Notice of Commencement of Construction
· Dark Orchid( ) is not completed by the reporting person, and [ ] Mark √ in the applicable boxes. (Front)
────────────┬───────┬───────────────┬────────────────────
Receipt Number │Reception Date │Processing Date │Processing Period 3day
────────────┴───────┴───────────────┴────────────────────
──────┬──────────────────────────────────────────────────
Reporting Person │BuildingOwner
├──────────────────────────────────────────────────
│Telephone Number
├──────────────────────────────────────────────────
│Address
──────┴──────────────────────────────────────────────────
────────────────────────────────┬────────────────────────
Site Location │① Lot Number
────────────────────────────────┼────────────────────────
Permit (Notification) Number │Date of Permission (Notification)
────────────────────────────────┼────────────────────────
Scheduled Start Date │ScheduledCompletionDate
────────────────────────────────┴────────────────────────
──────┬───────────────────────┬──────┬───────────────────
② │Name(Corporate Name) (Signature or seal) │QualificationNumber │Association Member Number
Designer ├───────────────────────┼──────┴───────────────────
│Office Name │Report Number
├───────────────────────┴──────────────────────────
│Office Address
│(Telephone Number:)
├───────────────────────┬──────────────────────────
│ContractDate │Contract Amount
│ │One
──────┴───────────────────────┴──────────────────────────
──────┬─────────────────────────┬────────────────────────
③ │Name (Signature or seal) │ContractDate
Construction Contractor├─────────────────────────┼────────────────────────
│Company Name │Contract Amount
│ │One
├─────────────────────────┼────────────────────────
│Date of Birth(Corporate Registration Number) │Registration number
├─────────────────────────┴────────────────────────
│Address (Telephone Number:)
├──────┬───────────────────────────────────────────
│Site Layout │Name
│Construction Engineer ├───────────────────┬───────────────────────
│ │Certification │QualificationNumber
──────┴──────┴───────────────────┴───────────────────────
──────┬──────────────────────────┬───────────────────────
④ │Name (Signature or seal) │QualificationNumber
Construction Supervisor├──────────────────────────┼───────────────────────
│Office Name │ReportNumber
├──────────────────────────┴───────────────────────
│Office Address (Telephone Number:)
├──────────────────────────┬───────────────────────
│ContractDate │Contract Amount
│ │Won
──────┴──────────────────────────┴───────────────────────
──────┬──────────────────────────┬───────────────────────
⑤ │Name (Signature or seal) │QualificationNumber
Site Manager├──────────────────────────┴───────────────────────
│Address (Telephone Number:)
──────┴──────────────────────────────────────────────────
─────────────┬───────────────────────────────────────────
Presence of Asbestos in Buildings │[ ]Ceiling material [ ]Insulation Material [ ]Roofing material
│[ ]Insulating material [ ]Other [ ]Not applicable
─────────────┼──────────────────┬────────────────────────
Specialized Guidance Agency for Construction Disaster Prevention│[ ]Target │[ ]Non-target
Whether subject to construction supervision ├──────────────────┼────────────────────────
│Institution Name │Business Registration Number
─────────────┴──────────────────┴────────────────────────
──────┬───────────┬───┬────────┬─────────────────────────
⑥ Relationship │Field │Certification│QualificationNumber │Address
Specialist├───────────┼───┼────────┼─────────────────────────
│( ) (Signature or seal)│ │ │
├───────────┼───┼────────┼─────────────────────────
│( ) (Signature or seal)│ │ │
├───────────┼───┼────────┼─────────────────────────
│( ) (Signature or seal)│ │ │
├───────────┼───┼────────┼─────────────────────────
│( ) (Signature or seal)│ │ │
──────┴───────────┴───┴────────┴─────────────────────────
210mm×297mm[White paper (80g/㎡) or medium paper (80g/㎡)]
(Back)
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
In accordance with Article 21, Paragraph 1 of the Building Act and Article 14, Paragraphs 1 and 6 of the Enforcement Rules of the same Act, I hereby submit the Notification of Commencement of Construction as stated above.
