Annex 8 — 산지관리법 시행령
286957 · 2026-06-16
■ Enforcement Decree of the Mountain Area Management Act [Table 8] <Amended June 16, 2026>
Standards for Permit for Soil and Stone Extraction (Related to Article 36, Paragraph 1)
┏━━━━━━━━┯━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━┓
┃Category │PermitCriteria ┃
┠────────┼──────────────────────────────┨
┃1. Morphology of the mountain range │A. Terrain ┃
┃ │ To excavate or extract soil and rock (hereinafter referred to as "extraction, etc." in this table) ┃
┃ │The region (hereinafter referred to as the "harvesting region" in this table) is the relevant production area ┃
┃ │(Highness: The height of the mountain peak based on the lower part of the mountain slope ┃
┃ │refers to. The same applies hereinafter) shall be 70% or less. However, the following ┃
┃ │In any of these cases, it is not the case. ┃
┃ │ 1) By extracting, etc., a parcel of area is leveled without cut slopes ┃
┃ │If it can be done as a branch ┃
┃ │ 2) If the elevation of the relevant mountain area is less than 300m ┃
┃ │ 3) In the case where a business plan pursuant to Subparagraph 8(d) has been established ┃
┃ │B. Slope ┃
┃ │ The average slope of the extraction area must be 35 degrees or less, and extraction, etc. ┃
┃ │The slope of the cut slope after completion (horizontal distance relative to the height of the slope ┃
┃ │refers to the ratio of [the same applies hereinafter in this table]) according to the following criteria ┃
┃ │It shall be suitable as a flat area without cut slopes by extraction, etc. ┃
┃ │shall not apply where it is possible. ┃
┃ │ 1) In the case of architectural stone, 1:0.4 or less ┃
┃ │ 2) In the case of excavation or extraction of stone other than construction stone 1 : ┃
┃ │0.5 or less ┃
┃ │ 3) In the case of excavation or extraction of soil, 1:1.0 or less ┃
┃ │. Delete <2012.5.22> ┃
┃ │. Delete <2012.5.22> ┃
┠────────┼──────────────────────────────┨
┃2. Composition of Timber │A. Stock of standing timber ┃
┃ │ The timber volume per hectare in the harvesting area is under the jurisdiction of the basic forest statistics ┃
┃ │less than 150 percent of the standing timber volume per hectare in cities, counties, and autonomous districts ┃
┃ │that. However, that which has experienced forest fires, thinning, or artificial logging ┃
┃ │If five years have not elapsed since the occurrence of a forest fire, thinning, or ┃
┃ │It shall be applied by converting to the timber volume prior to felling. However, Forest Basic Logistics ┃
┃ │Starting from the year following the announcement of the system, new basic forest statistics will be announced again. ┃
┃ │Until then, the average growth rate by city and province notified by the Minister of the Korea Forest Service... ┃
┃ │Applying the timber volume per hectare of the competent city, county, or district for the relevant year ┃
┃ │, 5 years after wildfires, thinning, and logging have been carried out ┃
┃ │Even when it does not appear, by applying the average growth rate for the relevant city/province, ┃
┃ │Calculate the volume of standing timber prior to forest fires, thinning, or felling. ┃
┃ │B. Distribution of Standing Trees ┃
┃ │ of broadleaf forests aged 50 years or older growing within the harvesting area ┃
┃ │The ratio must be 50 percent or less. ┃
┠────────┼──────────────────────────────┨
┃ │ ┃
┃ │ ┃
┃3. Soil and rock extraction area │The parcel of area to be sampled must be 50,000 square meters or more. However, the following ┃
┃ │This is not the case if it falls under any of the items. ┃
┃ │ a. The entire mountainous area adjacent to the area where extraction is being carried out with permission ┃
┃ │If the sieve area is less than 50,000 square meters ┃
┃ │ a. By continuing to extract from the remaining mountainous land, it will become a flat area without slopes ┃
┃ │If possible ┃
┃ │ . In order to restore the slopes of the quarrying area, stone materials were inevitably extracted ┃
┃ │In cases where it must be taken (of the restoration design document pursuant to Article 40, Paragraph 4 of the Act ┃
┃ │Limited to the minimum area required to meet approval criteria ┃
┃ │) ┃
┃ │ . In the process of converting or temporarily using mountain land, stone materials incidentally ┃
┃ │In case of collection ┃
┃ │ E. Adjacent to the area for which a soil and rock extraction permit has been obtained, a soil and rock extraction permit ┃
┃ │In the case of seeking to obtain [permit] 1/100 of the area for which a soil and rock extraction permit has already been obtained ┃
┃ │20 (limited to once, ┃
┃ │Building stone pursuant to Note 2, Item (a) of Attached Table 7 or Item (b) of the same item ┃
┃ │In the case of a permit for the extraction of earth and stone for craft stone materials pursuant to the item ┃
┃ │is limited to 2 times) ┃
┃ │ B. Ancillary facilities required for soil and rock extraction (product disposal site, access roads and pipes ┃
┃ │In case of intending to install or change (referring to the office) ┃
┃ │ Company. Without changing the area for which a permit for soil and rock extraction, such as underground extraction, soil ┃
┃ │In case the amount of stone extracted increases ┃
