ENFORCEMENT DECREE OF THE ACT ON CONTRACTS TO WHICH THE STATE IS A PARTY
11372 · 2006-04-30
ENFORCEMENT DECREE OF THE ACT ON CONTRACTS TO WHICH THE STATE IS A PARTY
Presidential Decree No. 19463, Apr. 28, 2006
Presidential Decree No. 14710, Jul. 6, 1995
Amended by Presidential Decree No. 14973, Apr. 8, 1996
Presidential Decree No. 15186, Dec. 31, 1996
Presidential Decree No. 15433, Jul. 10, 1997
Presidential Decree No. 15582, Dec. 31, 1997
Presidential Decree No. 15581, Dec. 31, 1997
Presidential Decree No. 15614, Feb. 2, 1998
Presidential Decree No. 15661, Feb. 24, 1998
Presidential Decree No. 16308, May 13, 1999
Presidential Decree No. 16448, Jun. 30, 1999
Presidential Decree No. 16548, Sep. 9, 1999
Presidential Decree No. 16682, Dec. 31, 1999
Presidential Decree No. 16919, Jul. 27, 2000
Presidential Decree No. 16943, Aug. 5, 2000
Presidential Decree No. 17019, Dec. 27, 2000
Presidential Decree No. 17344, Aug. 25, 2001
Presidential Decree No. 17546, Mar. 25, 2002
Presidential Decree No. 17585, Apr. 20, 2002
Presidential Decree No. 17688, Jul. 30, 2002
Presidential Decree No. 17791, Dec. 5, 2002
Presidential Decree No. 17824, Dec. 30, 2002
Presidential Decree No. 18155, Dec. 11, 2003
Presidential Decree No. 18359, Apr. 6, 2004
Presidential Decree No. 18666, Dec. 31, 2004
Presidential Decree No. 18903, Jun. 30, 2005
Presidential Decree No. 19035, Sep. 8, 2005
Presidential Decree No. 19321, Feb. 8, 2006
Presidential Decree No. 19463, Apr. 28, 2006
CHAPTER I GENERAL PROVISIONS
법령보기 화면
Article 1 (Purpose)
The purpose of this Decree is to prescribe the matters delegated by the
Act on Contracts to Which the State is a Party
and the matters necessary for its enforcement.
<Amended by Presidential Decree No. 19035, Sep. 8, 2005>
법령보기 화면
Article 2 (Definitions)
For the purpose of this Decree, the definitions of the terms shall be as follows:
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 19035, Sep. 8, 2005>
1.
The term "estimated price" means the price which is calculated pursuant to the provisions of
Article 7
in order to be used as criteria for judging whether or not goods, construction works, services, etc. are objects of international tender under the provisions of
Article 4 of the Act on Contracts to Which the State is a Party
(hereinafter referred to as the "Act") before determining the projected price in concluding the procurement contracts for goods, construction works, services, etc.;
2.
The term "projected price" means the price which is determined in advance and maintained under the provisions of
Article 8
of this Decree in order to be used as criteria for determining the successful bidder and contract amount before proceeding with the tender or the conclusion of contract;
3.
The term "notified amount" means the amount notified by the Minister of Finance and Economy under the provisions of the main sentence of
Article 4 (1) of the Act
; and
4.
The term "performance bond for construction work" means a written undertaking to perform any contractual obligations under a contract for construction work on behalf of the other party if the other party thereto fails to perform contractual obligations for construction work, and guarantees to pay a fixed amount if the guarantor fails to perform any obligation under a guarantee.
법령보기 화면
Article 3 (Relationship with Other Acts and Subordinate Statutes)
(1)
With respect to the contracts to which the State is a party, except as otherwise provided for in other Acts and subordinate statutes, such contracts shall be governed by the provisions of this Decree.
(2)
Matters which are applicable only to government procurement contracts through international tender shall be prescribed separately by the Presidential Decree.
법령보기 화면
Article 4 (Principles of Contract)
The head of each central government agency or any public official who is delegated and commissioned by a central government agency (hereinafter referred to as the "public official in charge of contracts") shall, when concluding the contract, not enter into any special agreements or stipulate any conditions which unfairly limit the contractual profit of the other party to the contract prescribed in the Act, this Decree, and related Acts and subordinate statutes.
