Annex 1 — 철도의 건설 및 철도시설 유지관리에 관한 법률 시행령
262339 · 2024-05-17
■ Enforcement Decree of the Act on the Construction of Railways and Maintenance of Railway Facilities [Attached Table 1] <Amended Mar. 12, 2019>
Method of Calculating Compensation (Related to Article 14-2, Paragraph 2)
┌────────────────────────────────────────┐
│ Compensation = Land (referring to the surface land vertically corresponding to the area of the underground portion of the land) │
│Appropriate price of (does) × Three-dimensional use impairment rate × Area for establishment of subdivided surface rights │
└────────────────────────────────────────┘
Remarks: 1. The appropriate price of land is in accordance with Article 2, Paragraph 5 of the "Act on Public Announcement of Real Estate Prices and Appraisal"
Based on the officially assessed standard land price under [Name], the appraisal pursuant to Article 28 of the same Act [Name]
Among corporations, the value assessed by an appraisal firm designated by the Minister of Land, Infrastructure and Transport
.
2. Three-dimensional use impairment rate = Building use impairment rate + Underground part use impairment rate + Other use impairment
rate
a. Building Utilization Impairment Rate = α × Utilization Rate of Impaired Floor
B. Utilization impairment rate of the underground portion = β × Utilization rate of the impaired underground depth
. Other usage inhibition rates
1) Cases where other uses of both the above-ground and underground parts are hindered = γ
2) In cases where other use of either the above-ground or underground portion is hindered
= γ×V12/(V12+V22) or γ×V22/(V12+V22)
. α, β, and γ each follow the following formula.
Height│ V11 : Building Ground Floor Usage Value
├───┐ V12 : Usage value of communication facilities, advertising towers, or chimneys
│V12 │ V21 : Building basement floor usage value
│ │ V22 : Groundwater usage facilities or burial of special materials, etc.
├───┴┐ Usage Value
Z │V11 │
Table─┼───┬┴─
│V21 │
├──┬┘
│V22 │
├──┘
│
1) Three-dimensional Use Value (A) = Building Use Value (V11) + Underground Use Value (V21) + Other
Usage Value(V12+V22)
2) Utilization rate due to building use (α) = V11/A
3) Utilization rate due to use of the underground portion (β) = V21/A
Utilization rate due to other uses (γ) = (V12+V22)/A
5) Three-dimensional land utilization rate: α+β+γ = 1
3. The area for establishing a divided surface right is the area of the divided surface right established in the real estate register of the relevant land
Do it head-on.
4. Other utilization inhibition rates, inhibition layers, or inhibition sites necessary for the calculation of the three-dimensional utilization inhibition rate
The specific calculation criteria for the utilization rate, use value, etc. of the depth map are the relevant land and adjacent land
, the Minister of Land, Infrastructure and Transport
is determined and announced.