Annex 12 — 환경오염시설의 통합관리에 관한 법률 시행령
283023 · 2026-02-01
■ Enforcement Decree of the Act on the Integrated Management of Environmental Pollution Facilities [Table 12] <Amended May 3, 2022>
Targets, methods, and timing of attachment by measuring instrument, and targets, items, and methods of measurement (related to Article 18, Paragraph 2)
1. Measuring instruments related to air pollutants
a. Energy meter
1) Attachment Target
Regarding air pollutant emission facilities under Article 2, Subparagraph 2, Item (b) of the Act, Article 26 of the "Air Environment Preservation Act"
. However, the following pollution control facilities are excluded.
a) Pollution control facilities connected to an exhaust outlet equipped with automatic chimney measuring devices
b) Install an energy meter, such as when the pollution control facility and the emission facility use the same power supply equipment.
Prevention facility that allows checking operating status without START
d) Pollution control facilities that must always be in operation to perform the function of recovering raw materials or products
2) Attachment Method
a) The cumulative power meter is configured to accumulate all power consumed in the operation of pollution control facilities.
must be attached. However, regarding auxiliary facilities such as machinery or equipment attached to the pollution control facility
Since the voltage or power extraction point used differs, the energy meter
to major auxiliary facilities (referring to blowers and pumps),
can be attached.
b) Electricity used by facilities other than pollution control facilities shall be separately collected so that it is not accumulated together.
. However, the power consumption of emission facilities, etc., air pollution control facilities
, it is not separately distinguished and
can attach.
3) Timing of attachment: Before the report of commencement of operation pursuant to Article 12, Paragraph 1 of the Act
B. Automatic chimney measuring instrument
1) Attachment Target
Workplaces subject to the installation of automatic chimney measuring devices are those subject to air pollution under Article 6, Paragraph 1, Subparagraph 1 of the Act
It shall be workplaces with an annual generation of 10 tons or more of pollutants, and emission facilities subject to attachment and
The measurement items are the attachment-대상 items specified in Item 1 of Annex 3 of the Enforcement Decree of the Air Environment Preservation Act.
In accordance with the release facility and measurement items.
2) Exemption from attachment of automatic chimney measuring devices
If an emission facility subject to the installation of automatic chimney measuring devices falls under any of the following cases
. However, for
, within 6 months from the date the relevant grounds for exemption ceased to exist, automatic chimney measuring equipment
and the chimney original pursuant to Article 19, Paragraph 1, Subparagraph 1 of the Enforcement Decree of the Air Environment Preservation Act
The measurement results must be transmitted normally to the remote monitoring system control center.
a) exempted from the installation of pollution control facilities pursuant to the proviso to Article 26, Paragraph 1 of the Air Environment Preservation Act
In cases where the installation of pollution control facilities for measurement items of automatic chimney measuring devices is exempted (
applies only to cases)
b) As a facility where combustion gases or flames do not come into direct contact with raw materials or products,
In cases where clean fuel is used pursuant to Article 43 of the Enforcement Decree of the Air Environment Preservation Act (발
Exhibition facilities are excluded)
) As a combustion facility using only liquid fuel, the pollution control facility for removing sulfur oxides
In cases where there is no START (excluding power generation facilities, and only the installation of sulfur oxide measuring devices is exempted)
d) In the case of a boiler planning to switch the fuel used to clean fuel within 6 months
U
e) In the case of emission facilities with an annual operating period of less than 30 days
f) In the case of pollution control facilities with an annual operating period of less than 30 days
Company) Having a plan to close the emission facility within 6 months from the date it became a facility subject to attachment
case
3) Attachment Timing and Attachment Grace Period
a) Automatic chimney measuring devices must be installed by the date of the report on the commencement of operation pursuant to Article 12, Paragraph 1 of the Act.
must be done. However, at the same workplace, a new automatic chimney measuring device must be installed
If there are 10 or more exhaust outlets that must be completed, all within 6 months from the start of operation
must also be attached.
b) Notwithstanding a), Class 4 workplaces pursuant to Annex 1 of the Enforcement Decree of the Air Environment Preservation Act
or a Class 5 workplace as a Class 1, Class 2, or Class 3 workplace according to the same table
In the event that you intend to change the workplace (hereinafter referred to as "change in workplace size"), the change
From the date of obtaining permission or filing a change notification (hereinafter referred to as the "date of change in land use scale"), 9
Automatic chimney measuring devices must be installed within the START month.
c) Notwithstanding a) and b), pursuant to Subparagraph 2 of Annex 8 of the Enforcement Decree of the Air Environment Preservation Act
The installation of automatic chimney measuring devices for emission facilities is deferred according to the following classifications.
