■ Enforcement Rules of the Building Act [Attachment Form No. 15] <Amended Nov. 29, 2018>
Certificate of Commencement of Construction
The building's use/scale is an overview of the entire building.
──────────┬─────────────────────────────────────────────────────
BuildingClassification │Date of Permission (Notification)
──────────┴─────────────────────────────────────────────────────
───────┬────────────────────────────────────────────────────────
BuildingOwner │
───────┼────────────────────────────────────────────────────────
Location │
───────┼────────────────────────────────────────────────────────
Site Area │ ㎡
───────┼─┬───┬──────────────────────────────────────────────────
Building Name │ │Main Purpose│
───────┼─┼───┼──────────────────────────────────────────────────
Building Area │㎡│Building Coverage Ratio│%
───────┼─┼───┼──────────────────────────────────────────────────
Total Floor Area │㎡│Floor Area Ratio│%
───────┼─┴───┴──────────────────────────────────────────────────
Scheduled Start Date│
───────┴────────────────────────────────────────────────────────
In accordance with the commencement of construction report submitted by you, the Certificate of Commencement of Construction is hereby issued pursuant to Article 14, Paragraph 4 of the Enforcement Rules of the Building Act.
Submit.
Year month day
┏━━┓
Mayor of a Special City, Mayor of a Metropolitan City, Mayor of a Special Self-Governing City, Governor of a Special Self-Governing Province, Mayor, County Head, District Head┃Official Seal┃
┗━━┛
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Important Notes
────────┬───────────────────────────────────────────────────────
「Building Act」 │If the permit holder falls under any of the following subparagraphs, the permit shall be revoked, and if construction begins within one year from the date of the building notification...
Article 11, Paragraph 7, │If not complied with, it shall lose its validity. However, if a justifiable reason is recognized, the commencement period of the construction may be extended within a range of one year.
Article 14, Paragraph 5 │can be installed.
│ 1. 2 years from the date of approval (establishment or expansion of a factory pursuant to Article 13 of the "Act on Promotion of Industrial Agglomeration and Factory Establishment" or
│If a factory that has received approval for a change of business type does not commence construction within 3 years
│ 2. In cases where construction commenced within the period specified in Subparagraph 1 but is deemed impossible to complete
│ 3. From the time the building owner loses ownership of the land through auction or public sale, etc., prior to the commencement of construction report under Article 21 of the Building Act, 6 years
│If it is determined that commencement of construction is impossible after the month has elapsed
────────┴───────────────────────────────────────────────────────