■ Enforcement Decree of the Act on Promotion of Industrial Agglomeration and Factory Establishment [Appendix 5] <Amended July 2, 2024>
Method for Calculating Development Profit of Industrial Complex Structure Advancement Project (Related to Article 58-5, Paragraph 1)
The development profit of the Industrial Complex Structure Advancement Project shall be calculated according to the following formula.
┌────────────────────────────────────────┐
│Development Profit = Completion Standard Land Price - (Established Standard Land Price + Normal Land Price Increase + Expenses) │
└────────────────────────────────────────┘
Remarks
1. “Completion Standard Land Price” refers to the amounts in each of the following items.
a. In cases where development profits are settled: prior to the application date for completion approval of the Industrial Complex Structure Advancement Project 6
The appraised value of land subject to the Industrial Complex Structural Advancement Project evaluated within [number] months (「Appraisal
Appraised by two or more appraisal corporations, etc. pursuant to the “Act on Appraisal and Appraisers”
refers to the arithmetic mean of the amounts. (The same applies hereinafter in this table)
b. In cases where development profit is estimated: Within 6 months prior to the application date for approval of the structural advancement project plan
, the Industrial Complex
Appraisal value reflecting the land use as of the application date for completion approval of the structural upgrading project
2. “Established Standard Land Price” refers to the price assessed within 6 months prior to the application date for approval of the structural upgrading project plan
Refers to the appraised value of the land subject to the Industrial Complex Structure Advancement Project.
3. “Normal land price increase” refers to the established standard land price plus the date of application for approval of the structural upgrading project plan
It refers to the amount calculated by multiplying by the land price fluctuation rate up to the appraisal date pursuant to Subparagraph 1(a).
4. “Land price fluctuation rate” refers to the Ministry of Land, Infrastructure and Transport pursuant to Article 19 of the Act on Reporting Real Estate Transactions, etc.
The city or county to which the land subject to the industrial complex structural upgrading project investigated by the Minister belongs, or
It refers to the rate of change in land prices of land use zones in autonomous districts.
5. “Expenditure” refers to the acquisition tax on real estate acquired for the implementation of the Industrial Complex Structure Advancement Project and
refers to appraisal costs.