Annex 1 — 도시교통정비 촉진법 시행령
287283 · 2026-07-01
■ Enforcement Decree of the Urban Traffic Management Promotion Act [Attached Table 1] <Amended Feb. 6, 2024>
Scope of Projects Subject to Traffic Impact Assessment and Timing of Submission and Review of Traffic Impact Assessment Report
(Related to Article 13-2 Paragraph 3 and Article 13-3 Paragraph 1)
1. Development Project
┏━━━━━━━━━┯━━━━━━━━━━━━━━━━━━┯━━━━━━━━━━━━━━━┓
┃Classification │Scope of Projects Subject to Traffic Impact Assessment │of the Traffic Impact Assessment Report ┃
┃ │ │Submission/Review Period ┃
┠─────────┼──────────────────┼───────────────┨
┃a. The city's dog │Article 2, Paragraph 1, Subparagraph 2 of the "Urban Development Act" │Article 17, Paragraph 2 of the Urban Development Act ┃
┃From │Urban development project following START │Authorization of the implementation plan pursuant to the START clause of ┃
┃ │ - Site area 100,000㎡ or more │Previous ┃
┃ │ │ ┃
┃ │Article 2 of the Urban and Residential Environment Improvement Act │「Urban and Residential Environment Improvement Act」 ┃
┃ │No. 2 (residential environment improvement work under subparagraph (a) of the same subparagraph │Implementation of project pursuant to Article 50 ┃
┃ │Among the businesses under Article 23, Paragraph 1, Subparagraph 1 of the same Act │Before plan approval, local government ┃
┃ │are excluded) pursuant to │implementing that business ┃
┃ │Maintenance Business │, the project implementation plan ┃
┃ │ - Site area 50,000㎡ or more │Before the announcement of the price ┃
┃ │ │ ┃
┃ │ │ ┃
┃ │3) "Act on Planning and Utilization of National Land" │「To the Planning and Use of National Land ┃
┃ │Among the infrastructure facilities pursuant to Article 2, subparagraph 6, the following │Article 88, Paragraph 2 of the "Act concerning..." ┃
┃ │의 시설에 관한 도시계획시설사업 │따른 실시계획의 인가 전 ┃
┃ │ a) Road │ ┃
┃ │ - │ ┃
┃ │Interchange, intersection section and other between │ ┃
┃ │Connection with the main road │ ┃
┃ │ b) Distribution Business Facilities │ ┃
┃ │ - Total building area of 15,000㎡ or more or │ ┃
┃ │Site area 55,000㎡ or more │ ┃
┃ │ da) Park │ ┃
┃ │ - Site area over 300,000㎡ │ ┃
┃ │ ra) Amusement Park │ ┃
┃ │ - Site area 150,000㎡ or more │ ┃
┃ │ │ ┃
┃ │4) Site development pursuant to Article 15 of the Housing Act│Pursuant to Article 15 of the "Housing Act" ┃
┃ │Business │Before approval of business plan ┃
┃ │ - Site area 100,000㎡ or more │ ┃
┃ │ │ ┃
┃ │Pursuant to Article 2, Subparagraph 4 of the "Residential Land Development Promotion Act"│Article 9 of the "Residential Land Development Promotion Act" ┃
┃ │Land development projects or "special public housing projects"│Land development project pursuant to Paragraph 1 ┃
┃ │Public housing pursuant to Article 2, Subparagraph 3, Item (a) of the "Act" │Before approval of the implementation plan or ┃
┃ │District Development Project │"Special Act on Public Housing" No. 17 ┃
┃ │ - Site area 100,000㎡ or more │Public housing district plan according to the START clause ┃
┃ │ │Prior to approval of the plan ┃
┃ │ │ ┃
┃ │6) "Regarding the development and operation of logistics facilities │「Development and operation of logistics facilities ┃
┃ │Logistics complex development pursuant to Article 2, Subparagraph 9 of the Act │Article 28 of the "Act on the Management of the Land" ┃
┃ │StartBusiness │Of the implementation plan pursuant to Paragraph 1 ┃
┃ │ - Site area 50,000㎡ or more │Before Approval ┃
┃ │ │ ┃
┃ │7) "Regarding the development and operation of logistics facilities │「Development and operation of logistics facilities ┃
┃ │Water pursuant to Article 2, subparagraphs 2 and 4 of the "Act"│Article 9 of the "Act on the Management of..." ┃
