ACT ON CONSTRUCTION OF DAMS AND ASSISTANCE TO THEIR ENVIRONS

6329 · 2004-07-30

ACT ON CONSTRUCTION OF DAMS AND ASSISTANCE TO THEIR ENVIRONS  Act No. 7158, Jan. 29, 2004   Act No. 6021, Sep. 7, 1999 Amended by Act No. 6587, Dec. 31, 2001 Act No. 6656, Feb. 4, 2002 Act No. 6655, Feb. 4, 2002 Act No. 6841, Dec. 30, 2002 Act No. 6916, May 29, 2003 Act No. 7158, Jan. 29, 2004 CHAPTER I GENERAL PROVISIONS 법령보기 화면  Article 1 (Purpose) The purpose of this Act is to develop the national economy through the rational development and utilization of water resources by providing the construction and management of dams, the reuse of construction costs, post-dam-construction environment measures and assistance to the residents of areas adjacent to dams. 법령보기 화면  Article 2 (Definitions) For purpose of this Act, the definitions of terms used in this Act shall be as follows: <Amended by Act No. 6656, Feb. 4, 2002; Act No. 7158, Jan. 29, 2004> 1. The term "dam" means an installation having a height of 15 meters or higher which blocks a river stream to utilize the stored water for tap water, industry, farming, power generation, flood control and other purposes (hereinafter referred to as "specific purpose"), and it shall include the spillways, auxiliary dams and other facilities or installations which function en bloc with the relevant dam and effect its full utility; 2. The term "multipurpose dam" means a dam which is constructed by the Minister of Construction and Transportation to be used for not less than two specific purposes (excluding any facility and installation used exclusively for the specific purpose); 3. The term "right to use the dam" means the right to use a certain quantity of water from a multipurpose dam for specific purposes by securing it in a certain area; and 4. The term "person migrating from the area to be submerged" means those who are to lose their living basis due to an implementation of dam construction projects, and who are subject to the countermeasures for migrations as referred to in Article 78 (1) of the Act on the Acquisition of Land, etc. for Public Works and the Compensation Therefor . 법령보기 화면  Article 3 (Scope of Applications) This Act shall apply to any multipurpose dam and such dams as constructed by persons falling under each of the following subparagraphs in order to supply the tap and industrial water or to make the flood control: Provided , That the provisions of Article 4 shall apply to all kinds of dams: <Amended by Act No. 7158, Jan. 29, 2004> 1. The Minister of Construction and Transportation; 2. Special Metropolitan City Mayor, Metropolitan City Mayor or Do governor (hereinafter referred to as the "Mayor/ Do governor"); and 3. Other persons as prescribed by the Presidential Decree. CHAPTER II CONSTRUCTION AND MANAGEMENT OF DAMS Section 1 Construction Of Dams 법령보기 화면  Article 4 (Long-Term Plans for Dam Construction) (1) The Minister of Construction and Transportation shall devise a longterm plan for dam construction every ten years in order to develop water resources efficiently and environment-friendly, which includes matters falling under each of the following subparagraphs: 1. Basic principle for dam construction; 2. Prospects of the supply and demand of water for various purposes; 3. Dam construction plans by water system (a dam for agricultural purpose shall be limited to one with storing capacity of not less than 10 million tons; 4. Plans for securing financial resources; 5. Standards for selecting a dam construction site; 6. Means to minimize the environmental impact of dam construction; and 7. Other matters as prescribed by the Presidential Decree. (2) The Minister of Construction and Transportation shall, where he intends to devise a long-term plan for dam construction under paragraph (1), ask in advance the heads of central administrative agencies concerned to devise and furnish their respective long-term plans for dam construction. (3) When the Minister of Construction and Transportation intends to formulate the long-term plan for dam construction as referred to in paragraph (1), he shall go through a deliberation by the Central River Management Committee as referred to in Article 60 of the Rivers Act , after hearing the opinions of the competent Mayor/ Do governor and holding a consultation with the heads of related central administrative agencies. In such case, the matters concerning the dams that have gone through a deliberation of the Electric Source Development Project Promotion Committee as referred to in Article 4 of the Act on Special Cases concerning Electric Source Development , shall be excluded from the matters for deliberation. <Added by Act No. 7158, Jan. 29, 2004> (4) The Minister of Construction and Transportation shall examine every five years whether or not the long-term plan for dam construction is compatible with its propriety, and reflect the results therefrom to the long-term plan for dam construction. <Added by Act No. 7158, Jan. 29, 2004> (5) Provisions of paragraph (3) shall apply mutatis mutandis to alterations of the long-term plan for dam construction: Provided , That the same shall not apply to the minor matters as prescribed by the Presidential Decree. <Added by Act No. 7158, Jan. 29, 2004> (6) When the Minister of Construction and Transportation has formulated or altered the long-term plan for dam construction as referred to in paragraphs (1) and (5), he shall promptly notify the heads of related central administrative agencies and the competent Mayor/ Do governor thereof. <Added by Act No. 7158, Jan. 29, 2004> 법령보기 화면  Article 5 (Designation, etc. of Areas Intended for Dam Construction) (1) The Minister of Construction and Transportation may designate a certain area necessary for a dam construction (including an area scheduled submerging by a dam construction) as an area intended for dam construction (hereinafter referred to as an "area intended for dam construction"): Provided , That in the case of dams to be constructed by the Mayor/ Do governor, the management agency in charge of managing a river in which such dam is to be constructed (hereinafter referred to as the "river management agency") shall designate an area intended for dam construction. (2) The Minister of Construction and Transportation or the river management agency shall, where he or it intends to designate an area intended for dam construction under paragraph (1), go through deliberations of the Central River Management Committee as referred to in Article 60 of the River Act in the case of the Minister of Construction and Transportation, and of the Local River Management Committee as referred to in the same Article in the case of the River Management Agency, after consulting with the heads of related administrative agencies: Provided , That where the Minister of Construction and Transportation designates the area intended for dam construction in the local river, he shall hear the opinions of the Management Agency in charge of the management of relevant river, prior to the deliberation of the Central River Management Committee. <Amended by Act No. 7158, Jan. 29, 2004> (3) The Minister of Construction and Transportation or the river management agency shall, where he or it has designated an area intended for dam construction under paragraph (1), publish such designation under the conditions as prescribed by the Presidential Decree. (4) The Minister of Construction and Transportation or the river management agency shall, where he or it publishes an area intended for dam construction under paragraph (3), also publish a person who intends to construct such dam (hereinafter referred to as the "implementer of dam construction project"). (5) The provisions of paragraphs (1) through (4) shall apply mutatis mutandis to any alteration or cancellation of an area intended for dam construction. 법령보기 화면  Article 6 (Restrictions on Acts in Area Intended for Dam Construction) (1) A person who intends to perform the acts falling under each of the following subparagraphs in an area intended for dam construction shall obtain permission from the head of Si / Gun or the head of autonomous Gu (hereinafter referred to as the "head of Si / Gun / Gu ") under the conditions as prescribed by the Presidential Decree: 1. New construction, reconstruction or expansion of any structures or any installations as prescribed by the Presidential Decree; 2. Alteration of form and quality of lands: Provided , That the case of cultivation shall be excepted; 3. Planting or transplanting of perennial trees; and 4. Raising of livestock falling under species and scopes as prescribed by the Presidential Decree. (2) Notwithstanding the provisions of paragraph (1), a person who has initiated a construction or a project by obtaining permission or authorization, etc. for the acts falling under each subparagraph of paragraph (1) pursuant to the relevant Acts and subordinate statutes at the time when a designation and publication of an area intended for dam construction are made (including a person who has initiated a construction or a project without obtaining permission or authorization, etc. in case where the relevant acts are not subject to permission or authorization under the relevant Acts and subordinate statutes), may continue to implement it, after filing a report thereon with the head of Si / Gun / Gu under the conditions as prescribed by the Presidential Decree. (3) The head of Si / Gun / Gu shall, when he intends to grant permission under paragraph (1), consult in advance with the implementer of dam construction project. (4) The head of Si / Gun / Gu shall, where deemed that the acts of seeking a permission under paragraph (1) is doing no harm to a dam construction, permit such act. (5) The head of Si / Gun / Gu may order a person who has violated the provisions of paragraph (1) to restore the original state. (6) A person who has obtained permission under paragraph (1) shall, when he intends to alter permitted matters, obtain permission thereof from the head of Si / Gun / Gu : Provided , That the same shall not apply to an alteration of minor matters as prescribed by the Presidential Decree. (7) The provisions of paragraphs (1) through (5) shall apply mutatis mutandis to the permission of alteration under paragraph (6). 