Annex 5 — 도시 및 주거환경정비법 시행령
287285 · 2026-07-01
■ Enforcement Decree of the Urban and Residential Environment Improvement Act [Table 5-2] <Amended July 23, 2024>
Criteria for Imposing Surcharges (Related to Article 89-2, Paragraph 1)
┌─────────────────┬────────────┬──────┐
│Violation │Legal Basis │Amount of Penalty │
├─────────────────┼────────────┼──────┤
│a. A construction contractor or registered business operator under the Act │Article 113-2, Paragraph 1, Subparagraph 1 of the Act │ │
│In case of violation of Article 132, Paragraph 1 │ │ │
│ │ │ │
│ 1) A construction contractor or registered business operator │ │of construction costs │
│in violation of Article 132, Paragraph 1 of the Act, the same │ │20/100 │
│is the act of each subparagraph of the paragraph (hereinafter “illegal │ │ │
│provided) (referred to as “provision”) │ │ │
│If the total is 30 million won or more │ │ │
│ │ │ │
│ 2) A construction contractor or registered business operator │ │of construction costs │
│in violation of Article 132, Paragraph 1 of the Act │ │15/100 │
│The total value of refined products provided is 10 million won. │ │ │
│In the case of 30 million won or more but less than │ │ │
│ │ │ │
│ 3) A construction contractor or registered business operator │ │of construction costs │
│in violation of Article 132, Paragraph 1 of the Act │ │100/100 │
│The total value of refined products provided is 5 million won │ │ │
│In the case of more than or equal to less than 10 million won │ │ │
│ │ │ │
│ 4) A construction contractor or registered business operator │ │of construction costs │
│In violation of Article 132, Paragraph 1 of the Act, [unclear text] │ │5/100 │
│The total value of refined products provided is 5 million won │ │ │
│is less than │ │ │
│ │ │ │
│or. A construction contractor or registered business operator under the Act │Article 113-2, Paragraph 1, Subparagraph 1 of the Act │ │
│In case of violation of Article 132, Paragraph 2 │ │ │
│ │ │ │
│ 1) A construction contractor or registered business operator │ │ofconstruction costs │
│In violation of Article 132, Paragraph 2 of the Act, the same │ │20/100 │
│is unrelated to the construction of each subparagraph of │ │ │
│(hereinafter “Proposal excluding construction”) │ │ │
│(It is said that the sum of the values is 3,000 ) │ │ │
│If it is 10,000 won or more │ │ │
│ │ │ │
│ 2) A construction contractor or registered business operator │ │ofconstruction costs │
│In violation of Article 132, Paragraph 2 of the Act, the │ │15/100 │
│The sum of the values of the externally proposed amounts is 10 million │ │ │
│If the amount is 1 won or more but less than 30 million won │ │ │
│ │ │ │
│ 3) A construction contractor or registered business operator │ │ofconstruction costs │
│In violation of Article 132, Paragraph 2 of the Act, the │ │10/100 │
│The sum of the values of the externally proposed amounts is 5 million │ │ │
│If the amount is 10 million won or more but less than 10 million won │ │ │
│ │ │ │
│ 4) A construction contractor or registered business operator │ │ofconstruction costs │
│In violation of Article 132, Paragraph 2 of the Act, the │ │5/100 │
│The sum of the values of the externally proposed amounts is 5 million │ │ │
│If less than one won │ │ │
│ │ │ │
│. A construction contractor or registered business operator is statutory │Article 113-2, Paragraph 1, Subparagraph 2 of the Act │ │
│In violation of Article 132-2, management/detention │ │ │
│and other necessary measures not taken │ │ │
│, an executive or employee of the service provider │ │ │
│In case of violation of Article 132, Paragraph 1 of the Act │ │ │
│ │ │ │
│ 1) An executive or employee of a service provider [is] Article 132 │ │ofconstruction costs │
│provided improperly in violation of Paragraph 1 │ │20/100 │
│In cases where the sum of the values is 30 million won or more │ │ │
│U │ │ │
│ │ │ │
│ 2) An executive or employee of a service provider [is] Article 132 │ │of construction costs │
│provided improperly in violation of Paragraph 1 │ │15/100 │
│The sum of the values is 10 million won or more, or 30 million │ │ │
│If less than 10,000 won │ │ │
│ │ │ │
│ 3) An executive or employee of a service provider [is] Article 132 │ │ofconstruction costs │
│provided improperly in violation of Paragraph 1 │ │10/100 │
│The sum of the values is 5 million won or more and 1,000 │ │ │
│If less than 10,000 won │ │ │
│ │ │ │
│ 4) An executive or employee of a service provider [is] Article 132 │ │of construction costs │
│providing fraudulently in violation of Paragraph 1 │ │5/100 │
│In cases where the sum of the values is less than 5 million won │ │ │
│U │ │ │
└─────────────────┴────────────┴──────┘