Form 3 — 항만공사법 시행규칙
282713 · 2026-01-02
■ Enforcement Rules of the Port Authority Act [Attachment Form No. 3] <Amended June 21, 2017>
┏━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━┓
┃ ┃
┃First 호 ┃
┃ ┃
┃Certificate of Confirmation of Completion ┃
┃ ┃
┃ ┃
┃Institution Name: ┃
┃ ┃
┃Representative Name: ┃
┃ ┃
┃Address: (Phone Number: ) ┃
┃ ┃
┃ For the port facility construction undertaken by you, completion is hereby confirmed under Article 24(2) of the Port Authority Act ┃
┃and Article 6(2) of its Enforcement Rules, and the following certificate ┃
┃is issued. ┃
┃ ┃
┃ 1. Port Name (Location): ┃
┃ ┃
┃ 2. Type of work: ┃
┃ ┃
┃ 3. Construction Site: ┃
┃ ┃
┃ 4. Purpose of Construction: ┃
┃ ┃
┃ 5. Construction Period (Completion Date): ┃
┃ ┃
┃ 6. Completed Facilities (Whether Vested in the State): ┃
┃ ┃
┃Year month day ┃
┃ ┃
┃ ┏━━┓ ┃
┃ Director of Regional Maritime Affairs and Fisheries┃Official Seal┃ ┃
┃ ┗━━┛ ┃
┃ ┃
┗━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━┛
210㎜×297㎜[White Paper (150g/㎡)]