Form 5 — 건설기술 진흥법 시행규칙
286885 · 2026-06-11
■ Enforcement Rules of the Construction Technology Promotion Act [Attachment Form No. 5] <Amended Dec. 30, 2022>
Certificate of New Technology Utilization Performance
───────────┬──────────────┬─────┬──────────────────────────
Receipt Number │Date of Receipt │Real name verification │Processing Period Immediate
───────────┴──────────────┴─────┴──────────────────────────
─────┬──────────────────────────┬──────────────────────────
Applicant │Trade Name or Corporate Name │Representative Name
├──────────────────────────┴──────────────────────────
│Address
├─────────────────────────────────────────────────────
│New Technology Utilization Status
│ [ ]Developer [ ]User Agreement Holder [ ]Contractor [ ]Designer [ ]Construction Project Manager [ ]Supervisor [ ]Other
─────┴─────────────────────────────────────────────────────
─────┬─────────────────────────────────────────────────────
Target │Designation number
New Technology ├─────────────────────────────────────────────────────
│Scope of Technology (Write as specified in the New Technology Designation Certificate)
─────┴─────────────────────────────────────────────────────
─────┬─────────────────────────────────────────────────────
Service contents│Service name
├────────────────────┬────────────────────────────────
│Service Period │Service Contract Amount
├────────────────────┼────────────────────────────────
│Amount of New Technology Design Application (Thousand Won) │Amount Applied (Thousand Won) for Design Reflecting Shareholding Ratio (_%)
─────┴────────────────────┴────────────────────────────────
─────┬─────────────────────────────────────────────────────
Construction Details│Construction name
├─────────────┬──────┬─────────────┬──────────────────
│ContractDate │DateOfConstruction │(Scheduled) Completion Date │① Order Type
├─────────────┴──────┼─────────────┴──────────────────
│Total Contract Amount for the Project (Thousand Won) │② Amount of New Technology Applied to the Relevant Construction (Thousand Won)
├────────────────────┼────────────────────────────────
│Total Contract Amount for the Relevant Year (Thousand Won) │③ Amount of New Technology Applied in the Relevant Year (Thousand Won)
├────────────────────┼────────────────────────────────
│Relevant Year New Technology Performance (Thousand Won) │Shareholding Ratio(_%) Reflected Completed Performance (Thousand Won)
─────┴────────────────────┴────────────────────────────────
I hereby apply for certification of new technology utilization performance pursuant to Article 10 of the Enforcement Rule of the Construction Technology Promotion Act.
Year month day
─────┬──────────────────────┬──────────────────────────────
Ordering Authority │Trade Name or Corporate Name (Representative Name) │Business Registration Number
(Contractor)│ │(Corporate Registration Number)
│ (in) │
│ │
├──────────────────────┴──────────────────────────────
│Address and Contact
│ (U )
│ (Phone: , Fax: )
━━━━━┷━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
In accordance with Article 10 of the Enforcement Rule of the Construction Technology Promotion Act, I hereby certify that the new technology has been utilized as stated above.
Year month day
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Important Notes
───────────────────────────────────────────────────────────
①Order Type: General(1), Nominated(2), Restricted(3), Private(4), Alternative Bid(5), Design-Build-Build(6), BTL(7), Private Construction(8), Other(9)
Find the corresponding form and write the number.
②,③ refers to the direct costs incurred in the construction of the new technology.
In principle, the contracting authority verifies the certificate of performance, and in the case of subcontracted work, the contractor may verify it.
For the performance report required to undergo a detailed evaluation of the business performance capabilities of service providers for design and other services, construction details must not be included.
For performance reports submitted to undergo a detailed evaluation of the business performance capabilities of service providers, such as construction project management, service details must not be stated.
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
processing procedure
───────────────────────────────────────────────────────────
┌──────┐ ┌───────┐ ┌────┐ ┌─────────┐ ┌─────┐ ┌─────┐
│Fill out report │?│Certificate(Issuance)New│?│Receipt │?│Check Attachments and │?│Earnings Approval │?│Notification and │
│ │ │Confirm Blueprint │ │ │ │Review (Request for Supplementation) │ │ │ │Aftercare │
└──────┘ └───────┘ └────┘ └─────────┘ └─────┘ └─────┘
Applicant Ordering Authority Specialized Agency Specialized Agency Specialized Agency Ministry of Land, Infrastructure and Transport
Specialized Agency
───────────────────────────────────────────────────────────
210mm×297mm[White paper (80g/㎡) or medium paper (80g/㎡)]