Annex 7 — 산림복지 진흥에 관한 법률 시행령
280575 · 2025-12-23
■ Enforcement Decree of the Act on the Promotion of Forest Welfare [Table 7] <Amended July 2, 2019>
Detailed Standards for Ecological Mountain Use in Forest Welfare Complexes (Related to Article 34, Paragraph 1)
1. Between the parts where facilities are installed or the characteristics of the mountain land are changed, at least 60% is forest
Preserve it or create a forest belt at least 30 meters wide.
a. Install facilities while maintaining the existing topography and vegetation as much as possible.
a. In order to prevent disconnection from the surrounding ecosystem due to forest land conversion, ecological corridors such as trees and herbaceous plants, and
Establish an ecological corridor management plan
. Significant obstacles to maintaining the natural ecological functions of forests, such as the conservation of rare wild animals and plants
Will not occur
2. In order to maintain the topography of the mountainous area, the volume of cut earth, fill earth, earthwork volume, and area of land alteration shall be minimized
Extinguish the slope and ensure the height of the slope is 12 meters or less
a. The volume of cut and fill, and the volume of soil movement resulting from mountain land conversion, are the relevant Forest Welfare Complex construction
It shall be the minimum amount required for the project.
B. Considering the nature of the forest welfare complex development project, the surrounding landscape, and the layout of the facilities to be installed
When starting, include the minimum area of the mountain land to be exclusively used.
It is the cut and fill slopes subject to restoration resulting from the alteration of the land use of mountainous areas (hereinafter referred to as "slopes").
) is
Shall not exceed 50 percent of the area of forest land conversion
. In the development plan, the vertical height of the slope resulting from mountain land conversion shall be 12 meters or less.
Reflect this. However, if other laws specifically stipulate the height of a building, ex
and.
E. Terraced mountain land conversion (along the slopes of the mountain to maintain the existing topography as much as possible)
In the case of constructing stairs and converting mountain land) the project site created on the stairs
Width[Berm (小段: a narrow step installed in the middle to ease the slope of a hillside
[Excluding the width of the flat part] shall each be 12 meters or more
3. To preserve the water quality and soil of mountainous areas, the rainwater impermeability shall be 30% or less of the exclusive use area
and prepare separate pollution prevention measures
a. The forest land intended for conversion shall comply with the standards of Article 31, Paragraph 2.
a. Minimize rainwater runoff from impervious surfaces generated after mountain land conversion
Install water storage facilities to do so.
1) Public facilities capable of collecting rainwater by minimizing its movement during rainfall
Install at designated locations for each facility in residential complexes, etc.
2) Ensure smooth water collection and drainage, and the rivers, sewers, and
Ensure smooth connection with waterways, etc.
3) So that the original function of the retention facility is not damaged and rainwater can be safely collected
thing
In cases where the area of converted mountain land is 300,000 square meters or more, rainwater is to be infiltrated and retained to the maximum extent.
To reduce and utilize emissions, the paving of facilities must be made of a material with high rainwater permeability.
Use the method and introduce a decentralized rainwater management system.
4. Installing erosion control facilities to minimize changes in water volume in mountainous areas and to prepare for landslides and soil runoff
Prepare disaster prevention measures such as START
a. The average slope of the mountain area to be exclusively used shall be 25 degrees or less.
b. Except in cases where the drainage volume is small and there is no risk of soil runoff or collapse, rivers or
Drainage facilities must be installed so that water is drained through other drainage facilities, etc., and due to the drainage, water
Ensure that the quality is not contaminated
. If mountain land conversion significantly affects the increase in flow rate in downstream areas during floods,
There shall be no concern regarding sediment runoff. In this case, check dams to prevent sediment runoff downstream,
Sedimentation ponds (ponds for settling sand or soil), retention ponds, etc. installed
In the case of , it is deemed that there is no risk of soil runoff.
. The slope of the embankment (referring to the ratio of the horizontal distance to the height of the embankment) is the
To prevent collapse, the following criteria shall be met according to soil type. However, terraced mountainous areas
In the case of exclusive use, the slope gradient must be 1:1.4 or less regardless of soil type, and the
As a result of conducting a quality inspection, it is recognized as safe or retaining walls, piles, anchors (anchor: structure
Recognized as safe by installing disaster prevention facilities such as anchoring agents that bind water and ground
is performed.
