■ Enforcement Rules of the Small Stream Improvement Act [Attachment Form No. 7] <Amended June 11, 2020>
Small Stream Improvement Implementation Plan
────────────────────────────────────────────────────────────────────────────────────────
<○○ Special Self-Governing City·City·County·District> (Year ○○○○)
─────┬───┬───┬───┬───┬──┬───────────────────────────────────────────────────────────────
Water-system │Small stream│Small Stream│Small stream│Watershed( │Plan│Improvement Plan
name │Number │name │Total Length│watershed) │river├──────────┬──────────┬─────────────────────────────┬───────────
│ │ │(km) │Area │Width │Total │Improved sections │This implementation │Future Plans
│ │ │ │(㎢) │(m) ├─────┬────┼─────┬────┼──────┬─────┬─────┬──────────┼─────┬─────
│ │ │ │ │ │Work quantity (m) │Project Cost │Work quantity (m) │Project Cost │Location │Work quantity (m) │Project Cost │Project effects │Work quantity (m) │Project Cost
│ │ │ │ │ │ │(1 million won)│ │(1 million won)│ │ │(1 million won) │ │ │(1 million won)
│ │ │ │ │ ├──┬──┤ ├─┬───┤ ├───┬──┼──┬──┼──┬──┼──┬───┬───┼──┬──┤
│ │ │ │ │ │Embank │호 │ │Embank│호 │ │Start │End│Embankment construction│Revetment│National Fund│Local│Farm│building │Water quality │Embankment construction│Revetment│
│ │ │ │ │ │ment │Revetment │ │ment│Revetment │ │ing │ing │ │ │ │funds │land │(units) │(pp │ │ │
│ │ │ │ │ │(Embank │(Revetment │ │ │ │ │Point │Point│ │ │ │ │(ha)│ │m) │ │ │
│ │ │ │ │ │ment) │an) │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │
─────┼───┼───┼───┼───┼──┼──┼──┼────┼─┼───┼────┼───┼──┼──┼──┼──┼──┼──┼───┼───┼──┼──┼─────
Total │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │
─────┼───┼───┼───┼───┼──┼──┼──┼────┼─┼───┼────┼───┼──┼──┼──┼──┼──┼──┼───┼───┼──┼──┼─────
│ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │
─────┴───┴───┴───┴───┴──┴──┴──┴────┴─┴───┴────┴───┴──┴──┴──┴──┴──┴──┴───┴───┴──┴──┴─────
Attached Documents
1. A document containing the details of each of the following items
A. Name of Maintenance for Small Streams, etc.
B. Purpose and Overview of Maintenance of Small Streams, etc.
c. Name and address of the person implementing improvement of small streams, etc.
d. Scheduled date of commencement and completion of maintenance of small streams, etc.
E. Specifications regarding the following items or rights to be expropriated or used, and specifications regarding the names and addresses, etc., of the owners and rights holders other than the owners
1) Land, buildings or objects affixed to the land
2) Rights other than ownership relating to the land, buildings, or objects affixed to the land in 1)
f. Matters concerning management of completed small stream facilities
g. Area of anticipated abandoned riverbed land
2. Location map of areas where maintenance of small streams, etc. is being implemented (referring to one drawn on a 1:50,000 scale topographic map)
3. Detailed design documents (if divided into two or more construction sections, documents prepared for each section)
4. Planned construction schedule
5. Plan for Project Costs and Financing (including annual investment plan)
6. Documents containing matters necessary for the implementation of small stream construction, such as matters concerning nature-friendly small stream maintenance
────────────────────────────────────────────────────────────────────────────────────────
210mm×297mm[White Paper 80g/㎡(Recycled)]