Form 3 — 궤도운송법 시행규칙
284533 · 2026-03-12
■ Enforcement Rules of the Rail Transport Act [Attachment Form No. 3] <Amended June 23, 2016>
Application for Approval of Dedicated Track Operation
(Front)
────────┬────────────────────────┬─────────────────────────
Receipt Number │Date of Receipt │Processing Period 15days
────────┴────────────────────────┴─────────────────────────
────┬──────────┬──┬─────────────┬──────────────────────────
Applicant│Name(in the case of a corporation that │ │Resident Registration Number(Corporate's │
│Name and Representative) │ │(Corporate Registration Number) │
├──────────┼──┴─────────────┴──────────────────────────
│Address │
│ │(Phone Number: )
├──────────┼───────────────────────────────────────────
│Trade Name │
────┴──────────┴───────────────────────────────────────────
───────────────┬───────────────────────────────────────────
Types of Track Facilities │[ ]Cableway([ ]Round trip [ ]Automatic Circulation Type [ ]Fixed-Cycle Type [ ]Towing type)
│[ ]Tram [ ] Steel-wheeled light rail
│[ ]Monorail [ ]Rubber-wheeled light rail
│[ ]Cable Railway [ ]Linear Induction Motor Type Light Rail
│[ ]Maglev Train [ ]Other( )
───────────────┼───────────────────────────────────────────
Special Construction Approval Status │[ ]Approved [ ]Not applicable
───────────────┼───────────────────────────────────────────
Location of Workplace │
───────────────┼───┬───────────────────────────────────────
Date │Commencement of Construction │Completion
├───┼───────────────────────────────────────
│ │
───────────────┴───┴───────────────────────────────────────
───────────────────────────────────────────────────────────
Pursuant to the main text of Article 5, Paragraph 1 and Paragraph 2 of the Rail Transport Act, and Article 5, Paragraph 1 of the Enforcement Rules of the same Act, as above
I hereby apply.
Year month day
Applicant (Signature or seal)
Mayors of Special City and Metropolitan City
┌─ ─┐ │
│ │
│ │To:│
│ Mayor of a Special Self-Governing City · Governor of a Special Self-Governing Province │
│ │ │
│ Mayor/County Governor/District Head │
└─ ─┘
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
───────┬──────────────────────────────────────────────┬────
Applicant │ 1. Facility Operation Plan │Fee
Documents to be submitted │ 2. Among the documents in each of the following items, the relevant documents │20,000 Won
│ A. Basic Design Documents │
│ B. Construction Specifications │
│ C. Regarding the safety of specialized safety inspection agencies, etc., pursuant to Article 20 of the Rail Transport Act and Article 16 of the Enforcement Decree of the same Act │
│Review Opinion │
│ d. Permission or approval from administrative agencies, etc. having jurisdiction over roads, rivers, farmland, forests, parks, cultural heritage protection zones, etc. │
│is required in the area where the rail facilities are operated │
│Documents proving │
│ E. In the case where an impact assessment regarding the environment, traffic, disasters, etc. has been conducted, the impact assessment result report │
───────┼──────────────────────────────────────────────┤
Responsible Public Official │ 1. Certificate of Corporate Registration (Applicable only to corporations) │
Items to Be Verified │ │
───────┴──────────────────────────────────────────────┴────
Consent Form for Joint Use of Administrative Information
─────────────────────────────────────────────────────────────────────
I, the undersigned, in relation to the processing of this matter, [confirm] the above-mentioned public official through the joint use of administrative information pursuant to Article 36, Paragraph 1 of the Electronic Government Act
I agree to confirm the terms. If you do not agree, the applicant must submit the relevant documents in person.
Applicant(Representative) (Signature or seal)
─────────────────────────────────────────────────────────────────────
210mm×297mm[White Paper 80g/㎡]
(rear)
┍━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━┑
│ProcessingProcedure │
├────────────────────────────────────────────┤
│ │
│ │
│ This application will be processed as follows. │
├──────────────┬─────────────────────────────┤
│Applicant │Processing Agency │
│ ├─────────────────────────────┤
│ │Special City ㆍ Metropolitan City ㆍ Special Autonomous City ㆍ Special Autonomous Province ㆍ City ㆍ County │
│ │· District │
├──────────────┼─────────────────────────────┤
│ │ │
│ ┌───┐ │ ┌───────┐ │
│ │Shin Cheong│ │ ▶│Adjacent 수 │ │
│ │ ├──────┼────── │ │ │
│ │ │ │ │ │ │
│ └───┘ │ └┬──────┘ │
│ │ │ │
│ │ │ │
│ │ │ │
│ │ │
│ │ ▼ │
│ │ ┌───────┐┌───────────┐│
│ │ │Review of submitted documents││Consultation with relevant local governments ││
│ │ │ ││(In two or more administrative districts ││
│ │ │ ├┤where the track passes through two or more administrative districts││
│ │ │ ││ ││
│ │ └┬──────┘└───────────┘│
│ │ │ │
│ │ │ │
│ │ │ │
│ │ │ │
│ │ │
│ │ ▼ │
│ │ ┌───────┐ │
│ │ │Approval Approval │ │
│ │ │ │ │
│ │ │ │ │
│ │ └┬──────┘ │
│ │ │ │
│ │ │ │
│ │ │ │
│ │ │
│ │ ▼ │
│ ┌───┐ │ ┌───────┐ │
│ │Certificate of Approval│◀ │Certificate Issuance │Approval Granted │ │
│ │ │ ─────┼───────┤ │ │
│ │ │ │ │ │ │
│ └───┘ │ └───────┘ │
│ │ │
└──────────────┴─────────────────────────────┘
210mm×297mm[White Paper 80g/㎡]