1) In the case of hard rock: 1:0.5 or less
2) In the case of weathered rock: 1:0.8 or less
3) In the case of soil: 1:1.0 or less
4) In the case of gravel and soil layers of embankment land: 1:1.0 or less
E. When installing structures on slopes, they shall be safe against earth pressure.
b. In cases where there is a concern that disasters, etc. may occur due to the slope, the following protective measures
value in the business plan
1) Installation of drainage facilities of sufficient size
2) Installation of facilities to prevent sand blowing or rockfall
d. It shall not be a region falling under any of the following. However, if the installation of disaster prevention facilities ...
case.
Pursuant to Article 41, Paragraph 1 of the Framework Act on Disaster and Safety Management, the Mayor, County Governor, or District Head [referring to] a risk
Area designated as zone
2) Areas determined to have a high probability of landslides through landslide risk map analysis
3) Area where landslides occurred
5. The design, color, and materials of the building shall be in harmony with the surrounding mountain landscape.
a. By conducting view analysis and mountain landscape impact simulations, reduce landscape damage
shall establish countermeasures. However,
.
B. The colors of the building shall be in harmony with the colors of the surrounding forest, and the colors of the surrounding forest
and set the saturation lower than the analysis result
It is designed with roof shapes and fences that harmonize with the surrounding area, and natural materials such as wood, earth, and stone.
materials and eco-friendly materials
d. Consider the building layout and design to maximize natural light
E. In the case of installing a building on a slope, the skyline and trees of mountainous or hilly areas...
While preserving characteristic landscape elements such as rock formations to the maximum extent, damage to green spaces due to terraced mountain land conversion
Minimize START
B. Materials used in construction do not impede human health or the growth of animals and plants, so
It must not cause soil contamination
6. Ensure appropriate height, density, building coverage ratio, and floor area ratio of buildings
a. The height of the building shall not exceed 16 meters. However, the height of the building as stipulated in other laws
This is not the case if this is specifically determined.
B. The floor area ratio and building coverage ratio of buildings shall be for the uses prescribed in the "Act on Planning and Utilization of National Land"
Must be below the floor area ratio and building coverage ratio for each region
. When installing stairs within the sidewalk depending on topographical characteristics, ramps must be installed in parallel
Ensure that there is no hindrance to the walking of children, the elderly, and persons with disabilities.
7. To improve the energy efficiency and the use of new and renewable energy in buildings and greenhouse gas emissions
Minimize output
a. Buildings utilize new and renewable energy sources such as forest biomass including wood pellets, and solar and geothermal energy.
Fossil fuel consumption, such as using energy for cooling and heating or installing heat supply facilities
Minimize greenhouse gas emissions by minimizing START
B. Minimize the discharge of household and industrial waste during the construction and utilization of buildings, and so
Maximize the reuse and recycling of waste per
Buildings increase energy efficiency by installing facilities utilizing new and renewable energy, thereby reducing greenhouse gas emissions.
Minimize emissions
[Remarks]
1. The method for measuring the average slope pursuant to Subparagraph 4(a) is as follows:
a. Average slope refers to a digital topographic map (referring to the digital computer file of a 1:5000 scale topographic map. This
). However, if the digital topographic map does not match reality or the digital topographic
For areas without maps, in accordance with Article 17 of the "Act on the Establishment and Management of Spatial Information, etc."
After conducting a public survey to create a digital topographic map and using it to measure the average slope,
.
B. The grid for measuring the average slope is set to a size of 10 meters in width and 10 meters in height, and the grid
is the intersection of the tangent to the western boundary and the tangent to the northern boundary of the measurement site
.
. After generating an irregular triangular mesh on the digital topographic map using a spatial analysis program, within the grid
Calculate the average slope of the measurement site by applying the area ratio to the slope of the triangular face.
2. Details necessary for applying the standards pursuant to the provisions of Nos. 1 through 7 are forestry
The Commissioner shall determine and announce it.