┃ │ A. In the case where a permit for soil and rock extraction was obtained for the purpose of soil and sand extraction ┃
┃ │ J. In case of intending to reduce the area for which a permit for soil and rock extraction was obtained ┃
┃ │ ┃
┃ │ ┃
┠────────┼──────────────────────────────┨
┃4. Buffer Zone │a. Setting of buffer zone ┃
┃etc. │ In order to prevent the collapse of adjacent land due to extraction, etc., from Subparagraph 3(a) onwards ┃
┃ │Except for cases corresponding to subparagraphs (d) and (f), the permitted area's ┃
┃ │A buffer zone with a width of 10 meters must be established inward from the boundary. ┃
┃ │. In this case, extraction, etc. must not be carried out in the same area ┃
┃ │. ┃
┃ │B. Soil Erosion Prevention Facilities ┃
┃ │ Areas where water accumulates to prevent soil erosion caused by extraction, etc. ┃
┃ │. ┃
┠────────┼──────────────────────────────┨
┃5. Method of extracting soil and rock │a. Except for cases where topsoil is to be removed, the upper part of the extraction area ┃
┃ │to the bottom, or without slopes ┃
┃ │Extraction, etc., must be carried out to create a flat terrain. In this case, in a terraced manner ┃
┃ │When performing extraction, etc., for one step, when the extraction, etc. is completed ┃
┃ │, collection, etc. must be carried out for the next step. ┃
┃ │a. In the case of underground extraction, etc., the materials reflected in the restoration plan ┃
┃ │A soil procurement plan suitable for the rainy season must be reasonable and feasible. ┃
┃ │. ┃
┃ │. Sampling should be performed to minimize vibration, noise, and dust ┃
┃ │Topsoil must be extracted in accordance with the annual project plan, and for restoration... ┃
┃ │Necessary topsoil and soil shall not be removed externally ┃
┠────────┼──────────────────────────────┨
┃6. of the surrounding forest │The forest road shall not be severed due to extraction, etc. However, the severed ┃
┃Management and Administration │After installing a forest road that can replace the forest road or after extraction, etc. ┃
┃ │can also continue to perform the function of replacing a forest road ┃
┃ │It is not so. ┃
┠────────┼──────────────────────────────┨
┃ │ ┃
┃ │ ┃
┃7. Business Plan and │a. The content of the business plan related to extraction, etc. is specific and reasonable, so ┃
┃Prevention of forest damage │The applicant for permission shall be able to perform collection, etc. without delay after receiving permission. ┃
┃ │a. The annual timber felling plan and the soil and rock extraction, production, and removal plan are specific ┃
┃ │and valid ┃
┃ │. The nature of the project, the surrounding landscape, the layout of the facilities to be installed, etc. ┃
┃ │, the area for ancillary facilities shall not be excessively included ┃
┃ │d. Damage prevention plan to prevent dust, soil runoff, landslides, etc. ┃
┃ │The interim restoration plan for the completed soil and rock extraction site shall be valid. In this case, the interim restoration plan for the completed soil and rock extraction site shall be valid. ┃
┃ │Damage prevention plans, such as START plans, must also be included. ┃
┃ │E. In accordance with coastal erosion control projects pursuant to Article 3, Paragraph 2 of the Erosion Control Projects Act ┃
┃ │Established forests shall not be incorporated into the project plan site. ┃
┃ │ ┃
┃ │ ┃
┣━━━━━━━━┿━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━┫
┃ │ ┃
┃ │ ┃
┃8. Landscape damage and │a. In cases where the extraction area is 70,000 square meters or more, the impact on the mountain landscape ┃
┃Disaster Prevention │Landscape damage, such as lowering the elevation of the extraction area by conducting simulations ┃
┃ │. However, ┃
┃ │In the case of additional excavation or extraction of soil and rocks underground within the permitted area, also ┃
┃ │is a [process] that has undergone deliberation pursuant to Article 28, Paragraph 2 of the Natural Environment Conservation Act ┃
┃ │is excluded. ┃
┃ │b. Processing facilities in areas visible from roads, houses, or factories, etc. ┃
┃ │In the case of installation, a shielding forest is created to block noise and dust ┃
┃ │Establish measures for prevention and landscape preservation. However, regarding rocky terrain, etc. ┃
┃ │, a screening facility shall be used instead ┃
┃ │can do. ┃
┃ │. The vertical height of the slope subject to restoration after soil and rock extraction is 15 meters or more ┃
┃ │, the width of the slope at intervals of 15 meters or less in vertical height ┃
┃ │(小段: slope of the embankment ┃
┃ │A flat section installed with a narrow width in the middle to relieve ┃
┃ │) is formed. In this case, the slope subject to restoration ┃
┃ │If the vertical height of the surface is 60 meters or more, the vertical height is 60 meters ┃
┃ │or less, a width of 10 meters or more excluding the width of the slope ┃
┃ │Establish disaster prevention measures, such as creating additional small terraces. ┃
┃ │. To prevent damage to the landscape, up to the lower part of the opposite slope beyond the ridge ┃
┃ │In the case of intending to extract land, the slope resulting after extraction is the most ┃