법령보기 화면  Article 7 (Basic Plans) (1) An implementer of dam construction project shall devise a basic plan for dam construction (hereinafter referred to as the "basic plan") which includes matters falling under each of the following subparagraphs: <Amended by Act No. 6587, Dec. 31, 2001; Act No. 7158, Jan. 29, 2004> 1. Objective of the construction; 2. Title of a project, and location and size of a place for project implementation; 3. Scale and type; 4. Quantity of the stored water, and matters concerning a distribution by use of such stored water; 5. Name or title of a person scheduled to be granted a right to use the dam (hereinafter referred to as the "person to be granted a right for dam use"), and the contents of a right to use the dam; 6. Dam construction costs (including expenses required for the consolidation of dam environs borne by the implementer of dam construction project under Article 42 ) and the contents of the share thereof; 7. Implementer of dam construction project; 8. Project period; 9. If lands or buildings to be expropriated or used, and other goods or rights are in existence, details thereof; 10. Damages on environments expected by a dam construction, and matters concerning the means for reducing them and for preserving water quality; 11. Matters concerning the project capable of contributing to the social, cultural and economic development of the dam environs, and the project for promoting the usefulness of a dam; and 12. Other principal matters concerning the dam construction. (2) An implementer of dam construction project who is not the Minister of Construction and Transportation or the Mayor/ Do governor shall, when he intends to devise a basic plan under paragraph (1), obtain permission from the Minister of Construction and Transportation. (3) The Minister of Construction and Transportation or the Mayor/ Do governor shall, when he intends to devise a basic plan or grant permission under paragraph (1) or (2), consult in advance with the heads of administrative agencies concerned, and seek the opinions from a person to be granted a right for dam use. (4) The Minister of Construction and Transportation or the Mayor/ Do governor shall, when he has devised a basic plan or granted permission, publish it under the conditions as prescribed by the Presidential Decree. (5) The provisions of paragraphs (1) through (4) shall apply mutatis mutandis to the alteration of basic plans (excluding an alteration of minor matters as prescribed by the Presidential Decree) or the abolition thereof. 법령보기 화면  Article 8 (Implementation Plan) (1) An implementer of dam construction project shall devise an implementation plan relating to dam construction (hereinafter referred to as the "implementation plan") under the conditions as prescribed by the Presidential Decree, after devising a basic plan. (2) An implementer of dam construction project who is neither the Minister of Construction and Transportation nor the Mayor/ Do governor shall, when he intends to devise an implementation plan, obtain approval from the Minister of Construction and Transportation. (3) The Minister of Construction and Transportation or the Mayor/ Do governor shall, when he has devised an implementation plan or granted approval under paragraph (1) or (2), promptly publish the contents thereof, and notify thereof to the heads of administrative agencies concerned and a person to be granted a right for dam use. (4) The provisions of paragraphs (1) through (3) shall apply mutatis mutandis to the alteration of an implementation plan (excluding an alteration of minor matters as prescribed by the Presidential Decree), or the abolition thereof. 법령보기 화면  Article 9 (Legal Fiction of Authorization and Permission, etc. under Other Acts) (1) When the Minister of Construction and Transportation or the Mayor/ Do governor has devised, altered, or approved an implementation plan under Article 8 (1) or (2), the permission, report, cancellation, consultation, approval, authorization or designation, etc. falling under each of the following subparagraphs (hereinafter referred to as the "authorization or permission, etc.") shall be deemed to have been made, and when an implementation plan has been published under Article 8 (3), the publication or public notice of the authorization or permission, etc. falling under each of the following subparagraphs shall be deemed to have been made: <Amended by Act No. 6655, Feb. 4, 2002; Act No. 6841, Dec. 30, 2002; Act No. 7158, Jan. 29, 2004> 1. Permission for occupancy and use of public waters under Article 5 of the Public Waters Management Act ; 2. Permission for or consultation on the diversion of farmland under Article 36 of the Farmland Act ; 3. Permission for or a report on the diversion of a mountainous district under Articles 14 and 15 of the Management of Mountainous Districts Act, permission for the quarrying under Article 25 of the same Act, and permission for the cutting, etc. of standing timber under Articles 62 (1) and 90 (1) of the Forestry Act ; 4. Permission for the deforestation, etc. under Article 14 of the Work against Land Erosion or Collapse Act, and the cancellation of designation of an erosion control area under Article 20 of the same Act; 5. Permission for a reburial of the grave as referred to in Article 23 (1) of the Funeral Services, etc. Act; 6. Consultation on or approval of matters to be permitted by the management agency under Article 6 of the River Act , permission for an implementation of a river work under Article 30 of the same Act , and permission for the occupancy of a river under Article 33 of the same Act ; 7. Approval of the installation of excreta treatment facilities under Article 21 of the Act on the Disposal of Sewage, Excreta and Livestock Wastewater ; 8. Approval of or report on the installation of waste treatment facilities under Article 30 of the Wastes Control Act ; 9. Permission for the implementation of a road work under Article 34 of the Road Act , and permission for the occupancy of a road under Article 40 of the same Act ; 10. Permission for the implementation of a public sewerage work under Article 13 of the Sewerage Act , and permission for the occupancy under Article 20 of the same Act ; 11. License for the reclamation under Article 9 of the Public Waters Reclamation Act , and authorization for the implementation plan under Article 15 of the same Act ; 12. Permission for opening a private road under Article 4 of the Private Road Act ; 13. Permission for occupancy and use under Article 23 of the Natural Parks Act ; 14. Permission for the creation of a grassland under Article 5 of the Grassland Act, and permission for the diversion of a grassland under Article 23 of the same Act; 15. Consultations, etc. on matters to be permitted by an administrative agency under Article 10 of the Protection of Military Installations Act ; 16. Approval of other uses of an agricultural infrastructure than its objectives under Article 20 of the Rearrangement of Agricultural and Fishing Villages Act; 17. Decision on the urban management plans under Article 30 of the National Land Planning and Utilization Act (limited to the facilities under subparagraph 6 of Article 2 of the same Act ), permission for the development activities under Article 56 of the same Act , designation of the implementer of an urban planning facilities project under Article 86 of the same Act , and authorization for an implementation plan under Article 88 of the same Act ; and 18. Permission for occupancy under Article 14 of the Small River Maintenance Act . (2) The Minister of Construction and Transportation or the Mayor/ Do governor shall, when he intends to devise, alter or approve an implementation plan which includes the contents falling under each of paragraph (1), consult in advance with the heads of administrative agencies concerned. In this case, the heads of administrative agencies in receipt of a request for such consultations shall furnish their opinions within 30 days from the date when such a request is received. 