Form 6 — 건축물관리법 시행규칙

271531 · 2025-06-02

■ Enforcement Rules of the Building Management Act [Form No. 6-5] <Amended Jan. 3, 2024> Building Demolition [ ] Application for Permission to Change [ [ ] Change Notification [ Do not complete shaded sections; check the relevant box [ ]. (Front) ───────────────┬─────────┬──────┬────────────────────────────────── Change Permit (Notification) Number │Filing Date │Processing Date │Processing Period 7 days (subject to deliberation by the Architectural Committee │ │ │ , 7 days from that day) ───────────────┴─────────┴──────┴────────────────────────────────── ───────┬────────────────────┬────────────────────────────────────── Administrator │Name(Corporate Name) │Date of Birth (Business Registration Number or Corporate Registration Number) ├────────────────────┴────────────────────────────────────── │Address │(Phone Number: ) ├──────┬──────────────────────────────────────────────────── │Email │I consent to the service of documents using an information and communications network pursuant to Article 14 of the Administrative Procedure Act. │Consent to Delivery ├──────────┬───────────────────────────────────────── │ │[ ] Agree │[ ] Disagree │ ├───────┬──┴───────────────────────────────────────── │ │Email Address │@ ───────┼──────┴───────┴────┬─────────────────────────────────────── Application Details │Permit (Notification) Number │Date of Approval (Notification) │ │ ├───────────────────┴─────────────────────────────────────── │Reason for change ├─────────────────────────────────────────────────────────── │Changes ├───────────────────┬─────────────────────────────────────── │Before change │after change ───────┼───────────────────┴─────────────────────────────────────── Decommissioning Plan │ Whether Changed │[ ] Corresponding [ ] Not applicable ───────┼─────────────────────────────────────────────────────────── Building Status │Location ├─────────┬───────────────────────────────────────────────── │Total Floor Area │Number of buildings to be demolished │㎡ │ Main Building (East) │ │ Attached Buildings (East) ───────┴─────┬───┴─────────────────────────────────┬─────────────── Asbestos-containing material │[ ] Ceiling materials (Ascaltex, Amatex, etc.) [ ] Flooring (Asphaltile, etc.) │[ ] Not applicable Retention Status │[ ] Roofing materials (slate, etc.) [ ] Pipe Insulation (Asbestos Cloth) │ │[ ] Ceiling Insulation (Asbestos Cloth) [ ] Other Matters │ ─────────────┼─────────────────────────────────────┴─────────────── Gas Facilities (Including Gas Piping) │[ ] Demolition and safety measures completed [ [ ] Scheduled demolition and safety measures (Scheduled date: ) [ ] Not applicable Safety Measures Status │※ Gas Business Operator Name: (Contact: ) ─────────────┴───────────────────────────────────────────────────── Demolition of the building as stated above pursuant to Article 30-3, Paragraph 1 of the Building Management Act and Article 12-3, Paragraphs 1 and 2 of the Enforcement Rules of the same Act I am submitting the Application for Permission for Change (Notification of Change). Year month day Applicant(Reporter) (Signature or seal) Mayor of a Special Self-Governing City, Governor of a Special Self-Governing Province, or Mayor, County Head, or District Head Your ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━ ─────────┬───────────────────────────────────────┬───────────────── Attached Documents │Prepared pursuant to Article 30, Paragraph 4 of the Building Management Act or reviewed pursuant to Paragraph 5 of the same Article │Fee │Demolition Plan (Attach only if the demolition plan has been changed) │None ─────────┴───────────────────────────────────────┴───────────────── ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━ Basis Regulation of the "Building Management Act" ─────────┬───────────────────────────────────────────────────────── 「Building Management Act」│ The manager applies a demolition method different from the demolition plan among the matters permitted or reported pursuant to Article 30, Paragraph 1 or 2. Article 30-3 Paragraph 1 │To change matters prescribed by Presidential Decree, such as [documents], [obtain] a change permit from the licensing authority in accordance with the Ordinance of the Ministry of Land, Infrastructure and Transport. │or a change notification must be submitted to the licensing authority. In this case, matters concerning the change, etc. of the dismantling plan are under Article 30, Paragraph 3 to Article 7 │and Article 9 shall apply mutatis mutandis. ─────────┴───────────────────────────────────────────────────────── 210mm×297mm[White Paper (80g/㎡)] . (Back) ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━ ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━ Important Notes ──────────┬─────────────────────────────────────────────────────── 