┃ │Installation of logistics terminals or complex logistics terminals │Approval of construction execution pursuant to Clause 1 ┃
┃ │ - Site area 25,000㎡ or more │is before ┃
┃ │ │ ┃
┃ │8) "Act on Planning and Utilization of National Land │「Regarding the Planning and Use of National Land ┃
┃ │Rate within urban areas pursuant to Article 50 │Article 30, Paragraph 1 of the "Act on the..." ┃
┃ │Urban and County Management Plan Regarding District Unit Planning │within urban areas ┃
┃ │MTQ1e3da3b06a57b87601563Determination of START │Regarding district unit planning ┃
┃ │ - Site area 100,000㎡ or more │Decision on City/County Management Plan ┃
┃ │ │Previous ┃
┃ │ │ ┃
┃ │9) "Special provisions regarding the creation and development of innovation cities│「On the creation and development of innovation cities ┃
┃ │Innovation City development pursuant to Article 2, Subparagraph 5 of the "Special Act" │Article 12, Paragraph 1 of the "Special Act Concerning START" ┃
┃ │StartBusiness │Prior to approval of the implementation plan pursuant to the START clause of ┃
┃ │ - Site area 100,000㎡ or more │ ┃
┃ │ │ ┃
┃ │10) "Act on the Development and Utilization of Station Areas│「Development and Utilization of Station Areas ┃
┃ │Station area development company pursuant to Article 2, Subparagraph 2 of the "START rate" │Article 13 of the "Act on START" ┃
┃ │Among businesses with a business area of 250,000 square meters or more │Promotion of the implementation plan pursuant to Clause 1 ┃
┃ │business │ex ┃
┃ │ │ ┃
┃B. Industrial Location │1) "Industrial Location and Development Act" │「Regarding industrial site and development ┃
┃and Industrial Complex │Industrial complex development project pursuant to Article 2, Subparagraph 9 │Article 17 of the "Act on..." ┃
┃Composition of START │and industrial complex pursuant to Subparagraph 11 of the same Article │Article 2, Article 18, Article 18's ┃
┃ │Regeneration Business │2 and implementation pursuant to Article 19 ┃
┃ │ - Site area 200,000㎡ or more │Prior to approval of the plan or the same ┃
┃ │ │Re- ┃
┃ │ │Before approval of the implementation plan ┃
┃ │ │ ┃
┃ │2) "Special Act on the Promotion of Research and Development Special Zones│「On fostering R&D special zones ┃
┃ │Special zone pursuant to Article 6-2, Paragraph 2, Subparagraph 4 of the "Act" │Article 27 of the "Special Act Concerning START" ┃
┃ │DevelopmentProject │따른 실시계획의 승인 전 ┃
┃ │ - Site area 200,000㎡ or more │ ┃
┃ │ │ ┃
┃. Energy change │pursuant to Article 2, subparagraph 2 of the "Act on Promotion of Electric Power Development" │Article 5 of the "Power Generation Promotion Act" ┃
┃From │Power development projects (excluding transmission lines │Of the implementation plan pursuant to Paragraph 1 ┃
┃ │) │Before Approval ┃
┃ │ - Site area 3 million m² or more │ ┃
┃ │ │ ┃
┃. Port construction │port pursuant to Article 2, subparagraph 1 of the "Port Act" │Pursuant to Article 10 of the "Port Act" ┃
┃Section │Construction (functional city pursuant to subparagraph 5, item b of the same article│establishment of other implementation plans or ┃
┃ │As a facility, automated equipment such as port pipelines│Prior to approval, provided, however, "Port Authority ┃
┃ │, the approving authority for the construction of the port │Port facility construction pursuant to the "START Act" ┃
┃ │external transportation demand via vehicles does not occur │is executed, the same ┃
┃ │Acknowledging that it is not, the Minister of Land, Infrastructure and Transport and │is the actual ┃
┃ │(Projects agreed upon are excluded) │Before approval of the city plan ┃
┃ │ - Annual unloading capacity over 1.5 million tons │ ┃
┃ │ │ ┃
┃E. Construction of roads │Construction of a road pursuant to Article 10 of the "Road Act"│Pursuant to Article 25 of the "Road Act" ┃
