Form 19 — 건설산업기본법 시행규칙
282375 · 2026-01-02
■ Enforcement Rules of the Framework Act on the Construction Industry [Attached Form No. 19-2] <Newly Inserted Oct. 16, 2024>
Certification of Construction Project Progress
(Application for Construction Project Progress Certification)
(Front)
──────────────────────┬────────────────────────────────────┬──────────────────────────────────────────
Receipt No. │Receipt Date │Processing Period Immediate
──────────────────────┴────────────────────────────────────┴──────────────────────────────────────────
───────┬───────────────────────────────────────┬──────────────────────────────────────────────────────
Applicant │Company Name(or Name of Corporation) │Representative
├───────────────────────────────────────┼──────────────────────────────────────────────────────
│Business Type │Main Field of Business
├───────────────────────────────────────┼──────────────────────────────────────────────────────
│Office Address │Registration No.
───────┴───────────────────────────────────────┴──────────────────────────────────────────────────────
──────────────────────────────────────────────────────────────────────────────────────────────────────
Project Details
───────────────────────────────────────────────┬──────────────────────────────────────────────────────
Project Name │Project Contract Value
│ Million KRW
───────────────────────────────────────────────┴──────────────────────────────────────────────────────
Project Location(including specific address with the street number)
──────────┬─────────────────────────┬───────────────────┬─────────────────────┬───────────────────────
Category of │General Construction Works │① Type of Works │② Area of Construction │③ Description of General Construction Works
Construction Works│(write both General Construction Works │ │ │
│and Specialized Construction Works) │ │ │
├─────────────────────────┼───────────────────┴─────────────────────┴───────────────────────
│Specialized Construction Works │④ Description of Specialized Construction Works
│(write only Specialized Construction Works) │
──────────┴─────────────────────────┴────────────┬────────────────────────────────────────────────────
Authority Authorization/Permitting the Project │Date of Authorization/Permission (YYYY/MM/DD)
──────┬───────┬──────┬──────────────────┬────────┴──────────┬──────────────────┬──────────────────────
Contract │Commencement │Completion │Contract Amount(Current Year) │Value of Construction Works Compl │Progress Payment Made in the │Value of Material Supplies from
Date │Date │Date │or Carryover Amount │eted in the Current Year │Current Year │the Project Owner in the Current Y
(YY/MM) │(YY/MM) │(Scheduled) │ │ │ │ear
│ │(YY/MM) ├──────────────────┼───────────────────┼──────────────────┼──────────────────────
│ │ │Total Contract Amount │Value of Construction Works Compl │Total Progress Payments Made u │Value of Materials Supplies fro
│ │ │ │eted until the Previous Year │ntil the Previous Year │m the Project Owner until the P
│ │ │ │ │ │revious Year
│ │ ├─┬───┬──┬─┬──┬──┬─┼─┬───┬───┬─┬──┬──┬─┼─┬───┬──┬─┬──┬──┬─┼─┬───┬──┬─┬──┬──┬────┐
│ │ │Tn│100Bn │10Bn│Bn│100M│10M │M │Tn│100Bn │10Bn │Bn│100M│10M │M │Tn│100Bn │10Bn│Bn│100M│10M │M │Tn│100Bn │10Bn│Bn│100M│10M │M │
──────┼───────┼──────┼─┼───┼──┼─┼──┼──┼─┼─┼───┼───┼─┼──┼──┼─┼─┼───┼──┼─┼──┼──┼─┼─┼───┼──┼─┼──┼──┼────┘
│ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │
│ │ ├─┼───┼──┼─┼──┼──┼─┼─┼───┼───┼─┼──┼──┼─┼─┼───┼──┼─┼──┼──┼─┼─┼───┼──┼─┼──┼──┼─────
│ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │
──────┼───────┼──────┼─┼───┼──┼─┼──┼──┼─┼─┼───┼───┼─┼──┼──┼─┼─┼───┼──┼─┼──┼──┼─┼─┼───┼──┼─┼──┼──┼─────
│ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │
│ │ ├─┼───┼──┼─┼──┼──┼─┼─┼───┼───┼─┼──┼──┼─┼─┼───┼──┼─┼──┼──┼─┼─┼───┼──┼─┼──┼──┼─────
│ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │ │
──────┴───────┴──────┼─┴───┴──┴─┴──┴──┴─┴─┴───┴───┴─┴──┴──┴─┴─┴───┴──┴─┴──┴──┴─┴─┴───┴──┴─┴──┴──┴─────
Other Matters │
(Scope/Method of construction, │
details of joint contract, etc.) │
─────────────────────┴───────────────────────────────────────────────────────────────────┬────────────
Please certify the progress made on the construction project as described above in the year ( ). │No Fee
─────────────────────────────────────────────────────────────────────────────────────────┴────────────
Application Date (YYYY/MM/DD)
Applicant Name (Signature or Seal)
──────────────────────────────────────────────────────────────────────────────────────────────────────
This certification(application) was drafted in accordance with relevant facts.
