Form 7 — 도심 복합개발 지원에 관한 법률 시행규칙
269053 · 2025-02-07
■ Enforcement Rules of the Act on Support for Urban Complex Development [Attachment Form No. 7]
Report on Construction Completion and Application for Approval of Completion
※ The applicant shall not fill in the shaded fields.
───────────┬────────────┬──────────────────────────────────────────
Receipt Number │Date of Receipt │Processing Period
│ │ 15 days
───────────┴────────────┴──────────────────────────────────────────
──────────┬────────────────────────────────────────────────────────
Approval Number (Year-Month-Day)│
────┬─────┼─────────────┬────┬─────────────────────────────────────
Business │Name │ │Registration number│
Implementer├─────┼─────────────┼────┼─────────────────────────────────────
│Address │ │Representative │
────┼─────┼─────────────┼────┼─────────────────────────────────────
Designer│Name │ │Registration number│
├─────┼─────────────┼────┼─────────────────────────────────────
│Address │ │Representative │
────┼─────┼─────────────┼────┼─────────────────────────────────────
Contractor│Name │ │Registration number│
├─────┼─────────────┼────┼─────────────────────────────────────
│Address │ │Representative │
────┼─────┼─────────────┼────┼─────────────────────────────────────
Construction │Name │ │Registration number│
Supervisor├─────┼─────────────┼────┼─────────────────────────────────────
│Address │ │Representative │
├─────┼─────────────┼────┼─────────────────────────────────────
│Resident Supervisor│ │Qualifications Held│
────┴─────┼─────────────┴────┴─────────────────────────────────────
Project Location │
──────────┼────────────┬─────┬─────────────────────────────────────
Construction Start Date │ Year month day │Construction Completion Date│ Year month day
─────┬────┼────────────┼─────┼─────────────────────────────────────
Buildings │Main Use │ │Main Structure │
Overview ├────┼────────────┼─────┼─────────────────────────────────────
│Number of households │ │Number of floors │Aboveground ( )Floor/Underground ( )Floor
─────┴────┴────────────┴─────┴─────────────────────────────────────
Pursuant to Article 32 (1) of the Act on Support for Urban Complex Development and Article 8 (1) of its Enforcement Rules, I hereby apply for completion approval of the
complex development project as stated above.
Year month day
Applicant (Signature or seal)
Mayor of a Special Self-Governing City · Governor of a Special Self-Governing Province To
Mayor, County Governor, District Head
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
─────┬─────────────────────────────────────────────────┬───────────
Applicant │1. Specifications for the installation of buildings and infrastructure facilities pursuant to Article 5, Paragraph 1, Subparagraph 7 of the "Act on Support for Complex Urban Development" │Fee
Submission Documents│and Installation Specifications of Living Infrastructure │No
│2. Construction Supervisor's Opinion │
│3. Where the costs required for constructing or installing facilities referred to in Article 38 (1) of the Act on Support for Urban Complex Development have been paid under the proviso to that paragraph,│
│documents evidencing such payment │
─────┴─────────────────────────────────────────────────┴───────────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Processing Procedure
───────────────────────────────────────────────────────────────────
┌───┐ ┌───┐ ┌────────────────┐ ┌───────┐ ┌─────┐ ┌───┐ ┌────────┐
│Application│?│Receipt │?│Field Survey │ㆍ│Consultation with relevant agencies │?│Completion Approval │?│Public Notice │?│Notification │
│Write │ │ │ │AND Review │ │ │ │ │ │ │ │ │
└───┘ └───┘ └────────────────┘ └───────┘ └─────┘ └───┘ └────────┘
Applicant Processing Agency: Special Self-Governing City·Special Self-Governing Province·City·County·District Related Agencies Processing Agency: Special Self-Governing City·Special Self-Governing Province·City·County·District
───────────────────────────────────────────────────────────────────