Annex 2 — 건설기계관리법 시행령
284659 · 2026-03-24
■ Enforcement Decree of the Construction Machinery Management Act [Table 2-2] <Newly Inserted Aug. 2, 2022>
Criteria for Imposing Surcharges (Related to Article 17-5, Paragraph 1)
1. General Standard
a. The criteria for imposing increased penalty surcharges based on the number of violations are the same violations over the past two years
This applies in cases where a penalty surcharge has been imposed. In this case, the calculation of the period is based on the violation
Regarding the above, on the date the administrative fine was imposed and the same violation committed again after the disposition...
Based on the date of detection.
b. In cases where an aggravated disposition is imposed pursuant to subparagraph a, the order of application of the aggravated disposition is the violation
The previous disposition order (where there were two or more dispositions imposing administrative fines within the period pursuant to subparagraph (a)
, it refers to the higher order) and shall be the next order.
. In cases where there are two or more violations, and the respective disposition criteria are all business
In the case of suspension, within a range not exceeding the sum of the administrative fines according to each disposition standard
In , it is increased within the range of one-half of the penalty amount corresponding to the heavy disposition standard.
d. In any of the following cases, the imposing authority shall, in accordance with the individual standards of Subparagraph 2
The amount of the penalty surcharge may be reduced within the range of one-half. However, if the penalty surcharge is...
This is not the case for violators who are paying.
1) Where the violation is recognized as being due to minor negligence or error
2) Cases where the offender is recognized to have made efforts to correct or resolve the state of violation of the law
Woo
3) In addition, the need to reduce the administrative fine by considering the degree of the violation, motive, and consequences, etc.
MTQ152e908843f1b13601343Where START is recognized as existing
E. In any of the following cases, the imposing authority shall, in accordance with the individual standards of Subparagraph 2
The amount of the penalty surcharge may be increased within the range of one-half of the amount. However, the total amount of the penalty surcharge
shall not exceed the amount under Article 35-3, Paragraph 1 of the Act.
1) When the nature and degree of the violation are serious and it is recognized that the damage caused to users, etc. is significant
is the case
2) If the period of violation is 6 months or more
3) In addition, the need to increase the administrative fine in consideration of the degree of the violation, motive, and consequences, etc.
MTQ152e908843f1b13601351 Where START is recognized as existing
2. Individual Basis
A. Criteria for Imposition on Manufacturers of Construction Machinery Registration Number Plates
(Unit: 10,000 KRW)
┌───────────────────┬──────┬───────────────┐
│위반행위 │Legal Basis │Amount of Fine │
│ │ ├────┬────┬─────┤
│ │ │1st Violation│2차 위반│3차 이상 │
│ │ │ │ │Violation │
├───────────────────┼──────┼────┼────┼─────┤
│1) By false or other fraudulent means, etc.│Article 8-2 of the Act │300 │- │- │
│Produce a registration number tag or a new │Paragraph 7, Subparagraph 1 │ │ │ │
│If long │ │ │ │ │
├───────────────────┼──────┼────┼────┼─────┤
│2) Production of registration number plates without justifiable cause │Article 8-2 of the Act │100 │300 │- │
│or if engraving of the registration number is refused │Paragraph 7, Subparagraph 2 │ │ │ │
└───────────────────┴──────┴────┴────┴─────┘