┃Description │Among newly established routes with a total length of 5 km or more, in │Before the determination of other road zones ┃
┃ │Tchanges, junctions, intersections and other │ ┃
┃ │Connection with main road │ ┃
┃ │ │ ┃
┃B. Railway Construction │1) "Construction of railways and maintenance of railway facilities│「To the Planning and Use of National Land ┃
┃Section │" and "National Land │City pursuant to the "Act concerning" ┃
┃ │Article 2 of the "Act on the Planning and Use of START" │Implementing as a planned project ┃
┃ │Construction of a railway pursuant to No. 6. However, "railway│Above, Article 88, Paragraph 2 of the same Act ┃
┃ │Jeon Yong-cheol pursuant to Article 2, Subparagraph 5 of the "Provincial Business Act" │Approval of the implementation plan pursuant to the clause ┃
┃ │(Excluding cases where the drawing is installed inside the factory) │is before, otherwise ┃
┃ │. │「Railway Construction and Railway City ┃
┃ │ - Total including 1 or more stations │Act on the Maintenance of Facilities ┃
┃ │Length 5km or more │rate pursuant to Article 9, Paragraph 1 ┃
┃ │ │Before approval of implementation plan ┃
┃ │ │ ┃
┃ │2) pursuant to Article 2, Subparagraph 2 of the "Urban Railway Act"│Article 7 of the "Urban Railway Act" ┃
┃ │Construction project of municipal railways │따른 사업계획 승인 전 ┃
┃ │ - Total including 1 or more stations │ ┃
┃ │Length 3km or more │ ┃
┃ │ │ ┃
┃Company. Airport construction │Article 2, subparagraphs 2 and 3 of the "Airport Facilities Act" │Article 7, Paragraph 3 of the Airport Facilities Act ┃
┃Description │Installation of airfields and airports according to START │Approval of implementation plan pursuant to the START clause of ┃
┃ │ - Annual passenger handling capacity of over 300,000 │and pursuant to paragraph 6 of the same article ┃
┃ │ │BeforeNotice ┃
┃ │ │ ┃
┃Ah. Of the tourist complex │Article 2, Subparagraph 6 and Subparagraph 7 of the Tourism Promotion Act │Article 54 of the Tourism Promotion Act ┃
┃Development │Creation of tourist sites and tourist complexes pursuant to the START │Promotion of the development plan pursuant to Clause 1 ┃
┃ │Business │ex ┃
┃ │ - Facility planning area of 50,000㎡ or more or│ ┃
┃ │Land area of 500,000 m² or more │ ┃
┃ │ │ ┃
┃ │2) Opening of hot springs pursuant to Article 2 of the "Hot Spring Act"│Pursuant to Article 10 of the "Hot Spring Act" ┃
┃ │StartBusiness │Approval of the hot spring development plan ┃
┃ │ - Site area 100,000㎡ or more │Previous ┃
┃ │ │ ┃
┃. Specific region's │1) "Act on Regional Development and Support" │ 「Regarding regional development and support ┃
┃Development │Regional development project pursuant to Article 2, Subparagraph 3 │Article 23, Paragraph 1 of the "Act on..." ┃
┃ │ - Site area 100,000㎡ or more │Prior to the approval of the implementation plan pursuant to START ┃
┃ │ │ ┃
┃ │2) "Pyeongtaek City following the relocation of USFK bases │「Due to the relocation of USFK bases ┃
┃ │Article 2 of the "Special Act on Support, etc."│With support from Pyeongtaek City, etc., etc. ┃
┃ │Development project of an internationalization planning district pursuant to START No. 9 │Article 17 of the "Special Act Concerning START" ┃
┃ │or Pyeongtaek City development pursuant to Article 16 of the same Act│The city of Pyeongtaek City development project according to ┃
┃ │Business │prior to approval or the same law ┃
┃ │ - Site area 100,000㎡ or more │Internationalization system pursuant to Article 23 ┃
┃ │ │Approval of Lot District Development Plan ┃
┃ │ │Previous ┃
┃ │ │ ┃
┃ │3) "Annual │「Follow-up measures for the new administrative capital ┃
┃ │Construction of the Multifunctional Administrative City in the Gi-Gongju Region │Administration for the Yeongi and Gongju regions for the purpose of START ┃
