Form 7 — 산지관리법 시행규칙
287565 · 2026-06-24
■ Enforcement Rules of the Mountain Area Management Act [Form No. 7-5] <Amended June 24, 2026>
Temporary Reasonse of Mountain Area [Permit/Notification] [ ]Request for Consultation [ ]Request for Change Consultation [
(Front)
──────────┬────┬────┬─────────────────────────────────
Receipt Number │Reception Date│Processing Date│Processing Period 30days
──────────┴────┴────┴─────────────────────────────────
──────────┬───────────────────────────────────────────
Consultation Classification │ [ ] Temporary Reasonse Permit for Mountain Land [ [ ] Declaration of Temporary Reasonse of Mountain Land [
──────────┼───────────────────────────────────────────
Consultation Request Head of Agency │
──────────┼───────────────────────────────────────────
Purpose of temporary use in mountain area │
──────────┼───────────────────────────────────────────
Legal Basis │
──────────┴───────────────────────────────────────────
─────┬────┬───────────────────────────────────────────
TTemporary Reasonse│Location │Address and others Plot
Mountain Area Details├────┼─┬───────────┬─────────────────────────────
│Category │Total│Protected Mountain Area(㎡) │Quasi-conservation mountainous land (square meters)
│ │ ├─────┬─────┤
│ │ │Forestry Land│Public Interest Forest Land│
├────┼─┼─────┼─────┼─────────────────────────────
│Total │ │ │ │
├────┼─┼─────┼─────┼─────────────────────────────
│National Land │ │ │ │
├────┼─┼─────┼─────┼─────────────────────────────
│Commons │ │ │ │
├────┼─┼─────┼─────┼─────────────────────────────
│Private land │ │ │ │
─────┴─┬──┴─┴─────┴─────┴─────────────────────────────
Replacement Forest │ [ ] Payment before administrative disposition (Article 19(1) of the Mountain Area Management Act)
Resource formation cost │ [ ] Payment following administrative disposition, conditional on payment by the due date (Article 19(2)1 of the Mountain Area Management Act)
Payment │ ※ Mark with ∨ in the corresponding box
───────┴──────────────────────────────────────────────
─────┬─────┬───────┬──────────────────────────────────
Changes│Before change │after change │Company Reason
├─────┼───────┼──────────────────────────────────
│ │ │
├─────┼───────┼──────────────────────────────────
│ │ │
─────┴─────┴───────┴──────────────────────────────────
Pursuant to Article 15-2, Paragraph 8 of the Mountain Area Management Act and Article 15-5 of the Enforcement Rules of the same Act, the forest land as above
Temporary Use [Permit/Notification] [ ]Consultation [ ]Requesting consultation on changes.
Year month Iljang
Requestor (Signature or seal)
Minister of the Korea Forest Service, City/Provincial Governors, Mayors/County Heads/District Heads,
Director of a Regional Forest Service, Director of a State Forest Management Office under a Regional Forest Service, Director of the National Arboretum, To
Director of the National Forest Seed Management Center, President of the National Institute of Forest Science, Director of the National Natural Recreation Forest Management Office
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
* Attachments, fees, notes: Refer to back
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
210mm×297mm[White paper (80g/㎡) or medium paper (80g/㎡) ]
(Back)
─────┬──────────────────────────────────────────────────────
Attached Documents│1. Consultation regarding temporary use permit for mountainous areas
│ a. Project Plan (Purpose of temporary use of mountain land, project period, land use plan for the mountain land to be temporarily used, timber disposal plan, soil and rock disposal
│(Must include plans and damage prevention plans, etc.) 1 copy
│ b. One copy of the report on the results of the feasibility study for forest land conversion pursuant to Article 18-2 of the Mountain Area Management Act. In this case, the said report is subject to the permit
│Refers to the report on the results of a feasibility study for forest land conversion completed within 5 years prior to the application date.
│ c. Documents proving ownership or the right to use and benefit from the mountain land intended for temporary use (where such rights cannot be verified
│Limited to cases where it is not possible, the scope and period of the right to use and profit must be specified in the documents proving the right to use and profit.
│must be specified) 1 copy
│ d. A topographic map with a cadastral scale of 1:25,000 or larger indicating a planned site for temporary mountain use (「Framework Act on Land Reasonse Regulation」
│Pursuant to Article 12, if a database of topographic maps displaying cadastral information has not been established in the National Land Reasonse Information System, or
│and cadastral records, 1 copy of the cadastral map)
│ e. A person who has registered for a surveying business pursuant to Article 44, Paragraph 3 of the "Act on the Establishment and Management of Spatial Information, etc." or a "National Public
│Scales from 1:6,000 to 1:1,200 surveyed by the Korea Land and Geospatial Informatics Corporation, established pursuant to Article 12 of the Framework Act on Geospatial Informatics
│Actual Survey Map of Planned Temporary Mountain Reasonse Site
│ f. As a forestry technician affiliated with a forestry technology service provider or a forestry project implementing business operator, under the "Act on the Promotion and Management of Forestry Technology"
│A forest survey report surveyed and prepared by a person meeting the placement standards for forest survey projects in Annex 5 of the Enforcement Decree (type of forest, forest
│Includes the type of tree, forest age, average tree height, and timber volume, and surveyed and prepared within 2 years prior to the permit application date
│(limited to cases where trees are present) 1 copy
│ g. One copy of the restoration plan including the longitudinal and transverse sections of the mountain area to be restored, as well as the types, methods, and cross-sections of the restoration work (the items to be restored
│Limited to cases where mountainous land exists, and in the case of intending to submit a restoration design plan pursuant to the first part of Article 40, Paragraph 2 of the Mountain Area Management Act
│in lieu of a restoration plan, the restoration design in the application for approval of the restoration design in Annex 40 of the Enforcement Rules of the Mountain Area Management Act
│may be submitted by attaching the restoration design plan).