┃ │Establish a business plan to satisfy all of the following requirements so as to be digested ┃
┃ │things to do ┃
┃ │ 1) The vertical height of the cut slope in the extraction area due to extraction is 20 meters or ┃
┃ │Hail Thing ┃
┃ │ 2) From the upper part of the mountain so that the extraction area is not visible from the outside ┃
┃ │Sample downwards in a stepped manner ┃
┃ │E. Waste rock dust and topsoil generated during the stone extraction process ┃
┃ │Store in a safe place within the area, and fill in the waste rock dust and topsoil. ┃
┃ │, the slope of the embankment surface shall be 1:1.0 or less, and the ┃
┃ │Disaster prevention team ┃
┃ │Establish a book ┃
┃ │B. In order to minimize damage to the living environment such as noise, vibration, and dust, residents' ┃
┃ │After gathering opinions, establish a damage mitigation plan, such as access road paving. ┃
┃ │However, environmental impact assessment pursuant to Article 2, subparagraph 2 of the Environmental Impact Assessment Act ┃
┃ │has been passed. ┃
┃ │ ┃
┃ │ ┃
┗━━━━━━━━┷━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━┛
※ Remarks
1. Unlike the business plan at the time of the initial permit application, extraction, etc. in a stepped manner pursuant to Subparagraph 5
or slopes that are difficult to restore occurred due to blasting the lower part of the extraction area
In such cases, measures such as the revocation of permission may be taken pursuant to Article 31 of the Act. In this case, [unclear text]
When extracting aggregates, pursuant to Article 19, Paragraph 1 of the Aggregate Extraction Act, the Minister of Land, Infrastructure and Transport
Can a request be made to the relevant authority to order the cancellation of registration or suspension of operations of the aggregate extraction business?
.
2. Detailed matters necessary for applying the standards of Subparagraphs 1 and 2 are as follows: Agriculture, Forestry and Fisheries
It shall be determined by the Ordinance of the Ministry of Food and Rural Affairs.
3. Conservation state forests that do not fall under any of the following items, and passing through
, of the area intended for extraction, etc.
Transport roads may be installed within protected state forests within a range of 10/100.
a. Natural recreation forests pursuant to Article 13, Paragraph 1 of the "Act on Forest Culture and Recreation," "San
Seed forests pursuant to Article 19, Paragraph 1 of the "Act on the Creation and Management of Forest Resources," the same
Experimental forests pursuant to Article 47, Paragraph 1 of the Act and forests pursuant to Article 7, Paragraph 1 of the Forest Protection Act
RimProtectionMtQb18067662884aebf00164END
B. Article 2, Subparagraph 1 and Subparagraph 1-2 of the "Act on the Establishment and Promotion of Arboretums and Gardens"
에 따른 수목원 및 정원
. An erosion control area pursuant to Article 2, Subparagraph 4 of the "Erosion Control Act"
4. Depending on the topographical conditions of the mountainous site where soil and rock are to be excavated or extracted, or the nature of the project, the above standards
, only in the following cases
Apply with relaxation following deliberation by the Central Mountain Area Management Committee or the Local Mountain Area Management Committee
can do.
A. Subparagraph 1, Item A (Altitude of Mountain Area)
b. Subparagraph 1 (cutting of slopes occurring when extracting, etc. underground)
Slope slope)
. No. 3 (Soil and rock extraction area)
d. Subparagraph 5, Item (a) (Method of extracting soil and rock in cases of underground extraction, etc.)
E. Subparagraph 8, Item C (formation of terraces and disaster prevention measures in cases of underground extraction, etc.)
Establishment)
5. The method for determining the mountain peak and the lower foothills is as follows:
a. "Mountain peak" refers to the highest peak of the slope to which the mountain incorporated into the project area belongs.
refers to. However, in the case of a composite slope, within 1km from the boundary line of the project area
.
b. "Lower part of the mountain slope" refers to the forest map of the slope to which the mountain land incorporated into the project area belongs (林
A [landscape drawing] refers to a drawing prepared to understand the condition of trees within a forest.
It refers to the highest point of the forest boundary.
"Imgyeongji" refers to mountainous areas and other lands indicated on forest maps with a scale of 1/5,000 or larger.
. However, the boundary with any of the following lands refers to
I do not regard this as Imgyeongji.
1) Land consisting of a linear shape, such as roads and railways
2) 면적 3ha 미만의 농지·초지 등 산지가 아닌 토지(이하 "농지·초지
등"이라 한다)
. In the case of areas without clinical maps or areas where the local clinical map is inconsistent
Farmland, grasslands, etc. that are continuously connected without being interrupted by mountainous terrain (mountain land conversion permit·
Upon receiving a report, land or ditches/roads being used for other purposes and contiguously connected to them
The highest point of (excluding connected farmland, grasslands, etc.) as the lower foothills
See.