법령보기 화면  Article 10 (Access to Land, etc.) (1) An implementer of dam construction project may, when he is in need of an examination or survey for a dam construction or if necessary for such dam construction, enter or temporarily use the other person's lands; and if especially necessary, alter or remove the bamboos, trees, earth, stones and other obstacles therein. (2) An implementer of dam construction project shall, when he intends to enter the other person's lands under paragraph (1), notify the relevant date and place to the owner, occupant, or manager of the relevant land not later than three days prior to the date when he intends to enter. In this case, an implementer of dam construction project who is not an administrative agency shall obtain in advance permission from the head of Si / Gun / Gu . (3) An implementer of dam construction project shall, when he intends to alter or remove the bamboos, trees, earth, stones and other obstacles under paragraph (1), obtain a consent from the owner, occupant or manager of such obstacles. (4) An implementer of dam construction project may, when he is unable to obtain a consent under paragraph (3) from the owner, occupant or manager of the obstacles due to an obscurity of the address or residence of such owner, occupant or manager, alter or remove such obstacles after filing notice thereof with the head of Si / Gun / Gu : Provided , That where the implementer of dam construction project is not an administrative agency, he shall obtain permission therefor in advance from the head of Si / Gun / Gu . (5) A person who intends to alter or remove the obstacles pursuant to paragraph (3) shall notify thereof to the owner, occupant or manger of the obstacles not later than three days prior to the date when he intends to alter or remove such obstacles: Provided , That the same shall not apply to the case of paragraph (4). (6) No one shall enter the building sites or other person's lands girded by walls or fences, without a consent of the land occupant before the sunrise or after the sunset. (7) The land occupant shall not obstruct or refuse the acts of an implementer of dam construction project under paragraph (1), without any justifiable reasons. (8) A person who intends to perform the acts under paragraph (1) shall carry a certificate showing his identity, and produce it to the persons concerned under the conditions as prescribed by the Ministerial Decree of Construction and Transportation. (9) An implementer of dam construction project shall, where any person has suffered a loss arising from the acts under paragraph (1), compensate such loss. (10) With respect to a compensation for losses under paragraph (9), an implementer of dam construction project and the person suffered from such loss shall reach an agreement through consultations. (11) An implementer of dam construction project or a person suffered from such loss may, in case where they fail to reach an agreement under paragraph (9) or unable to hold such consultations, apply the Land Expropriation Committee for an adjudication. 법령보기 화면  Article 11 (Expropriation and Use of Land, etc.) (1) An implementer of dam construction project may expropriate or use any land, buildings and other articles attached to the land, rights other than ownership, mining right, fishing right, and right for water use (hereinafter referred to as the "land, etc."), which are required for his dam construction. (2) In applying the provisions of paragraph (1), where a basic plan is published under Article 7 (4), a project approval and a publication of such project approval under Articles 20 (1) and 22 of the Act on the Acquisition of Land, etc. for Public Works and the Compensation Therefor shall be deemed to have been made; and an application for adjudication shall be filed within a period of project as fixed in a basic plan, notwithstanding the provisions of Articles 23 (1) and 28 (1) of the Act on the Acquisition of Land, etc. for Public Works and the Compensation Therefor . <Amended by Act No. 6656, Feb. 4, 2002> (3) The Act on the Acquisition of Land, etc. for Public Works and the Compensation Therefor shall apply mutatis mutandis to the expropriation and use of the land, etc. under paragraph (1), except as otherwise provided for in this Act. <Amended by Act No. 6656, Feb. 4, 2002> 법령보기 화면  Article 12 (Publication of Completion of Dam Construction) (1) The Minister of Construction and Transportation or the Mayor/ Do governor shall, when the construction of dam is completed, promptly publish matters falling under each of the following subparagraphs: 1. Purport that a dam construction has been completed; 2. River area under Article 2 (1) 2 of the River Act , from among the area for a dam construction; and 3. Purport that the relevant dam is attached to the river under Article 2 (1) 3 of the River Act . (2) An implementer of dam construction project who is not the Minister of Construction and Transportation or the Mayor/ Do governor shall, when he has completed a dam construction, promptly file an application for an authorization for the completion of construction with the Minister of Construction and Transportation under the conditions as prescribed by the Presidential Decree, and the Minister of Construction and Transportation shall, where deemed that the dam has been constructed as determined by an implementation plan, deliver an ending certificate of authorization for work completion, and publish matters of each subparagraph of paragraph (1). (3) When a publication of paragraph (1) or (2) is made, a consent under the proviso of Article 2 (1) 3 of the River Act shall be deemed to have been obtained, and a decision and publication of a river area under Article 9 (4) of the River Act shall be deemed to have been made. (4) When a publication under paragraph (1) or (2) is made, a completion inspection or a completion authorization of the relevant work or project according to an authorization or permission, etc. as fictionized under Article 9 (1) as well as a publication thereof shall be deemed to have been made. 법령보기 화면  Article 13 (Reversion of Public Facilities, etc.) (1) Where an implementer of dam construction project installs, through his dam construction project, the new public facilities or other public facilities to substitute the existing public facilities, the previous public facilities shall revert without compensation to the implementer of dam construction project, and the new public facilities shall revert without compensation to the State or a local government in charge of managing the relevant public facilities, notwithstanding the provisions of the State Properties Act and the Local Finance Act . (2) The Minister of Construction and Transportation or the Mayor/ Do governor shall, when he intends to devise, alter or approve an implementation plan which includes matters relating to the reversion of the public facilities under paragraph (1), hear in advance the opinions of a management agency of such public facilities: Provided , That where the management agency has yet to be designated, he shall hear the opinions of a management agency, after such management agency is designated, and prior to granting a completion authorization. (3) An implementer of dam construction project shall notify the relevant management agency of the kinds and details of public facilities to revert to himself and the State or a local government prior to the completion of dam construction, and the relevant public facilities shall revert to each person described in paragraph (1) respectively on the date when the completion of dam construction is published under Article 12 . (4) In registering the public facilities and lands under paragraphs (1) through (3), the publication of the implementation plan under the provisions of Article 8 and the publication of completion of a dam construction under Article 12 shall substitute the document attesting a cause of registration under Article 40 of the Registration of Real Estate Act . (5) The scope of public facilities under paragraphs (1) through (4) shall be prescribed by the Presidential Decree. 법령보기 화면  Article 14 (Disposal of State and Public Property) (1) Any property owned by the State or a local government in an area intended for dam construction may be rented or transferred by a free contract to an implementer of dam construction project, notwithstanding the provisions of the State Properties Act or the Local Finance Act . (2) The Minister of Construction and Transportation or the Mayor/ Do governor shall, when he intends to devise, alter or approve an implementation plan which includes matters relating to the disposal of State and public properties under paragraph (1), consult in advance with the management agency in charge of such properties. (3) From among the State properties to be rented or transferred to an implementer of dam construction project under paragraph (1), the Minister of Economy and Finance shall be deemed the management agency, with respect to any property for which the competent management agency is obscure. Section 2 Management Of Dams 법령보기 화면  Article 15 (Dam Management Agency and Entrusted Dam Manager) (1) The Minister of Construction and Transportation shall manage dams: Provided , That the dams constructed by the Mayor/ Do governor shall be managed by the relevant Mayor/ Do governor. (2) The Minister of Construction and Transportation or the Mayor/ Do governor who manages dams under paragraph (1) (hereinafter referred to as the "dam management agency") may, where deemed necessary for managing such dams, entrust the dam management to a person granted the right to use a dam (hereinafter referred to as the "person holding a right for dam use") or a government-invested institution performing the business of constructing and managing dams. (3) Matters necessary for the entrustment of dam management under paragraph (2) shall be prescribed by the Presidential Decree. 