Form 19 — 총포ㆍ도검ㆍ화약류 등의 안전관리에 관한 법률 시행규칙

282777 · 2026-01-08

■ Enforcement Rules of the Act on the Safe Management of Firearms, Swords, Explosives, etc. [Attachment Form No. 19] <Amended Jan. 8, 2026> Application for Permission to Install (Change) Explosives Storage ※ Please read the precautions at the back before filling out. (Front) ─────────┬────────┬────────────────────────────────────── Receipt Number │Date of Receipt │Processing Period 10 days ─────────┴────────┴────────────────────────────────────── ────┬──────────────┬───────────────────────────────────── Applicant│Name │Resident Registration Number │ │ ├──────────────┴───────────────────────────────────── │Address │(Phone number : ) ────┴──────────────────────────────────────────────────── ────┬──────────────────────────────────────────────────── Corporate │Name │ ├──────────────────────────────────────────────────── │Address │(Phone Number : ) ────┴──────────────────────────────────────────────────── ────┬────────────┬─────────────────────────────────────── Application │Business name │Purpose of installing the storage facility Content │ │ ├────────────┴─────────────────────────────────────── │Office Location │(Phone Number : ) ├──────────────────────────────────────────────────── │Types and number of storage facilities │ ├──────────────────────────────────────────────────── │Permitted storage quantities by category │ ├───┬──────────────────────────────────────────────── │Storage facility│Before change │Location │ │ ├──────────────────────────────────────────────── │ │After change │ │ ├───┴────────┬─────────────────────────────────────── │Date of completion and commencement of use │Reason for change │ │ ────┴────────────┴─────────────────────────────────────── Article 25, Paragraph 1 of the Act on the Safe Management of Firearms, Swords, Explosives, etc. and Article 34, Paragraph 1 of the Enforcement Rules of the same Act I hereby apply for a permit for an explosives storage facility (installation/modification) as stated above. Year month day Reporting Person (Signature or seal) City/Provincial Police Commissioner, Police Station Chief To ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━ ─────┬────────────────────────────────────────────┬────── Attached Documents│1. Medical examination certificate (issued by a designated health examination institution within three │Fee │months before the application date) (1 copy) │See back │2. One copy each of the blueprints of the repository and its specifications │ │3. Sketch map of the facility and surrounding area (within a 500-meter radius); for a change permit, only if the location is changed│ │) (1 copy) │ │4. One copy of the Technical Review Opinion issued by the Association (only applicable if requested by the licensing authority) │ │5. Safety Inspection Plan and Hazard Prevention Plan (1 copy each) │ ─────┴────────────────────────────────────────────┴────── 210㎜×297㎜[White Paper 80g/㎡ (Recycled)] (Back) ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━ ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━ Important Notes ────────────────────────────────────────────── Please include the following items in the storage design specification. a. Conditions within a 500-meter radius and safety separation distances from protected objects B. Structural Equipment · Design Details . Other necessary matters (crime prevention and fire prevention facilities, etc.) ────────────────────────────────────────────── ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━ Processing procedure ────────────────────────────────────────────── ┌───┬──────────┬─────────────────────────────┐ │Applicant│Agency through which the application is routed │ProcessingAgency │ │ ├──────────┼─────────────────────────────┤ │ │PoliceStation │City/Provincial Police Agency │ │ │ │ │ │ │(Department in Charge of Firearms and Explosives)│(Department in Charge of Firearms and Explosives) │ ├───┴──────────┴─────────────────────────────┤ │ │ └────────────────────────────────────────────┘ ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━ Fee ────────────────────────────────────────────── ────────────────────────────────────────────── 1. Level 1 Repository Installation Permission: 10,000 KRW 2. Level 2 Repository Installation Permission: 8,000 KRW 3. Level 3 Repository Installation Permission: 5,000 KRW 4. Installation permit for storage facilities for underwater explosives, live ammunition, fireworks, toy fireworks and safety fuses, and simplified storage facilities: 3,000 won 5. Permission to change repository installation: 5,000 won ──────────────────────────────────────────────