■ Enforcement Rules of the Electric Power Business Act [Attachment Form No. 10] <Amended Oct. 1, 2025>
Application for Approval of Usage Rates and Other Conditions of Use for Transmission (Distribution) Electric Facilities
※ The applicant does not fill out sections with a dark background.
────────┬──────────────┬──────────────────────────────
Receipt Number │Date of Receipt │Processing Period 30days
────────┴──────────────┴──────────────────────────────
────┬─────────────────────────────────────────────────
Applicant│Company Name/Organization Name
├──────────────────┬──────────────────────────────
│Representative Name │Corporate Registration Number (Business Registration Number)
├──────────────────┼──────────────────────────────
│Location of principal office │Telephone Number
────┴──────────────────┴──────────────────────────────
Pursuant to Article 15 of the Electric Power Business Act and Article 15, Paragraph 1 of the Enforcement Rules of the same Act, the usage fees for transmission (distribution) electric facilities and the
other conditions of use for transmission (distribution) electrical facilities are hereby submitted for approval.
Year month day
Applicant (Signature or seal)
Minister of Climate, Energy and Environment Your
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
──────┬───────────────────────────────────────┬───────
Attached Documents │ 1. Draft of Usage Fees and Other Conditions of Use for Transmission and Distribution Electric Facilities │Fee
│ 2. Explanation regarding the basis for calculation or method for determining the amount of usage fees for transmission and distribution electrical facilities│No
│ 3. Annual Estimated Business Profit and Loss Statement (Form No. 2) for the 3-year period from the commencement of business │
│ 4. Installation or Investment Plan for Transmission and Distribution Electrical Facilities │
──────┴───────────────────────────────────────┴───────
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Processing Procedure
──────────────────────────────────────────────────────
This application will be processed as follows.
─────────────────┬────────────────────────────────────
Applicant │Processing Agency
├────────────────────────────────────
│Ministry of Climate, Energy and Environment
─────────────────┼────────────────────────────────────
│
┌───────┐ │ ┌───────────────────────┐
│Fill out application form │ │ ▶│Accept │
│ ├───┼─── │ │
│ │ │ │ │
└───────┘ │ └─┬─────────────────────┘
│ │
│
│ ▼
│ ┌───────────────────────┐
│ │Review │
│ └─┬─────────────────────┘
│ │
│
│ ▼
│ ┌───────────────────────┐
│ │Electricity Commission Deliberation │
│ └─┬─────────────────────┘
│ │
│
│ ▼
┌───────┐ │ ┌───────────────────────┐
│Approval │◀ │ │Decision │
│ │ ──┼────┤ │
│ │ │ │ │
└───────┘ │ └───────────────────────┘
│
─────────────────┴────────────────────────────────────
210mm×297mm(White paper 80g/㎡)