Form 3 — 궤도운송법 시행규칙

284533 · 2026-03-12

■ Enforcement Rules of the Rail Transport Act [Attachment Form No. 3] <Amended June 23, 2016> Application for Approval of Dedicated Track Operation (Front) ────────┬────────────────────────┬───────────────────────── Receipt Number │Date of Receipt │Processing Period 15days ────────┴────────────────────────┴───────────────────────── ────┬──────────┬──┬─────────────┬────────────────────────── Applicant│Name(in the case of a corporation that │ │Resident Registration Number(Corporate's │ │Name and Representative) │ │(Corporate Registration Number) │ ├──────────┼──┴─────────────┴────────────────────────── │Address │ │ │(Phone Number: ) ├──────────┼─────────────────────────────────────────── │Trade Name │ ────┴──────────┴─────────────────────────────────────────── ───────────────┬─────────────────────────────────────────── Types of Track Facilities │[ ]Cableway([ ]Round trip [ ]Automatic Circulation Type [ ]Fixed-Cycle Type [ ]Towing type) │[ ]Tram [ ] Steel-wheeled light rail │[ ]Monorail [ ]Rubber-wheeled light rail │[ ]Cable Railway [ ]Linear Induction Motor Type Light Rail │[ ]Maglev Train [ ]Other( ) ───────────────┼─────────────────────────────────────────── Special Construction Approval Status │[ ]Approved [ ]Not applicable ───────────────┼─────────────────────────────────────────── Location of Workplace │ ───────────────┼───┬─────────────────────────────────────── Date │Commencement of Construction │Completion ├───┼─────────────────────────────────────── │ │ ───────────────┴───┴─────────────────────────────────────── ─────────────────────────────────────────────────────────── Pursuant to the main text of Article 5, Paragraph 1 and Paragraph 2 of the Rail Transport Act, and Article 5, Paragraph 1 of the Enforcement Rules of the same Act, as above I hereby apply. Year month day Applicant (Signature or seal) Mayors of Special City and Metropolitan City ┌─ ─┐ │ │ │ │ │To:│ │ Mayor of a Special Self-Governing City · Governor of a Special Self-Governing Province │ │ │ │ │ Mayor/County Governor/District Head │ └─ ─┘ ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━ ───────┬──────────────────────────────────────────────┬──── Applicant │ 1. Facility Operation Plan │Fee Documents to be submitted │ 2. Among the documents in each of the following items, the relevant documents │20,000 Won │ A. Basic Design Documents │ │ B. Construction Specifications │ │ C. Regarding the safety of specialized safety inspection agencies, etc., pursuant to Article 20 of the Rail Transport Act and Article 16 of the Enforcement Decree of the same Act │ │Review Opinion │ │ d. Permission or approval from administrative agencies, etc. having jurisdiction over roads, rivers, farmland, forests, parks, cultural heritage protection zones, etc. │ │is required in the area where the rail facilities are operated │ │Documents proving │ │ E. In the case where an impact assessment regarding the environment, traffic, disasters, etc. has been conducted, the impact assessment result report │ ───────┼──────────────────────────────────────────────┤ Responsible Public Official │ 1. Certificate of Corporate Registration (Applicable only to corporations) │ Items to Be Verified │ │ ───────┴──────────────────────────────────────────────┴──── Consent Form for Joint Use of Administrative Information ───────────────────────────────────────────────────────────────────── I, the undersigned, in relation to the processing of this matter, [confirm] the above-mentioned public official through the joint use of administrative information pursuant to Article 36, Paragraph 1 of the Electronic Government Act I agree to confirm the terms. If you do not agree, the applicant must submit the relevant documents in person. Applicant(Representative) (Signature or seal) ───────────────────────────────────────────────────────────────────── 210mm×297mm[White Paper 80g/㎡] (rear) ┍━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━┑ │ProcessingProcedure │ ├────────────────────────────────────────────┤ │ │ │ │ │ This application will be processed as follows. │ ├──────────────┬─────────────────────────────┤ │Applicant │Processing Agency │ │ ├─────────────────────────────┤ │ │Special City ㆍ Metropolitan City ㆍ Special Autonomous City ㆍ Special Autonomous Province ㆍ City ㆍ County │ │ │· District │ ├──────────────┼─────────────────────────────┤ │ │ │ │ ┌───┐ │ ┌───────┐ │ │ │Shin Cheong│ │ ▶│Adjacent 수 │ │ │ │ ├──────┼────── │ │ │ │ │ │ │ │ │ │ │ └───┘ │ └┬──────┘ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ ▼ │ │ │ ┌───────┐┌───────────┐│ │ │ │Review of submitted documents││Consultation with relevant local governments ││ │ │ │ ││(In two or more administrative districts ││ │ │ │ ├┤where the track passes through two or more administrative districts││ │ │ │ ││ ││ │ │ └┬──────┘└───────────┘│ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ ▼ │ │ │ ┌───────┐ │ │ │ │Approval Approval │ │ │ │ │ │ │ │ │ │ │ │ │ │ └┬──────┘ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ ▼ │ │ ┌───┐ │ ┌───────┐ │ │ │Certificate of Approval│◀ │Certificate Issuance │Approval Granted │ │ │ │ │ ─────┼───────┤ │ │ │ │ │ │ │ │ │ │ └───┘ │ └───────┘ │ │ │ │ └──────────────┴─────────────────────────────┘ 210mm×297mm[White Paper 80g/㎡]