Annex 1 — 지방자치분권 및 지역균형발전에 관한 특별법 시행령
280903 · 2026-01-02
■ Enforcement Decree of the Special Act on Local Autonomy and Balanced Regional Development [Attached Table 1]
Processing period for permits, etc. (Related to Article 19, Paragraph 6 and Article 31, Paragraph 5)
┌──────────────────┬─────────────────────┐
│Category │처리기간 │
├──────────────────┼─────────────────────┤
│1.Building permit pursuant to Article 11 of the Building Act │a. Buildings to be constructed according to standard design documents: 7 │
│ │Day(3Days) │
│ │B. Subjects to Architectural Review by the City/Provincial Local Architectural Committee │
│ │Buildings (Buildings subject to prior approval by the City/Provincial Governor │
│ │(Includes water): 30 days (15 days) │
│ │. Other buildings: 14 days (7 days) │
├──────────────────┼─────────────────────┤
│2. Construction pursuant to Article 22 of the "Building Act" │a. Cases where water quality testing by a water quality testing agency is required │
│Water Use Approval │: 14th │
│ │or. In other cases: 6 days │
├──────────────────┼─────────────────────┤
│3. Pursuant to Article 23 of the "Air Environment Preservation Act" │10days │
│Installation of other air pollutant emission facilities │ │
│Permission │ │
├──────────────────┼─────────────────────┤
│4.「Activation of industrial clusters and factory establishment │a. If agenda processing is not required: 7 days │
│pursuant to Article 13, Paragraph 1 of the Act concerning [] │a. The entire contents of the approval application are the Mayor/County Governor/ │
│Approval of plant establishment, etc. │Cases falling under the authority of the District Head: 14 days │
│ │that requires consultation with other administrative agencies │
│ │In other cases, such as: 30 days │
├──────────────────┼─────────────────────┤
│5.Article 45 of the "Small and Medium Enterprise Startup Support Act" │a. If agenda processing is not required: 7 days │
│Approval of the factory establishment plan in accordance with START │b. The entire contents of the approval application are the Mayor, County Governor, or District │
│ │Where it falls under the authority of the Commissioner: 14 days │
│ │that requires consultation with other administrative agencies │
│ │In other cases, such as: 21st │
└──────────────────┴─────────────────────┘
Remarks
1. At the time of the building permit under Item 1 of the table above ( ) is for the architect to conduct on-site investigation and inspection
refers to the processing period when verification tasks are performed on behalf of others.
2. Cases where an environmental impact review by an external expert is required for the building permit under Item 1 of the table above
If the processing period in is less than 14 days, the processing period shall be 14 days.