┃ │action pursuant to Article 2, Subparagraph 1 of the "Special Act for the Purpose of..." │For the construction of a central complex city ┃
┃ │Jeong-si-jung-bok-chon-ga-si-gwan │Article 21, Paragraph 1 of the "Special Act" ┃
┃ │ - Site area 100,000㎡ or more │따른 실시계획의 승인 전 ┃
┃ │ │or pursuant to Article 53 of the same Act ┃
┃ │ │The plan for the surrounding area support project ┃
┃ │ │Before establishing a plan ┃
┃ │ │ ┃
┃ │Article 2, Paragraph 3 of the "Special Act on Enterprise City Development"│「Special Act on Enterprise City Development」 ┃
┃ │Enterprise City Development Project under START │Of the implementation plan pursuant to Article 12 ┃
┃ │ - Site area 100,000㎡ or more │Before approval ┃
┃ │ │ ┃
┃ │Article 3, Paragraph 4 of the "Special Act on the Creation of Yongsan Park"│「Yongsan Park Creation Special ┃
┃ │Yongsan Park within the Yongsan Park Redevelopment Zone pursuant to│Implementation pursuant to Article 16 of the "START Act" ┃
┃ │Development projects including garden creation │Before plan approval ┃
┃ │ - Site area 100,000㎡ or more │ ┃
┃ │ │ ┃
┃car. Sports facility's │1) "Act on the Installation and Use of Sports Facilities│「Installation and Use of Sports Facilities ┃
┃Install │rate of sports facilities pursuant to Article 2, Subparagraph 1 │Article 12 of the "Act on START" ┃
┃ │Installation work. However, regarding golf course installation work... │따른 사업계획의 승인 전 ┃
┃ │The above applies only to cases with 27 holes or more. │(State or local government ┃
┃ │ - Site area 150,000㎡ or more │is executed, ┃
┃ │ │「To the Planning and Use of National Land ┃
┃ │ │Article 88, Paragraph 2 of the "Act concerning START" ┃
┃ │ │Authorization of implementation plan pursuant to START ┃
┃ │ │before) ┃
┃ │ │ ┃
┃ │Article 2, Paragraph 1 and No. 2 of the "Cycling and Boat Racing Act" │Article 5 of the "Cycling and Boat Racing Act" ┃
┃ │Installation of bicycle racing or boat racing facilities pursuant to START│Prior to authorization under Section 1 ┃
┃ │Business │ ┃
┃ │ - Site area 150,000㎡ or more │ ┃
┃ │ │ ┃
┃ │Horse racing pursuant to Article 4 of the "Korea Racing Authority Act"│Article 4 of the "Korea Racing Authority Act" ┃
┃ │CHANG │따른 경마장 설치허가 전 ┃
┃ │ - Site area 150,000㎡ or more │ ┃
┃ │ │ ┃
┃K. Private Investment Company │「Private Investment in Social Infrastructure Act」 │「Private matters regarding social infrastructure ┃
┃UP │Private investment project pursuant to Article 2, subparagraph 5 │Pursuant to Article 15 of the "International Investment Act" ┃
┃ │ - Larger than the scale of the relevant business or facility │Before approval of other implementation plans ┃
┗━━━━━━━━━┷━━━━━━━━━━━━━━━━━━┷━━━━━━━━━━━━━━━┛
2. Architecture
A. Single-use building
┏━━━━━━━━┯━━━━━━━━━━━━━━━━┯━━━━━━━━━━┯━━━━━━━┓
┃Use │Types of Buildings by Use │Urban Traffic Improvement Area(㎡)│Traffic area (㎡) ┃
┠────────┼────────────────┼──────────┼───────┨
┃1) Multi-unit housing │Annex 1, Item 2 of the Enforcement Decree of the Building Act │Gross Floor Area │Total Building Area ┃
┃ │Apartment according to item A │60,000㎡ or more │More than 90,000㎡ ┃
┠────────┼────────────────┼──────────┼───────┨
┃2) Class 1 Neighborhood │Annex 1, Item 3 of the Enforcement Decree of the Building Act │Total Building Area │Gross Floor Area ┃
┃Living Facilities │Class 1 Neighborhood Living Facility pursuant to subparagraph (d) │25,000㎡ or more │37,500㎡ or more ┃
┃ │Chinese Clinics and Korean Medicine Clinics │ │ ┃
┃ ├────────────────┼──────────┼───────┨
┃ │Other Class 1 Neighborhood Living Facilities (Evacuation │Total Floor Area │Total Building Area ┃
┃ │Stations and substations are excluded) │12,000㎡ or more │18,000㎡ or more ┃