법령보기 화면  Article 16 (Basic Principle of Dam Management) In managing dams, the propriety shall be ensured so as to enhance the public interest by storing water in dams, to take heed to removal or minimization of any damages, and not to infringe a right for dam use. 법령보기 화면  Article 17 (Dam Management Regulations) (1) The dam management agency shall set forth a regulation for dam management according to the basic principle of dam management under Article 16 , under the conditions as prescribed by the Presidential Decree. (2) A person entrusted with the dam management under Article 15 (2) (hereinafter referred to as the "person entrusted with dam management") shall set forth a regulation for dam management, and obtain an approval thereof from the dam management agency. The same shall also apply to a case where he intends to alter a regulation for dam management. (3) A dam management agency shall, when it sets forth or approves a regulation for dam management under paragraph (1) or (2), consult in advance with the head of the related central administrative agency, and hear the opinions of a person to be granted a right for dam use or a person holding the right for dam use. The same shall also apply to a case where it intends to alter a regulation for dam management. (4) A dam management agency may, where deemed necessary to efficiently manage water resources, order a person entrusted with dam management to alter a regulation for dam management under paragraph (2), or have him file a report necessary for dam management, or give him an instruction thereof. 법령보기 화면  Article 18 (Measures to Prevent Dangers) A dam management agency or a person entrusted with dam management shall, where deemed that a discharge of stored water in a dam results in marked changes in the downstream, notify in advance the relevant Mayor/ Do governor under the conditions as prescribed by the Presidential Decree, in order to prevent the dangers due to such discharge, and take necessary measures for making such dangers known to the public. 법령보기 화면  Article 18-2 (Project for Management of Dams) Where the dam management agency or the person entrusted with dam management deems it necessary to ensure the propriety of dam management, it or he may implement the projects falling under each of the following subparagraphs under the conditions as prescribed by the Presidential Decree: 1. Project for a removal or mitigation of inundation damages or traffic inconveniences etc. that are caused by dams; and 2. Project for an increase of usefulness of dams, such as a creation of relaxation space and installation of athletic facilities, etc. [This Article Added by Act No. 7158, Jan. 29, 2004] Section 3 Special Case for Construction and Management of Multipurpose Dams 법령보기 화면  Article 19 (Person to be Granted Right for Dam Use) (1) A person to be granted a right for dam use shall be one who has filed an application for establishment of a right for dam use, and who satisfies the requirements of Article 25 . (2) A successor, a corporation incorporated due to a merger, and a general successor to the person to be granted a right for dam use, shall succeed the status under this Act which is held by such a person. 법령보기 화면  Article 20 (Bearing of Multipurpose Dam Construction Costs) (1) A person to be granted a right for dam use shall bear the cost computed under the conditions as prescribed by the Presidential Decree, from among the construction costs of a multipurpose dam. (2) The cost to be borne under paragraph (1) shall be computed taking into account the amount falling under each of the following subparagraphs: 1. An estimated investment amount computed from the usefulness which is obtained by using the stored water in a multipurpose dam for the purpose for which a right for dam use is to be established; and 2. An estimated cost amount necessary for a setup of installations having the same usefulness as the installations exclusively used for the purpose for which a right for dam use is to be established. (3) An amount claculated by deducting the cost to be borne under paragraph (1) from the construction costs for a multipurpose dam shall be borne by the National Treasury. (4) The Sate shall, when a person to be granted a right for dam use has failed to have a right for dam use, refund the cost paid by such person under paragraph (1): Provided , That such refund may be suspended until a new person to be granted a right for dam use is decided, except for a case where the basic plan is abolished. (5) The State shall, where it suspends the refund of costs under the proviso of paragraph (4), pay the interest under the conditions as prescribed by the Presidential Decree during the period of suspension. (6) Matters necessary for the scope of costs required for the construction of a multipurpose dam, the method of paying the cost to be borne, the deadline for such payment, and the refund of the cost to be borne, etc. shall be prescribed by the Presidential Decree. 법령보기 화면  Article 21 (Preceding Investment by State) The Minister of Construction and Transportation may, when there exist a need for flood control and other special needs, construct a multipurpose dam without designating a person to be granted a right for dam use. In this case, the provisions concerning a person to be granted a right for dam use or a person holding a right for dam use shall be applied from the time when such person is designated. 법령보기 화면  Article 22 (Bearing of Costs by Local Governments) The Minister of Construction and Transportation may have a local government which benefits significantly due to the construction of relevant dam (excluding a local government having jurisdiction over the dam construction area) bear a part of the costs to be borne by the National Treasury pursuant to Article 20 (3) from among the costs required for the construction of a multipurpose dam, under the conditions as prescribed by the Presidential Decree. 법령보기 화면  Article 23 (Shared Amount by Beneficiaries) (1) The Minister of Construction and Transportation may, where there exists any person who benefits significantly due to the construction of a multipurpose dam, have such person bear a part of the costs required for the construction of relevant multipurpose dam, within the limit of his relevant benefits. (2) Matters necessary for the scope of persons to bear the shared amount under paragraph (1), the computation and the collection methods of shared amounts shall be prescribed by the Presidential Decree. 법령보기 화면  Article 24 (Establishment of Right for Dam Use) (1) The Minister of Construction and Transportation shall, upon a request from a person who intends to use the stored water in a multipurpose dam for a specific purpose, establish a right to use such dam. (2) The Minister of Construction and Transportation shall, where he establishes a right to use a dam under paragraph (1), clarify matters falling under each of the following subparagraphs: 1. Objective of establishment; and 2. Maximum and minimum water level and quantity of stored water to be secured by the establishment of a right for dam use. (3) Matters of paragraph (2) 2 shall be prescribed so as to have the relevant dam exhibit its utility without a hitch. (4) The Minister of Construction and Transportation shall, when he has published the completion of dam construction under Article 12 , promptly establish a right to use such dam, for a person to be granted a right for dam use. (5) A person to be granted a right for dam use may use the stored water in a multipurpose dam for a specific purpose, after obtaining permission from the Minister of Construction and Transportation even prior to the establishment of a right to use a dam under paragraph (1). 법령보기 화면  Article 25 (Requirements for Establishment of Right for Dam Use) The Minister of Construction and Transportation shall, only where an applicant satisfies requirements falling under any of the following subparagraphs, establish a right to use a dam for him: 1. Where the use of stored water in a multipurpose dam for the purpose of establishing a right to use a dam is in conformity with the basic plan; and 2. Where permission or authorization, etc. required for running a business which uses the stored water in a multipurpose dam is obtained. 법령보기 화면  Article 26 (Restrictions on River Occupancy for Specific Purpose) A person who intends to use the stored water in a multipurpose dam for a specific purpose shall obtain permission for river occupancy under Article 33 of the River Act , and have a right for dam use under Article 24 established. 법령보기 화면  Article 27 (Rejection of Establishment of Right for Dam Use) (1) The Minister of Construction and Transportation may reject an establishment of a right for dam use to a person who is not designated as a person to be granted a right for dam use in the basic plan. (2) The Minister of Construction and Transportation shall reject an establishment of a right for dam use to a person to be granted a right for dam use, in case where he falls under any of the following subparagraphs: 1. Where he fails to conform with the requirements of Article 25 ; and 2. Where he fails to pay the shared amount under Article 20 (1). 법령보기 화면  Article 28 (Area to Secure Stored Water) An area in which the stored water is to be secured by a right for dam use shall be such area as is surrounded by the line which is formed by a contact of the maximum water level of stored water under Article 24 (2) 2 to the land. 