│ h. An elevation survey report investigated and prepared by a person falling under any of the following (submit only in the case of a solar energy generation facility
│) and average slope survey report (in cases where elevation and average slope were calculated using a digital topographic map, the original saved
│(including storage devices such as disks) 1 copy. However, in accordance with Article 4, Paragraph 2, Subparagraph 5 of the Enforcement Rule of the Mountain Area Management Act, the average slope
│Cases where a survey report has been submitted and the area of forest land intended for temporary use (in cases where the same person has applied for multiple temporary forest land use permits)
│refers to the area calculated by summing the areas of the mountain land for which a permit has been applied, within the scope where the identity of the purpose project is recognized.
│If the area is less than 660 square meters, an average slope survey report is not required.
│ Forest engineering technologist pursuant to Annex 3 of the Enforcement Decree of the Act on the Promotion and Management of Forest Technology
│ 2) A person who has obtained a qualification of Forestry Engineer, Civil Engineer, Surveying and Geospatial Information Engineer or higher pursuant to the National Technical Qualifications Act
│ 3) After acquiring the qualifications of Industrial Engineer in Forestry, Industrial Engineer in Civil Engineering, or Industrial Engineer in Surveying and Geospatial Information pursuant to the National Technical Qualifications Act
│Person with more than 10 years of experience in the relevant field
│ i. Documents corresponding to subparagraph 2) or 3) of Article 10, Paragraph 2, Item 1, Item J of the Enforcement Rules of the Mountain Area Management Act (Article 10, Paragraph 2, Subparagraph 1 of the Enforcement Rules of the Mountain Area Management Act
│(Applicable only in cases where proof of being an agricultural worker under Article 7, Subparagraph 1 is required) 1 copy
│ j. A forestry technician affiliated with a forestry technology service provider who meets the staffing standards for disaster risk
│review projects under Attached Table 5 of the Enforcement Decree of the Act on the Promotion and Management of Forestry Technology and who has surveyed and prepared an opinion pursuant to attached Form No. 4-2 of the Enforcement Rules of the Mountain Area Management Act
│1 copy of the disaster risk review opinion (where the area of mountain land for which temporary use permission is sought is at least 660 square meters but less than 5,000 square
│meters, or where the area of mountain land for which temporary use permission is sought is at least 5,000 square meters and the Natural
│Limited to cases not subject to disaster impact assessment consultation pursuant to Note 1 of Item 2 of Annex 1 of the Enforcement Decree of the Disaster Countermeasures Act
│, provided that if a person applying for a temporary forest land use permit applies for two or more such permits, the temporary forest land use permit
│(It is calculated by summing the areas of adjacent mountainous lands among the applied mountainous lands). However, in any of the following cases:
│a disaster risk review opinion need not be submitted.
│ 1) In the case where documents required for disaster impact assessment consultation under the "Natural Disaster Countermeasures Act" have been submitted
│ 2) Installation of solar energy generation facilities pursuant to Article 2, Subparagraph 2, Item (a) of the "Act on Promotion of Development, Reasontilization, and Dissemination of New and Renewable Energy"
│In the case of seeking a temporary use permit for mountain land to do so, regarding the installation of mountain solar power generation facilities pursuant to Form No. 4-3
│If a disaster risk review opinion has been submitted
│ k. One copy of the documents required for consultation on disaster impact assessment pursuant to the "Natural Disaster Countermeasures Act" (for the mountain land for which a temporary mountain land use permit is to be obtained
│Limited to cases where the area is 5,000 square meters or more, provided that the applicant for a temporary forest land use permit [applies to] two or more temporary forest land use permits
│where two or more temporary mountain area use permits are applied for, the area is calculated by adding together the areas of adjoining mountain land covered by those applications).
│However, cases not subject to disaster impact assessment consultation under the "Natural Disaster Countermeasures Act" are excluded.