┠────────┼────────────────┼──────────┼───────┨
┃3) Class 2 Neighborhood │Annex 1, Item 4 of the Enforcement Decree of the Building Act │Total Building Area │Gross Floor Area ┃
┃Living Facilities │에 따른 제2종 근린생활시설 │15,000㎡ or more │22,500㎡ or more ┃
┠────────┼────────────────┼──────────┼───────┨
┃4) Culture and Home │Annex 1, Item 5 of the Enforcement Decree of the Building Act │Gross Floor Area │Total Building Area ┃
┃Meeting Facilities │Culture and according to items A through C │15,000㎡ or more │22,500㎡ or more ┃
┃ │Assembly facilities (excluding wedding halls) │ │ ┃
┃ ├────────────────┼──────────┼───────┨
┃ │Annex 1, Item 5 of the Enforcement Decree of the Building Act │Gross Floor Area │Total Building Area ┃
┃ │Wedding halls among assembly halls pursuant to subparagraph (b) │3,000㎡ or more │4,500㎡ or more ┃
┃ ├────────────────┼──────────┼───────┨
┃ │Annex 1, Item 5 of the Enforcement Decree of the Building Act │Gross Floor Area │Total Building Area ┃
┃ │Exhibition hall according to item │15,000㎡ or more │22,500㎡ or more ┃
┃ ├────────────────┼──────────┼───────┨
┃ │Annex 1, Item 5 of the Enforcement Decree of the Building Act │Site Area │Site Area ┃
┃ │Zoos and botanical gardens according to the order M │20,000㎡ or more │30,000㎡ or more ┃
┠────────┼────────────────┼──────────┼───────┨
┃5) Religious facilities │Annex 1, Item 6 of the Enforcement Decree of the Building Act │Total Building Area │Gross Floor Area ┃
┃ │에 따른 종교시설 │15,000㎡ or more │22,500㎡ or more ┃
┠────────┼────────────────┼──────────┼───────┨
┃6) Sales facilities │Annex 1, Item 7 of the Enforcement Decree of the Building Act │Gross Floor Area │Total Floor Area ┃
┃ │Wholesale market according to item A │13,000㎡ or more │19,500㎡ or more ┃
┃ ├────────────────┼──────────┼───────┨
┃ │Annex 1, Item 7 of the Enforcement Decree of the Building Act │Gross Floor Area │Total Building Area ┃
┃ │Retail market according to item (b) │ 6,000㎡ or more │More than 9,000㎡ ┃
┃ ├────────────────┼──────────┼───────┨
┃ │ Annex 1, Item 7 of the Enforcement Decree of the Building Act │Gross Floor Area │Total Building Area ┃
┃ │Store according to item │11,000㎡ or more │16,500㎡ or more ┃
┠────────┼────────────────┼──────────┼───────┨
┃7) Transportation facilities │Annex 1, Item 8 of the Enforcement Decree of the Building Act │Gross Floor Area │Total Building Area ┃
┃ │Transportation facilities according to items (a) through (d)│11,000㎡ or more │16,500㎡ or more ┃
┠────────┼────────────────┼──────────┼───────┨
┃8) Medical facilities │Annex 1, Item 9 of the Enforcement Decree of the Building Act │Gross Floor Area │Total Building Area ┃
┃ │Hospital according to item │25,000㎡ or more │37,500㎡ or more ┃
┠────────┼────────────────┼──────────┼───────┨
┃9) Educational Research Facility │Annex 1, Item 10 of the Enforcement Decree of the Building Act │Total Building Area │Gross Floor Area ┃
┃ │Among the schools under item (a), colleges and universities│100,000㎡ or more │150,000㎡ or more┃
┃ ├────────────────┼──────────┼───────┨
┃ │Annex 1, Item 10 of the Enforcement Decree of the Building Act │Total Building Area │Total Building Area ┃
┃ │Educational year according to items (b) through (f) │37,000㎡ or more │55,500㎡ or more ┃
┃ │Old facilities (facilities pursuant to subparagraph (d) of the same item │ │ ┃
┃ │) │ │ ┃
┠────────┼────────────────┼──────────┼───────┨
┃10) Exercise facilities │Annex 1, Item 13 of the Enforcement Decree of the Building Act │Gross Floor Area │Gross Floor Area ┃
┃ │Exercise facilities according to START │10,000㎡ or more │15,000㎡ or more ┃
┃ │ │or grandstand │or grandstand ┃
┃ │ │2,000 seats or more │3,000 seats or more ┃
┠────────┼────────────────┼──────────┼───────┨
