Annex 9 — 산지관리법 시행령

286957 · 2026-06-16

■ Enforcement Decree of the Mountain Area Management Act [Appendix 9] <Amended Aug. 19, 2020> Fee (Related to Article 51, Paragraph 1) ┌──────────┬─────────────────────────────┐ │Classification │Amount │ ├──────────┼─────────────────────────────┤ │1. Article 14 and Article 15 of the Act│a. In cases where the mountainous site area for which a permit is applied is 10,000 square meters or less: 2 │ │pursuant to Article 2, Paragraph 1 │10,000 won │ │Mountain land conversion permit and mountain │a. Mountain land area for which a permit is applied exceeds 10,000 square meters │ │Temporary Use Permit │: For 20,000 won, an additional 2,000 won is charged for every 1,000 square meters exceeding │ │ │Amount Calculated │ ├──────────┼─────────────────────────────┤ │2. Article 15 of the Act and 15│a. In cases where the reported forest land area is 10,000 square meters or less: 5,000 won │ │pursuant to Article 2, Paragraph 4 │b. If the reported mountainous land area exceeds 10,000 square meters: 5 │ │Notification of Mountain Land Conversion and Mountain │1,000 won plus 1,000 won for every 2,000 square meters exceeding │ │Temporary Use Report │Liquid │ ├──────────┼─────────────────────────────┤ │3. Pursuant to Article 21 of the Act │5000won │ │ApprovalOfChangeOfUse │ │ ├──────────┼─────────────────────────────┤ │4. Article 25, Paragraph 1 of the Act │a. In cases where the mountainous site area for which a permit is applied is 10,000 square meters or less: 2 │ │Permit for soil and rock extraction pursuant to START │10000 │ │ │a. Mountain land area for which a permit is applied exceeds 10,000 square meters │ │ │: For 20,000 won, an additional 2,000 won is charged for every 1,000 square meters exceeding │ │ │Amount Calculated │ ├──────────┼─────────────────────────────┤ │5. Article 25, Paragraph 2 of the Act │5000won │ │Report of soil and sand extraction pursuant to START │ │ ├──────────┼─────────────────────────────┤ │6. Article 29, Paragraph 2 of the Act │a. In cases where the mountainous area for which designation is requested is 10,000 square meters or less: 2 │ │and the quarry complex according to │10000 │ │(Depending on application │a. When the mountainous area for which designation is applied exceeds 10,000 square meters │ │Limited to tablets) │: 20,000 won plus 2,000 won for every 1,000 square meters exceeded │ │ │amount │ ├──────────┼─────────────────────────────┤ │7. Pursuant to Article 40 of the Act │a. In cases where the mountainous site area for which approval is requested is 10,000 square meters or less: 2 │ │Approval of Recovery Plan │10000 │ │ │b. When the mountainous area for which approval is requested exceeds 10,000 square meters │ │ │: 20,000 won plus 2,000 won for every 1,000 square meters exceeded │ │ │amount │ ├──────────┼─────────────────────────────┤ │8. Other than Article 42 of the Act │5,000 won │ │Restoration Completion Inspection │ │ └──────────┴─────────────────────────────┘