. 19, 2025>
1. Install at least one location on each floor from the 2nd floor up to the 11th floor. However, installation may be omitted on floors with an entrance leading directly to the ground and on floors where the height of the upper surface of the floor structure exceeds 44 meters from the ground surface.
1-2. If the horizontal distance from the center of a window accessible to firefighters to the edge of the wall is 40 meters or more, an additional window accessible to firefighters shall be installed at intervals of no more than 40 meters. However, in unavoidable cases, this requirement may be relaxed in accordance with the review materials or opinions of the Head of the Fire Headquarters or the Head of the Fire Station pursuant to Article 6, Paragraph 5 of the Act on the Installation and Management of Firefighting Facilities.
2. It shall face a fire truck access road or an open space accessible to fire trucks
3. Mark the center of the window with an inverted triangle at least 20 centimeters in diameter using a reflective material or in red so that it is visible even at night.
4. Mark the impact point on one corner of the window as a circle with a diameter of at least 3 centimeters
5. The size of the window glass shall be at least 90 centimeters in width and 1 meter in height, and the height from the indoor floor to the bottom of the window shall be within 80 centimeters [120 centimeters in cases where a firefighter access window is inevitably installed on a balcony, etc. equipped with a railing (referring to a balcony, etc. pursuant to Article 40, Paragraph 1 of the Enforcement Decree)].
6. Use glass corresponding to any of the following items
A. Float plate glass with a thickness of 6 millimeters or less
b. Tempered glass or heat-strengthened glass with a thickness of 5 millimeters or less
c. Double glass composed of glass corresponding to Item (a) or (b)
D. Triple glass composed of glass corresponding to Item A or B. In this case, if an anti-shatter film is attached to each glass, the thickness of the film shall be 50 micrometers or less.
[This Article Newly Established 2019.8.6]
Article 19 (Structure of Boundary Walls, etc.)
① Boundary walls installed in a building pursuant to Article 49, Paragraph 4 of the Act shall be of a fire-resistant structure and shall extend to the underside of the roof or the floor slab of the immediately above floor. <Amended Nov. 28, 2014, Aug. 6, 2019>
② The boundary walls pursuant to Paragraph 1 shall be constructed in a manner corresponding to any of the following subparagraphs so as not to have any parts that hinder sound blocking. However, in the case of boundary walls between households in multi-family housing and apartment buildings, Article 14 of the “Regulations on Housing Construction Standards, etc.” shall apply. <Amended 2005.7.22, 2008.3.14, 2010.4.7, 2013.3.23, 2014.11.28>
1. Reinforced concrete structures or steel-reinforced concrete structures with a thickness of 10 centimeters or more
2. Plain concrete or masonry structures with a thickness of 10 centimeters or more (including the thickness of cement mortar, plaster, or gypsum plaster application)
3. Concrete block or brick masonry with a thickness of 19 centimeters or more
4. In addition to the items in Nos. 1 through 3, items whose performance has been confirmed in a quality test conducted by a person designated by the Minister of Land, Infrastructure and Transport or by the President of the Korea Institute of Construction Technology, in accordance with standards prescribed and notified by the Minister of Land, Infrastructure and Transport.
5. That which the President of the Korea Institute of Construction Technology recognizes in accordance with the recognition standards established pursuant to Article 27, Paragraph 1
③ Floors intended to prevent noise between households, etc., pursuant to Article 49, Paragraph 4 of the Act shall be constructed to block lightweight impact sound (referring to floor impact sound caused by relatively light and hard impacts) and heavyweight impact sound (referring to floor impact sound caused by heavy and soft impacts). <Newly added 2014.11.28, 2024.8.26>
④ Detailed standards for floors to prevent noise between households, households, etc. pursuant to Paragraph 3 shall be determined and announced by the Minister of Land, Infrastructure and Transport. <Newly added 2014.11.28>
[Title revised 2014.11.28]
Article 19-2 (Flood Prevention Facilities) In Article 49, Paragraph 5, Subparagraph 2 of the Act, the term "flood prevention facilities prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to the facilities set forth in each of the following subparagraphs. <Amended Aug. 26, 2024>
1. Water blocking plate
2. Check valve
[This Article Newly Established 2015.7.9]
Article 20 (Chimneys Installed in Buildings) Chimneys installed in buildings pursuant to Article 54 of the Enforcement Decree shall comply with the standards in each of the following subparagraphs. <Amended Apr. 7, 2010>
1. The vertical distance from the roof surface of a chimney protruding from the roof shall be at least 1 meter. However, in the case of a building with a ridge, stair tower, rooftop structure, etc., if there are obstacles around the chimney that obstruct the discharge of smoke, the top of the chimney shall be higher than the ridge, stair tower, rooftop structure, etc.
2. If there is another building within a horizontal distance of 1 meter from the top of the chimney, it shall be at least 1 meter higher than the eaves of that building.
3. For metal chimneys, the portion of the chimney located within the roof, above the ceiling, and beneath the lowest floor of the building shall be covered with non-combustible materials other than metal.
4. Metal chimneys shall be installed at a distance of at least 15 centimeters from wood or other combustible materials. However, this shall not apply if covered with non-combustible materials other than metal with a thickness of at least 10 centimeters.
Article 20-2 (Factory Buildings Excluded from Application of Fire-Resistant Structures) In the proviso to Subparagraph 3 of Article 56, Paragraph 1 of the Enforcement Decree, the term "factory prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to a factory falling under the business sectors listed in Annex 2, which is a factory of two stories or less whose main structural components are made of non-combustible materials. <Amended 2005.7.22, 2008.3.14, 2009.7.1, 2013.3.23>
[This Article Newly Established 2000.6.3]
Article 21 (Structure of Firewalls)
① Firewalls installed in buildings pursuant to Article 57, Paragraph 2 of the Enforcement Decree shall comply with the standards of each of the following subparagraphs. <Amended Apr. 7, 2010; Mar. 26, 2021; Nov. 15, 2024>
1. It shall be a fire-resistant structure capable of standing on its own
2. Both ends and the top end of the fire wall shall protrude at least 0.5 meters from the exterior walls and roof surfaces of the building.
3. The width and height of doors installed in firewalls shall each be 2.5 meters or less, and 60-minute+ fire doors or 60-minute fire doors shall be installed in said doors.
② The provisions of Article 14, Paragraph 2 shall apply mutatis mutandis to the structure of firewalls pursuant to the provisions of Paragraph 1.
Article 22 (Exterior Walls, etc. of Large-Scale Wooden Buildings)
① Pursuant to the provisions of Article 57, Paragraph 3 of the Enforcement Decree, wooden buildings with a gross floor area of 1,000 square meters or more shall have exterior walls and parts under the eaves that are susceptible to combustion constructed of fire-resistant materials, while the roofs shall be made of non-combustible materials.
② In Paragraph 1, the term "parts at risk of combustion" refers to any part of a building located within 3 meters of the first floor and within 5 meters of the second floor or higher from an adjacent site boundary, a road centerline, or the centerline between the outer walls of two or more buildings on the same site (buildings with a total floor area of 500 square meters or less shall be deemed as one building). However, parts arising from open spaces or water surfaces of parks, plazas, or rivers, or fire-resistant walls or similar structures, shall be excluded.
Article 22-2 (Indication of Evacuation Use for Evacuation Safety Zones, etc. in High-Rise Buildings) Pursuant to Article 50-2, Paragraph 2 of the Act, evacuation safety zones, evacuation facilities, or evacuation spaces installed in high-rise buildings shall be marked as being used for evacuation purposes in the event of fire, etc., in accordance with the provisions of each of the following subparagraphs.
1. Evacuation Safety Zone
a. Install a sign bearing the words "Evacuation Safety Zone" in a conspicuous place on the upper wall or side wall of the entrance.
B. Install a signboard in a conspicuous place on the side wall of the entrance stating the purpose and use of the space and a notice that it shall not be used for any other purpose.
2. Stairwells of special escape stairs and their ancillary rooms, stairwells of escape stairs and landings of escape elevators
a. Install a signboard in a conspicuous place on the side wall of the entrance stating the purpose and use of the space and a notice that it shall not be used for any other purpose.
B. If the building has an evacuation safety zone, indicate the floor containing the evacuation safety zone on the signboard pursuant to Subparagraph A.
3. Evacuation Space: Install a sign on the entrance door stating that the space is an evacuation area in case of fire, etc., and that it should not be used for other purposes such as storing items.
