Form 16 — 위험물안전관리법 시행규칙
287841 · 2026-07-01
■ Enforcement Rules of the Dangerous Goods Safety Management Act [Attachment Form No. 16] <Amended July 1, 2026>
Hazardous Materials [ ]Manufactory Application for Amendment Permit
[ ]Repository
[ ]Handling Station
※ Please read the instructions on the back before filling out, and [ ] with a check mark (√). (front)
───────────────┬────────────┬────────────────────────
Receipt Number │Date of Receipt │Processing Period Refer to No. 8 for instructions on how to fill out the back
───────────────┼────────────┼────────────────────────
Permission Number │PermissionDate │
───────────────┴────────────┴────────────────────────
──────────────┬─────────────────────┬────────────────
Installer │Name │Date of Birth
├─────────────────────┴────────────────
│Address
│ (Phone Number : )
──────────────┼──────────────────────────────────────
Installation Location │
──────────────┼────────────┬─────────────────────────
By region of installation location │Fire Prevention Zone Status │Zonings etc.
──────────────┼────────────┴─────────────────────────
Installation Permit Date and │
Permission Number │
──────────────┼────────────┬─────────────────────────
Classification of manufacturing facilities, etc. │ │Classification of storage or handling facilities
──────────────┼────────────┼─────────────────────────
Classification and Name of Hazardous Materials │ │Multiplier of specified quantity
(Specified Quantity) and Max Quantity │ │ship
──────────────┼────────────┴─────────────────────────
of location, structure and facilities │
Based │
──────────────┼──────────────────────────────────────
Details of changes │
──────────────┼──────────────────────────────────────
Reason for change │
──────────────┼────────────┬────────┬────────────────
Scheduled Start Date │ Year month day│ScheduledCompletionYearMonthDate │ Year month day
──────────────┼────────────┴────────┴────────────────
Other necessary matters │
──────────────┴──────────────────────────────────────
I hereby apply for a permit to change a manufacturing facility, etc. pursuant to Article 6, Paragraph 1 of the "Dangerous Goods Safety Management Act."
Year month day
Applicant Address
(PhoneNumber )
Name (Signature or seal)
Mayor of Special City · Integrated Special City Mayor · Metropolitan City Mayor · Special Self-Governing City Mayor · Provincial Governor · Special Self-Governing Provincial Governor Your
Fire Station Chief
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
──────────────┬──────────────┬───────────────────────
Attached Documents │ See back │Fee
│ │「Enforcement Rules of the Dangerous Goods Safety Management Act」
│ │ Amount pursuant to Subparagraph 2(b) of Attached Table 25
──────────────┴──────────────┴───────────────────────
──────────────┬──────────────┬───────────────────────
Part applying for approval of use│ As per attached drawing │Fee
│ │None
──────────────┴──────────────┴───────────────────────
210mm×297mm[White paper (80g/㎡) or medium paper (80g/㎡)]
(rear)
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Attached Documents
─────────────────────────────────
1. Certificate of Consent to Completion Inspection of Manufacturing Plant, etc.
2. Drawings relating to the location, structure, and facilities of a manufacturing plant, etc., specifying the details of each of the following items
a. Layout of major buildings and structures within the business premises including the relevant manufacturing plant, etc.
b. If there is a part within the building where the relevant manufacturing facility, etc. is installed that is not used for the purpose of the manufacturing facility, etc., the layout and structure of such part
. The layout of buildings, structures, machinery, equipment, and other facilities constituting the relevant manufacturing plant, etc. (in the case of a manufacturing plant or general handling plant, an outline of the process
)
d. Structure of buildings, structures, machinery, equipment, and other facilities storing or handling hazardous materials at the relevant manufacturing facility, etc. (in the case of a refueling station
Items related to changes (including the structure of buildings and structures pursuant to each item of Subparagraph V, Item 1 of Annex 13 of the Enforcement Rule of the Dangerous Goods Safety Management Act
E. Items related to changes in the overview of electrical facilities, lightning protection facilities, fire extinguishing facilities, alarm facilities, and evacuation facilities installed in the relevant manufacturing facility, etc.
b. In the case of manufacturing facilities, etc., that install equipment related to emergency measures such as pressure safety devices, leak detection devices, and emergency shut-off valves, changes in the overview of said equipment
related to something
3. Items related to changes among the structural and equipment specifications (Forms No. 3 through No. 14) of the Enforcement Rules of the Dangerous Goods Safety Management Act concerning the relevant manufacturing facility, etc.
