Annex 2 — 도로법 시행령
287115 · 2026-07-01
Standards for Road Occupancy Permit (Related to Article 54, Paragraph 5)
1. Place of Occupancy
a. The edge of the road slope (or the roadside side if there is no slope) of the occupancy structure installed on the road
, provided that in the case of roads with sidewalks, it shall be installed on the sidewalk facing the roadway. However,
In cases where it is deemed likely to cause significant impediment to the road structure or traffic, separation
It may be installed in intersections, intersections, and other similar areas.
b. No structures shall be installed in parts where roads intersect, connect, or curve. However,
This shall not apply to power lines and utility poles.
. When installing an occupied structure underground, it must comply with the following standards.
1) Occupied objects shall be installed so as not to be mixed with other occupied objects, provided that there is no impediment to construction or safety
shall be installed near another occupied object
2) Install the occupying structure as close to the ground as possible
d. In the case where the occupied object is a utility pole, power line, or public telephone booth, it must comply with the following standards.
1) There will be no place suitable for installation other than roads
2) Utility poles on the same route shall be installed parallel to the road, and in the case of a road without a sidewalk, the
If there is an occupied object on the opposite side, maintain a distance of at least 8 meters from it. However, road
crosses, connects, or bends.
3) Wires installed above ground must be 6 meters (4.5 meters in the case of communication wires) above the road surface
Install at a height above. However, if installed on the upper part of a sidewalk, install at a height of 5 meters from the road surface.
It can be made at a height of 3 meters or more (in the case of communication cables).
4) When installing new wires on existing wires, ensure they are not mixed up
thing
5) In cases where power lines are buried underground (excluding cases where they are buried across a road), the roadway
It shall be buried underground in parts other than the main line and shoulder. However, in unavoidable cases, limited to the main line of the power line
.
6) The upper portion of wires installed underground must be at least 0.8 meters in the case of the underground area of a roadway, and the underground area of a sidewalk
under, keep it at least 0.6 meters above the road surface. However, "Environmentally friendly vehicles
Installing charging facilities for electric vehicles pursuant to Article 2, Subparagraph 3 of the Act on the Promotion of Development and Dissemination of Electric Vehicles
In cases where it is not installed, or where there is no impediment to the execution of road construction or road safety, it shall not apply.
does not.
7) When installing power lines on a bridge, install them on both sides of the beam or under the deck.
E. In the case where the occupied object is a water pipe, sewer pipe, gas pipe, electric pipe, or telecommunications pipe, the following
Must comply with the standards.
1) There will be no place suitable for installation other than roads
2) When burying water pipes, sewer pipes, gas pipes, electric pipes, or telecommunications pipes (crossing the road
(Excluding cases where it is buried by a single step) it shall be buried underground in sidewalks and road slopes.
However, in unavoidable cases, it may be buried underground in the roadway and shoulder areas, limited to the main line.
.
3) In cases where the main line of a water pipe, gas pipe, electric pipe, or telecommunications pipe is buried, the upper part
to the road surface shall be as follows. However, in cases where it is unavoidable due to construction work,
Make it 0.6 meters or more.
a) Water pipe: 1.2 meters or more
b) Gas pipes/electric pipes: 1.0 meter or more
) Telecommunications conduit: 0.8 meters or more
4) When burying the main line of a sewer pipe, the distance between the upper part and the road surface is 3 meters (Construction
In cases where it is unavoidable due to implementation, it shall be at least 1 meter.
5) In the case of installing water pipes, sewer pipes, gas pipes, electric pipes, or telecommunications pipes on a bridge
Install on both sides of the beam or under the top plate.
Communication conduits or work openings (manholes) must be installed on the outer side of the roadway, and on the shoulder or sidewalk
When installing, safety measures such as making the height the same as the shoulder or sidewalk must be taken.
...will not obstruct traffic safety or pedestrian passage
B. If the occupied object is an oil pipeline, it must comply with the following standards.
1) Oil pipelines shall be buried underground. However, in cases where there are topographical conditions or other unavoidable reasons
may be installed above ground (excluding cases inside tunnels).
2) In cases where an oil pipeline is buried underground (excluding cases where it is buried across a road),
In principle, it should be buried in a location where the influence of vehicle load is minimal, but between the oil pipeline and the road boundary
Maintain a safe distance
3) When burying an oil pipeline underground beneath the road surface, the depth shall be as follows:
a) In cases where an oil pipeline is protected by a protective structure in an urban area, the said protective structure
The upper part of is 1.5 meters from the road surface (1.2 meters in cases where it is unavoidable due to construction).
meter, and in cases where the oil pipeline is not protected by a protective structure, oil
Keep the top of the pipe at least 1.8 meters above the road surface.
b) In areas outside of urban areas, the upper part of the oil pipeline (protecting the oil pipeline by protective structures
is performed, it refers to the upper part of the relevant protective structure) 1.5 meters from the road surface (Gong
In unavoidable cases due to the implementation of [business regulations], maintain a distance of at least 1.2 meters.