[This Article Newly Established 2015.7.9]
Article 23 (Roofs, fire doors, exterior walls, etc. in fire-prone areas)
① Pursuant to Article 51, Paragraph 3 of the Act, roofs of buildings within a fire-prone district that are not of a fire-resistant structure shall be made of non-combustible materials. <Amended 2005.7.22, 2010.12.30, 2015.7.9>
② In accordance with Article 51, Paragraph 3 of the Act, fire prevention facilities specified in each of the following subparagraphs shall be installed in windows, etc., installed on exterior walls facing the adjacent site boundary of a building within a fire prevention district, in parts where there is a risk of combustion pursuant to Article 22, Paragraph 2. <Amended 2005.7.22, 2010.4.7, 2010.12.30, 2021.3.26, 2024.11.15>
1. 60-minute+ fire door or 60-minute fire door
2. Drenchers installed on windows, etc. in accordance with the standards prescribed by fire safety laws
3. Walls, fences, or other similar fire prevention facilities made of fire-resistant structures or non-combustible materials that block the relevant windows, etc. from other parts of the building that are at risk of combustion
4. Fireproof cover made of non-combustible material or metal mesh with a mesh size of 2 millimeters or less installed in ventilation holes
Article 24 (Finishing Materials, etc. of Buildings)
① Pursuant to Article 52, Paragraph 1 of the Act, for buildings falling under each subparagraph of Article 61, Paragraph 1 of the Enforcement Decree, the finishing materials (including insulation materials in the case of buildings falling under Article 61, Paragraph 1, Subparagraph 4 of the Enforcement Decree) of the interior-facing parts of the walls and ceilings of living rooms (excluding ceiling moldings, window sills, and other similar items; hereinafter the same applies in this Article) shall be non-combustible, semi-non-combustible, or flame-retardant materials. However, the finishing materials for parts falling under each of the following subparagraphs shall be non-combustible or semi-non-combustible materials. <Amended 2005.7.22, 2010.4.7, 2010.12.30, 2021.9.3>
1. The main corridor and stairs leading from the living room to the ground floor, and other walls and ceilings facing the interior
2. Part using a composite material consisting of steel plate and core material as a finishing material
② Notwithstanding Paragraph 1, the finishing of the interior-facing parts of walls and ceilings of rooms falling under any of the following subparagraphs among buildings specified in each subparagraph of Article 61, Paragraph 1 of the Enforcement Decree shall be made of non-combustible or semi-non-combustible materials. <Amended Jan. 6, 2003; Jul. 22, 2005; Jun. 29, 2006; Apr. 7, 2010; Dec. 30, 2010>
1. A room, etc. used for purposes under each subparagraph of Article 61, Paragraph 1 of the Enforcement Decree, installed in a basement or underground structure (including doors and door frames)
2. A living room in a building used for the purpose under Article 61, Paragraph 1, Subparagraph 6 of the Enforcement Decree
③ Notwithstanding Paragraphs 1 and 2, in cases where insulation materials are used in a building falling under Subparagraph 4 of Paragraph 1 of Article 61 of the Enforcement Decree, and it is difficult to use non-combustible, semi-non-combustible, or flame-retardant materials as insulation materials considering the structure, design, or construction method of the said building, and the matter has been deliberated by the Architectural Committee pursuant to Article 4 of the Act (referring to the Architectural Committee established in a City, Province, or City, County, or District), insulation materials that are not non-combustible, semi-non-combustible, or flame-retardant materials may be used. <Newly Added 2021.9.3>
④ In Article 52, Paragraph 1 of the Act, the term "interior finishing materials" refers to finishing materials attached to ceilings, suspended ceilings, walls (including boundary walls), columns, etc., within a building. However, interior decorations pursuant to Article 3 of the Enforcement Decree of the Special Act on Safety Management of Multi-Use Facilities shall be excluded. <Newly added 2003.1.6, 2005.7.22, 2010.4.7, 2010.12.30, 2014.11.28, 2021.9.3>
⑤ Multi-unit dwellings pursuant to Article 61, Paragraph 1, Subparagraph 1-2 of the Enforcement Decree shall use building materials that do not exceed the pollutant emission standards pursuant to Article 11, Paragraph 1 of the Indoor Air Quality Management Act and Article 10 of the Enforcement Rule of the same Act. <Amended 2026.10.6>
6. For the exterior walls of buildings falling under Subparagraphs 1 through 3 and Subparagraph 5 of Article 61, Paragraph 2 of the Enforcement Decree, non-combustible or semi-non-combustible materials shall be used as finishing materials (including insulation materials, coating materials such as paint, and all other materials constituting finishing materials; hereinafter the same applies in this Article) in accordance with the latter part of Article 52, Paragraph 2 of the Act. However, flame-retardant materials (limited to those notifying composite materials composed of steel plates and core materials) may be used if the finishing materials are installed in compliance with the fire spread prevention structural standards prescribed and notified by the Minister of Land, Infrastructure and Transport. <Amended Aug. 6, 2019, Sep. 3, 2021, Feb. 10, 2022>
1. Deleted<2022.2.10>
2. Delete<2022.2.10>
7. Notwithstanding Paragraph 6, for buildings falling under Subparagraphs 1, 3, and 5 of Paragraph 2 of the Enforcement Decree that are five stories or less and less than 22 meters in height, flame-retardant materials (limited to those excluding composite materials composed of steel plates and core materials) may be used as finishing materials. However, if the exterior walls of the building are installed in accordance with the fire spread prevention structural standards prescribed and notified by the Minister of Land, Infrastructure and Transport, materials without flame-retardant performance (limited to those excluding composite materials composed of steel plates and core materials) may be used as finishing materials. <Amended Aug. 6, 2019; Sep. 3, 2021; Feb. 10, 2022>
⑧ Where the finishing materials under Paragraphs 6 and 7 are made of two or more materials, said finishing materials must satisfy all of the requirements of each of the following subparagraphs. <Newly added Feb. 10, 2022; Aug. 31, 2023>
1. The results of a full-scale model test (referring to testing using a model similar to the structure of the building to be actually constructed; hereinafter the same) conducted in accordance with the standards prescribed and notified by the Minister of Land, Infrastructure and Transport, treating the entire material constituting the finishing material as a single unit, shall satisfy the standards prescribed and notified by the Minister of Land, Infrastructure and Transport.
2. The results of flame retardant performance tests for each material constituting the finishing material shall satisfy the standards prescribed and notified by the Minister of Land, Infrastructure and Transport. However, in the case of materials manufactured by attaching another material (only applicable if the thickness is 5 millimeters or less) between non-combustible materials pursuant to Article 6, Subparagraph 1, the entire material may be treated as a single material for flame retardant performance testing; additionally, in the case of materials coated with a thickness of 0.1 millimeters or less on non-combustible materials pursuant to the same subparagraph, the flame retardant performance test may be omitted as it is deemed to satisfy the performance standards for non-combustible materials.
⑨ Among the changes in use between buildings falling under any of the subparagraphs of Article 14, Paragraph 4 of the Enforcement Decree, the change to a use corresponding to subparagraphs c (only applicable to bathhouses) and d of Subparagraph 3 of Table 1 of the Enforcement Decree, subparagraphs a, g, k, and p (only applicable to golf practice ranges and recreational facilities), d and r of Subparagraph 4 of the same Table, subparagraph c2) of Subparagraph 7 of the same Table, and subparagraphs a and b of Subparagraph 16 of the same Table, where the heads of sprinklers or simple sprinklers are installed within 60 centimeters from windows, etc., and the interior of the building is protected from fire, the provisions of Paragraphs 6 through 8 may not apply. <Newly added 2021.7.5, 2021.9.3, 2022.2.10, 2025.9.19>
10. For the exterior walls of a building falling under Article 61, Paragraph 2, Subparagraph 4 of the Enforcement Decree [including ceilings and walls facing the outside air in a pilotis structure], the parts of the first and second floors shall be finished with non-combustible or semi-non-combustible materials. <Newly added Aug. 6, 2019; Jul. 5, 2021; Sep. 3, 2021; Feb. 10, 2022>
⑪ When using a composite material composed of steel plate and core material as a finishing material, said composite material must satisfy all of the requirements of each of the following subparagraphs. <Newly added 2022.2.10>
1. The result of conducting a full-scale model test in accordance with the standards prescribed and notified by the Minister of Land, Infrastructure and Transport, treating the steel plate and core material as a whole, shall satisfy the standards prescribed and notified by the Minister of Land, Infrastructure and Transport.
2. Steel Plate: Must satisfy all criteria according to the classifications in each of the following items
A. Thickness [Refers to the thickness after plating and before painting]: 0.5 millimeters or more
B. Number of coats on the front: 2 or more
C. Amount of plating: Depending on the type of plating, it shall fall under any one of the following. In this case, the type of plating shall comply with the Korean Industrial Standard.
1) Hot-dip galvanized steel sheet: 180g/㎡ or more
2) Hot-dip galvanized steel sheet: 90g/㎡ or more
3) Hot-dip 55% Aluminum-Zinc-Magnesium Alloy Plated Steel Sheet: 90g/㎡ or more
4) Hot-dip 55% Aluminum-Zinc Alloy Coated Steel Sheet: 90g/㎡ or more
5) Other plating: Above the standards prescribed and notified by the Minister of Land, Infrastructure and Transport
3. Core material: The core material from which the steel plate has been removed shall fall under any of the following items
a. Glass wool insulation boards or mineral wool insulation boards in accordance with Korean Industrial Standards that comply with the standards prescribed and notified by the Minister of Land, Infrastructure and Transport
B. Non-combustible or semi-non-combustible materials
12. In accordance with Article 52, Paragraph 4 of the Act, if the distance between a window installed on an exterior wall adjacent to the adjacent land boundary of a building falling under each subparagraph of Article 61, Paragraph 2 of the Enforcement Decree and the adjacent land boundary is within 1.5 meters, the window must be installed as a fire-resistant glass window [limited to those having a non-thermal insulation performance of at least 20 minutes as a result of testing a glass partition composed of a window frame and glass, etc., according to the method prescribed in Korean Industrial Standard KS F 2845 (Fire Resistance Test Method for Glass Partitions)]. However, if the interior of the building is protected from fire by installing a sprinkler or simple sprinkler head within 60 centimeters of the window, it may not be installed as a fire-resistant glass window. <Newly added 2021.7.5, 2021.9.3, 2022.2.10, 2024.11.15>
[Title Revised 2021.7.5]
Article 24-2 (Finishing materials for buildings adjacent to factories with low fire risk)
① In Article 61, Paragraph 2, Subparagraph 1, Item (b) of the Enforcement Decree, the term "factory with low fire risk prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to a factory corresponding to the business sectors listed in Annex 3. However, buildings used in part or all of the factory for the purposes of dormitories and cafeterias shall be excluded. <Amended 2008.3.14, 2010.12.30, 2012.1.6, 2013.3.23, 2021.9.3>
② Delete <2021.9.3>
③ Delete <2021.9.3>
[This Article Newly Established 2005.7.22]
[Title Revised 2021.9.3]
Article 24-3 (Construction Material Quality Control Statement)
① In Article 62, Paragraph 1, Subparagraph 4 of the Enforcement Decree, the term "building materials prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to fire-resistant structures constituting fire compartments, automatic fire shutters, structures recognized for fire-resistant filling performance, and fire dampers in accordance with Article 46 of the Enforcement Decree and Article 14 of these Rules. <Amended Mar. 26, 2021; Dec. 23, 2021>
② In Article 52-4, Paragraph 1 of the Act, the term "quality control document containing matters prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to the forms classified according to the following subparagraphs. In this case, the documents prescribed in the following subparagraphs (limited to documents valid at the time of installation or construction of the relevant building materials) shall be attached. <Amended 2021.3.26, 2021.12.23, 2022.2.10, 2024.8.26>
1. In the case of Article 62, Paragraph 1, Subparagraph 1 of the Enforcement Decree: Attached Form No. 1. In this case, attach the documents listed in each of the following subparagraphs.
