Annex 8 — 댐건설ㆍ관리 및 주변지역지원 등에 관한 법률 시행령
270087 · 2026-03-26
■ Enforcement Decree of the Act on the Construction and Management of Dams and Support for Surrounding Areas, etc. [Appendix 8] <Amended 2011.11.30>
Allocation Criteria for Dam Surrounding Area Support Project Costs (Related to Article 44, Paragraph 2)
1. 30% of the subsidy is for the townships within the submerged area under the jurisdiction of each Mayor, County Governor, or District Head
Distribute according to the ratio.
2. 30% of the subsidy is for dam surrounding areas under the jurisdiction of each Mayor, County Governor, or District Head
Original project area (only applicable to the areas specified in the main text of Article 41, Paragraph 1, Subparagraph 1 and Subparagraph 2 of the same paragraph)
It is . The same applies to Subparagraph 3 below) shall be distributed according to the population ratio of the Eup, Myeon, and Dong to which it belongs.
, the population of Eup, Myeon, and Dong shall be calculated according to each item.
a. Population of Eup, Myeon, and Dong adjacent to the dam's planned flood level: Total population × 1
B. Planning of dams (excluding auxiliary dams; hereinafter the same applies to Subparagraph C, Subparagraph A and Subparagraph C)
Eup, Myeon, or Dong to which the catchment area within 2 kilometers from the water level line belongs (Eup under subparagraph A)
Population of (excluding Myeon and Dong): Total population × 0.7
. The catchment area within 5 kilometers of the dam's planned flood level is
Population of the affiliated Eup, Myeon, and Dong (excluding Eup, Myeon, and Dong under subparagraphs A and B): Total population
×0.5
d. Population of Eup, Myeon, and Dong not falling under the provisions of subparagraphs a through c: Total population
×0.3. However, the Dongs of Cities and Metropolitan Cities shall be 0.1 and 0.03, respectively.
3. 20 percent of the subsidy is for dam surrounding areas under the jurisdiction of each Mayor, County Governor, or District Head
It is allocated according to the area ratio of the original project area. In this case, by dam surrounding area support project area
The area shall be calculated according to each of the following items.
a. Catchment area within 2 kilometers of the dam's planned flood level: Relevant area × 1
B. Areas within 2 kilometers of the dam's planned flood level line, excluding those in item A:
Relevant area×0.7
. Catchment area within 5 kilometers exceeding 2 kilometers from the dam's planned flood level:
Relevant area×0.5
d. Areas not subject to the provisions of subparagraphs a through c: Relevant area × 0.3
4. 20 percent of the subsidy is provided by the Dam Management Agency or the dam trustee for balanced regional development and...
In accordance with standards determined through consultation with the Support Project Council, taking into consideration conditions such as traffic and the environment
allocates.