Annex 2 — 폐기물의 국가 간 이동 및 그 처리에 관한 법률 시행령
285285 · 2026-04-07
■ Enforcement Decree of the Act on the Transboundary Movement and Disposal of Waste [Appendix 2] <Amended Oct. 1, 2025>
Contents, methods, and timing of input into electronic information processing programs (related to Article 17-5, Paragraph 2)
1. Obtaining an export permit pursuant to Article 6, Paragraph 1 of the Act or filing an export declaration pursuant to Article 18-2, Paragraph 1 of the Act
A person who has obtained an import permit pursuant to Article 10, Paragraph 1 of the Act or Article 18 of the Act (hereinafter referred to as the “Exporter”)
A person who has filed an import declaration pursuant to Article 2, Paragraph 1 (hereinafter referred to as the “importer”), pursuant to Article 8, Paragraph 1 of the Act
Transporting export-import regulated waste or transporting imported waste pursuant to Article 18-3, Paragraph 3 of the Act
A person who disposes of waste (hereinafter referred to as the “Carrier”) or a person who recycles or disposes of waste (hereinafter referred to as the “Recycling
The “Usage/Disposal Person”) shall, in accordance with the classifications in each of the following subparagraphs, [take place] in the transfer and acceptance of import/export waste
must be entered into the electronic information processing program.
a. In the case of export
1) The exporter transports the export waste themselves or hands it over to a carrier for consignment transport
, the exporter shall, prior to transport or handover, the type and quantity of waste, the handover date, transport
The vehicle number and other information must be entered into the electronic information processing program for confirmation or reservation.
When entering a reservation, the confirmation must be completed within 2 days from the date of entry into the bonded area.
must exert.
2) The carrier, within 2 days from the date of receiving the waste from the exporter, [Name of exporter,] [End of text]
Input the vehicle number, quantity received, date of receipt, and other information into the electronic information processing program.
must be utilized. However, waste is collected using a vehicle with low loading capacity, and the loading capacity
In the case of transporting via a temporary storage area to transfer to a larger vehicle
can be entered within 2 days after bringing into the bonded area.
3) In the case of transporting export waste from a bonded area to an importing country by ship, the exporter
must, within 2 days from the date of completion of shipment, the shipment date, vessel number, shipping company name, cargo quantity, and bill of lading
A copy of the securities and the importing country must be entered into the electronic information processing program, and in the importing country, a copy of the securities and the importing country must be entered into the electronic information processing program, and from the importing country
Enter the unloading port and date within 14 days from the date the unloading of export waste is completed.
must.
4) When the exporter completes the customs clearance procedures for export waste in the importing country, the date of completion of customs clearance
The customs clearance volume and date must be entered into the electronic information processing program within 14 days from START.
.
or. In the case of imports
1) The importer transports the imported waste themselves or hands it over to a carrier for consignment transport
, the importer shall, prior to transportation or handover, the type and quantity of waste, the handover date, transportation
The vehicle number and other information must be entered into the electronic information processing program for confirmation or reservation.
and when a reservation is entered, 2 days after the recycler/disposer takes possession of the imported waste
.
2) The carrier shall, within 2 days from the date of receiving the waste from the importer, the importer's name, Transport
Vehicle number, quantity received and quantity handed over, date of receipt and handover, and other information are electronic information
You must input the waste into the processing program. However, with a vehicle having a small loading capacity, the waste...
Passing through a temporary storage area to collect and transfer to a vehicle with a large loading capacity,
In the case of transportation, you can enter the data within 2 days after handing it over to the recycler/disposer.
.
3) On the date the recycler/disposer receives the waste from the carrier (transported directly by the importer,
In the case of recycling and disposal, the date the waste arrives at the recycling or disposal site
), the acceptance date, acceptance quantity and weighed value, and other information [
Input into the self-information processing program (the measured value is in the first part of Article 25, Paragraph 3 of the "Waste Management Act"
) and recycle or dispose of the relevant waste
Input the throughput and processing date into the electronic information processing program within 2 days from the date of division.
must exert power.
2. An exporter, importer, carrier, or recycler/disposer of an error in an electronic information processing program,
Details regarding the transfer and acceptance of import and export waste due to reasons such as natural disasters or fire electronically
If input cannot be made into the information processing program, the following measures must be taken.
a. Transfer of import/export waste using alternative input methods such as ARS, wired/wireless telephones, etc.
Enter the details regarding the acquisition, and the reason for alternative input and alternative input period to the Korea Environment Corporation
etc. must be notified within 3 days.
or. When the alternative input period is extended or normal input becomes possible, the reason for the period extension or
The fact of normal operation must be reported to the Korea Environment Corporation.
. In the event of a failure in the electronic information processing program, the
The use of an electronic information processing program regarding the contents of the transfer and acceptance of import and export waste
Must be entered within 3 days from the earliest available date.
Remarks
1. “Confirmed Input” refers to the type, quantity, etc. of waste specified by a person intending to export or import waste
All information that must be entered into the electronic information processing program in relation to the transfer and acceptance of materials
refers to inputting.
2. “Reservation Input” refers to a person intending to export or import waste who is not equipped with weighing facilities
, electronic information processing program
It refers to entering the information that must be entered into the START system, excluding the amount of waste.
3. “Other information” refers to contents regarding the transfer and acceptance of imported and exported waste, Climate Energy Environment
Refers to information determined and notified by the Minister.