┃11) Office Facilities │Annex 1, Item 14 of the Enforcement Decree of the Building Act │Gross Floor Area │Total Building Area ┃
┃ │Public office facilities pursuant to item (a) │7,000㎡ or more │10,500㎡ or more ┃
┃ ├────────────────┼──────────┼───────┨
┃ │Annex 1, Item 14 of the Enforcement Decree of the Building Act │Gross Floor Area │Gross Floor Area ┃
┃ │General business facilities pursuant to subparagraph (b) │25,000㎡ or more │37,500㎡ or more ┃
┠────────┼────────────────┼──────────┼───────┨
┃12) Accommodation │Annex 1, Item 15 of the Enforcement Decree of the Building Act │Total Building Area │Total Building Area ┃
┃ │Accommodation facilities pursuant to items A and B │40,000㎡ or more │60,000㎡ or more ┃
┠────────┼────────────────┼──────────┼───────┨
┃13) Recreational facilities │Annex 1, No. 16 of the Enforcement Decree of the Building Act │Total Building Area │Total Building Area ┃
┃ │Recreational facilities according to items A through C│11,000㎡ or more │16,500㎡ or more ┃
┃ ├────────────────┼──────────┼───────┨
┃ │Annex 1, No. 16 of the Enforcement Decree of the Building Act │Total Building Area │Gross Floor Area ┃
┃ │Recreational facilities pursuant to items (e) and (f) │Over 6,000㎡ │More than 9,000㎡ ┃
┠────────┼────────────────┼──────────┼───────┨
┃14) Factory │Annex 1, No. 17 of the Enforcement Decree of the Building Act │ Total Building Area │Total Building Area ┃
┃ │Factory according to START │75,000㎡ or more │112,500㎡ or more┃
┠────────┼────────────────┼──────────┼───────┨
┃15) Warehouse Facilities │Annex 1, No. 18 of the Enforcement Decree of the Building Act │Gross Floor Area │Gross Floor Area ┃
┃ │Warehouse facilities pursuant to items (a), (c), and (d)│55,000㎡ or more │82,500㎡ or more ┃
┃ ├────────────────┼──────────┼───────┨
┃ │Annex 1, No. 18 of the Enforcement Decree of the Building Act │Site Area │Site Area ┃
┃ │Loading and unloading area according to subparagraph (b) │More than 55,000㎡ │82,500㎡ or more ┃
┠────────┼────────────────┼──────────┼───────┨
┃16) Car Management │Annex 1, No. 20 of the Enforcement Decree of the Building Act │Total Building Area │Total Building Area ┃
┃Related facilities(Construction │Automobile pursuant to items (a), (d), and (f) │ 13,000㎡ or more │19,500㎡ or more ┃
┃Installation Machinery Related │Related Facilities │ │ ┃
┃including facilities ├────────────────┼──────────┼───────┨
┃) │Annex 1, No. 20 of the Enforcement Decree of the Building Act │Total Building Area │Gross Floor Area ┃
┃ │Trading ledger according to item M │or site area │or site area ┃
┃ │ │25,000㎡ or more │37,500㎡ or more ┃
┠────────┼────────────────┼──────────┼───────┨
┃17) Broadcasting and Communication │Annex 1, No. 24 of the Enforcement Decree of the Building Act │Gross Floor Area │Total Building Area ┃
┃Facility(Type 1 │Broadcasting communication according to items A through E │43,000㎡ or more │64,500㎡ or more ┃
┃Neighborhood Living City │New facility │ │ ┃
┃corresponding to the │ │ │ ┃
┃is my │ │ │ ┃
┃Except) │ │ │ ┃
┠────────┼────────────────┼──────────┼───────┨
┃18) Cemetery Related │Annex 1, No. 26 of the Enforcement Decree of the Building Act │Site Area │Site Area ┃
┃Facility │에 따른 묘지 관련 시설 │12,000㎡ or more │18,000㎡ or more ┃
┠────────┼────────────────┼──────────┼───────┨
┃19) Sightseeing Rest │Annex 1, No. 27 of the Enforcement Decree of the Building Act │Total Building Area │Total Building Area ┃
┃Facilities │Tourist rest facilities pursuant to subparagraphs A and B│10,000㎡ or more │15,000㎡ or more ┃
┃ ├────────────────┼──────────┼───────┨
┃ │Annex 1, No. 27 of the Enforcement Decree of the Building Act │Total Building Area │Total Floor Area ┃
┃ │T Tourism leave according to items D through F│30,000㎡ or more │45,000㎡ or more ┃
