Form 26 — 하천법 시행규칙
279021 · 2025-10-01
■ Enforcement Rules of the River Act [Form No. 26] <Amended Dec. 28, 2021>
Application for Approval of an Implementation Plan (or Amendment thereto)
─────────┬─────────────────┬──────────────────────────────
Receipt Number │Date of Receipt │Processing Period 20 days
─────────┴─────────────────┴──────────────────────────────
─────┬─────────────────────┬──────────────────────────────
Applicant │Name (In the case of a corporation, its name and the name of its representative)│Date of Birth(Corporate Registration Number)
├─────────────────────┴──────────────────────────────
│Address
│(Phone Number : )
─────┴────────────────────────────────────────────────────
─────┬────────────────────────────────────────────────────
River construction│Name of the stream
Permission Details│
├────────────────────────────────────────────────────
│Permission Date and Number
│ Year month day No. 호
├────────────────────────────────────────────────────
│Location
│ (Area : ㎡)
├────────────────────────────────────────────────────
│Construction period
│ Year month to Year month ( (Daily)
├────────────────────────────────────────────────────
│Purpose and Reason
│
─────┴────────────────────────────────────────────────────
─────┬─────────────────────┬──────────────────────────────
Implementation plan│Construction Overview │Total construction cost
My For│ │
├─────────────────────┼──────────────────────────────
│Scheduled commencement date │Scheduled completion date
│ │
─────┴─────────────────────┴──────────────────────────────
Article 30, Paragraph 5 of the River Act, Article 31, Paragraphs 1 and 3 of the Enforcement Decree of the same Act, and Article 15, Paragraph 1 of the Enforcement Rules of the same Act
.
Year month day
Applicant (Signature or seal)
Heads of basin and regional environmental offices; head of the flood control office To
Mayor of a Special City · Mayor of a Metropolitan City · Mayor of a Special Self-Governing City · Governor of a Province · Governor of a Special Self-Governing Province
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
──────┬──────────────────────────────────────────────┬────
Attached Documents │1. Location plan and surveyed cadastral plan showing the project area │Fee
│2. Detailed Design Documents (If divided into two or more project zones, prepare documents for each project zone) │None
│3. Financing Plan and Annual Investment Plan │
│4. Proposed construction schedule │
│5. Location, lot number, land category, area of land, etc. intended for expropriation or use, and rights other than ownership relating to land, etc. │
│and the names and addresses of the owner and rights holders other than the owner ※ Modified in accordance with the main rules │
│Confirm │
│6. Environmental Impact Assessment Report pursuant to the Environmental Impact Assessment Act (Project subject to impact assessment pursuant to Article 22 of the Environmental Impact Assessment Act │
│only applies) │
──────┴──────────────────────────────────────────────┴────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Processing procedure
──────────────────────────────────────────────────────────
┌───┐ ┌──┐ ┌──┐ ┌──┐ ┌──┐ ┌───┐ ┌───┐
│Application│?│Receipt│?│Review│?│Approval│?│Register│?│Certification│?│Certificate│
│Written │ │ │ │ │ │ │ │Cleanup│ │Write │ │Issue │
└───┘ └──┘ └──┘ └──┘ └──┘ └───┘ └───┘
Applicant Processing Agencies: Basin Environmental Offices/Regional Environmental Offices, Flood Control Centers, Special Cities/Metropolitan Cities/Special Self-Governing Cities/Does/Special Self-Governing Provinces
210㎜×297㎜[White paper (80g/㎡) or medium paper (80g/㎡)]