Form 5 — 학교시설사업 촉진법 시행규칙
210529 · 2019-09-17
■ Enforcement Rules of the Act on the Promotion of School Facilities Projects [Attachment Form No. 5] <Amended Sep. 17, 2019>
Notification of Construction, etc. and Confirmation of Notification
※ Please refer to the instructions and guidelines on page 2. Do not fill in the □.. (Page 1 of 2)
──────┬──────────────────────────────────────────
BuildingClassification │ [ ] New Construction [ ] Extension [ ] Reconstruction [ ] Reconstruction [ ] Major repair [ ] Other
──────┴──────────────────────────────────────────
──────┬───────────┬──────────────────────────────
BuildingOwner │Name (Signature or seal)│Date of Birth
├───────────┴──────────────────────────────
│Address (Phone Number )
├──────────────────────────────────────────
│①Land Rights Relationship
──────┴──────────────────────────────────────────
Location
─────────────┬───────────────────────────────────
Site Zone □□□ │Site District □□□
─────────────┴───────────────────────────────────
Site Area ㎡
─────────────┬───────────────────────────────────
②Main Use □□□ │③Ancillary Use
─────────────┼───────────────────────────────────
④Building Area ㎡ │⑤Gross Floor Area ㎡
─────────────┼───────────────────────────────────
⑥Building Coverage Ratio % │Construction Area Ground( )Floor, Basement( )floor
─────────────┼───────────────────────────────────
⑦Floor Area Ratio % │Number of Floors (Above Ground, Underground)
─────────────┼───────────────────────────────────
⑧Structure □ │TypeOfConstruction
─────────────┼───────────────────────────────────
Scheduled Start Date │ScheduledDateOfCompletionInspection
─────────────┴───────────────────────────────────
Other Special Notes
─────────────────────────────────────────────────
I hereby report as above in accordance with Article 5-2 of the Act on the Promotion of School Facilities Projects and Article 9 of the Enforcement Decree of the same Act.
Year month day
Applicant (Signature or seal)
Superintendent of Education / Head of Local Office of Education To
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
──────┬──────────────────────────────────────────
Attached Documents │ None
──────┴──────────────────────────────────────────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Confirmation of Report for Construction, etc.
─────────────────────────────────────────────────
No. 호
Pursuant to Article 5-2 of the Act on the Promotion of School Facilities Projects and Article 9 of the Enforcement Decree of the same Act, a Certificate of Reporting is hereby issued as above.
Year month day
(Superintendent of Education / Head of Local Office of Education) (Signature or seal)
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
210mm×297mm[White Paper 80g/㎡(Recycled)]
(Page 2 of 2)
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Guide to Reporting Construction, etc.
───────┬─────────────┬────────────┬────────────────────
Submission Location │ │Processing Department │
───────┼─────────────┼────────────┼────────────────────
Fee │No │Processing Period │3 days
───────┼─────────────┴────────────┴────────────────────
Legal Basis │Article 5-2 of the "School Facilities Project Promotion Act" and Article 9 of the Enforcement Decree of the same Act
───────┴───────────────────────────────────────────────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Important Notes
───────────────────────────────────────────────────────
1. Column ① shall be filled out only when the building owner and the land owner are different, and the name of the right secured by the building owner (e.g., consent to use, surface rights)
etc.).
2. The “use” in ② and ③ shall be indicated in accordance with the classification in Annex 1 of the Enforcement Decree of the Building Act.
3. ④ “Building area” shall be the projected area enclosed by the centerlines of the outer walls or columns of a building, and for buildings 1 meter or less above ground
shall be excluded from building area; where eaves, awnings, or similar structures project at least 1 meter, the area shall be calculated using a line set back horizontally by 1 meter
from the projection.
4. ⑤ “Gross floor area” refers to the sum of the floor areas of each floor of a single building.
5. ⑥ “Building Coverage Ratio” is calculated as Building Area ÷ Site Area × 100(%).
6. ⑦ “Floor Area Ratio” is calculated as Gross Floor Area (excluding basement area and ancillary parking area on ground floors) ÷ Site Area × 100 (%).
7. ⑧ “Structure” shall be described as wooden, masonry, reinforced concrete, steel frame, steel-reinforced concrete, or others, provided that the structure of the walls and roof
differ, each structure shall be stated separately.
──────────────────────┬────────────────────────────────
Layout │Instructions for Writing
──────────────────────┼────────────────────────────────
│1. Using a black ballpoint pen, draw single lines at a scale appropriate to the size of the site
│on the drawing.
│2. Please indicate the bearing and scale.
│3. Please indicate the width and length of the road adjacent to the site.
│4. Please indicate the location of the existing building.
│5. Indicate the distance a building is set back from the site boundary
│.
──────────────────────┼────────────────────────────────
Plan │Instructions for Writing
──────────────────────┼────────────────────────────────
│1. Draw a single line using a black ballpoint pen.
│2. Please indicate the bearing and scale.
│3. Indicate the use of each room on the plan.
──────────────────────┴────────────────────────────────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
ProcessingProcedure
───────────────────────────────────────────────────────
┌───────┐ ┌───────┐ ┌─────────┐ ┌──────┐ ┌──────┐ ┌───┐
│Fill out application form │?│Submission of Application Documents │?│Check Required Documents and │?│Approval Re │?│Issuance of Approval Letter │?│Noti fication│
│ │ │ │ │Review │ │ │ │ │ │ │
└───────┘ └───────┘ └─────────┘ └──────┘ └──────┘ └───┘
Applicant City/Provincial Office of Education City/Provincial Office of Education City/Provincial Office of Education City/Provincial Office of Education
───────────────────────────────────────────────────────