Year month day
Reporter(Building Owner) (Signature or seal)
Mayor of a Special City, Mayor of a Metropolitan City, Mayor of a Special Self-Governing City, Governor of a Special Self-Governing Province, Mayor, County Head, District Head Your
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Reporting Guide
─────────┬───────────────────────────────────────────────┬────────
Attached Documents │1. Copy of the contract between parties involved in construction pursuant to Article 15 of the Building Act (limited to cases where applicable)│Fee
│2. Design documents pursuant to Annex 4-2 of the Enforcement Rules of the Building Act. However, building permit pursuant to Articles 11 and 14 of the Building Act │None
│If submitted when filing for building notification, it is not required to be submitted; however, if there are any changes, the changed design documents │
│. │
│3. Supervision Contract pursuant to Article 25, Paragraph 11 of the Building Act (limited to cases where applicable) │
│4. A copy of the insurance certificate or mutual aid certificate submitted pursuant to Article 21, Paragraph 2 of the Enforcement Decree of the Architects Act │
│5. Copy of Technical Guidance Contract pursuant to Form No. 104 of the Enforcement Rules of the Industrial Safety and Health Act (Industrial Safety and Health Act) │
│(Applicable only to construction projects subject to guidance from a specialized guidance agency for construction accident prevention pursuant to Article 73, Paragraph 1) │
─────────┴───────────────────────────────────────────────┴────────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Legal Basis
─────────┬────────────────────────────────────────────────────────
「Building Act」 │In the case of intending to commence construction of a building for which a permit has been obtained or a report has been filed pursuant to Articles 11, 14, and Article 20, Paragraph 1 of the Building Act
Article 21, Paragraph 1 │You must report to the licensing authority.
─────────┴────────────────────────────────────────────────────────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Important Notes
─────────┬────────────────────────────────────────────────────────
「Building Act」 │1. 2 years from the date of obtaining the building permit (new establishment or expansion of a factory pursuant to Article 13 of the "Act on Promotion of Industrial Agglomeration and Factory Establishment or
Article 11, Paragraph 7, │If a factory that has received approval for a change of business type does not commence construction within 3 years, the permit will be revoked, and within 1 year from the date of the building notification...
Article 14, Paragraph 5, │If construction is not commenced within the specified period, the validity shall be forfeited. However, if the licensing authority recognizes that there is a justifiable reason...
Article 21, Paragraph 3 │The commencement period of the construction can be extended within a range of one year.
and Article 111, subparagraph 1 │2. If, within three days from receiving the commencement-of-construction report, the permitting authority fails to notify the reporting person whether the report has been accepted or whether the processing period has been extended under the laws governing civil petitions,
│the report is deemed accepted on the day following the end of that period.
│3. If construction commences without filing a commencement report or by filing a false report, a fine of not more than 50 million won shall be imposed.
─────────┴────────────────────────────────────────────────────────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
How to write
──────────────────────────────────────────────────────────────────
1. ① : Enter the lot number pursuant to the "Act on the Establishment and Management of Spatial Information, etc.", and share pursuant to Article 8 of the "Act on the Management and Reclamation of Public Waters"
If permission for the occupation or use of a water surface has been obtained, and the location does not have a lot number, write down the location for which the occupation or use was permitted.
2. ② ~④: If there are multiple persons being changed, write "○○○ and ○ others," and submit the status of "other ○ others" as well.
3. ③ Construction Engineers: List the construction engineers assigned to the construction site in accordance with Article 40 of the Framework Act on the Construction Industry.
4.⑤: List the construction technicians assigned to the construction site in accordance with Article 24, Paragraph 6 of the "Building Act" (in each subparagraph of Article 41, Paragraph 1 of the "Framework Act on the Construction Industry")
Applies only to buildings that do not fall under this category).
5.⑥: Related professional technical experts who have received cooperation regarding site safety, structural safety of buildings, installation of building facilities, etc., pursuant to Article 67 of the Building Act
Write the character.
──────────────────────────────────────────────────────────────────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
ProcessingProcedure
──────────────────────────────────────────────────────────────────
┌────┐ ┌───┐ ┌───┐ ┌───┐ ┌───────┐ ┌───────┐
│Report │→│Accept │ → │Review │ → │Conclusion Re │ → │Preparation of Report Certificate │ → │Issuance of Report Certificate │
│Write │ │ │ │ │ │ │ │ │ │ │
└────┘ └───┘ └───┘ └───┘ └───────┘ └───────┘
Reporter(Building Owner) Special City, Metropolitan City, Special Self-Governing City, Special Self-Governing Province, or City, County, or District (Building Permit/Notification Department) Reporter(Building Owner)
──────────────────────────────────────────────────────────────────