│ l. One copy of the Disaster Risk Review Opinion Statement regarding the installation of mountain solar power generation facilities pursuant to Form No. 4-3 (「New Energy and Re
│To install solar energy generation facilities pursuant to Article 2, Subparagraph 2, Item (a) of the Act on the Promotion of Development, Reasontilization, and Dissemination of Renewable Energy, the site
│(Limited to cases where a usage license is sought)
│ m. Mountain land intended for temporary use (where the area is at least 300,000 square meters or where wind power generation facilities are to be installed
│One copy of landscape damage mitigation measures prepared by conducting a simulation of the impact on mountain landscapes regarding (limited to cases involving installation).
│However, if deliberation has been conducted pursuant to Article 28, Paragraph 2 of the Natural Environment Conservation Act, it shall not be submitted.
│ n. One copy of a pine wilt disease control plan under Article 13-2 of the Special Act on the Control of Pine Wilt Disease (where the relevant mountain land is within a restricted removal zone under Article 9 of the same Act
│Limited to cases where temporary use is intended for mountainous land including a district zone)
├──────────────────────────────────────────────────────
│2. Consultation regarding notification of temporary use of mountain land
│ a. Project Plan (Purpose of temporary use of mountain land, project period, land use plan for the mountain land to be temporarily used, timber disposal plan, soil and rock disposal
│(Must include plans and damage prevention plans, etc.) 1 copy
│ b. One copy of documents proving ownership or the right to use and profit from the forest land intended for temporary use (confirmed by a Certificate of Registered Matters of Land
│Limited to cases where it is not possible, and the scope and period of the right to use and profit shall be included in the documents proving the right to use and profit
│must be specified)
│ c. A topographic map at a scale of 1:25,000 or larger, showing cadastral details and the planned temporary use site (under the Framework Act on Land Use Regulation
│Pursuant to Article 12, if a database of topographic maps displaying cadastral information has not been established in the National Land Reasonse Information System or
│and cadastral records, 1 copy of the cadastral map)
│ d. A person registered as a surveying business operator under Article 44(3) of the Act on the Establishment and Management of Spatial Data, or the Korea
│Scales from 1:6,000 to 1:1,200 surveyed by the Korea Land and Geospatial Informatics Corporation, established pursuant to Article 12 of the Framework Act on Geospatial Informatics
│. However, pursuant to Article 15-3, Paragraph 3 of the Enforcement Rules of the Mountain Area Management Act, the temporary mountain use example
│You may submit forest road design documents, etc., instead of the actual survey map of the site)
│ e. Longitudinal and transverse sections of the mountainous area subject to restoration (in the case of access roads to wind power facilities, the slope of the original ground at 20-meter intervals
│Refers to the cross-section of the indicated access road) and one copy of the restoration plan including the restoration work type, method, and observation drawing (must be restored
│Limited to cases where there is mountain land to be managed, and in cases corresponding to Subparagraphs (b) and (c) of Item 4 of Annex 3-3 of the Enforcement Decree of the Mountain Area Management Act
│. However, pursuant to the first part of Article 40, Paragraph 2 of the Mountain Area Management Act,
│In cases where a restoration design document is to be submitted, Form No. 40 of the Annex to the Enforcement Rules of the Mountain Area Management Act shall be used in lieu of the restoration plan.
│You may submit the recovery plan attached to the application for approval of the recovery plan)
│ f. One copy of the document corresponding to subparagraph (j) of Article 10, Paragraph 2, Item 1 of the Enforcement Rules of the Mountain Area Management Act (Enforcement Rules of the Mountain Area Management Act
│(Applicable only to cases where proof of being an agricultural worker pursuant to Article 7, Subparagraph 1 of the [Rules])
│ g. One copy of a pine wilt disease control plan under Article 13-2 of the Special Act on the Control of Pine Wilt Disease (for mountain land within a restricted removal zone under Article 9 of the same Act
│Limited to cases where temporary use is intended for mountainous land including a district zone)
│ h. Other documents relevant to examining conditions and standards for each activity subject to notification of temporary use of a mountain area (including the activity-specific conditions
│and applies only if additional review of standards, etc. is necessary)
├──────────────────────────────────────────────────────
│3. Consultation on Change of Temporary Reasonse of Mountain Land: Documents related to the change consultation
─────┼──────────────────────────────────────────────────────
Fee │1. Consultation regarding temporary use permit for mountainous areas
│ a. If the permit application area is 10,000 square meters or less: 20,000 won
│ b. If the area for which permission is applied exceeds 10,000 square meters: 20,000 won plus 2,000 won for every 1,000 square meters exceeding that area
│2. Consultation regarding notification of temporary use of mountain land
│ a. If the forest land area to be reported is 10,000 square meters or less: 5,000 won
│ b. If the area of mountain land to be reported exceeds 10,000 square meters: 5,000 won plus 1,000 won for every 2,000 square meters exceeding that area
│Calculated Amount
│3. Consultation on Change of Temporary Use of Mountain Area: No fee
─────┴──────────────────────────────────────────────────────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Important Notes
────────────────────────────────────────────────────────────
In cases where land, etc. is expropriated or used pursuant to Article 19 of the Act on the Acquisition and Compensation of Land, etc. for Public Projects, mountain land
Documents proving ownership or the right to use and profit will not be submitted.
────────────────────────────────────────────────────────────