4) In cases where an oil pipeline is buried underground other than on the road surface, from the top of the pipeline to the ground surface
is 1.2 meters (in cases where the oil pipeline is protected by a protective structure, in urban areas
Maintain a distance of at least 0.9 meters (0.6 meters in non-urban areas)
5) When installing an oil pipeline above ground, the bottom of the pipeline must be 5 meters or less from the road surface
Item to display
6) When installing oil pipelines on bridges, they shall be installed on both sides of the beam or under the deck.
G. When installing an occupied structure beneath the road surface of an elevated road, it must comply with the following standards.
In this case, if there is another road beneath the road surface of the overpass, the occupation of that road is hindered
should not be given.
1) Install in a location that does not impede the structural preservation of the elevated road
2) Utility poles, power lines, public telephone booths, water pipes, sewer pipes, gas pipes, and telecommunication conduits are elevated roads
, there must be an unavoidable reason
3) Oil pipelines shall be buried in the underground portion beneath the road surface of the elevated road. However, topographical conditions, other factors...
In cases where there is a justifiable reason, it may be installed attached to the underside of a beam or deck beneath an overpass.
.
A. Occupied objects are private information signs (where a person other than the road management authority provides information about facilities they manage)
Guide signs installed in a road area after obtaining a road occupancy permit from the road management authority for the purpose of []
refers to (hereinafter the same) in cases where it must comply with the standards prescribed by the Minister of Land, Infrastructure and Transport
.
2. Occupancy Period
The period of occupation of the occupied property under Article 55, subparagraphs 1 through 5, 7, 9, and 10 is 10
The period shall be within one year, and the period of occupation of other occupied objects shall be within three years. Upon expiration of the period of occupation...
The same applies when updating.
3. Structure of Occupied Property
a. The structure of an occupancy structure installed on the ground shall comply with the following standards.
1) Road structure due to collapse, falling, peeling, contamination, fire, load, leakage, etc.
Will not impede safety or traffic
2) The stepping stones on the utility poles shall be installed parallel to the road direction
3) Temporary shops, etc. shall be installed on the minimum scale within a range that does not obstruct road traffic
thing
B. The structure of an occupied structure installed underground shall comply with the following standards.
1) It shall be sturdy and durable, and shall not interfere with other occupied objects
2) When buried in a roadway, it shall not impair the structural safety of the road
. In cases where an occupied object is installed attached to a bridge or overpass, the structure of the bridge or overpass
It must not impair safety.
4. Construction Method
a. Take necessary measures to ensure that the maintenance of the occupied property is not hindered.
b. Allow passage on one side of the road so as not to obstruct road traffic as much as possible, and
If traffic on one or more lanes is blocked, traffic flow measures shall be established. In this case, [the traffic flow]
Matters necessary for the establishment of traffic flow measures regarding expressways and national highways are the Ministry of Land, Infrastructure and Transport
As determined by the Minister, and for other roads, the local government to which the relevant road management authority belongs
It shall be determined by ordinance.
. Install fences or covers at construction sites, and turn on red or yellow lights at night, etc.
Take necessary measures to prevent danger to road traffic.
5. Timing of Construction
a. Consider the timing of other occupation works or road construction works
a. Conduct construction as much as possible during times of lowest traffic volume, such as nighttime hours.
6. Road Restoration
a. Restoration work resulting from excavation work shall be performed on the structure and function of the road as before the excavation work was carried out and
, provided that quality control regarding materials used, compaction degree, etc., is in accordance with the Road Construction Standard Specifications and Road
In accordance with the pavement design and construction guidelines and quality inspection standards pursuant to the Construction Technology Promotion Act, etc.
must.
B. When the Road Management Agency restores asphalt paved roads, it shall improve the road surface to be level and the road
In order to enhance user convenience, the excavation contractor shall cut the surface layer around the excavation surface
.
The scope of restoration pursuant to subparagraph (b) is the entire width of the excavated lane in the transverse direction of the road, and the vertical direction.
, it shall not exceed 0.5 meters from the excavation surface. However, on roads without lane markings
, the entire area shall be considered as a single lane, and if the paved width is 5
In cases where the width is greater than 1 meter or less than 8 meters, the lane is deemed to be located in the center of the paved width.
. The surface of the unpaved road shall be finished with the same material and thickness as the existing road before excavation
.
7. Indication of location of buried objects
a. Signs, etc. for marking road excavation points prior to the commencement of excavation work shall comply with the following standards
Must be installed properly.
1) Excavate the road according to the design documents and mark the road excavation points so that the occupied material can be buried
shall be constructed after installing signs, etc. and receiving confirmation from the road management authority
2) In cases where major underground utilities and general utilities are linear facilities such as gas pipes, the utilities'
Immediately above, and in the case of area-type facilities such as work shafts (manholes), inside and outside the boundary line of the excavation point
What to install
B. When marking the locations of major underground utilities and general utilities after the completion of excavation work, the buried
Markers, etc. must be installed on the ground above the water. In this case, the markers, etc. shall be major underground buried structures and a
The manager of the semi-buried structure shall maintain and manage it.
. Matters necessary for the installation standards of signs, etc. pursuant to subparagraphs (a) and (b) shall be prescribed by the Ordinance of the Ministry of Land, Infrastructure and Transport
determine.
■ Enforcement Decree of the Road Act [Appendix 2] <Amended Jan. 5, 2021>