「Building Management Act」 │1. Public danger while demolishing a building without obtaining a modification permit, or obtaining a modification permit through false or other fraudulent means Article 51 Paragraph 1 Section 14 │is caused, the offender shall be punished by imprisonment for up to 10 years or a fine not exceeding 100 million won. No. 15, │2. Public danger while demolishing a building after failing to report a change or reporting a change by false or other fraudulent means Article 51-2, subparagraph 3, │is caused, the offender shall be punished by imprisonment for up to 10 years or a fine not exceeding 100 million won. Article 52, Subparagraph 10, │3. If demolition work is carried out without obtaining a modification permit, or by obtaining a modification permit through false or other fraudulent means, 2 years Article 54 Paragraph 2 No. 8 │Punishable by imprisonment for a period not exceeding [amount] or a fine not exceeding 20 million won. No. 9 and No. 54 │4. If a change report is not filed, or if a change report is filed using false or other fraudulent methods and dismantling work is carried out, 1 year Article 3 Paragraph 3 │Punishable by imprisonment for a period not exceeding [amount] or a fine not exceeding 10 million won. │5. If a change report is not filed, or if a change report is filed using false or other fraudulent methods, an administrative fine not exceeding 5 million won shall apply. │Impose. │6. If a demolition plan not prepared (reviewed) by an expert (architect or professional engineer) is submitted to the permitting authority, a fine of 10 million won or less │. │7. In the case of demolishing a building containing asbestos, the asbestos must first be removed in accordance with relevant laws and regulations, such as the Industrial Safety and Health Act. │The building must be demolished after processing. │8. Any person intending to perform excavation work during the demolition of a building shall, before commencing excavation work, [refer to] Article 23-3, Paragraph 1 of the “High-Pressure Gas Safety Management Act” │Clause, pursuant to Article 30-3, Paragraph 1 of the City Gas Business Act and Article 49-3, Paragraph 1 of the Safety Management and Business Act for Liquefied Petroleum Gas │Whether gas pipelines are buried underground at the site of the relevant building, excavation work information support pursuant to Article 30-2 of the Urban Gas Business Act │center. │9. Any person intending to demolish a building on which city gas pipelines or city gas usage facilities are installed shall, pursuant to Article 28-3, Paragraph 2 of the “City Gas Business Act” │the safety measures prescribed in Article 28-3 (2) of the Urban Gas Business Act must be taken. ──────────┴─────────────────────────────────────────────────────── ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━ Processing Procedure ──────────┬─────────────────────────────────────────────────────── In the case of a change permit │┌──────┐ ┌───┐ ┌───┐ ┌────────┐ ┌──────┐ ┌─────┐ (originally the dismantling permit ││Amendment of Permit │?│Receipt │?│Review │?│Architectural review or │?│Change Permit │?│Change Permit│ and originally ││Fill out application form │ │ │ │ │ │Expert Review etc. │ │Written │ │Issue │ A dissolution report was filed │└──────┘ └───┘ └───┘ └────────┘ └──────┘ └─────┘ or reduction due to change │ and demolition work is permitted │ is the target │Applicant Special Self-Governing City/Special Self-Governing Province, City/County/Autonomous District Building Demolition Permit (Notification) Department case) │(Administrator) ※ In cases falling under Article 30, Paragraph 8 of the "Building Management Act," conduct a review of the demolition plan by the National Institute of Construction Safety and Management ──────────┼─────────────────────────────────────────────────────── In the case of a change notification │┌─────┐ ┌───┐ ┌───┐ ┌────────┐ ┌─────┐ ┌─────┐ (originally the dissolution report ││Change Notification Form│?│Reception │?│Review │?│(if necessary) │?│Report change │?│Change Notification │ and the original││Create │ │ │ │ │ │Architectural review or │ │Confirmation │ │Confirmation │ received approval but ││ │ │ │ │ │ │Expert Review etc. │ │Written │ │Issue │ , │└─────┘ └───┘ └───┘ └────────┘ └─────┘ └─────┘ Demolition work reporting │ (If it becomes │ │Applicant Special Self-Governing City/Special Self-Governing Province, City/County/Autonomous District Building Demolition Permit (Notification) Department │(Administrator) ※ In cases falling under Article 30, Paragraph 8 of the "Building Management Act," conduct a review of the demolition plan by the National Institute of Construction Safety and Management ──────────┴─────────────────────────────────────────────────────── 210mm×297mm[White Paper (80g/㎡)]