4. In the case of manufacturing facilities, etc., where fire extinguishing equipment (excluding fire extinguishing devices) is installed, items related to changes among the design documents of the relevant equipment
5. In the case of manufacturing facilities, etc., where fire detection equipment is installed, items related to changes among the design documents of the said equipment
6. In the case of an outdoor tank storage facility with a capacity of 500,000 liters or more, the foundation, ground, and tank body of the tank of the said outdoor tank storage facility (hereinafter referred to as "outdoor storage tank")
Design documents, construction plans, construction schedules, geological survey data, and other necessary materials regarding foundations and ground, as well as specifications regarding welded parts, etc., regarding the tank
Related to changes in fees
7. In the case of a rock cavern tank storage facility, design documents, construction plans, construction schedules, and other facilities of the rock cavern tank said thereis
Related to changes in quality and hydraulic survey reports
8. An outdoor storage tank is an underground tank (where the bottom is below the ground level and the top is above the ground level, and the highest liquid level of hazardous materials within the tank is below the ground level
In the case of a cylindrical vertical type hazardous material tank, the design documents, construction plan, construction schedule, and geological [documents] of the ground and tank body of the relevant underground tank [documents]
Data related to changes among ground data such as survey data
9. An outdoor storage tank refers to a marine tank [a hazardous material tank that is stationary at the same location at sea and connected to facilities and piping installed on land.
], the design drawings of the tank body, stationary facilities (referring to facilities for stationing the offshore tank in the same location), and other facilities of the offshore tank in question
, Construction Plan, and Construction Schedule related to changes
10. Technical review report issued by the Korea Fire Industry Technology Institute pursuant to Article 14 of the Act on the Promotion of the Fire Industry (Article 6, Paragraph 3 of the Enforcement Decree of the Dangerous Goods Safety Management Act
) Among those related to changes
11. Documents specifying measures for fire prevention pursuant to the proviso of Article 9, Paragraph 1 of the "Dangerous Goods Safety Management Act" (parts unrelated to the modification work prior to the completion inspection
(only if the portion unrelated to the alteration work is to be used before the completion inspection)
─────────────────────────────────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
How to fill out etc.
─────────────────────────────────
1. This application is used for applications for permission to change manufacturing facilities, etc., other than transfer handling facilities.
2. The section for applying for temporary use approval should be filled out only if you intend to use parts unrelated to the alteration work before the final inspection (Temporary Use Approval
If you intend to establish a separate agency, use Form No. 27 of the Enforcement Rules of the Dangerous Goods Safety Management Act).
3. In the Land Use Zone, etc. section, enter the land use zones, land use districts, and land use areas as defined in the "Act on Planning and Utilization of National Land."
4. For a corporation, enter the name of the corporation and the name of the representative in the name field, the corporate registration number in the date of birth field, and the location of the principal office in the address field.
Start, and for foreigners, enter your Alien Registration Number or Passport Number in the Date of Birth field.
5. When specifying the product name (designated quantity), if the designated quantity of the relevant hazardous material is not clear from the product name alone ( ) enter the applicable designated quantity inside the parentheses
is small.
6. In the classification column regarding standards for location, structure, and facilities, write the relevant provision in the attached table of the applicable “Enforcement Rules of the Dangerous Goods Safety Management Act.”
7. Shaded parts are not written.
8. The processing period is as follows:
a. In the case of attaching a technical review report issued by the Korea Institute of Fire Industry & Technology pursuant to Article 14 of the Act on the Promotion of the Fire Industry: 3 days
B. In cases other than Item A: 4 days
─────────────────────────────────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
ProcessingProcedure
─────────────────────────────────
───────────────────┬─────────────
Applicant │ProcessingAgency
├─────────────
│City/Province or Fire Department (Hazardous Materials Department)
───────────────────┼─────────────
│
┌──────────────┐ │ ┌─────┐
│Application │ │ ▶ │Receipt │
│ ├──┼─ │ │
│ │ │ │ │
└──────────────┘ │ └───┬─┘
│ │
│
│ ▼
│ ┌─────┐
│ │Review │
│ │(Field survey if necessary)│
│ │ │
│ └───┬─┘
│ │
│
│ ▼
┌──────────────┐ │ ┌─────┐
│Notice of Permission Denial or Request for Supplementation │◀ │(If non-conforming)│Drafting · Approval│
│ │ ─┼─────┤ │
│ │ │ │ │
└──────────────┘ │ └───┬─┘
│ │
│
│ ▼
┌──────────────┐ │ ┌─────┐
│Notification of Change Permission │◀ │ │Captain 정리 │
│ │ ─┼─────┤ │
│ │ │ │ │
└──────────────┘ │ └─────┘
│
───────────────────┴─────────────