Minimum length of transmission lane (related to Article 8, Paragraph 1)
1. In the case of District Unit Planning Zones and Areas for Establishing Phase 2 Implementation Plans
a. In the case of installing a deceleration lane on the main line
(Unit: Meter)
┌───────────┬─────────┬────────┬──────────┐
│Facility │Number of parking spaces or │Length of reduction section │Length of acceleration section │
│ │Number of households etc. ├────┬───┼─────┬────┤
│ │ │With deceleration vehicle│Taper│Acceleration Lane │Taper │
├───────────┼─────────┼────┼───┼─────┼────┤
│1) Industrial complex access roads, etc. │- │40 │15 │65 │20 │
│ │ │(25) │(10) │(45) │(15) │
├───────────┼─────────┼────┼───┼─────┼────┤
│2) Rest Areas and Gas Stations │- │40 │15 │65 │20 │
│etc │ │(25) │(10) │(45) │(15) │
├───────────┼─────────┼────┼───┼─────┴────┤
│3) Auto repair shops, etc. │- │25 │10 │Direct acceleration lane │
│ │ │(15) │(10) │30(20) │
├───────────┼─────────┼────┴───┴──────────┤
│4) Sado · Farm Road · Village │The width of passages, etc. is │Curving of road edges │
│Access road or other │6m Less than │(Curve radius: 7m) │
│에 이와 유사한 교 ├─────────┼────┬───┬──────────┤
│General passageway etc. │The width of passages, etc. │15 │10 │Direct acceleration lane │
│ │6m or more │(10) │(10) │25(20) │
├───────────┼─────────┼────┼───┼──────────┤
│5) Sales facilities and general │20s and under │15 │10 │Direct acceleration lane │
│Restaurants etc. │ │(10) │(10) │25(20) │
│ ├─────────┼────┼───┼──────────┤
│ │21 units or more 50 units │25 │10 │Direct acceleration lane │
│ │Below │(15) │(10) │30(20) │
│ ├─────────┼────┼───┼─────┬────┤
│ │51 units or more │40 │15 │65 │20 │
│ │ │(25) │(10) │(45) │(15) │
├───────────┼─────────┼────┴───┴─────┴────┤
│6) Parking Lot·Construction Machinery │20s and under │Curving of road corners │
│Aperage·Transportation Facilities │ │(Curve radius: 7m) │
│·Medical Facilities·Exercise ├─────────┼────┬───┬──────────┤
│Facilities·Viewing Facilities· │21 units or more 50 units │25 │10 │Direct acceleration lane │
│Assembly facilities and recreational city │Below │(15) │(10) │30(20) │
│Seoul etc ├─────────┼────┼───┼─────┬────┤
│ │51 units or more │40 │15 │65 │20 │
│ │ │(25) │(10) │(45) │(15) │
├───────────┼─────────┼────┴───┴─────┴────┤
│7) Factory·Accommodation· │20s and under │Curving of road corners │
│Office Facilities·Neighborhood Life │ │(Curve radius: 7m) │
│Activity facilities and other cities ├─────────┼────┬───┬──────────┤
│Description │21 units or more 50 units │25 │10 │Direct acceleration lane │
│ │Below │(15) │(10) │30(20) │
│ ├─────────┼────┼───┼─────┬────┤
│ │51 units or more │40 │15 │65 │20 │
│ │ │(25) │(10) │(45) │(15) │
├───────────┼─────────┼────┴───┴─────┴────┤
│8) House driveways, etc. │5 households or less │Curving of road corners │
│ │ │(Curve radius: 3m) │
│ ├─────────┼───────────────────┤
│ │6 households or more 20 │Curving of road corners │
│ │구 아래 │(Curve radius: 5m) │
│ ├─────────┼────┬───┬──────────┤
│ │21 households or more 100 │25 │10 │Direct acceleration lane │
│ │Furniture Below │(15) │(10) │30(20) │
│ ├─────────┼────┼───┼─────┬────┤
│ │101 households more than │40 │15 │65 │20 │
│ │ │(25) │(10) │(45) │(15) │
├───────────┼─────────┼────┴───┴─────┴────┤
│Rural small-scale cities │- │Curving of road corners │
│(Small-scale livestock barn also │ │(Curve radius: 3m) │
│is warehouse, etc.) and Tae │ │ │
│Solar power generation facilities, etc. │ │ │
└───────────┴─────────┴───────────────────┘
b. In the case of installing a deceleration lane on the sidewalk
(Unit: Meter)
┌───────────┬─────────┬─────────┬─────────┐
│Facility │Number of parking spaces or │Length of reduction section │Length of acceleration section │
│ │Number of households ├────┬────┼─────┬───┤
│ │ │deceleration vehicle│Taper │Acceleration Lane │Taper│
├───────────┼─────────┼────┼────┼─────┼───┤
│1) Item A 1) and 2) │- │10 │3.5 │15 │5 │