Date (YYYY/MM/DD)
Project Owner(Contractor)
ㆍCompany Name
ㆍCorporate Registration No. or Date of Birth
ㆍName of Representative (Signature or Seal)
ㆍAddress
ㆍTel.
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
210mm×297mm[White paper (80g/㎡) or medium paper (80g/㎡)]
(Back)
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Notice
───────────────────────────────────────────────────────────────────────────────────────────────
1.Fill in the “Main Field of Business”, when the constructor was contracted to perform construction works in its
registered main field of business.
2.“Category of Construction Works” refers to either “New Construction Works” or “Maintenance and Repair Works.”
-New Construction Works include a) extension, alteration, reconstruction, and substantial repair of buildings, b) expansion
and extension of facilities other than buildings, and c) restoration, reinforcement, and alteration of main
structures after their dismantlement.
-“Maintenance and Repair Works” refer to improvement, repair and reinforcement works after the completion of a
facility.
3.① Type of Works: [For all types of Construction Works(General·Specialized)] Write down the type of general construction
works(Civil Engineering, Building, Industrial and Environmental Facilities, Landscaping) provided based on the “Table 3
of ?Enforcement Regulation of the Framework Act on the Construction Industry?.”
4.② Area of Construction: [For all types of Construction Works(General·Specialized)] Write down the Area of
Construction from the “Table of General Construction Works” below.
5.③ Description of General Construction Works: [For all types of Construction Works(General·Specialized)] Write down
the description of general construction works from the “List of General Construction Works” below.
6.④ Description of Specialized Construction Works: Write down the description of specialized construction works from the “List
of Specialized Construction Works” below.
───────────────────────────────────────────────────────────────────────────────────────────────
- Table of General Construction Works
───────┬───────┬─────────────────────────────────────────────────────────────────────────────
Works │Area of │List of General Construction Works
│Construction │
───────┼───────┼─────────────────────────────────────────────────────────────────────────────
Civil │1.Traffic │? Roads ? Road Bridges ? Airports ? Subways
Engineering │Facilities │? Controlled Access Highways ? Railway Bridges ? Conventional Railways ? Road Tunnels
│ │? Expressways ? High-speed Railways ? Railway Tunnels
├───────┼─────────────────────────────────────────────────────────────────────────────
│2.Water │? Dams ? Flood Control, River Erosion ? Irrigation Canals ? Water Treatment Plant
│Resource │? Ports Control ? Water Supply System ? Sewage System
│Facilities │? Canals ? Aqueduct Tunnel (1,000㎜ or longer)
│ │ ? Water Supply System
│ │ (shorter than 1,000㎜)
├───────┼─────────────────────────────────────────────────────────────────────────────
│3.Other Civil │? Reclamation ? Residential Land Development ? Other Tunnels
│Engineering │? Farmland Reorganization ? Industrial Site Development ? Other Civil Engineering Facilities
│Facilities │ ? Erosion Control
───────┼───────┼─────────────────────────────────────────────────────────────────────────────
Building │1.Residential │? Detached Houses and ? High-rise Apartments ? Multipurpose Buildings
│Facilities │Tenement Houses (6 ~15 floors) (Residential and Commercial)
│ │? Low-rise Apartments ? Super High-rise Apartments
│ │(up to 5 floors) (16 floors and higher)