A. A copy of the test report for composite materials (limited to core materials) indicating flame-retardant performance [In cases where quality recognition has been obtained pursuant to Article 52-5, Paragraph 1 of the Act, the Quality Recognition Certificate prescribed and notified by the Minister of Land, Infrastructure and Transport pursuant to Article 52-6, Paragraph 7 of the Act (hereinafter referred to as "Quality Recognition Certificate")]
B. Copy of the quality inspection certificate from the steel sheet manufacturer indicating the thickness, type of plating, and amount of plating applied to the steel sheet
C. Copy of the composite material test report indicating the results of the full-scale model test (or the quality certification in cases where quality certification has been obtained pursuant to Article 52-5, Paragraph 1 of the Act)
2. In the case of Article 62, Paragraph 1, Subparagraph 2 of the Enforcement Decree: Form No. 2 attached hereto. In this case, attach the documents listed in each of the following items.
A. A copy of the insulation test report indicating flame-retardant performance. In this case, if the insulation is made of two or more materials, a separate report must be attached for each material.
B. Copy of insulation test report showing full-scale model test results (to be attached only if the exterior wall finishing material is made of two or more materials)
3. In the case of Article 62, Paragraph 1, Subparagraph 3 of the Enforcement Decree: Attach Form No. 3. In this case, attach a copy of the fire door test report (or the quality certification if quality certification has been obtained pursuant to Article 52-5, Paragraph 1 of the Act) indicating the performance ability to block smoke, flames, and heat.
3-2. In the case of fire-resistant structures: Form No. 3-2. In this case, attach a copy of the test report indicating the fire resistance performance time (or the quality certification if quality certification has been obtained pursuant to Article 52-5, Paragraph 1 of the Act).
4. For automatic fire shutters: Attach Form No. 4. In this case, attach a copy of the automatic fire shutter test report (or the quality certification if quality certification has been obtained pursuant to Article 52-5, Paragraph 1 of the Act) indicating the performance ability to block smoke and flames.
5. For structures with recognized fire-resistant filling performance: Attach Form No. 5. In this case, attach a copy of the test report for the fire-resistant filling structure indicating the performance to block smoke, flames, and heat (or the certificate of quality recognition in cases where quality recognition has been obtained pursuant to Article 52-5, Paragraph 1 of the Act).
6. For fire dampers: Attach Form No. 6. In this case, attach a copy of the test report certifying compliance with the smoke control test method for fire dampers specified in the Korean Industrial Standards pursuant to the Industrial Standardization Act.
③ The construction contractor shall prepare a building materials quality control ledger in the form of Annex 7, identical to the contents of the quality control document prepared pursuant to Article 52-4, Paragraph 1 of the Act, and submit it to the construction supervisor.
4. The construction supervisor shall verify whether the contents of the building material quality control ledger submitted pursuant to Paragraph 3 are identical to the contents of the quality control document submitted pursuant to Article 62, Paragraph 3 of the Enforcement Decree, and submit this to the building owner pursuant to Article 62, Paragraph 4 of the Enforcement Decree.
⑤ The building owner shall submit the ledger of building material quality control certificates received pursuant to Paragraph 4 to the licensing authority in accordance with Article 62, Paragraph 4 of the Enforcement Decree.
[Wholly Revised 2019.10.24]
Article 24-4 (Disclosure of Quality Control Information for Construction Materials)
① The head of a testing institution commissioned to conduct a performance test of building materials pursuant to Article 52-4, Paragraph 2 of the Act (hereinafter referred to as the "Head of the Building Material Performance Testing Institution") shall issue a test report (hereinafter referred to as the "Test Report") containing matters prescribed and notified by the Minister of Land, Infrastructure and Transport according to the type of building material to the manufacturer and distributor who commissioned the performance test.
② The head of the building material performance testing institution that issued the test report pursuant to Paragraph 1 shall submit a copy of the test report to an institution or organization designated and notified by the Minister of Land, Infrastructure and Transport (hereinafter referred to as "institution or organization") within 7 days from the date of issuance. However, this shall not apply in any of the following cases:
1. In cases where a manufacturer or distributor who requested a performance test of building materials requested the test for the purpose of not using the material in a building
2. Cases where it cannot be used in a building due to failing to meet the performance standards prescribed by law
③ Manufacturers and distributors of building materials who have received a test report pursuant to Paragraph 1 shall notify the relevant institution or organization of the type, use, color, material, and specifications of the building material for which the performance test was requested within one month from the date of issuance of the test report. However, this shall not apply in cases falling under any of the subparagraphs of Paragraph 2.
4. Institutions or organizations shall, in accordance with Article 52-4, Paragraph 4 of the Act, post the matters in each of the following subparagraphs on their websites, etc., so that the general public may be aware of them.
1. Copy of the test report submitted pursuant to Paragraph 2
2. Type, use, color, material and specifications of building materials notified pursuant to Paragraph 3
⑤ An institution or organization shall notify the head of the building material performance testing institution that issued the test report one month prior to the expiration of the validity period of the test report prescribed and notified by the Minister of Land, Infrastructure and Transport.
⑥ An institution or organization shall indicate the fact regarding test reports that have expired pursuant to Paragraph 5 and post them on the website, etc., of the relevant institution or organization.
7. Institutions or organizations shall report the performance of information disclosure pursuant to Paragraphs 4 and 6 to the Minister of Land, Infrastructure and Transport on a quarterly basis.
[This Article Newly Established 2019.10.24]
Article 24-5 (Insulation materials required to display information on the surface of building materials) In Article 52-4, Paragraph 5 of the Act, the term "insulation materials prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to insulation materials pursuant to Article 62, Paragraph 1, Subparagraph 2 of the Enforcement Decree.
[This Article Newly Established 2019.10.24]
Article 24-6 (Composite materials, etc. subject to quality recognition)
① In Article 63-2, Subparagraph 1 of the Enforcement Decree, the term "composite material composed of steel plate and core material prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to a composite material composed of steel plate and insulation material.
② In subparagraph 4 of Article 63-2 of the Enforcement Decree, "building materials and fire-resistant structures prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to fire-resistant structures pursuant to subparagraphs 8 through 10 of Article 3.
[This Article Newly Established 2021.12.23]
Article 24-7 (Standards for Quality Recognition of Construction Materials, etc.) In Article 52-5, Paragraph 1 of the Act, the term "standards prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to the standards set forth in each of the following subparagraphs. <Amended Oct. 6, 2026>
1. As a result of verifying the applicant's manufacturing site, the person applying for quality certification or extension of the quality certification validity period shall be complying with each of the following items:
A. Standards regarding each of the following items submitted by the applicant when applying for quality accreditation or extension of the validity period of quality accreditation (in the case of an application for extension of the validity period, this refers to the accredited standards)
1) Quality Control Standards for Raw Materials and Finished Products
2) Manufacturing Process Control Standards
3) Calibration Standards for Manufacturing and Inspection Equipment
B. Assignment of Lot Numbers to Construction Materials, etc. (hereinafter referred to as "Construction Materials, etc.") pursuant to Article 52-5, Paragraph 1 of the Act
2. As a result of testing on building materials, etc., the building materials, etc. shall satisfy the quality standards according to the classifications in each of the following items.
A. Composite materials under Article 63-2, Subparagraph 1 of the Enforcement Decree: Flame retardant performance pursuant to Article 24
B. Automatic fire shutters under Article 63-2, Subparagraph 2, Item A of the Enforcement Decree: Installation standards for automatic fire shutters pursuant to Article 14, Paragraph 2, Subparagraph 4
C. Structures recognized for fire-resistant filling performance under Article 63-2, Subparagraph 2, Item B of the Enforcement Decree: Standards for fire resistance time pursuant to Item 1 of Annex 1 (referring to the fire resistance time applied to constituent members filled with structures recognized for fire-resistant filling performance)
D. Fire doors under Article 63-2, Subparagraph 3 of the Enforcement Decree: Smoke, flame, and heat blocking time according to the classifications in each subparagraph of Article 64, Paragraph 1 of the Enforcement Decree
E. Fire-resistant structure pursuant to Article 24-6, Paragraph 2: Fire resistance performance standards pursuant to Annex 1
B. Newly developed products or products outside the standard specifications where it is difficult to determine performance or quality standards: Recognition standards established by the President of the Korea Institute of Construction Technology pursuant to Article 27, Paragraph 1
3. Satisfy other standards related to quality recognition prescribed and notified by the Minister of Land, Infrastructure and Transport
[This Article Newly Established 2021.12.23]
Article 24-8 (Quality Certification Fee for Construction Materials, etc.)