법령보기 화면  Article 29 (Nature of Right for Dam Use) A right for dam use shall be deemed the property rights, and the provisions concerning the real estates shall apply mutatis mutandis to a right for dam use, except as otherwise provided in this Act. 법령보기 화면  Article 30 (Restrictions on Disposal of Right for Dam Use) (1) A right for dam use shall not be a subject-matter of other rights than a succession, a merger of corporations and other general successions, a transfer, a disposition taken against arrears, a compulsory execution and a mortgage. (2) A right for dam use for which a mortgage creation is registered shall not be divided or merged, and its purpose of creation shall not be altered or waived, without a consent of the mortgagee. 법령보기 화면  Article 31 (Revocation etc. against Right for Dam Use) (1) The Minister of Construction and Transportation shall, where he cancels in whole or in part the permission for river occupancy under Article 33 of the River Act against a person holding a right for dam use, and where he is unable to recognize an occupancy of streaming water as before with respect to other persons than those holding a right for dam use, take the disposition of revocation or alteration corresponding thereto against a right for dam use. (2) The Minister of Construction and Transportation may, where he cancels in whole or in part the permission for river occupancy under Article 33 of the River Act against a person holding a right for dam use, and where there exists a need to recognize anew an occupancy of streaming water to other persons than one holding a right for dam use, order the relevant holder of a right for dam use, with fixing a considerable period of time, to transfer in whole or in part his right for dam use to other persons. (3) In case where a person holding a right for dam use fails to transfer in whole or in part his right for dam use to other persons within the specified period under paragraph (2), the Minister of Construction and Transportation may, only where a person other than one holding a right for dam use is deemed eligible for obtaining a permission for river occupancy with the same contents as a permission for river occupancy granted to a person holding a right for dam use, take a disposition to revoke in whole or in part the relevant right for dam use. (4) Where the Minister of Construction and Transportation deems it difficult to maintain the right for dam use as it is, that are the cases falling under each of the following subparagraphs, he may take dispositions of revocation or alteration against the right for dam use. In such case, he shall hear in advance the opinions from the holders of rights for dam uses: <Added by Act No. 7158, Jan. 29, 2004> 1. Where the quantity of water-storage has been changed due to an expansion or reconstruction etc. of dams; and 2. Where the status of utilization etc. of the water-storage in dams. (5) Where the Minister of Construction and Transportation takes dispositions of revocation or alteration against the right for dam use as referred to in paragraph (4), he shall alter the matters concerning a distribution of water-storage by usages from among the publicized basic plans as referred to in Article 7 (4), and make a public notification thereof. <Added by Act No. 7158, Jan. 29, 2004> 법령보기 화면  Article 32 (Registration) (1) A right for dam use and the creation, alteration, transfer, extinction, and restrictions on disposals, of a mortgage with a subject-matter of a right for dam use, shall be null and void unless they are registered in the registration ledger of rights for dam use which is kept in the Ministry of Construction and Transportation. (2) Matters necessary for the registration of a right for dam use, and of any mortgage created with a subject-matter of a right for dam use shall be prescribed by the Presidential Decree. 법령보기 화면  Article 33 (Fees) A person holding a right for dam use shall, except for a case where his right for dam use is established under Article 24 (4), pay the fees computed under the conditions as prescribed by the Presidential Decree to the National Treasury. In this case, in computing such fees, the estimated investment amount computed under Article 20 (2) 1 shall be taken into account. 법령보기 화면  Article 34 (Refund of Shared Amount) (1) The State shall, when it takes a disposition to revoke or alter a right for dam use under Article 31 , refund a part of the shared amount paid under Article 20 (1) or of the fees paid under Article 33. (2) The amount to be refunded under paragraph (1) shall be computed in the same manner as that for computing the relevant shared amount or the fees, and the amount to be refunded to a person who has had his right for dam use established under Article 24 (1) shall not exceed the amount calculated by deducting the depreciation amount computed under the conditions as prescribed by the Presidential Decree from the shared amount under Article 20 (1). (3) The State shall, where a mortgage creation is registered on a right for dam use which has been extinguished by a disposition of revocation or alteration under Article 31 , deposit a refund payment under paragraph (1), except for a case of the consent by a mortgagee. In this case, such mortgagee on a right for dam use may exercise his right on the refund payment deposited. 법령보기 화면  Article 35 (Collection of Fees) (1) A person holding a right for dam use or a person to be granted a right for dam use may collect the fees from a person who uses the stored water in the relevant dam: Provided , That the same shall not apply to the case of using the river water by obtaining a permission for the occupancy of such river under Article 33 of the River Act prior to the construction of such dam. (2) The fees under paragraph (1) shall be determined taking into account the quantity of water used by a person using the stored water in a dam, within the limit of the shared amount under Article 20 (1) or the paid amount under Article 33 by a person holding a right for dam use or a person to be granted a right for dam use. (3) A person holding a right for dam use or a person to be granted a right for dam use shall, where he intends to collect the fees under paragraph (1), set forth a computation manner, a method and period of collection, and obtain in advance permission thereof from the Minister of Construction and Transportation. 법령보기 화면  Article 36 (Bearing of Expenses for Management of Multipurpose Dam) (1) Expenses required for a maintenance, repair and other managements of multipurpose dams shall be borne by the National Treasury, a person holding a right for dam use, or a person entrusted with the dam management. In this case, the expenses to be borne by a person entrusted with the dam management shall be within the limit of revenues accruing from the entrusted management of relevant dam. (2) Matters necessary for the bearing of expenses under paragraph (1) shall be prescribed by the Presidential Decree. 법령보기 화면  Article 37 (Compulsory Collection of Shared Amount, etc.) (1) The Minister of Construction and Transportation shall, where there exists a person who fails to pay the shared amount or the fees falling under each of the following subparagraphs, fix a payment period and urge in writing: 1. Shared amount under Article 20 (1); 2. Shared amount by beneficiaries under Article 23 ; 3. Fees under Article 33 ; and 4. Shared amount by a person holding a right for dam use under Article 36 . (2) The Minister of Construction and Transportation may, where a person urged under paragraph (1) fails to pay the shared amount or fees by a specified period, collect them according to the example of taking a disposition to collect national taxes in arrears. (3) A right to collect the shared amount and fees under paragraph (1) shall be extinguished by prescription when it has not been exercised for five years. 법령보기 화면  Article 38 (Recognition of Multipurpose Dam, etc.) (1) The Minister of Construction and Transportation may, with respect to a dam constructed by other person than himself which is deemed a multipurpose dam with a great usefulness, consult with a person who has constructed such dam, and properly compensate him, and make the relevant dam a multipurpose dam under this Act. In this case, the Minister of Construction and Transportation may establish a right for dam use to a person who has constructed the relevant dam under the conditions as prescribed by the Presidential Decree. (2) Where the Minister of Construction and Transportation has made the dam that is not a multipurpose one as a multipurpose dam under paragraph (1), he shall promptly make a public notification of the matters falling under each of the following subparagraphs under the conditions as prescribed by the Presidential Decree: <Added by Act No. 7158, Jan. 29, 2004> 1. Reasons for a recognition of the multipurpose dam; 2. Matters falling under Article 7 (1) 2 through 4; and 3. Matters concerning the compensation to the builders of relevant dams. (3) With respect to a dam constructed by other person than the Minister of Construction and Transportation which is deemed as a multipurpose dam with a great usefulness, the State may provide the subsidies or arrange the loans, for a person constructing the relevant dam, to cover part of the costs required for such a construction. (4) The Minister of Construction and Transportation may, where he has provided the subsidies or arranged the loans under paragraph (3), give