├───────────┼─────────┼────┴────┴─────┴───┤
│2) A3) │- │Curving of road corners │
│ │ │(Curve radius: 7m) │
├───────────┼─────────┼───────────────────┤
│3) A4) │- │Curving of road corners │
│ │ │(Curve radius: 5m) │
├───────────┼─────────┼───────────────────┤
│4) Item A 5) through 7) │50s and under │Curving of road edges │
│ │ │(Curve radius: 7m) │
│ ├─────────┼─────┬────┬─────┬──┤
│ │51 units or more │10 │3.5 │15 │5 │
├───────────┼─────────┼─────┴────┴─────┴──┤
│5) 8) │5 households or less │Curving of road corners │
│ │ │(Curve radius: 3m) │
│ ├─────────┼───────────────────┤
│ │6 Household More than │Curving of road corners │
│ │20 households or less │(Curve radius: 5m) │
│ ├─────────┼───────────────────┤
│ │21 households or more │Curving of road edges │
│ │100 households or less │(Curve radius: 7m) │
│ ├─────────┼────┬────┬─────┬───┤
│ │101 Households or more │10 │3.5 │15 │5 │
├───────────┼─────────┼────┴────┴─────┴───┤
│6) A-9) │- │Curving of road corners │
│ │ │(Curve radius: 3m) │
└───────────┴─────────┴───────────────────┘
. Application criteria
1) "District Unit Planning Area" refers to, pursuant to Article 51 of the Act on Planning and Utilization of National Land
Refers to the designated area.
"Area for the establishment of the Phase 2 implementation plan" refers to Article 85 of the Act on Planning and Utilization of National Land
Refers to an urban area where the Phase 2 implementation plan has been established among the phased implementation plans pursuant to START.
Item (a) is the standard for roads with 4 or more lanes in both directions, and the number in parentheses is for 2 lanes in both directions.
This is a standard for roads.
4) In cases where connecting roads are adjacent and acceleration/deceleration lanes overlap, the length of the overlapping lane corresponds to the number of parking spaces
Sum them up and set the length to correspond to the summed number of parking spaces, and the number of parking spaces can be applied
In the event of overlap with non-existent facilities, the larger value among them shall be used as the basis.
5) In the column for the number of parking spaces or households, etc. under Item 4), "width of passageway, etc." refers to a passageway, etc. where a car
Parts used for the passage of a certain amount (including shoulders, bicycle paths, sidewalks, and other facilities)
).
6) When calculating Items 5) through 7) of Subparagraph (a) and Item 4) of Subparagraph (b), the provisions of Annex 1 of the Enforcement Decree of the Parking Lot Act
Follows the standard.
2. For other regions
a. In the case of installing a deceleration lane on the main line
(Unit: Meter)
┌──────────┬─────────┬─────────┬──────────┐
│Facility │Number of parking spaces or │Length of reduction section │Length of acceleration section │
│ │Number of households ├─────┬───┼──────┬───┤
│ │ │deceleration vehicle │Taper│Acceleration Lane │Taper│
├──────────┼─────────┼─────┼───┼──────┼───┤
│1) Industrial complex access roads, etc. │- │45 │15 │90 │30 │
│ │ │(30) │(10) │(65) │(20) │
├──────────┼─────────┼─────┼───┼──────┼───┤
│2) Rest Areas and Gas Stations │- │45 │15 │90 │30 │
│etc │ │(30) │(10) │(65) │(20) │
├──────────┼─────────┼─────┼───┼──────┼───┤
│3) Auto repair shops, etc.│- │30 │10 │60 │20 │
│ │ │(20) │(10) │(40) │(20) │
├──────────┼─────────┼─────┼───┼──────┼───┤
│4) Sado · Farm Road · Village │- │20 │10 │40 │20 │
│Access road or other │ │(15) │(10) │(30) │(20) │
│에 이와 유사한 교 │ │ │ │ │ │
│General passageway etc. │ │ │ │ │ │
├──────────┼─────────┼─────┼───┼──────┼───┤
│5) Sales facilities and general │10s or less │20 │10 │40 │20 │
│Restaurants etc. │ │(15) │(10) │(30) │(20) │
│ ├─────────┼─────┼───┼──────┼───┤
│ │11 units or more 30 units │30 │10 │60 │20 │
│ │Below │(20) │(10) │(40) │(20) │
│ ├─────────┼─────┼───┼──────┼───┤
│ │31 units or more │45 │15 │90 │30 │
│ │ │(30) │(10) │(65) │(20) │
