Form 8 — 해양이용영향평가법 시행규칙
268295 · 2025-01-14
■ Enforcement Rules of the Marine Use Impact Assessment Act [Attachment Form No. 8]
Notification of Action Results
(Institution Name: )
1. General Requirements
───────┬───────────────────────────────────────
Business Name │
───────┼───────────────┬────────────┬──────────
Project Area Location│ │Project Implementer │
───────┼───────────────┼────────────┼──────────
Date of Consultation │ │Consultation Document Number │
───────┼───────────────┼────────────┼──────────
Disposal Authority │ │Date of Commencement of Construction │
───────┼───────────────┼────────────┼──────────
(Scheduled) Completion Date│ │Date of Final Survey Verification │
───────┼───────────────┴────────────┴──────────
Construction Progress │ 20 . . . Current %
───────┴───────────────────────────────────────
───────────────────────────────────────────────
2. Details
┌───┬────────┬────────┬──────┬────────┬───────┐
│Classification │Marine Environmental Impact Assessment│Damage to the Marine Environment │Details of Measures Taken (③)│Results of Measures Taken (④) │Specifics(⑤) │
│ │Content(①) │Occurrence Details(②) │ │ │ │
├───┼────────┼────────┼──────┼────────┼───────┤
│ │ │ │ │ │ │
└───┴────────┴────────┴──────┴────────┴───────┘
───────────────────────────────────────────────
3. Overall Findings
───────────────────────────────────────────────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Instructions for Completion
───────────────────────────────────────────────
1. In column ①, write the details of the marine environmental impact survey where marine environmental damage is recognized.
2. Write the details of the damage to the marine environment in box ②.
3. In column ③, specifically describe the details of measures related to damage to the marine environment (request for implementation, request for suspension of construction, filing of a complaint, etc.).
4. In column ④, classify the results of the action as completed (including temporary suspension of construction), in progress, scheduled for implementation, non-implementation (partial or full), on-site re-investigation, etc.
Enter the applicable details.
5. In column ⑤, write any specific details regarding the damage.
───────────────────────────────────────────────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Processing Procedure
───────────────────────────────────────────────
┌───────┐ ┌──────┐ ┌──────────┐ ┌───────┐
│Request for Action │?│Receipt and Action│? │Preparation of Action Result Notification│?│Receipt and Confirmation │
└───────┘ └──────┘ └──────────┘ └───────┘
Regional Maritime Affairs and Fisheries Office Disposal Authority Disposal Authority Regional Maritime Affairs and Fisheries Office
(Business Owner) (Business Owner)
───────────────────────────────────────────────