■ Enforcement Rules of the Act on the Safe Management of Firearms, Swords, Explosives, etc. [Attachment Form No. 19] <Amended Jan. 8, 2026>
Application for Permission to Install (Change) Explosives Storage
※ Please read the precautions at the back before filling out. (Front)
─────────┬────────┬──────────────────────────────────────
Receipt Number │Date of Receipt │Processing Period 10 days
─────────┴────────┴──────────────────────────────────────
────┬──────────────┬─────────────────────────────────────
Applicant│Name │Resident Registration Number
│ │
├──────────────┴─────────────────────────────────────
│Address
│(Phone number : )
────┴────────────────────────────────────────────────────
────┬────────────────────────────────────────────────────
Corporate │Name
│
├────────────────────────────────────────────────────
│Address
│(Phone Number : )
────┴────────────────────────────────────────────────────
────┬────────────┬───────────────────────────────────────
Application │Business name │Purpose of installing the storage facility
Content │ │
├────────────┴───────────────────────────────────────
│Office Location
│(Phone Number : )
├────────────────────────────────────────────────────
│Types and number of storage facilities
│
├────────────────────────────────────────────────────
│Permitted storage quantities by category
│
├───┬────────────────────────────────────────────────
│Storage facility│Before change
│Location │
│ ├────────────────────────────────────────────────
│ │After change
│ │
├───┴────────┬───────────────────────────────────────
│Date of completion and commencement of use │Reason for change
│ │
────┴────────────┴───────────────────────────────────────
Article 25, Paragraph 1 of the Act on the Safe Management of Firearms, Swords, Explosives, etc. and Article 34, Paragraph 1 of the Enforcement Rules of the same Act
I hereby apply for a permit for an explosives storage facility (installation/modification) as stated above.
Year month day
Reporting Person (Signature or seal)
City/Provincial Police Commissioner, Police Station Chief To
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
─────┬────────────────────────────────────────────┬──────
Attached Documents│1. Medical examination certificate (issued by a designated health examination institution within three │Fee
│months before the application date) (1 copy) │See back
│2. One copy each of the blueprints of the repository and its specifications │
│3. Sketch map of the facility and surrounding area (within a 500-meter radius); for a change permit, only if the location is changed│
│) (1 copy) │
│4. One copy of the Technical Review Opinion issued by the Association (only applicable if requested by the licensing authority) │
│5. Safety Inspection Plan and Hazard Prevention Plan (1 copy each) │
─────┴────────────────────────────────────────────┴──────
210㎜×297㎜[White Paper 80g/㎡ (Recycled)]
(Back)
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Important Notes
──────────────────────────────────────────────
Please include the following items in the storage design specification.
a. Conditions within a 500-meter radius and safety separation distances from protected objects
B. Structural Equipment · Design Details
. Other necessary matters (crime prevention and fire prevention facilities, etc.)
──────────────────────────────────────────────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Processing procedure
──────────────────────────────────────────────
┌───┬──────────┬─────────────────────────────┐
│Applicant│Agency through which the application is routed │ProcessingAgency │
│ ├──────────┼─────────────────────────────┤
│ │PoliceStation │City/Provincial Police Agency │
│ │ │ │
│ │(Department in Charge of Firearms and Explosives)│(Department in Charge of Firearms and Explosives) │
├───┴──────────┴─────────────────────────────┤
│ │
└────────────────────────────────────────────┘
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Fee
──────────────────────────────────────────────
──────────────────────────────────────────────
1. Level 1 Repository Installation Permission: 10,000 KRW
2. Level 2 Repository Installation Permission: 8,000 KRW
3. Level 3 Repository Installation Permission: 5,000 KRW
4. Installation permit for storage facilities for underwater explosives, live ammunition, fireworks, toy fireworks and safety fuses, and simplified storage facilities: 3,000 won
5. Permission to change repository installation: 5,000 won
──────────────────────────────────────────────