instructions required for a construction of the relevant dam to a person benefited from such subsidies or loans, or have him check the facilities of the relevant dam which is an objective of construction, or report thereon. <Amended by Act No. 7158, Jan. 29, 2004> CHAPTER III SUPPORT FOR RESIDENTS OF DAM CONSTRUCTION AREA 법령보기 화면  Article 39 (Support for Unsettled Persons etc. into Resettlement Lands) The implementer of the dam construction project may, under the conditions as prescribed by the Presidential Decree, support a person who fails to migrate to resettlement lands and other persons as prescribed by the Presidential Decree, from among the persons migrating from the area to be submerged, taking into account a loss of hometown and living basis, etc. due to a dam construction. <Amended by Act No. 7158, Jan. 29, 2004> [This Article Wholly Amended by Act No. 6587, Dec. 31, 2001] 법령보기 화면  Article 40 (Support for Persons Migrating from Area to be Submerged) (1) The Minister of Construction and Transportation may, where deemed necessary to create a living basis such as a new construction of housing so as to have the persons migrating from the area to be submerged migrate and settle smoothly, support them preferentially with the National Housing Fund pursuant to the Housing Act . <Amended by Act No. 6916, May 29, 2003> (2) An implementer of dam construction project may, where deemed necessary to create a living basis for the persons migrating from the area to be submerged, ask the Minister of Construction and Transportation for a preferential supports with the National Housing Fund pursuant to the Housing Act . <Amended by Act No. 6916, May 29, 2003> (3) The head of a local government having jurisdiction over a dam construction area or an area to benefit from a water supply due to a dam construction, and a person scheduled to be entrusted with dam management, may take measures necessary for supports to the livelihood of the persons migrating from the area to be submerged, such as conducting a vocational training program, under the conditions as prescribed by the Presidential Decree. 법령보기 화면  Article 41 (Consolidation Projects for Dam Environs) (1) The head of Si / Gun / Gu having jurisdiction over the environs of a dam which exceeds the standards as prescribed by the Presidential Decree shall undertake a consolidation project (hereinafter referred to as the "consolidation project for dam environs") during a dam construction period in order to promote the economy and improve the living environment of relevant dam environs, paying due regards to the changes in given conditions due to a construction of relevant dam. (2) When the basic plan for a dam corresponding to the standards of paragraph (1) is published, the Mayor/ Do governor having jurisdiction over an area where an intrinsic entity of a dam is located shall promptly devise a plan for the consolidation project for dam environs, and obtain an approval from the Minister of Construction and Transportation: Provided , That in a case of the dam constructed by the Mayor/ Do governor, an approval from the Minister of Construction and Transportation shall not be required. (3) The Mayor/ Do governor shall, when he intends to devise a plan for a consolidation project for dam environs under paragraph (2), consult with an implementer of dam construction project and the head of competent Si / Gun / Gu . (4) Matters necessary for the scope of dam environs under paragraph (1) and the specific details of projects to be executed as a consolidation project for dam environs shall be prescribed by the Presidential Decree. 법령보기 화면  Article 42 (Financial Resources for Consolidation Projects for Dam Environs) (1) A consolidation project for dam environs shall be executed within the limit of standard amount including additional amounts, as computed by the method prescribed by the Presidential Decree, taking account of the basic amount of 30 billion won and reservoir area, total volume of reservoir, submerged households and demands for development pursuant to the local features, etc. <Amended by Act No. 6587, Dec. 31, 2001> (2) Financial resources required for the consolidation project for dam environs shall be borne by an implementer of dam construction project and the head of the competent Si / Gun / Gu . (3) Matters necessary for the specific standards for bearing financial resources required for the consolidation project for dam environs under paragraph (2) and their management shall be prescribed by the Presidential Decree. 법령보기 화면  Article 43 (Support Project for Dam Environs) (1) A dam management agency or a person entrusted with the dam management shall devise a plan for the support project for dam environs (hereinafter referred to as a "plan for the support project for dam environs") every year under the conditions as prescribed by the Presidential Decree, after the completion of a dam construction, in order to increase the income of residents in dam environs and to promote the welfare as prescribed by the Presidential Decree. <Amended by Act No. 6587, Dec. 31, 2001> (2) A dam management agency or a person entrusted with the dam management shall, where he intends to devise a plan for the support project for dam environs under paragraph (1), consult in advance with the head of Si / Gun / Gu having jurisdiction over the dam environs. (3) A person entrusted with the dam management shall, when he has devised the plan for support projects for dam environs under paragraph (1), furnish such plan to the dam management agency. (4) The support project for dam environs shall be executed by a person falling under each of the following subparagraphs, under the conditions as prescribed by the Presidential Decree: 1. A dam management agency or a person entrusted with the dam management; and 2. The head of Si / Gun / Gu having jurisdiction over the dam environs. (5) The scope of areas for which a plan for support project for dam environs under paragraph (1) is to be devised, shall be prescribed by the Presidential Decree. 법령보기 화면  Article 44 (Financial Resources for Support Project for Dam Environs) (1) Financial resources required for the support project for dam environs shall be raised with the funds falling under each of the following subparagraphs: Provided , That the contributions falling under subparagraphs 1 and 2 shall be limited to the dams subject to the support project for dam environs under the provisions of Article 43 : 1. Contributions by a dam management agency or a person holding a right for dam use; 2. Contributions by a tap water business operator from the dams for living and industrial water; 3. Borrowings; and 4. Revenues accruing from the operation of raised funds. (2) A dam management agency, a person holding a right for dam use or a tap water business operator from the dams for living and industrial water shall pay the amount of the ratio falling under each of the following subparagraphs as contributions under paragraph (1) 1 and 2: <Amended by Act No. 6587, Dec. 31, 2001; Act No. 7158, Jan. 29, 2004> 1. Not more than 6/100 of revenues from the sale of power during the year before last year; and 2. Not more than 20/100 of the amount that derives from multiplying the quantity of tap and industrial water sold during the year before last year by a unit price of dam water, which is set by the Korea Water Resources Corporation, during the year before last year. (3) Financial resources raised under paragraph (1) for the support project for dam environs shall be managed by a dam management agency or a person entrusted with the dam management. In this case, a dam management agency or a person entrusted with the dam management shall manage the financial resources for support projects for dam environs under paragraph (1) by dividing them as a separate account. 법령보기 화면  Article 44-2 (Creation of Environment-Friendly Space in Dam Environs) (1) The head of Si / Gun / Gu having jurisdiction over the multi-purpose dam environs under Articles 41 and 43 may, under the conditions as prescribed by the Presidential Decree, execute the projects to create the space for recreation, culture, leisure activities, etc. (hereinafter referred to as the "environment-friendly space"), such as the nature learning place, ecology park, aquatic physical facilities taking advantage of lakes of dam or the neighboring scenery, etc. in order to ensure the development of dam environs, within the scope harmless to the gross amount management of pollution under the relevant Acts, such as the Water Quality Conservation Act , etc. (2) The head of Si / Gun / Gu shall, where he intends to execute the projects to create the environment-friendly space in the dam environs under paragraph (1), consult in advance with the dam management agency. [This Article Added by Act No. 6587, Dec. 31, 2001] 법령보기 화면  Article 44-3 (Preferential Installment of Public Facilities etc.) The head of central administrative agency and the head of competent Si / Gun / Gu may preferentially execute the installment of public facilities such as roads, bridges, tap water, etc. and other projects as prescribed by the Presidential Decree, in order to develop the economy in dam environs and to improve living environments. <Amended by Act No. 7158, Jan. 29, 2004> [This Article Added by Act No. 6587, Dec. 31, 2001] 법령보기 화면  Article 44-4 (Installation of Public Sewerage) (1) Where deemed necessary for an implementation of the details of