① The types of fees pursuant to Article 52-6, Paragraph 2 of the Act are as follows:
1. Quality Certification Application Fee
2. Fee for Application for Extension of Quality Certification Validity Period
② The fees pursuant to Paragraph 1 are as set forth in Attached Table 4.
③ Any person who intends to apply for quality certification or an extension of the validity period of quality certification shall pay a fee at the time specified in each of the following subparagraphs.
1. Basic and additional fees: When applying for quality certification or extension of the validity period of quality certification
2. Travel expenses and consulting fees among the fees: Payment timing notified by the President of the Korea Institute of Construction Technology
④ The President of the Korea Institute of Construction Technology shall refund all or part of the paid fees in any of the following cases.
1. In the case where the applicant withdraws the application before the testing, inspection, etc. for quality accreditation or the extension of the validity period of quality accreditation is conducted
2. In case the application is rejected
3. In case of overpayment of fees
⑤ Detailed matters necessary for the payment and refund of fees, such as the method of payment and refund and the amount of refund, shall be determined and announced by the Minister of Land, Infrastructure and Transport.
[This Article Newly Established 2021.12.23]
Article 24-9 (Inspection of Manufacturers, etc. of Quality-Certified Materials, etc.)
① The President of the Korea Institute of Construction Technology shall, in accordance with Article 52-6, Paragraph 4 of the Act, inspect the testing sites of testing institutions pursuant to Article 52-4, Paragraph 2 of the Act, the manufacturing sites of manufacturers pursuant to Article 52-6, Paragraph 4 of the Act, the distribution sites of distributors, and construction sites at least once a year.
② When the President of the Korea Institute of Construction Technology inspects manufacturing sites, etc. pursuant to Paragraph 1, he/she shall verify the matters in each of the following subparagraphs.
1. Raw data, test specimen fabrication and verification records prepared by a testing institution pursuant to Article 52-4, Paragraph 2 of the Act in relation to quality-certified materials, etc.
2. Validity period of quality recognition and quality recognition mark of quality-recognized materials, etc. (hereinafter referred to as "quality-recognized materials, etc.") pursuant to Article 52-6, Paragraph 3 of the Act
3. Delivery Confirmation and Quality Control Statement prepared by the Manufacturer
4. Documents in each of the following items that can verify the construction status at the construction site
A. Detailed Approval Contents of Quality-Approved Materials, etc.
B. Design Documents and Work Manuals
C. Documents concerning construction supervision
D. Other documents capable of verifying the construction status, as prescribed and notified by the Minister of Land, Infrastructure and Transport
③ The detailed procedures and methods for the inspection under Paragraph 1 shall be determined and announced by the Minister of Land, Infrastructure and Transport.
[This Article Newly Established 2021.12.23]
Article 25 (Structure of Basement Floors)
① The structure and facilities of basement floors installed in a building pursuant to Article 53 of the Act shall comply with the standards set forth in each of the following subparagraphs. <Amended Jan. 6, 2003; Jul. 22, 2005; Jun. 29, 2006; Apr. 7, 2010; Dec. 30, 2010; Aug. 26, 2024>
1. On floors where the floor area of a living space is 50 square meters or more, emergency exits and ventilation shafts leading to the evacuation floor or the ground shall be installed in addition to direct staircases. However, this shall not apply if two or more direct staircases conforming to the standards of each subparagraph of Article 8, Paragraph 2 are installed.
1-2. In buildings where the total floor area of the rooms on a floor used for the purposes of a multi-use business pursuant to Article 2 of the Enforcement Decree of the Special Act on Safety Management of Multi-use Establishments is 50 square meters or more, and where two or more direct staircases conforming to the standards of each subparagraph of Article 8, Paragraph 2 are installed, the following shall be installed: 1-2. Among Class 2 Neighborhood Living Facilities, performance halls, bars, billiard halls, and karaoke rooms; among Culture and Assembly Facilities, wedding halls and performance halls; among Training Facilities, residential training facilities and nature training facilities; among Accommodation Facilities, inns and guesthouses; among Entertainment Facilities, bars and nightclubs; or among Entertainment Facilities, bars and nightclubs.
2. For floors with a floor area of 1,000 square meters or more, at least one direct staircase leading to the evacuation floor or the ground shall be installed in each section partitioned by fire compartments pursuant to Article 46 of the Enforcement Decree, and shall be constructed as an evacuation staircase or a special evacuation staircase.
3. Ventilation equipment shall be installed on floors where the total floor area of living spaces is 1,000 square meters or more
4. For basement floors with a floor area of 300 square meters or more, at least one water tap for drinking water supply shall be installed.
② Emergency exits in basement floors pursuant to Paragraph 1, Subparagraph 1 shall comply with the standards of each of the following subparagraphs. However, this shall not apply to residential buildings. <Amended June 3, 2000, April 7, 2010>
1. The effective width of the emergency exit shall be at least 0.75 meters, and the effective height shall be at least 1.5 meters.
2. Emergency exit doors shall open in the direction of evacuation and be designed to be openable from the interior at all times; emergency exit signs shall be marked on the interior and exterior.
3. Emergency exits shall be installed at a distance of at least 3 meters from the entrance.
4. If the height from the basement floor to the lower part of the emergency exit is 1.2 meters or more, install a ladder on the wall with a step width of 20 centimeters or more.
5. Emergency exits shall be installed so as to directly connect to or link to corridors or direct staircases leading to the evacuation floor or the ground floor, and the effective width of the evacuation passageway leading to the corridor or direct staircase leading to the evacuation floor or the ground floor shall be at least 0.75 meters, and the finish and substrate of the parts of the evacuation passageway facing the interior shall be made of non-combustible materials.
6. Do not leave objects or install facilities that obstruct passage in the entrances to emergency exits or evacuation routes.
7. The installation of guide lights for emergency exits and emergency lighting for evacuation passages shall comply with the Fire Prevention Act.
Article 26 (Structure of Fire Doors) Fire doors pursuant to Article 64, Paragraph 1 of the Enforcement Decree shall secure performance in accordance with the standards set forth in each subparagraph of Article 64, Paragraph 1 of the Enforcement Decree as a result of quality testing conducted by the President of the Korea Institute of Construction Technology in accordance with the procedures prescribed and notified by the Minister of Land, Infrastructure and Transport. <Amended 2021.12.23>
1. Delete<2021.12.23>
2. Delete<2021.12.23>
[Wholly Revised 2021.3.26]
Article 27 (Recognition pursuant to the recognition standards for new products)
① In cases where the President of the Korea Institute of Construction Technology intends to grant performance or quality recognition for newly developed products or products outside of standard specifications (hereinafter referred to as "new products") for which it is difficult to determine performance or quality standards pursuant to Articles 3, 19, and 24-7, he/she may establish standards for verifying performance and quality that have undergone deliberation by the Advisory Committee (hereinafter referred to as the "Committee"). <Amended 2026.10.6>
② A committee composed of relevant experts shall be established at the Korea Institute of Construction Technology to provide consultation pursuant to Paragraph 1.
③ The President of the Korea Institute of Construction Technology shall notify the relevant applicant of the accreditation standards determined pursuant to Paragraph 1 without delay and post them on the internet homepage of the Korea Institute of Construction Technology.
④ The standards and procedures for performance and quality recognition pursuant to the provisions of Paragraphs 1 through 3, the operation and composition of the Committee, and other necessary specific matters shall be determined by the President of the Korea Institute of Construction Technology. <Amended Oct. 6, 2026>
[This Article Newly Established 2010.4.7]
Article 28 (Application for Enactment or Amendment of Recognition Standards)
① Any person who wishes to obtain performance recognition in accordance with the standards under Article 27 may apply to the President of the Korea Institute of Construction Technology for the enactment or amendment of recognition standards for new products.
② In the event that an application for the enactment or amendment of accreditation standards is submitted pursuant to Paragraph 1, the President of the Korea Institute of Construction Technology shall review the contents of the application and notify the applicant of whether or not to proceed with the enactment or amendment within 30 days from the date of application. In this case, if it is decided not to enact or amend the accreditation standards, the applicant shall be informed of the reasons; if the applicant has an objection, they may request a re-review.
[This Article Newly Established 2010.4.7]
Article 29 Deleted <2018.10.18>
Article 30 (Installation Standards for Evacuation Elevators) In Subparagraph 5 of Article 91 of the Enforcement Decree, the term "standards for structures and facilities, etc. prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport" refers to each of the following subparagraphs. <Amended Mar. 5, 2014; Oct. 18, 2018; Mar. 26, 2021; Aug. 26, 2024; Nov. 15, 2024>
1. Structure of Evacuation Elevator Landing
a. Areas excluding the entrances to the platform shall be separated from other parts of the building by fire-resistant floors and walls.
B. Elevator landings shall be connected to the interior of each floor, and 60-minute+ fire doors or 60-minute fire doors shall be installed at their entrances. In this case, the fire doors must be designed to remain closed at all times.
C. The finish (including the base for the finish) of parts facing the interior (referring to all parts facing the interior, such as floors and ceilings) shall be made of non-combustible materials.
D. Delete <2018.10.18>
E. Delete <2018.10.18>
B. Delete <2018.10.18>
G. Delete <2014.3.5>
A. Install any of the following facilities
1) Smoke Exhaust System
2) Smoke control equipment pursuant to Item 5, Subparagraph (a) of Annex 4 of the Enforcement Decree of the Act on the Installation and Management of Firefighting Facilities (hereinafter referred to as "smoke control equipment")
Okay. Delete <2014.3.5>
2. Structure of Evacuation Elevator Shaft
a. The elevator shaft shall be partitioned from other parts of the building by a fire-resistant structure.