B. Criteria for Imposition on Inspection Agencies
(Unit: 10,000 KRW)
┌───────────────────┬──────┬───────────────┐
│위반행위 │Legal Basis │Amount of Fine │
│ │ ├────┬────┬─────┤
│ │ │1st Violation│2차 위반│3차 이상 │
│ │ │ │ │Violation │
├───────────────────┼──────┼────┼────┼─────┤
│1) Compliant with the standards pursuant to Article 14, Paragraph 2 of the Act│Article 14 of the Act │200 │600 │- │
│If it does not become │Paragraph 4 No. 2 │ │ │ │
├───────────────────┼──────┼────┼────┼─────┤
│2) An inspection agent or its affiliated technical personnel │Article 14 of the Act │ │ │ │
│The compliance matters pursuant to Article 14, Paragraph 3 of the Act above │Paragraph 4 No. 3 │ │ │ │
│In case of │ │ │ │ │
│ │ │ │ │ │
│ a) in violation of Article 14, Paragraph 3, Subparagraph 1 of the Act │ │1,200 │2,400 │- │
│In connection with inspection duties, illicit money or valuables │ │ │ │ │
│receiving or committing other fraudulent acts │ │ │ │ │
│case │ │ │ │ │
│ │ │ │ │ │
│ b) in violation of Article 14, Paragraph 3, Subparagraph 2 of the Act │ │1,200 │2,400 │- │
│falsely test without conducting the test │ │ │ │ │
│or assuming that the company has conducted the inspection or the inspection result │ │ │ │ │
│Write the department differently from the actual test results │ │ │ │ │
│case │ │ │ │ │
│ │ │ │ │ │
│ d) In violation of Article 14, Paragraph 3, Subparagraph 3 of the Act │ │200 │400 │600 │
│In accordance with the inspection standards of Article 13, Paragraph 3 of the Act │ │ │ │ │
│When not all inspection items have been checked │ │ │ │ │
│Woo │ │ │ │ │
│ │ │ │ │ │
│ d) In violation of Article 14, Paragraph 3, Subparagraph 4 of the Act │ │200 │400 │600 │
│In accordance with the inspection work regulations of Paragraph 2 of the same Article │ │ │ │ │
│If inspection work was not performed │ │ │ │ │
├───────────────────┼──────┼────┼────┼─────┤
│3) Submission of data pursuant to Article 14, Paragraph 11 of the Act │Article 14 of the Act │600 │1,200 │- │
│If not started or submitted falsely │Paragraph 4 Subparagraph 3-2 │ │ │ │
├───────────────────┼──────┼────┼────┼─────┤
│4) Inspection agency business due to reasons such as poor management│Article 14 of the Act │600 │1,200 │- │
│It is not appropriate to continue START. │Paragraph 4 No. 4 │ │ │ │
│and if recognized │ │ │ │ │
├───────────────────┼──────┼────┼────┼─────┤
│5) Sentenced to a fine or higher penalty for violating the law│Article 14 of the Act │1,200 │2,400 │- │
│received case │Paragraph 4 No. 5 │ │ │ │
└───────────────────┴──────┴────┴────┴─────┘
. Imposition standards for construction machinery business operators
(Unit: 10,000 KRW)
┌───────────────────┬──────┬───────────────┐
│위반행위 │Legal Basis │Amount of Fine │
│ │ ├────┬────┬─────┤
│ │ │1st Violation│2차 위반│3차 이상 │
│ │ │ │ │Violation │
├───────────────────┼──────┼────┼────┼─────┤
│1) Construction machinery not conforming to safety standards│Article 35 of the Act │300 │900 │- │
│By renting installation machinery, the “Industrial Safety and Health Act” │2 Paragraph 1 No. 2 │ │ │ │
│where a serious accident pursuant to Article 2, subparagraph 2 occurred │of2 │ │ │ │
│case │ │ │ │ │
├───────────────────┼──────┼────┼────┼─────┤
│2) In accordance with the registration standards under Article 21, Paragraph 2 of the Act│Article 35 of the Act │100 │300 │- │
│In case of reaching │2 Paragraph 1 No. 3 │ │ │ │
├───────────────────┼──────┼────┼────┼─────┤
│3) Change notification in violation of Article 24, Paragraph 1 of the Act │Article 35 of the Act │300 │900 │- │
│If START is not performed or false reporting is made │2 Paragraph 1 No. 4 │ │ │ │
└───────────────────┴──────┴────┴────┴─────┘