(1) Existing emission facilities are being replaced with new automatic chimney measuring devices due to a change in the size of the business site
In cases where it has become a facility subject to installation, at least once a month during the year prior to the date of change in classification scale
As a result of measuring pollutant emissions, pollutants were 30 percent of the permissible emission standards
In cases where emissions are always below the "Basic Assessment Standard" (hereinafter referred to as the "Basic Assessment Standard"), pollution
Attachment is deferred until the substance is emitted above the basic charge standard. However,
If emissions exceed the basic assessment standards after a grace period for attachment has been granted, then...
Within 6 months from the date of emission exceeding the basic assessment standards, automatic chimney monitoring equipment
A START device must be attached.
(2) New facilities until pollutants are emitted above the basic charge standard, chimney
The installation of automatic measuring devices is deferred. However, for emissions exceeding the basic assessment standards...
, for 6 months from the date of emission exceeding the basic charge standard (operation start
If emissions exceed the basic charge standard within 6 months from the start date, operation
Automatic chimney monitoring equipment must be installed within one year from the start.
2. Measuring instruments related to water pollutants
A. Total Electricity Meter and Total Flow Meter
1) Attachment Target
It is in accordance with Annex 7 of the Enforcement Decree of the Water Environment Preservation Act.
2) Attachment Method
a) The cumulative power meter is configured to accumulate all power consumed in the operation of pollution control facilities.
Install it, but ensure that electricity used by facilities other than pollution control facilities is not accumulated together.
Must be attached separately.
b) In cases where tap water, industrial water, groundwater, river water, etc. are used, respectively water
An integrated flow meter must be installed. However, in accordance with relevant laws and regulations, the flow rate used must be measured
If a meter capable of doing so is installed, it is considered that a water cumulative flow meter has been installed.
.
d) After primary treatment of wastewater, a joint pollution control facility, a public wastewater treatment facility, or a public sewerage treatment facility
In cases where wastewater is discharged into facilities for secondary treatment, the primary treatment for each business site
A sewage and wastewater cumulative flow meter must be installed at each treated water discharge port.
d) Workplaces required to install automatic water quality measuring devices and ancillary facilities pursuant to subparagraph b
Automatic measurement data measured by sewage and wastewater cumulative flow meters is [related to] the "Environmental Field Testing and Inspection
As prescribed in the Standard Environmental Pollution Test Methods pursuant to Article 6 of the Act on the Corporations, etc.
In accordance with the water quality remote monitoring system pursuant to Article 37, Paragraph 2 of the Enforcement Decree of the Water Environment Preservation Act
It must be attached so that it can be transmitted to the control center.
3) Timing of attachment: Until the report of commencement of operation pursuant to Article 12, Paragraph 1 of the Act
B. Automatic water quality measuring instrument
1) Measurement Subjects and Items
It is in accordance with Annex 7 of the Enforcement Decree of the Water Environment Preservation Act.
2) Attachment Method
a) Automatic measurement data of automatic water quality measuring instruments [regarding] testing, inspection, etc. in the environmental field
In accordance with the Environmental Standard Testing Methods pursuant to Article 6 of the Act, the "Water Environment Protection
To be transmitted to the water quality remote monitoring system control center pursuant to Article 37, Paragraph 2 of the Enforcement Decree of the Act
It must be attached so that it can be attached.
b) If regional conditions or wastewater characteristics differ, install two or more pollution control facilities
Businesses subject to the above shall install automatic water quality measuring devices for each facility. However,
In the case of START sounds, they may not be attached per facility.
(1) Individual treatment facilities with a treatment capacity of less than 200 m³/day have automatic water quality monitoring
The device may not be attached.
(2) Wastewater of the same nature treated at two or more treatment facilities (change permit or change approval
In the case of processing at a facility under construction (including facilities that have been received), as one final
When discharging treated water into the discharge outlet, automatic water quality measuring devices for each treatment facility
.
c) Automatic water quality measuring instruments pursuant to a) and b) are [related to] the "Environmental Testing and Inspection, etc."
Measuring instruments that have received type approval pursuant to Article 9 of the Act ( pursuant to Article 9-2 of the same Act
(including measuring instruments that have received preliminary type approval) must be.
3) Timing of attachment: Within 2 months after filing the report of commencement of operation pursuant to Article 12, Paragraph 1 of the Act. However,
In cases where a workplace becomes subject to the installation of measuring devices due to an increase in wastewater discharge volume, Article 6 of the Act
Within 9 months from the date of the change permit or change notification pursuant to Paragraph 2, automatic water quality measuring equipment
must be attached.