┃ │Public facility │ │ ┃
┠────────┼────────────────┼──────────┼───────┨
┃20) Funeral facilities │Annex 1, No. 28 of the Enforcement Decree of the Building Act │Total Building Area │Total Building Area ┃
┃ │에 따른 장례시설 │Over 6,000㎡ │ More than 9,000㎡ ┃
┗━━━━━━━━┷━━━━━━━━━━━━━━━━┷━━━━━━━━━━┷━━━━━━━┛
B. Buildings for mixed use
A mixed-use building with a total building floor area (Swa) of 10,000 m² or more, calculated according to the following formula
Building (used for two or more of the uses specified in Subparagraph 2(a) in the same building or on the same site
The new construction of a building (hereinafter the same) is subject to traffic impact assessment.
Swa = × 10,000
Here, Pia is the sum of the building floor area or site floor area by use for each building (㎡), and Mia is
Refers to the minimum traffic impact assessment target scale (㎡) of each building.
Remarks
1. Among the scope of the target business, the scale of the business refers to the scale of the business for which authorization, permission, approval, etc. is sought
says.
2. Businesses deemed to have received approval, etc. under other laws and regulations, and the scope of the target business
Projects falling under the above are deemed to require a traffic impact assessment.
3. If a single project falls within the scope of two or more target projects, submit a traffic impact assessment report
shall be the time when approval, etc. is first sought.
4. The timing for submitting the traffic impact assessment report for a building is pursuant to Article 11 of the "Building Act"
prior to permit, provided that in the case of buildings implemented under individual laws, for the construction of such building
Until authorization or permission is granted pursuant to the relevant laws.
5. Special Provisions for Traffic Impact Assessment
a. Expand a project or building that has been completed after conducting a traffic impact assessment as follows
In the case of , the scope is applied to the area obtained by adding the expanded portion to the completed area.
1) In cases where the project area is expanded by more than 30 percent of the previously completed project area (multiple expansions
(In cases where the expansion scale is greater than or equal to the target scale according to Item 1 of the table above, all of these shall be summed) or the expansion scale is greater than or equal to the target scale according to Item 1 of the table above.
,
2) In the case of port construction projects, if the increase exceeds 30 percent of the existing annual cargo handling capacity
(If cargo handling capacity is increased multiple times, all are added together)
3) In the case of railway or urban railway construction projects, constructing additional stations on existing lines or
Double-tracking a line or expanding an existing station by more than 30 percent of its total floor area...
(In the case of multiple extensions, add them all up)
4) In the case of a road construction project, within the construction section of the road (including carriageways and sidewalks; hereinafter the same applies)
The sum of the road areas of interchanges, junctions, and intersections is the interchange/junction of an existing intersection
In cases where the increase exceeds 30 percent of the total road area of the starting point and intersection (multiple
In cases where expansion is performed only on roads with a width of less than 12m, all of these shall be added together). However, if expansion is performed only on roads with a width of less than 12m, all of these shall be added together.
In cases where an intersection is formed by connecting, the road area of the interchange, junction, and intersection section
Do not sum.
