Annex 9 — 산지관리법 시행령
286957 · 2026-06-16
■ Enforcement Decree of the Mountain Area Management Act [Appendix 9] <Amended Aug. 19, 2020>
Fee (Related to Article 51, Paragraph 1)
┌──────────┬─────────────────────────────┐
│Classification │Amount │
├──────────┼─────────────────────────────┤
│1. Article 14 and Article 15 of the Act│a. In cases where the mountainous site area for which a permit is applied is 10,000 square meters or less: 2 │
│pursuant to Article 2, Paragraph 1 │10,000 won │
│Mountain land conversion permit and mountain │a. Mountain land area for which a permit is applied exceeds 10,000 square meters │
│Temporary Use Permit │: For 20,000 won, an additional 2,000 won is charged for every 1,000 square meters exceeding │
│ │Amount Calculated │
├──────────┼─────────────────────────────┤
│2. Article 15 of the Act and 15│a. In cases where the reported forest land area is 10,000 square meters or less: 5,000 won │
│pursuant to Article 2, Paragraph 4 │b. If the reported mountainous land area exceeds 10,000 square meters: 5 │
│Notification of Mountain Land Conversion and Mountain │1,000 won plus 1,000 won for every 2,000 square meters exceeding │
│Temporary Use Report │Liquid │
├──────────┼─────────────────────────────┤
│3. Pursuant to Article 21 of the Act │5000won │
│ApprovalOfChangeOfUse │ │
├──────────┼─────────────────────────────┤
│4. Article 25, Paragraph 1 of the Act │a. In cases where the mountainous site area for which a permit is applied is 10,000 square meters or less: 2 │
│Permit for soil and rock extraction pursuant to START │10000 │
│ │a. Mountain land area for which a permit is applied exceeds 10,000 square meters │
│ │: For 20,000 won, an additional 2,000 won is charged for every 1,000 square meters exceeding │
│ │Amount Calculated │
├──────────┼─────────────────────────────┤
│5. Article 25, Paragraph 2 of the Act │5000won │
│Report of soil and sand extraction pursuant to START │ │
├──────────┼─────────────────────────────┤
│6. Article 29, Paragraph 2 of the Act │a. In cases where the mountainous area for which designation is requested is 10,000 square meters or less: 2 │
│and the quarry complex according to │10000 │
│(Depending on application │a. When the mountainous area for which designation is applied exceeds 10,000 square meters │
│Limited to tablets) │: 20,000 won plus 2,000 won for every 1,000 square meters exceeded │
│ │amount │
├──────────┼─────────────────────────────┤
│7. Pursuant to Article 40 of the Act │a. In cases where the mountainous site area for which approval is requested is 10,000 square meters or less: 2 │
│Approval of Recovery Plan │10000 │
│ │b. When the mountainous area for which approval is requested exceeds 10,000 square meters │
│ │: 20,000 won plus 2,000 won for every 1,000 square meters exceeded │
│ │amount │
├──────────┼─────────────────────────────┤
│8. Other than Article 42 of the Act │5,000 won │
│Restoration Completion Inspection │ │
└──────────┴─────────────────────────────┘