├──────────┼─────────┼─────┼───┼──────┼───┤
│6) Parking Lot·Construction Machinery │30s and under │30 │10 │60 │20 │
│Aperture·Transportation Facilities │ │(20) │(10) │(40) │(20) │
│·Medical Facilities·Exercise ├─────────┼─────┼───┼──────┼───┤
│Facilities·Viewing Facilities· │31 units or more │45 │15 │90 │30 │
│Assembly Facilities and Recreation │ │(30) │(10) │(65) │(20) │
│Facilities etc. │ │ │ │ │ │
├──────────┼─────────┼─────┼───┼──────┼───┤
│7) Factory·Accommodation· │20s and under │20 │10 │40 │20 │
│Office Facilities·Neighborhood Life │ │(15) │(10) │(30) │(20) │
│Activity facilities and other cities ├─────────┼─────┼───┼──────┼───┤
│Description │21 units or more 50 units │30 │10 │60 │20 │
│ │Below │(20) │(10) │(40) │(20) │
│ ├─────────┼─────┼───┼──────┼───┤
│ │51 units or more │45 │15 │90 │30 │
│ │ │(30) │(10) │(65) │(20) │
├──────────┼─────────┼─────┴───┴──────┴───┤
│8) House driveways, etc. │5 households or less │Curving of road corners (Curve radius: 3m) │
│ ├─────────┼─────┬───┬─────┬────┤
│ │6 households or more 100 households │30 │10 │60 │20 │
│ │구 아래 │(20) │(10) │(40) │(20) │
│ ├─────────┼─────┼───┼─────┼────┤
│ │101 Households or more │45 │15 │90 │30 │
│ │ │(30) │(10) │(65) │(20) │
├──────────┼─────────┼─────┴───┴─────┴────┤
│Rural small-scale cities │- │Curving of road corners (Curve radius: 3m) │
│(Small-scale livestock barn also │ │ │
│is warehouse, etc.) and Tae │ │ │
│Solar power generation facilities, etc. │ │ │
└──────────┴─────────┴────────────────────┘
b. In the case of installing a deceleration lane on the sidewalk
(Unit: Meter)
┌───────────┬────────┬──────────┬─────────┐
│Facility │Number of parking spaces or │Length of reduction section │Length of acceleration section │
│ │Number of households ├─────┬────┼────┬────┤
│ │ │deceleration vehicle │Taper │Acceleration Lane│Taper │
├───────────┼────────┼─────┼────┼────┼────┤
│1) Item A 1) and 2) │- │10 │3.5 │15 │5 │
├───────────┼────────┼─────┴────┴────┴────┤
│2) A3) │- │Curving of road corners │
│ │ │(Curve radius: 7m) │
├───────────┼────────┼────────────────────┤
│3) A4) │- │Curving of road corners │
│ │ │(Curve radius: 5m) │
├───────────┼────────┼────────────────────┤
│4) Item A 5) and 6) │30s and under │Curving of road corners │
│ │ │(Curve radius: 7m) │
│ ├────────┼─────┬────┬────┬────┤
│ │31 units or more │10 │3.5 │15 │5 │
├───────────┼────────┼─────┴────┴────┴────┤
│5) 7) │50s and under │Curving of road edges │
│ │ │(Curve radius: 7m) │
│ ├────────┼─────┬────┬────┬────┤
│ │51 units or more │10 │3.5 │15 │5 │
├───────────┼────────┼─────┴────┴────┴────┤
│6) 8) │5 households or less │Curving of road corners │
│ │ │(Curve radius: 3m) │
│ ├────────┼────────────────────┤
│ │6 Household More than │Curving of road corners │
│ │100 households or less │(Curve radius: 7m) │
│ ├────────┼─────┬────┬────┬────┤
│ │101 Households or more │10 │3.5 │15 │5 │
├───────────┼────────┼─────┴────┴────┴────┤
│7) Item 9) │- │Curving of road corners │
│ │ │(Curve radius: 3m) │
└───────────┴────────┴────────────────────┘
. Application criteria
Item (a) is the standard for roads with 4 or more lanes in both directions, and the number in parentheses is for 2 lanes in both directions.
This is a standard for roads.
2) In cases where connecting roads are adjacent and acceleration/deceleration lanes overlap, the length of the overlapping lane corresponds to the number of parking spaces
Sum them up to the length corresponding to the summed number of parking spaces, and the number of parking spaces can be applied
In the event of overlap with non-existent facilities, the larger value among them shall be used as the basis.
3) When calculating the number of parking spaces under Items 5) through 7) of Subparagraph A and Items 4) and 5) of Subparagraph B, the "Enforcement Decree of the Parking Lot Act
It shall comply with the installation standards of Annex 1 of the [Ordinance].