├───────┼─────────────────────────────────────────────────────────────────────────────
│2.Non- │? Shopping Centers ? Hotels and Lodging Facilities ? Traditional Style Buildings ? Warehouses, Garages,
│residential │and Department Stores ? Public Office Buildings ? Churches, Temples, and Terminal Buildings
│Facilities │? Office Buildings (up to 11 floors) and Other Religious Buildings ? Factory and Workshop Buildings
│ │? Studio Apartments ? Public Office Buildings ? Cultural Heritage ? Mechanical Equipment Facilities
│ │? Intelligent Buildings (12 floors and higher) and Historic Buildings (not including Plants)
│ │ ? Schools ? Performance and Meeting Halls ? Hazardous Material Storage
│ │ ? Hospitals ? Stadiums and Sports Grounds Facilities
│ │ ? Exhibition Facilities ? Substation and Power Plant
│ │ Buildings
│ │ ? Others
───────┴───────┼─────────────────────────────────────────────────────────────────────────────
Industrial and │? Steelworks, Petrochemical ? Hydroelectric Power Plants ?(DESF) Oil Pipeline ? Sewage Terminal Treatment
Environmental │Plants, and Other Industrial ? Solar photovoltaic power station ?(DESF) Bulk Storage Tank Plant
Facilities │Production Facilities ? Wind Power Plants ?(DESF) Gas Pipe ? Wastewater Terminal Treatment
│? Nuclear Power Plants ? Tidal Power Plants ?(DESF) Gas Storage Facilities Plant
│? Thermal Power Plants * DESF : District Energy Supply Facilities ? Other Environmental Facilities
│? Combined Heat Power Plants ? Waste Incineration Facilities ? Other Plant Installation
───────────────┼─────────────────────────────────────────────────────────────────────────────
Landscaping │? Arboretums ? Park ? Other Landscaping Works
───────────────┴─────────────────────────────────────────────────────────────────────────────
- Table of Specialized Construction Works
───────────────────────────────────────────────────────────────────────────────────
List of Specialized Construction Works
───────────────────┬────────────────────┬──────────────────────┬───────────────────
General Earthworks │General Painting Works │Water Supply Facility Works │Building Mechanical Equipment Works
Blasting Works │Repainting Works │Sewerage Facility Works │Plant Mechanical Equipment Works
General Paving Works │Lane Marking Works │Railway and Track Works │Automatic Control Works
Pavement Maintenance Works │Plaster Works │Works on Steel Structures │Gas Facility Works (Type 1)
General Boring and Grouting Works │Tile Works │Pedestrian Steel Bridge Installation Works │Gas Facility Works (Type 2)
Groundwater Development Works │Waterproofing Works │Steel Structure Installation Works │Gas Facility Works (Type 3)
Piling Works │Masonry Works │Bridge Steel Structure Installation Works │Heating Facility Works (Type 1)
General Interior Construction Works │Stoneworks │Underwater Works │Heating Facility Works (Type 2)
Wooden Window Frames │General Landscaping and Planting Works │Dredging Works │Heating Facility Works (Type 3)
and Wooden Structures Works │Landscaping Maintenance Works │General Elevator Installation Works │
Metal Structure Works │Landscaping Facility Installation Works │Mechanical Parking System Installation Works│
Window Works │Reinforced Concrete Works │Cableway Installation and Removal Works │
Greenhouse Installation Works │Structural Demolition Works │Cableway Maintenance Works │
Roofing and Sheet Metal Works │Scaffolding Works │ │
Building Assembly Works │ │ │
───────────────────┴────────────────────┴──────────────────────┴───────────────────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
210mm×297mm[White paper (80g/㎡) or medium paper (80g/㎡)]