agreement as referred to in Articles 17 through 22 of the Act on Assessment of Impacts of Works on Environment, Traffic, Disasters, etc. (including the details of re-agreement as referred to in Article 23 of the same Act and the scheme for mitigating impacts as referred to in Article 24 of the same Act ), the implementer of dam construction project may obtain an entrustment of installation of public sewerage from the Public Sewerage Management Agency as referred to in the proviso of Article 8 of the Sewerage Act and install it during the dam construction period. (2) Persons falling under each of the following subparagraphs may bear all or part of the local cost shares, from among the expenses required for installing public sewerage as referred to in paragraph (1): 1. In a case of the multipurpose dams, persons to be granted a right for dam use to utilize the water-storage of dams for living and industrial water; and 2. In a case of the dams for living and industrial water, the tap water business operator. [This Article Added by Act No. 7158, Jan. 29, 2004] Section 4 Supplementary Provisions 법령보기 화면  Article 45 (Authority of Minister of Construction and Transportation, etc.) (1) When the basic plan for a dam construction is published, the dispositions etc. falling under each of the following subparagraphs in the area intended for dam construction and in the river area published under Article 12 (1) and (2) shall be taken by the Minister of Construction and Transportation, notwithstanding the provisions of Article 6 and the provisions of the River Act and the Aggregate Picking Act : Provided , That in the case of a dam to be constructed by the Mayor/ Do governor, the relevant Mayor/ Do governor shall take it, and in case where a dam management is entrusted under Article 15 (2), the dispositions etc. belonging within the scope of such entrustment shall be taken by a person entrusted with a dam management under the conditions as prescribed by the Presidential Decree: <Amended by Act No. 7158, Jan. 29, 2004> 1. Permission for the implementation of a work by a person who is not a management agency under Article 30 of the River Act , and permission, etc. for a river occupancy under Article 33 of the same Act ; 2. Receipt of a report on the transfer of rights and obligations under Article 4 of the River Act to a person granted permission under subparagraph 1; 2-2. Designation of the areas in which such fishing activities are prohibited as are to pollute the rivers by making a camping or cooking, and by using the bait, such as the paste and fish meal, etc. prescribed under subparagraph 4 of Article 71 of the River Act ; 3. Permission for picking the aggregate under Article 22 of the Aggregate Picking Act ; and 4. Dispositions under the following items relating to dispositions etc. under subparagraphs 1 through 3: (a) Disposition taken to cancel permission or suspend a work, etc. under Article 64 or 65 of the River Act ; and (b) Revocation of permission for picking the aggregate or suspension of picking the aggregate under Article 31 of the Aggregate Picking Act , and orders to restore the original state, etc. under Article 33 of the same Act . (2) The Minister of Construction and Transportation, the Mayor/ Do governor or a person entrusted with the dam management shall, where he intends to take the dispositions etc. under paragraph (1), consult in advance with the heads of the related administrative agencies. <Amended by Act No. 7158, Jan. 29, 2004> (3) The Minister of Construction and Transportation or the Mayor/ Do governor shall, where he intends to take dispositions etc. under paragraph (1), hear in advance the opinions of a person entrusted with the dam management. <Amended by Act No. 7158, Jan. 29, 2004> (4) A person entrusted with the dam management may, notwithstanding the provisions of Article 38 of the River Act , collect the occupancy fees or the use fees from a person granted a permission under paragraph (1) 1 through 3, and spend them for the management expenses. 법령보기 화면  Article 46 (Relation with River Act) The River Act shall apply to the matters necessary for a construction and management of a dam, except as otherwise provided in this Act. 법령보기 화면  Article 47 (Hearings) A dam management agency shall, where it intends to take the dispositions falling under each of the following subparagraphs, hold hearings: 1. Orders to transfer a right for dam use under Article 31 (2); and 2. Revocation of a permission under Article 45 (1) 4. 법령보기 화면  Article 48 (Delegation of Authority) The Minister of Construction and Transportation may delegate part of his authority under this Act to the heads of agencies belonging to him or the Mayor/ Do governor under the conditions as prescribed by the Presidential Decree. CHAPTER IV PENAL PROVISIONS 법령보기 화면  Article 49 (Penal Provisions) Officers and employees of a person entrusted with the dam management who have caused damages to the public or obstacles to flood control in contravention of Article 18 shall be punished by imprisonment for not more than five years or by a fine not exceeding thirty million won. 법령보기 화면  Article 50 (Penal Provisions) A person who has performed the acts falling under each subparagraph of Article 6 (1) without obtaining permission under Article 6 (1) or (6) or by obtaining such permission in an illegal manner shall be punished by imprisonment for not more than two years or by a fine not exceeding ten million won. 법령보기 화면  Article 51 (Penal Provisions) A person falling under each of the following subparagraphs shall be punished by imprisonment for not more than six months or by a fine not exceeding three million won: 1. Person who has obstructed or refused the acts under Article 10 (1) without any justifiable reasons; and 2. Person other than administrative agencies, who has performed the acts under Article 10 (1) without obtaining permission or consent under paragraphs (2) through (4) of the same Article. 법령보기 화면  Article 52 (Joint Penal Provisions) If the representative of a corporation or the agent, servant or employee of a corporation or an individual performs the act of violating Articles 49 through 51 in relation to the business of such corporation or individual, the corporation or the individual shall be fined according to the corresponding Article in addition to the punishment of the actor. ADDENDA Article 1 (Enforcement Date) This Act shall enter into force six months after the date of its promulgation. Article 2 (Repeal of Other Act) The Specific Multi-Purpose Dams Act is hereby repealed. Article 3 (General Transitional Measures) Any disposition, process and other acts performed under the previous Specific Multipurpose Dams Act at the time when this Act is enforced shall be deemed to have been performed under the provisions of this Act unless they are in conflict of this Act. Article 4 (Transitional Measures concerning Area Intended for Construction of Multipurpose Dam) (1) An area intended for a construction of multipurpose dam designated and published under Article 5-3 of the previous Specific Multipurpose Dams Act at the time when this Act is enforced shall be deemed to have been designated and published as an area intended for a construction of a dam under Article 5 . (2) A permission granted by the Minister of Construction and Transportation for the acts under each subparagraph of Article 6 (1) in the area intended for a construction of a multipurpose dam under Article 5-3 (3) of the previous Specific Multipurpose Dams Act at the time when this Act is enforced shall be deemed to have been granted by the head of Si / Gun / Gu under Article 6 (1). (3) A person who raises livestock under Article 6 (1) 4 in the area intended for a construction of a multipurpose dam under Article 5-3 (3) of the previous Specific Multipurpose Dams Act at the time when this Act is enforced may continue to do so, notwithstanding the provisions of Article 6 : Provided , That he shall file a report thereon with the head of Si / Gun / Gu within 3 months from the date on which this Act is enforced. Article 5 (Transitional Measures concerning Area Intended for River of Dam) (1) An area intended for a river of dams being constructed for the tap and industrial water under the Acts and subordinate statutes other than the previous Specific Multipurpose Dams Act at the time when this Act is enforced shall be deemed to have been designated and published as an area intended for dam construction under Article 5 . (2) A permission granted by a river management agency for the acts under each subparagraph of Article 6 (1) in the area intended for a river of dams for the tap and industrial water under construction under the Acts and subordinate statutes other than the previous Specific Multipurpose Dams Act at the time when this Act is enforced shall be deemed to have been granted by the head of Si / Gun / Gu under Article 6 (1). (3) A person who is performing the acts newly subjected to a permission under Article 6 (1) in the area intended for a river of a dam for the tap and industrial water under the Acts and subordinate statutes other than the previous Specific Multipurpose Dams Act may continue to do so, notwithstanding the provisions of Article (6): Provided , That he shall file a report thereon with the head of Si / Gun / Gu within 3 months from the date on which this Act is enforced. Article 6 (Transitional Measures concerning Existing Multipurpose Dams) (1) A