5) By expanding an existing completed building, the total building floor area or site area is 30 percent
In cases of increase exceeding (in the case of multiple extensions, all are summed up) and expansion scale
increases beyond the scale subject to traffic impact assessment according to Item 2 of the table above
b. In the case of changing the use of an existing completed building to a different use, the use after the change of use
Whether or not a project is subject to a traffic impact assessment is determined based on the total floor area of buildings by province.
. Industrial land development projects or industrial complex development projects pursuant to Item 1, Subparagraph (a) 1) and Subparagraph (b) of the above table
For factories installed on the site of a project or in Eup and Myeon areas, the Traffic Act
No prospective evaluation is conducted.
. Delete <2020. 9. 8.>
E. As a project under Item 1 of the above table, the layout of facilities subject to traffic impact assessment, building coverage ratio, floor area ratio, and parking regulations
Traffic impact including specific architectural plans such as the location of entrances and exits and acceleration/deceleration lanes
In cases where an evaluation is conducted and a project is implemented or facilities are installed in accordance with necessary improvements, etc.,
No traffic impact assessment will be conducted.
B. At the time of obtaining the business authorization, permit, approval, etc., it falls under the category of a project subject to traffic impact assessment, but
One of the following projects for which a traffic impact assessment was not conducted because it is below the threshold scale for such assessment
If it falls under , a traffic impact assessment must be conducted for the entire project.
1) After the authorization, permit, or approval of a project is granted, the criteria for the scale subject to traffic impact assessment is strengthened
In cases where it has not been converted, and the project scale due to a change in the business plan within the same influence zone traffic impact
reaching the scale subject to evaluation or new permits, etc., the scale of previously permitted business and newly
When the sum of the permitted project scales reaches the scale subject to traffic impact assessment
2) If this table is revised after the authorization, permit, approval, etc. of the project has been granted, the traffic impact assessment
In cases where the criteria for the scale of the award have been strengthened and any of the following apply
a) Projects that are smaller than the scale subject to traffic impact assessment under the relevant amended regulations at the time of the amendment of this table
If the scale of the relevant company within the same area of influence changes the business plan or obtains new permits, etc.
Increased by more than 30 percent compared to the scale at the time the business was authorized, permitted, or approved, etc., traffic
If the scale subject to impact assessment is reached
b) At the time of the revision of this table, the scale subject to traffic impact assessment under the relevant revised regulations
If the scale of a project within the same influence zone is affected by a change in the business plan or new permit, etc.
If the scale of the business increases by more than 30 percent compared to the time when authorization, permission, or approval was obtained, or
Even if it is less than 30 percent, if the increase in project scale is greater than or equal to the scale subject to traffic impact assessment
case
Company. At the time of obtaining the business authorization, permit, approval, etc., it did not qualify as a project subject to traffic impact assessment
In the case where a project for which a traffic impact assessment has not been conducted falls under any of the following:
shall conduct a traffic impact assessment for the entire project.
1) After the authorization, permit, or approval, etc. of the project is granted, if this table is revised, the traffic impact assessment subject
project, the traffic impact assessment in accordance with the relevant amended regulations at the time of the amendment
A project below the target scale, within the same influence zone, due to a change in the business plan or new permit, etc.
The scale is 30 percent lower than the scale at the time the project was authorized, permitted, or approved.
If it increases to the scale subject to traffic impact assessment
2) After the authorization, permit, or approval, etc. of the project is granted, if this table is revised, the subject of traffic impact assessment
As a project that became eligible for the START project, the traffic impact assessment in accordance with the relevant amended regulations at the time of the amendment
For a project corresponding to the target scale, a change in the business plan or new permit, etc. in the same influence zone
With a scale of 30 percent compared to the scale at the time the business was authorized, permitted, or approved, etc.
Even if the increase is more than or less than 30 percent, if the increase in project scale [traffic impact assessment]
If START is greater than or equal to the target size
A. In the case of conducting a traffic impact assessment for the logistics complex development project pursuant to Item 1, Subparagraph A, 6) of the above table
Regarding the warehouse facilities under Item 2, Subparagraph (a) 15) of the above table constructed on the site, traffic
No impact assessment is conducted.
J. The area of student dormitories among the teaching facilities in Appendix 2 of the "Regulations on the Establishment and Operation of Universities" is Item 2 of the above table
Colleges and universities are excluded from the calculation of total floor area pursuant to Item 9).