B. Delete <2018.10.18>
C. Install smoke exhaust or smoke control equipment on the upper part of the elevator shaft.
3. Structure of the Evacuation Elevator Machine Room
a. Areas excluding entrances shall be separated from other parts of the building by fire-resistant floors and walls.
B. Install 60-minute+ fire doors or 60-minute fire doors at entrances.
4. Dedicated backup power for evacuation elevators
a. Install separate backup power facilities capable of operating evacuation elevators, machine rooms, landings, and closed-circuit television in the event of a power outage.
B. The backup power supply pursuant to Subparagraph A shall have a capacity capable of operating for at least 2 hours in the case of super high-rise buildings and for at least 1 hour in the case of semi-super high-rise buildings.
C. Be equipped with facilities capable of automatically or manually switching the supply of commercial power and backup power.
D. Conduit and wiring shall use heat-resistant materials capable of withstanding high temperatures, and waterproofing measures shall be taken.
[This Article Newly Established 2012.1.6]
Article 31 Deleted <2015.10.7>
[Attachment Form No. 1] <Amended Oct. 6, 2026>
Composite Material Quality Control Sheet
────────────────────────────────────────────────────────────────────────
Quality Control Document Number
─────┬──────────────────────────────────────────────────────────────────
Submitter's Name (Company Name)
(Building Owner)
Address (Phone Number : )
─────┼──────────────────────────────────────────────────────────────────
Construction Site Site Name
├────────────────────┬─────────────────────────────────────────────
Site Location Lot Number
─────┼────┬───────────────┼───┬─────────────────────────────────────────
Material Performance □ Non-combustible □ Semi-non-combustible Product Name Quality Certification Number
Overview
Application Area □ Interior Finish □ Interior/Exterior Finish
━━━━━┿━━━━┷━━━━━━━━━━━━━━━┿━━━┷━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Composite Material Name Quality-certified composite material ㎡
Manufacturer □ Material Distributor □ Supplied to Construction Contractor
Company Name Corporate Registration Number
├─────┴──────────────┤
Lot Number Year Month Day
Affiliation Statement (Signature or Seal)
Address
(Phone Number : )
━━━━━┿━━━━━━━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Material Name Quality-certified composite material ㎡
Supplied to distributor and construction contractor
Company Name Corporate Registration Number
├─────┴──────────────┤
Lot Number Year Month Day
Affiliation Statement (Signature or Seal)
Address
(Phone Number : )
━━━━━┿━━━━━━━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Construction Statement Quality-certified composite materials ㎡
Contractor □ Material Manufacturer □ Received from Material Distributor
Company Name Corporate Registration Number Year Month Day
Affiliation Statement (Signature or Seal)
Address
Quality-certified composite material ㎡
Installed properly
Year Month Day
Affiliation Name (Signature or Seal)
(Phone Number : )
━━━━━┿━━━━━┯━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Construction Name Qualification Number Confirmed that quality-certified composite materials were properly used in construction
Supervisor
Office Name Report Number
Year Month Day
Office Address Affiliation Name (Signature or Seal)
(Phone Number : )
─────┴────────────────────┴─────────────────────────────────────────────
Article 52-4 of the Building Act, Article 62, Paragraph 1, Subparagraph 1 of the Enforcement Decree of the same Act, and the Rules on Standards for Evacuation, Fire Protection, Structures, etc. of Buildings
In accordance with Article 24-3, Paragraph 2, Subparagraph 1, I hereby submit the Quality Control Document as stated above.
Year Month Day
Submitter (Building Owner) (Signature or Seal)
To the Mayor of a Special City, Metropolitan City, Special Self-Governing City, or Special Self-Governing Province, and to the Mayor, County Head, or District Head
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Remarks
────────────────────────────────────────────────────────────────────────
1. Attached Documents: Quality Certification (including detailed certification contents) recognized pursuant to Article 52-5, Paragraph 1 of the "Building Act" and Quality Inspection Certificate from the steel plate manufacturer (steel plate thickness, plating
(Including indication of type and plating amount) Copy
2. The construction contractor and the construction supervisor shall sign or affix their seal after verifying whether the attached Certificate of Quality Certification has been forged or altered.
3. The construction supervisor shall attach this form to the construction supervision completion report and submit it to the building owner, and when the building owner applies for approval of use pursuant to Article 22 of the Building Act
It must be submitted together with the Application for Approval of Use (Form No. 17 of the Enforcement Rules of the Building Act).
4. If there are multiple delivery dates or construction completion dates for composite materials, complete this form for each separately; if the quantity of materials delivered is large, they may be indicated separately on the reverse side.
────────────────────────────────────────────────────────────────────────
210mm×297mm [white paper 80g/㎡]
Original file: /LSW/flDownload.do?flSeq=170445183
Original file: /LSW/flDownload.do?flSeq=170445187
Original file: /LSW/flDownload.do?flSeq=170445185
[Attachment Form No. 2] <Amended Oct. 6, 2026>
Exterior Wall Insulation Quality Control Sheet
──────────────────────────────────────────────────────────────────────
Quality Control Document Number
───────┬──────────────────────────────────────────────────────────────
Submitter's Name (Company Name)
(Building Owner)
Address (Phone Number : )
───────┼──────────────────────────────────────────────────────────────
Construction Site Site Name
├────────────────────────────┬─────────────────────────────────
Site Location Lot Number
───────┼────┬───────────────────────┼───────────┬─────────────────────
Material Flame Retardancy Performance □ Non-combustible □ Semi-non-combustible □ Flame Retardant Test Report Issuing Authority Report Number
Overview
Application □ Exterior Insulation Surface Information □ Yes Insulation Density (Unit: K)
□ Whether interior insulation is indicated □ No
───────┴────┴──────────┴─────┴──────┴─────────────────────────────────
───────┬───────────────┬────────────┬───────────┬─────────────────────
Flame Retardancy Performance of Material Insulation □ Non-combustible □ Semi-non-combustible □ Flame Retardant Test Report Issuing Authority Report Number
Overview
(Multiple physical model tests □ Yes □ No Test Report Issuing Authority Report Number
The material is (composite exterior wall finishing material)
combined
product, exterior wall finishing materials 1. Construction method 4. Final finishing material 5. Flame retardant performance of finishing material
Additional Writing) Detailed Configuration □ Dry □ Wet A. Type of Finishing Material □ Non-combustible □ Semi-non-combustible □ Flame Retardant
(Example) B. Thickness of 150mm insulation mm
Semi-noncombustible PF board composite panel 2. Type of insulation C. Finishing material manufacturer 6. Whether information is marked on the surface of the insulation material
(Aluminum Panel 0.5mm + Semi-noncombustible □ Exterior Insulation □ Interior Insulation □ Yes □ No
50mm Glass Wool Core + Aluminum
Aluminum panel 0.5mm) 3. Insulation thickness mm 7. Insulation density (Unit: K)
━━━━━━━┿━━━━━━━━━━━━━━━┷━━━━━━━━━━━━┿━━━━━━━━━━━┷━━━━━━━━━━━━━━━━━━━━━
Insulation material with exterior wall performance specifications m²
Insulation material □ Material distributor □ Supplied to construction contractor
Manufacturer Company Name Corporate Registration Number
Year Month Day
Lot Number Affiliation Name (Signature or Seal)
├────────────────────────────┤
Address
(Phone Number : )
━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Insulation material with material statement performance m²
Supplied to distributor and construction contractor
Company Name Corporate Registration Number
Year Month Day
Lot Number Affiliation Name (Signature or Seal)
├────────────────────────────┤
Address
(Phone Number : )
━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Accepted m² of insulation meeting construction statement performance
Contractor Year Month Day
Company Name Corporate Registration Number Affiliation Name (Signature or Seal)
├───────────────┴────────────┤
Insulation material with address performance of ㎡ was properly installed
Year Month Day
(Phone Number: ) Affiliation Name (Signature or Seal)
━━━━━━━┿━━━━━━━━━━━━━━━┯━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Construction Name Qualification Number Confirmed that insulation meeting performance requirements has been properly installed
Supervisor
Office Name Report Number Year Month Day
Affiliation Statement (Signature or Seal)
Office Address
(Phone Number : )
───────┴────────────────────────────┴─────────────────────────────────
Article 52-4 of the Building Act, Article 62, Paragraph 1, Subparagraph 2 of the Enforcement Decree of the same Act, and the Rules on Standards for Evacuation, Fire Protection, Structures, etc. of Buildings
In accordance with Article 24-3, Paragraph 2, Subparagraph 2, the Quality Control Document is hereby submitted as above.
Year Month Day
Submitter (Building Owner) (Signature or Seal)
To the Mayor of a Special City, Metropolitan City, Special Self-Governing City, or Special Self-Governing Province, and to the Mayor, County Head, or District Head
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Remarks
──────────────────────────────────────────────────────────────────────
1. Attached Documents
A. Copy of test report for insulation material with indicated flame-retardant performance (submit each separately if made of two or more materials)
B. Copy of test report showing full-scale model test results (attach only if the exterior wall finishing material is made of two or more materials)
2. This Quality Control Report is prepared for insulation materials, which are finishing materials used on the exterior walls of buildings.
3. The construction contractor and the construction supervisor shall sign or affix their seal after verifying whether the attached test report has been forged or altered.
4. The construction supervisor shall attach this form to the construction supervision completion report and submit it to the building owner, and when the building owner applies for approval of use pursuant to Article 22 of the Building Act
It must be submitted together with the Application for Approval of Use (Form No. 17 of the Enforcement Rules of the Building Act).
5. If there are multiple delivery dates or construction completion dates for composite materials, complete this form for each.