multipurpose dam constructed under the previous Specific Multipurpose Dams Act at the time when this Act is enforced shall be deemed to have been constructed under this Act. (2) Dam management regulations prepared or approved under Article 32 of the previous Specific Multipurpose Dams Act at the time when this Act is enforced shall be deemed to have been prepared or approved under Article 17 . (3) A right for dam use established and any mortgage created for that purpose under Article 15 (1) of the previous Specific Multipurpose Dams Act at the time when this Act is enforced shall be deemed to have been established and created under Article 24 . (4) A plan devised for support projects for dam environs under Article 42-3 of the previous Specific Multipurpose Dams Act at the time when this Act is enforced shall be deemed to have been devised under Article 43 . Article 7 (Transitional Measures concerning Multipurpose Dam under Construction) (1) A basic plan or an implementation pan devised for multipurpose dams under construction in accordance with Articles 5 and 5-2 of the previous Specific Multipurpose Dams Act at the time when this Act is enforced shall be deemed to have been devised under Articles 7 and 8 : Provided , That where a basic plan under Article 5 of the previous Multipurpose Dams Act has been devised, and where an implementation plan under Article 5-2 of the same Act has yet to be devised, the provisions of Article 5-2 and 5-5 of the previous Specific Multipurpose Dams Act shall apply to a formulation of an implementation plan and a land expropriation with respect to a construction of the relevant dam. (2) In the case of a dam for which an implementation plan has been devised and published under Article 5-2 of the previous Specific Multipurpose Dams Act prior to December 31, 1996 from among the multipurpose dams under construction under the previous Specific Multipurpose Dams Act, the support for those unsettled into resettlement lands under Article 39 shall be governed by Article 42 of the previous Specific Multipurpose Dams Act. (3) With respect to a multipurpose dam under construction in accordance with the previous Specific Multipurpose Dams Act at the time when this Act is enforced, the consolidation project for dam environs under Articles 41 and 42 may be implemented under the conditions as prescribed by the Presidential Decree. Article 8 (Transitional Measures concerning Existing Dam for Tap and Industrial Water) A dam constructed for the tap and industrial water under the Acts and subordinate statutes other than the previous Specific Multipurpose Dams Act at the time when this Act is enforced shall be deemed a dam constructed for the tap and industrial water under this Act. Article 9 (Transitional Measures concerning Dam for Tap and Industrial Water Under Construction) With respect to a dam for the tap and industrial water under construction under the Acts and subordinate statutes other than the previous Specific Multipurpose Dams Act at the time when this Act is enforced, the relevant Acts and subordinate statutes shall apply until a construction of such dam is completed, and with respect to a management after the completion of its construction, this Act shall govern: Provided , That with respect to a dam other than those already in use by obtaining an approval for use prior to the authorization of a completion of construction under relevant Acts and subordinate statutes, the consolidation project for dam environs may be executed by the mutatis mutandis application of Articles 41 and 42 under the conditions as prescribed by the Presidential Decree. Article 10 (Transitional Measures concerning River Area in Dam Construction Area) (1) In applying the provisions of Article 45 with respect to permission, etc. for a river area in an area intended for dam construction or a dam construction area, the river area falling under each of the following subparagraphs shall be deemed a river area in an area intended for dam construction or a dam construction area under this Act: 1. A river area in an area intended for dam construction or in a dam construction area, in which a multipurpose dam was constructed or is under construction under the previous Specific Multipurpose Dams Act; and 2. A river area in which a dam for the tap or industrial water was constructed or is under construction under the Acts and subordinate statutes other than the previous Specific Multipurpose Dams Act. (2) In case where a permission has been granted under the River Act or the Aggregate Picking Act with respect to the acts falling under each subparagraph of Article 45 (1) in the river area under paragraph (1) 2 at the time when this Act is enforced shall be deemed to have been granted under Article 45 (1). Article 11 (Transitional Measures concerning Penal Provisions) In applying the penal provisions to any act committed prior to the enforcement of this Act, the provisions of the previous Specific Multipurpose Dams Act shall apply. Article 12 Omitted. Article 13 (Relation with Other Acts and Subordinate Statutes) Where the previous Specific Multipurpose Dams Act or its provisions are cited by other Acts and subordinate statutes at the time when this Act is enforced, and where this Act has any provisions corresponding to such citation, this Act or the corresponding provisions of this Act shall be deemed to have been cited. ADDENDA<Act No. 6587, Dec. 31, 2001> Article 1 (Enforcement Date) This Act shall enter into force sic months after the date of its promulgation. Article 2 (Application Example to Supports for Those Unsettled into Resettlement Lands) The amended provisions of Article 39 shall apply from the dam for which a basic plan pursuant to Article 7 has been first devised and publicly notified after January 1, 2001. Article 3 (Application Example to Financial Resources for Consolidation Projects for Dam Environs) The amended provisions of Article 42 shall apply from the dam for which a basic plan pursuant to Article 7 has been first devised and publicly notified after January 1, 2001. Article 4 (Transitional Measures for Existing Dams) (1) With respect to the dams which have been completed and publicly notified before March 7, 2000, the consolidation projects for dam environs may be executed by applying mutatis mutandis the provisons of Article 41 and previous Article 42. (2) The expenses to be borne by the implementer of a dam construction project from among the expenses for consolidation projects of dam environs under paragraph (1), shall be borne by the dam management agency, a person holding a right for dam use, or the tap water business operator from the dams for living and industrial water. (3) The amount borne by a person holding a right for dam use under paragraph (2) shall, in applying the provisions of Article 35 (2), be included in the shares of the relevant person to be granted a right for dam use or in the paid amount of the relevant person holding a right for dam use. (4) The dam subject to a consolidation project for dam environs under paragraph (1), devising of plans and time for execution and financial resources shall be prescribed by the Presidential Decree. Article 5 (Application Example to Financial Resources for Support Projects for Dam Environs) The amended provisions of Article 44 shall apply from the portion of the first contributions by a person holding a right for dam use to create the financial resources for a support project for dam environs after January 1, 2003. ADDENDA<Act No. 6655, Feb. 4, 2002> Article 1 (Enforcement Date) This Act shall enter into force on January 1, 2003. Articles 2 through 25 Omitted. ADDENDA<Act No. 6656, Feb. 4, 2002> Article 1 (Enforcement Date) This Act shall enter into force on January 1, 2003. Articles 2 through 12 Omitted. ADDENDA<Act No. 6841, Dec. 30, 2002> Article 1 (Enforcement Date) This Act shall enter into force nine months after the date of its promulgation. Articles 2 through 12 Omitted. ADDENDA<Act No. 6916, May 29, 2003> Article 1 (Enforcement Date) This Act shall enter into force six months after the date of its promulgation. Articles 2 through 13 Omitted. ADDENDA<Act No. 7158, Jan. 29, 2004> (1) (Enforcement Date) This Act shall enter into force six months after the date of its promulgation. (2) (Application Example concerning Financial Resource for Supporting Project to Dam Environs) The amended provisions of Article 44 shall apply from the portion of contributions by the dam management agency, the holder of rights to use the dam or the tap water business operator from dams for living and industrial water, for the first time after an enforcement of this Act, in order to create the financial resource for supporting project to dam environs. (3) (Transitional Measures concerning Dams for Flood Control under Construction) With regard to a construction of dams for flood control under construction as referred to other Acts at the time of enforcement of this Act, the relevant Act shall be applied not later than the time when the relevant construction is completed, notwithstanding the amended provisions of Article 3 , but with regard to the management after the completion of construction, this Act shall govern: Provided , That the consolidation project for dam environs may be implemented by applying mutatis mutandis the provisions of Articles 41 and 42 , under the conditions as prescribed by the Presidential Decree. Last updated : 2009-07-26