Form 4 — 농어촌도로 정비법 시행규칙
235315 · 2021-09-07
[Attachment Form No. 4]
┏━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━┓
┃Application for Completion Inspection of Road Improvement Works ┃
┠──────┬────────────┬───┬────────────┨
┃Types of Roads │ │Route name│ ┃
┠──────┼────────────┴───┴────────────┨
┃Date of Permission │ Year month day ┃
┠──────┼─────────────────────────────┨
┃Types of Construction │ ┃
┠──────┼─────────────────────────────┨
┃section │start point: Myeon ri, Endpoint: Myeon ri( Km)┃
┠──────┼─────────────────────────────┨
┃Construction Site│ ┃
┠──────┼───────────┬─────┬───────────┨
┃DateOfCommencement │ Year month day│DateOfCompletion│ Year month day┃
┠──────┴───────────┴─────┴───────────┨
┃ Pursuant to Article 4(5) of the Enforcement Decree of the Rural Road Maintenance Act, the road improvement┃
┃project described above has been completed and I hereby submit an application for completion inspection. ┃
┃ ┃
┃Year month day ┃
┃ ┃
┃RoadMaintenanceImplementer (Signature or seal) ┃
┃ ┃
┃ Required Documents: 1. 1 copy of As-built Design Drawings ┃
┃2. 1 copy of the completed cadastral map ┃
┃3. 1 copy each of photos during construction and completion ┃
┗━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━┛
21305-00411Min 210mm × 297mm
92.4.6 Approved (Printing Paper (Grade 2) 60g/㎡)