──────────────────────────────────────────────────────────────────────
210mm×297mm [white paper 80g/㎡]
Original file: /LSW/flDownload.do?flSeq=170445189
Original file: /LSW/flDownload.do?flSeq=170445193
Original file: /LSW/flDownload.do?flSeq=170445191
[Attachment Form No. 3] <Amended Oct. 6, 2026>
Fire Door Quality Control Sheet
───────────────────────────────────────────────────────────────────────
Quality Control Document Number
─────┬─────────────────────────────────────────────────────────────────
Submitter's Name (Company Name)
(Building Owner)
Address (Phone Number : )
─────┼─────────────────────────────────────────────────────────────────
Construction Site Site Name
├─────────────────────┬───────────────────────────────────────────
Site Location Lot Number
─────┼──┬───┬──────────────┼───┬───────────────────────────────────────
Material Performance Thermal Insulation □ 30 min □ 60 min □ 90 min Product Name Quality Certification Number
Overview
□ 120 min □ 150 min □ 180 min
│ │ │ │ │
□ Not applicable
│ ├───┼──────────────┤ │
Non-thermal □ 30 min □ 60 min □ 90 min
│ │ │ │ │
□ 120 min □ 150 min □ 180 min
│ │ │ │ │
□ Not applicable
├──┴───┼──────────────┼───┴───────────────────────────────────────
Application Area □ Special Evacuation Stairs □ Fire Door Dimensions (Width × Height × Thickness) mm
□ Apartment Evacuation Space □ Other □ Elevator Effective Opening Dimensions (Width × Height) mm
━━━━━┿━━━━━━┷━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Material Name Quality-certified fire door number
Manufacturer □ Material Distributor □ Supplied to Construction Contractor
Company Name Corporate Registration Number
├───────┴─────────────┤
Lot Number Year Month Day
Affiliation Statement (Signature or Seal)
Address
(Phone Number : )
━━━━━┿━━━━━━━━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Material Name Quality-certified fire door number
Supplied to distributor and construction contractor
Company Name Corporate Registration Number
├───────┴─────────────┤
Lot Number Year Month Day
Affiliation Statement (Signature or Seal)
Address
(Phone Number : )
━━━━━┿━━━━━━━━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Construction Statement Quality-certified fire door number
Acquired from Contractor □ Manufacturer □ Distributor
Company Name Corporate Registration Number Year Month Day
Affiliation Statement (Signature or Seal)
Address
Number of quality-certified fire doors were properly installed
Year Month Day
(Phone Number: ) Affiliation Name (Signature or Seal)
━━━━━┿━━━━━━━┯━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Construction Name Qualification Number Confirmed that quality-certified fire doors have been properly installed
Supervisor
Office Name Report Number
Year Month Day
Office Address Affiliation Name (Signature or Seal)
(Phone Number : )
─────┴─────────────────────┴───────────────────────────────────────────
Article 52-4 of the Building Act, Article 62, Paragraph 1, Subparagraph 3 of the Enforcement Decree of the same Act, and the Rules on Standards for Evacuation, Fire Protection, Structures, etc. of Buildings
In accordance with Article 24-3, Paragraph 2, Subparagraph 3, I hereby submit the Quality Control Document as stated above.
Year Month Day
Submitter (Building Owner) (Signature or Seal)
To the Mayor of a Special City, Metropolitan City, Special Self-Governing City, or Special Self-Governing Province, and to the Mayor, County Head, or District Head
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Remarks
───────────────────────────────────────────────────────────────────────
1. Attached Documents: Copy of the Certificate of Quality Accreditation (including detailed accreditation contents) recognized pursuant to Article 52-5, Paragraph 1 of the Building Act
2. The construction contractor and the construction supervisor shall sign or affix their seal after verifying whether the attached Certificate of Quality Certification has been forged or altered.
3. The construction supervisor shall attach this form to the construction supervision completion report and submit it to the building owner, and when the building owner applies for approval of use pursuant to Article 22 of the Building Act
It must be submitted together with the Application for Approval of Use (Form No. 17 of the Enforcement Rules of the Building Act).
4. If there are multiple delivery dates or installation completion dates for fire doors, complete this form for each separately; if the quantity of materials delivered is large, it may be indicated separately on the back.
───────────────────────────────────────────────────────────────────────
210mm×297mm [white paper 80g/㎡]
Original file: /LSW/flDownload.do?flSeq=170445195
Original file: /LSW/flDownload.do?flSeq=170445199
Original file: /LSW/flDownload.do?flSeq=170445197
[Form No. 3-2] <Amended Oct. 6, 2026>
Fire-resistant Structure Quality Control Document
───────────────────────────────────────────────────────────────────────
Quality Control Document Number
─────┬─────────────────────────────────────────────────────────────────
Submitter's Name (Company Name)
(Building Owner)
Address (Phone Number : )
─────┼─────────────────────────────────────────────────────────────────
Construction Site Site Name
├────────────────────────┬────────────────────────────────────────
Site Location Lot Number
─────┼────┬───────────────────┼───┬────────────────────────────────────
Material Performance □ 0.5 hours □ 1 hour □ 1.5 hours Structure Name Quality Certification Number
Overview □ 2 hours □ 3 hours
├────┼───────────────────┤ │
Area of Use □ Beam □ Column □ Roof □ Non-load-bearing Wall
□ Load-bearing wall □ Floor □ Other
━━━━━┿━━━━┷━━━━━━━━━━━━━━━━━━━┿━━━┷━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Material Name Quality-certified fire-resistant structure (㎡,㎥,㎏,L,piece)*
Manufacturer □ Material Distributor □ Supplied to Construction Contractor
Company Name Corporate Registration Number * Unit: Walls, Roofs (㎡), Wood (㎥), Spray Coatings (㎏), Paints (L), Others (pieces)
├─────┴──────────────────┤
Lot Number
Year Month Day
Address Affiliation Name (Signature or Seal)
│ │
(Phone Number : )
━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Material Name Quality-certified fire-resistant structure (㎡,㎥,㎏,L,piece)
Supplied to distributor and construction contractor
Company Name Corporate Registration Number
├─────┴──────────────────┤
Lot No. Year Month Day
Affiliation Statement (Signature or Seal)
Address
(Phone Number : )
━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Construction Statement Quality-certified fire-resistant structure (㎡,㎥,㎏,L,piece)
Contractor □ Material Manufacturer □ Received from Material Distributor
Company Name Corporate Registration No. Year Month Day
Affiliation Statement (Signature or Seal)
Address
Quality-certified fire-resistant structures (㎡,㎥,㎏,L,pieces)
Installed properly
Year Month Day
(Phone Number: ) Affiliation Name (Signature or Seal)
━━━━━┿━━━━━┯━━━━━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Construction Name Qualification Number Confirmed that the quality-certified fire-resistant structure has been properly constructed
Supervisor
Office Name Report Number
Year Month Day
Office Address Affiliation Name (Signature or Seal)
(Phone Number : )
─────┴────────────────────────┴────────────────────────────────────────
Article 52-4 of the Building Act, Article 62, Paragraph 1, Subparagraph 4 of the Enforcement Decree of the same Act, and the Rules on Standards for Evacuation, Fire Protection, Structures, etc. of Buildings
In accordance with Article 24-3, Paragraph 2, Subparagraph 3-2, I hereby submit the Quality Control Document as stated above.
Year Month Day
Submitter (Building Owner) (Signature or Seal)
To the Mayor of a Special City, Metropolitan City, Special Self-Governing City, or Special Self-Governing Province, and to the Mayor, County Head, or District Head
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Remarks
───────────────────────────────────────────────────────────────────────
1. Attached Documents: Copy of the Certificate of Quality Accreditation (including detailed accreditation contents) recognized pursuant to Article 52-5, Paragraph 1 of the Building Act
2. The construction contractor and the construction supervisor shall sign or affix their seal after verifying whether the attached Certificate of Quality Certification has been forged or altered.
3. The construction supervisor shall attach this form to the construction supervision completion report and submit it to the building owner, and when the building owner applies for approval of use pursuant to Article 22 of the Building Act
It must be submitted together with the Application for Approval of Use (Form No. 17 of the Enforcement Rules of the Building Act).
4. If there are multiple delivery dates or construction completion dates for fire-resistant structures, complete this form for each separately; if the quantity of materials delivered is large, it may be indicated separately on the back.
...
