Annex 1 — 건축사법 시행령
243997 · 2022-08-04
■ Enforcement Decree of the Architects Act [Appendix 1-2] <Amended Feb. 11, 2016>
Minimum Training Days by Practical Training Subject and Training Area (Related to Article 6-5)
┏━━━━━━┯━━━━━━━━━━━━━┯━━━━━━━━━━━━━┯━━━━━━━┓
┃Training Area │Training Subject │Training Item │Minimum training days ┃
┠──────┼─────────────┼─────────────┼───────┨
┃1. Design │A. Planning │1) Program Planning │365 days or more ┃
┃ │ │2) Site and Surroundings Analysis │ ┃
┃ ├─────────────┼─────────────┤ ┃
┃ │B. Planning, Design, and Intermediate Design│1) Review of Relevant Regulations │ ┃
┃ │ │2) Planning & Design │ ┃
┃ │ │3) Construction Cost Estimation │ ┃
┃ │ │4) Structural and Facility Planning │ ┃
┃ │ │5) Intermediate Design │ ┃
┃ ├─────────────┼─────────────┤ ┃
┃ │. Detailed design │1) Detailed Design │ ┃
┃ │ │2) Design Specification and Material Review│ ┃
┃ │ │3) Review and Adjustment of Design Documents │ ┃
┠──────┼─────────────┼─────────────┼───────┨
┃2. Construction Management │A. Management by Construction Phase │1) Supervision Contract and Construction Contract │80 days or more ┃
┃ │ │2) Post-design management │ ┃
┃ │ │3) Construction Supervision │ ┃
┃ ├─────────────┼─────────────┤ ┃
┃ │B. Project Management │Project Management │ ┃
┠──────┼─────────────┼─────────────┼───────┨
┃3. Other │A. Office Management │Office Management │20 days or more ┃
┃ ├─────────────┼─────────────┤ ┃
┃ │B. Related Activities │Function-related Activities │ ┃
┠──────┼─────────────┼─────────────┼───────┨
┃ │Total │ │465 days or more ┃
┗━━━━━━┷━━━━━━━━━━━━━┷━━━━━━━━━━━━━┷━━━━━━━┛