Form 8 — 해양이용영향평가법 시행규칙

268295 · 2025-01-14

■ Enforcement Rules of the Marine Use Impact Assessment Act [Attachment Form No. 8] Notification of Action Results (Institution Name: ) 1. General Requirements ───────┬─────────────────────────────────────── Business Name │ ───────┼───────────────┬────────────┬────────── Project Area Location│ │Project Implementer │ ───────┼───────────────┼────────────┼────────── Date of Consultation │ │Consultation Document Number │ ───────┼───────────────┼────────────┼────────── Disposal Authority │ │Date of Commencement of Construction │ ───────┼───────────────┼────────────┼────────── (Scheduled) Completion Date│ │Date of Final Survey Verification │ ───────┼───────────────┴────────────┴────────── Construction Progress │ 20 . . . Current % ───────┴─────────────────────────────────────── ─────────────────────────────────────────────── 2. Details ┌───┬────────┬────────┬──────┬────────┬───────┐ │Classification │Marine Environmental Impact Assessment│Damage to the Marine Environment │Details of Measures Taken (③)│Results of Measures Taken (④) │Specifics(⑤) │ │ │Content(①) │Occurrence Details(②) │ │ │ │ ├───┼────────┼────────┼──────┼────────┼───────┤ │ │ │ │ │ │ │ └───┴────────┴────────┴──────┴────────┴───────┘ ─────────────────────────────────────────────── 3. Overall Findings ─────────────────────────────────────────────── ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━ Instructions for Completion ─────────────────────────────────────────────── 1. In column ①, write the details of the marine environmental impact survey where marine environmental damage is recognized. 2. Write the details of the damage to the marine environment in box ②. 3. In column ③, specifically describe the details of measures related to damage to the marine environment (request for implementation, request for suspension of construction, filing of a complaint, etc.). 4. In column ④, classify the results of the action as completed (including temporary suspension of construction), in progress, scheduled for implementation, non-implementation (partial or full), on-site re-investigation, etc. Enter the applicable details. 5. In column ⑤, write any specific details regarding the damage. ─────────────────────────────────────────────── ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━ Processing Procedure ─────────────────────────────────────────────── ┌───────┐ ┌──────┐ ┌──────────┐ ┌───────┐ │Request for Action │?│Receipt and Action│? │Preparation of Action Result Notification│?│Receipt and Confirmation │ └───────┘ └──────┘ └──────────┘ └───────┘ Regional Maritime Affairs and Fisheries Office Disposal Authority Disposal Authority Regional Maritime Affairs and Fisheries Office (Business Owner) (Business Owner) ───────────────────────────────────────────────