───────────────────────────────────────────────────────────────────────
210mm×297mm [white paper 80g/㎡]
Original file: /LSW/flDownload.do?flSeq=170445201
Original file: /LSW/flDownload.do?flSeq=170445205
Original file: /LSW/flDownload.do?flSeq=170445203
[Attachment Form No. 4] <Amended Oct. 6, 2026>
Automatic Fire Shutter Quality Control Document
──────────────────────────────────────────────────────────
Quality Control Document Number
─────┬────────────────────────────────────────────────────
Submitter's Name (Company Name)
(Building Owner)
Address (Phone Number : )
─────┼────────────────────────────────────────────────────
Construction Site Site Name
├─────────────────────┬──────────────────────────────
Site Location Lot Number
─────┼──────┬──────────────┼───┬──────────────────────────
Material Classification □ Vertical □ Horizontal □ Other Product Name Quality Certification Number
Overview
Performance Thermal Insulation □ 30 min □ 60 min □ 90 min
│ │ │ │ │
□ 120 min □ 150 min □ 180 min
│ │ │ │ │
□ Not applicable
│ ├───┼──────────────┤ │
Non-thermal □ 30 min □ 60 min □ 90 min
│ │ │ │ │
□ 120 min □ 150 min □ 180 min
│ │ │ │ │
□ Not applicable
├──┴───┼──────────────┼───┴──────────────────────────
Area of Use □ Fire compartment openings in buildings □ Slats □ Shutter curtains (Width × Height) ㎜
□ Other Guide Rail (Width × Height × Thickness) mm
━━━━━┿━━━━━━┷━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Material Name Quality-certified automatic fire shutters number
Manufacturer □ Material Distributor □ Supplied to Construction Contractor
Company Name Corporate Registration Number
Year Month Day
Lot Number Affiliation Name (Signature or Seal)
├─────────────────────┤
Address
(Phone Number : )
━━━━━┿━━━━━━━━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Material Name Quality-certified supplied shutter inner specifications number
Supplied to distributor and construction contractor
Company Name Corporate Registration Number
Year Month Day
Lot Number Affiliation Name (Signature or Seal)
├─────────────────────┤
Address
(Phone Number : )
━━━━━┿━━━━━━━━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Construction Statement Quality-certified automatic fire shutters
Contractor □ Material Manufacturer □ Received from Material Distributor
Company Name Corporate Registration Number Year Month Day
Affiliation Statement (Signature or Seal)
Address
Number of quality-certified automatic fire shutters were properly installed
Year Month Day
(Phone Number: ) Affiliation Name (Signature or Seal)
━━━━━┿━━━━━━━━━━━━┯━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Construction Name Qualification Number Confirmed that quality-certified automatic fire shutters have been properly installed
Supervisor
Office Name Report Number Year Month Day
Affiliation Statement (Signature or Seal)
Office Address
(Phone Number : )
─────┴─────────────────────┴──────────────────────────────
Article 52-4 of the Building Act, Article 62, Paragraph 1, Subparagraph 4 of the Enforcement Decree of the same Act, and the Rules on Standards for Evacuation, Fire Protection, Structures, etc. of Buildings
In accordance with Article 24-3, Paragraph 2, Subparagraph 4, the Quality Control Document is hereby submitted as above.
Year Month Day
Submitter (Building Owner) (Signature or Seal)
To the Mayor of a Special City, Metropolitan City, Special Self-Governing City, or Special Self-Governing Province, and to the Mayor, County Head, or District Head
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Remarks
──────────────────────────────────────────────────────────
1. Attached Documents: Copy of the Certificate of Quality Accreditation (including detailed accreditation contents) recognized pursuant to Article 52-5, Paragraph 1 of the Building Act
2. The construction contractor and the construction supervisor shall sign or affix their seal after verifying whether the attached Certificate of Quality Certification has been forged or altered.
3. The construction supervisor shall attach this form to the construction supervision completion report and submit it to the building owner, and when the building owner applies for approval of use pursuant to Article 22 of the Building Act
It must be submitted together with the Application for Approval of Use (Form No. 17 of the Enforcement Rules of the Building Act).
4. If there are multiple delivery dates or construction completion dates for automatic fire shutters, this form shall be completed for each; if the quantity of materials delivered is large, it may be indicated separately on the reverse side.
...
──────────────────────────────────────────────────────────
210mm×297mm [white paper 80g/㎡]
Original file: /LSW/flDownload.do?flSeq=170445207
Original file: /LSW/flDownload.do?flSeq=170445211
Original file: /LSW/flDownload.do?flSeq=170445209
[Attachment Form No. 5] <Amended Oct. 6, 2026>
Refractory Filling Structure Quality Control Document
───────────────────────────────────────────────────────────────────────
Quality Control Document Number
─────┬─────────────────────────────────────────────────────────────────
Submitter's Name (Company Name)
(Building Owner)
Address (Phone Number : )
─────┼─────────────────────────────────────────────────────────────────
Construction Site Site Name
├─────────────────┬───────────────────────────────────────────────
Site Location Lot Number
─────┼──┬──────────────┼───┬───────────────────────────────────────────
Material Performance □ Thermal Insulation □ Flame Resistant Structure Name Quality Certification Number
Overview
□ 0.5 hours □ 1 hour
□ 2 hours □ 2.5 hours □ 3 hours
├──┼──────────────┤ │
Application □ Equipment Penetration ( Locations)
□ Linear Joint ( Locations)
━━━━━┿━━┷━━━━━━━━━━━━━━┿━━━┷━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Material Name Quality-certified refractory filling structure pieces
Manufacturer □ Material Distributor □ Supplied to Construction Contractor
Company Name Corporate Registration Number
├────┴────────────┤
Lot Number Year Month Day
Affiliation Statement (Signature or Seal)
Address
(Phone Number : )
━━━━━┿━━━━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Material Name Quality-certified refractory filling structure pieces
Supplied to distributor and construction contractor
Company Name Corporate Registration Number
├───┴─────────────┤
Lot Number Year Month Day
Affiliation Statement (Signature or Seal)
Address
(Phone Number : )
━━━━━┿━━━━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Construction Statement Quality-certified fire-filled structure pieces
Contractor □ Material Manufacturer □ Received from Material Distributor
Company Name Corporate Registration Number Year Month Day
Affiliation Statement (Signature or Seal)
Address
Appropriately constructed several quality-certified fire-resistant filling structures
Year Month Day
(Phone Number : ) Affiliation Name (Signature or Seal)
━━━━━┿━━━━┯━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Construction Name Qualification Number Confirmed that the quality-certified fire-resistant filling structure was properly constructed
Supervisor
Office Name Report Number
Year Month Day
Office Address Affiliation Name (Signature or Seal)
(Phone Number : )
─────┴─────────────────┴───────────────────────────────────────────────
Article 52-4 of the Building Act, Article 62, Paragraph 1, Subparagraph 4 of the Enforcement Decree of the same Act, and the Rules on Standards for Evacuation, Fire Protection, Structures, etc. of Buildings
In accordance with Article 24-3, Paragraph 2, Subparagraph 5, the Quality Control Document is submitted as above.
Year Month Day
Submitter (Building Owner) (Signature or Seal)
To the Mayor of a Special City, Metropolitan City, Special Self-Governing City, or Special Self-Governing Province, and to the Mayor, County Head, or District Head
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Remarks
───────────────────────────────────────────────────────────────────────
1. Attached Documents: Copy of the Certificate of Quality Accreditation (including detailed accreditation contents) recognized pursuant to Article 52-5, Paragraph 1 of the Building Act
2. The construction contractor and the construction supervisor shall sign or affix their seal after verifying whether the attached Certificate of Quality Certification has been forged or altered.
3. The construction supervisor shall attach this form to the construction supervision completion report and submit it to the building owner, and when the building owner applies for approval of use pursuant to Article 22 of the Building Act
It must be submitted together with the Application for Approval of Use (Form No. 17 of the Enforcement Rules of the Building Act).
4. If there are multiple delivery dates or construction completion dates for the refractory filling structure, complete this form for each separately; if the quantity of materials delivered is large, it may be indicated separately on the reverse side.
...
───────────────────────────────────────────────────────────────────────
210mm×297mm [white paper 80g/㎡]
Original file: /LSW/flDownload.do?flSeq=170445213
Original file: /LSW/flDownload.do?flSeq=170445217
Original file: /LSW/flDownload.do?flSeq=170445215
[Attachment Form No. 6] <Amended Oct. 6, 2026>
Fire Damper Quality Control Document
──────────────────────────────────────────────────────────────────────
Quality Control Document Number
─────┬────────────────────────────────────────────────────────────────
Submitter's Name (Company Name)
(Building Owner)
Address (Phone Number : )
─────┼────────────────────────────────────────────────────────────────
Construction Site Site Name
├──────────────┬─────────────────────────────────────────────────
Site Location Lot Number
─────┼─────┬────────┼──────────┬──────────────────────────────────────
Material Flame Resistant Performance □ Yes □ No Test Report Issuing Authority Report Number
Overview
Steel plate thickness mm
━━━━━┿━━━━━┷━━━━━━━━┿━━━━━━━━━━┷━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Manufactured fire dampers equipped with material statement performance
Manufacturer
Company Name Corporate Registration Number
├──────┴───────┤
Lot Number
├──────────────┤
Address
│ │
(Phone Number : ) Year Month Day
Affiliation Statement (Signature or Seal)
━━━━━┿━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Fire damper units equipped with material statement performance
Distributed to construction contractor
Company Name Corporate Registration Number
├──────┴───────┤
Lot Number
├──────────────┤
Address
│ │
(Phone Number : )
│ │
Year Month Day
Affiliation Statement (Signature or Seal)
━━━━━┿━━━━━━━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Received fire dampers equipped with construction statement performance
Contractor Year Month Day
Company Name Corporate Registration Number Affiliation Name (Signature or Seal)
├──────┴───────┤
A number of fire dampers with address performance were appropriately installed
Year Month Day
(Phone Number : ) Affiliation Name (Signature or Seal)
━━━━━┿━━━━━━┯━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Construction Name Qualification Number Confirmed that fire dampers meeting the performance requirements have been properly installed
Supervisor
Office Name Report Number
├──────┴───────┤
Office Address
│ │
(Phone Number : )
Year Month Day
Affiliation Statement (Signature or Seal)
─────┴──────────────┴─────────────────────────────────────────────────
Article 52-4 of the Building Act, Article 62, Paragraph 1, Subparagraph 4 of the Enforcement Decree of the same Act, and the Rules on Standards for Evacuation, Fire Protection, Structures, etc. of Buildings
In accordance with Article 24-3, Paragraph 2, Subparagraph 6, the Quality Control Document is hereby submitted as above.
Year Month Day
Submitter (Building Owner) (Signature or Seal)
To the Mayor of a Special City, Metropolitan City, Special Self-Governing City, or Special Self-Governing Province, and to the Mayor, County Head, or District Head
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Remarks
──────────────────────────────────────────────────────────────────────
1. Attached Document: Copy of test report certifying compliance with the smoke control test method for fire dampers specified in the Korean Industrial Standards pursuant to the Industrial Standardization Act
2. The construction contractor and the construction supervisor shall sign or affix their seal after verifying whether the attached test report has been forged or altered.
3. The construction supervisor shall attach this form to the construction supervision completion report and submit it to the building owner, and when the building owner applies for approval of use pursuant to Article 22 of the Building Act
It must be submitted together with the Application for Approval of Use (Form No. 17 of the Enforcement Rules of the Building Act).
4. If there are multiple delivery dates or construction completion dates, etc. for the fire damper, complete this form for each.
──────────────────────────────────────────────────────────────────────
210mm×297mm [white paper 80g/㎡]
Original file: /LSW/flDownload.do?flSeq=170445219
Original file: /LSW/flDownload.do?flSeq=170445223
Original file: /LSW/flDownload.do?flSeq=170445221
■ Rules on Standards for Evacuation, Fire Protection, and Structures of Buildings [Attachment Form No. 7] <Newly Inserted Oct. 24, 2019>
Construction Material Quality Control Register
───┬──┬────┬────┬─────────┬─────────┬─────────────────────────────────
No. Incoming Material Type Material Name Lot Number (Product Number) Supply Quantity (Unit Display) Remarks
Date
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┼──┼────┼────┼─────────┼─────────┼─────────────────────────────────
│ │ │ │ │ │
───┴──┴────┴────┴─────────┴─────────┴─────────────────────────────────
Article 52-4 of the Building Act, Article 62 of the Enforcement Decree of the same Act, and Article 24-3, Paragraph 3 of the Rules on Standards for Evacuation, Fire Protection, Structures, etc. of Buildings
, I hereby submit the Quality Control Document as above.
Year Month Day
Author (Contractor) (Signature or Seal)
Reviewer (Supervisor) (Signature or Seal)
To the Mayor of a Special City, Metropolitan City, Special Self-Governing City, or Special Self-Governing Province, and to the Mayor, County Head, or District Head
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Remarks
──────────────────────────────────────────────────────────────────────
The construction contractor preparing the Quality Control Document shall complete this form in accordance with the contents of the Quality Control Document.
The construction supervisor shall review whether the contents of this form match those of the quality control document, attach it to the construction supervision completion report, and submit it to the building owner.
When a building owner applies for approval of use pursuant to Article 22 of the “Building Act,” the application for approval of use in Form No. 17 of the “Enforcement Rules of the Building Act” and the “Evacuation and Fire Prevention of Buildings
It must be submitted together with the Quality Control Document in accordance with the "Rules on Standards for Structure, etc."
──────────────────────────────────────────────────────────────────────
210mm×297mm [white paper 80g/㎡]
Original file: /LSW/flDownload.do?flSeq=170445225
Original file: /LSW/flDownload.do?flSeq=170445229
Original file: /LSW/flDownload.do?flSeq=170445227
Revision
⊙Ministry of Land, Infrastructure and Transport Decree No. 1631
The Partial Amendment to the Rules on Standards for Evacuation, Fire Protection, and Structures of Buildings is hereby promulgated as follows.
October 6, 2026
Minister of Land, Infrastructure and Transport (Seal)
Partial Amendment to the Rules on Standards for Evacuation, Fire Protection, and Structures of Buildings
The Rules on Standards for Evacuation, Fire Protection, and Structures of Buildings, etc. are partially amended as follows.
A proviso is newly added to Article 14, Paragraph 2, Subparagraph 4, Item (a) as follows.
However, this does not apply in cases where a composite fire shutter (referring to an automatic fire shutter equipped with a fire door for evacuation) is installed.
In the part other than the subparagraphs of Article 15, Paragraph 1, replace "each subparagraph" with "each subparagraph"; in Subparagraph 6 of Paragraph 2 of the same article, replace "the Rules on Industrial Safety Standards" with "the Rules on Industrial Safety and Health Standards"; in the part other than the subparagraphs of Paragraph 4 and Paragraph 5 of the same article, replace "each subparagraph" with "each subparagraph" respectively; in Subparagraph 3 of the same paragraph, replace "the Act on the Guarantee of Convenience Promotion for Persons with Disabilities, the Elderly, Pregnant Women, etc." with "in the Act on the Guarantee of Convenience Promotion for Persons with Disabilities, the Elderly, Pregnant Women, etc."; and in Paragraph 6 of the same article, replace "each subparagraph" with "each subparagraph".
In the main text of Article 15-2, Paragraph 4, Subparagraph 4, "Article 64, Subparagraph 1 of the Enforcement Decree" shall be changed to "Article 64, Paragraph 1, Subparagraph 1 or 2 of the Enforcement Decree".
Paragraphs 5 and 6 of Article 24 shall be as follows:
⑤ In multi-unit dwellings pursuant to Article 61, Paragraph 1, Subparagraph 1-2 of the Enforcement Decree, building materials that do not exceed the pollutant emission standards under Article 11, Paragraph 1 of the Indoor Air Quality Management Act and Article 10 of the Enforcement Rule of the same Act shall be used.
⑥ Pursuant to the latter part of Article 52, Paragraph 2 of the Act, finishing materials (including insulation materials, coating materials such as paint, and all other materials constituting finishing materials; hereinafter the same applies in this Article) classified according to the following subparagraphs shall be used on the exterior walls of buildings falling under Subparagraphs 1 through 3, 5, and 6 of Article 61, Paragraph 2 of the Enforcement Decree.
1. In the case of buildings falling under Subparagraphs 1 through 3 and 5 of Article 61, Paragraph 2 of the Enforcement Decree: Non-combustible or semi-non-combustible materials shall be used as finishing materials. However, flame-retardant materials (limited to those notifying composite materials consisting of steel plates and core materials) may be used if the finishing materials are installed in compliance with the fire spread prevention structural standards prescribed and notified by the Minister of Land, Infrastructure and Transport.
2. In the case of buildings falling under Article 61, Paragraph 2, Subparagraph 6 of the Enforcement Decree: Non-combustible materials shall be used as finishing materials.
Subparagraph (f) is newly added to Article 24-7, Subparagraph 2 as follows.
B. Newly developed products or products outside the standard specifications where it is difficult to determine performance or quality standards: Recognition standards established by the President of the Korea Institute of Construction Technology pursuant to Article 27, Paragraph 1
In Article 27, Paragraph 1, "performance standards pursuant to Articles 3 and 19" shall be changed to "performance standards and quality standards pursuant to Articles 3, 19, and 24-7," "performance recognition" shall be changed to "performance recognition and quality recognition," and "performance" shall be changed to "performance and quality"; and in Paragraph 4 of the same Article, "performance recognition" shall be changed to "performance recognition and quality recognition".
In the "Industrial Facilities" column of the Use Classification in Item 1 of Attached Table 1, "facilities related to natural circulation" shall be changed to "facilities related to resource circulation."
Forms No. 1 through No. 3, Form No. 3-2, and Forms No. 4 through No. 6 are each as attached.
Supplementary Provisions
Article 1 (Enforcement Date) This Rule shall enter into force on the date of its promulgation. However, the amended provisions of Article 24, Paragraph 6 shall enter into force six months after the date of promulgation.
Article 2 (Applicability to Installation Standards for Fire Compartments) The amended provisions of the proviso to Article 14, Paragraph 2, Subparagraph 4, Item (a) shall also apply to cases where an application or report under any of the following subparagraphs was made prior to the enforcement of this Rule.
1. Application for a building permit pursuant to Article 11 of the Act (including a permit for change pursuant to Article 16 of the Act) (including cases where an application for deliberation by the Architectural Committee pursuant to Article 4-2, Paragraph 1 of the Act has been made in order to apply for a building permit)
2. Building notification pursuant to Article 14 of the Act (including notification of change pursuant to Article 16 of the Act)
3. Application for permission for change of use pursuant to Article 19 of the Act (including a notification of change of use or an application for change of contents in the building register pursuant to the same Article)
4. Application for or notification of permission, authorization, approval, etc. under other laws where the permission or notification under Subparagraphs 1 and 2 is deemed to exist.
Article 3 (Applicability to Finishing Materials of Buildings) The amended provisions of Article 24, Paragraph 6 shall apply from the time an application or report under each of the following subparagraphs is made after the effective date pursuant to the proviso of Article 1 of the Addenda.
1. Application for a building permit pursuant to Article 11 of the Act (including a permit for change pursuant to Article 16 of the Act) (including cases where an application for deliberation by the Architectural Committee is made pursuant to Article 4-2, Paragraph 1 of the Act in order to apply for a building permit)
2. Building notification pursuant to Article 14 of the Act (including notification of change pursuant to Article 16 of the Act)
3. Application for permission for change of use pursuant to Article 19 of the Act (including a notification of change of use or an application for change of contents in the building register pursuant to the same Article)
4. Application for or notification of permission, authorization, approval, etc. under other laws where the permission or notification under Subparagraphs 1 and 2 is deemed to exist.
Reason for Enactment/Amendment
[Partial revision]
◇ Reasons for Amendment and Key Contents
In cases where a fire door is installed on an automatic fire shutter, a separate fire door may not be required to be installed within 3 meters; furthermore, to prevent casualties caused by fire, finishing materials used on the exterior walls of facilities storing or processing hazardous materials will be restricted from using 'non-combustible or semi-non-combustible materials' in the past to using only 'non-combustible materials,' while...
This is intended to improve and supplement certain shortcomings observed in the operation of the current system, such as by adding criteria that allow the Advisory Committee of the Korea Institute of Construction Technology, which deliberates on performance recognition for newly developed products or products outside of standard specifications where performance criteria are difficult to assess, to also deliberate on quality recognition in the future.