법령보기 화면
Article 5 (Notification of Proxy, Taking Partial Charge of Duties, and Appointment of Contract Official)
(1)
If the head of a central government agency has appointed an official who takes charge of the duties regarding a contract (hereinafter referred to as the "contract official") or has caused others to act for the contract official or to take partial charge of the duties of the contract official under the provisions of
Article 6 (1) of the Act
, he shall notify the finance officer and the disbursement officer provided for in the provisions of Article 22 of the Management of the National Funds Act and the Board of Audit and Inspection.
<Amended by Presidential Decree No. 19035, Sep. 8, 2005>
(2)
The public official who takes charge of all of the duties of the public official under the provisions of
Article 6 (1) of the Act
shall be referred to as the "proxy contract official"; the public official who takes charge of a part thereof as the public official in partial charge of contracts; and the public official who acts for the duties of the public official in partial charge of contracts as the "proxy public official in partial charge of contracts", respectively.
(3)
The head of each central government agency, when intending to commission the duties of the public official to the public official under the control of another central government agency under the provisions of
Article 6 (2) of the Act
, shall obtain the approval in advance of the head of the other central government agency with respect to the public official to be entrusted with such duties and the scope of duties which the head of each central government agency intends to entrust to him, and shall notify the Board of Audit and Inspection thereof. In case of appointing the public official who acts for the whole duties or in partial charge of duties of the contract official, the same shall apply.
(4)
The provisions of paragraph (3) of this Article shall apply
mutatis mutandis
to cases where the head of each central government agency commissions the duties regarding the contract falling under the jurisdiction of the head of each central government agency to another government agency under the provisions of
Article 6 (3) of the Act
.
법령보기 화면
Article 6 (Financial Guarantee for Public Official in Charge of Contracts)
(1)
The head of each central government agency shall prescribe and operate matters concerning the financial guarantee for the public official under its control under the provisions of
Article 6 (5) of the Act
.
(2)
Common matters necessary for the financial guarantee under the provisions of paragraph (1) of this Article shall be prescribed by the Minister of Finance and Economy.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
CHAPTER II ESTIMATED PRICE AND PROJECTED PRICE
법령보기 화면
Article 7 (Calculation of Estimated Price)
The head of each central government agency or the public official in charge of contracts shall calculate the estimated price by using the amount, etc. appropriated in the budget as the criteria therefor and it shall be equal to the amount under the criteria falling under any of the following subparagraphs:
1.
In case of a contract for construction work, the amount exclusive of the price for the portion to be furnished as government supplied resources;
2.
In case of a unit cost contract, the amount calculated by multiplying the estimated price of the goods concerned by the estimated volume to be procured;
3.
In case of a contract in which an individual remand for procurement is made in a multiple or divided way, the amount to be chosen from any one of the following items:
(a)
The amount adjusted by the total amount of similar contracts which were concluded for the fiscal year immediately preceding or the twelve months immediately preceding the year when the related contract was concluded by taking into consideration the estimated fluctuating portion of the volume and the amount for the immediately following twelve months; and
(b)
The total amount of the contract which shall be concluded for the same fiscal year or the immediate next twelve months;
4.
In case of a contract in which the total amount of the contract for lease, rent, or purchase by installment of goods or services is not fixed, the amount falling under any of the following items:
(a)
In case of a contract in which the duration of the contact is fixed, the amount to be estimated based on the entire duration of the contract; and
(b)
In case of a contract in which the duration of the contract is not fixed or is vague, the amount calculated by multiplying the estimated payment for one month by 48; and
5.
In case where optional items are included in the targeted goods or services to be procured, the maximum amount including such optional items to be procured.
[This Article Newly Inserted by Presidential Decree No. 15186, Dec. 31, 1996]
법령보기 화면
Article 7-2 (Making Projected Price Available)
(1)
The head of each central government agency or the public official in charge of contracts shall determine the projected price based on the related specifications and the design, etc. with regard to those matters which shall be referred to a public tender or negotiated contract, etc., and shall have them tightly sealed to be made available in advance at the place where the tender will be opened and the price will be negotiated in such a way that the projected price shall not be disclosed.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(2)
The head of each central government agency or the public official in charge of contracts, where he intends to conclude a negotiated contract referred to in
Article 26
(1) 3 and 5, a contract by negotiation referred to in
Article 43
, or a contract based on a rough estimate referred to in
Article 70
, may not determine the projected price, and in case of a tender on a package deal basis or a shop design and construction tender under the provisions of subparagraph 5 of
Article 79
of this Decree, the estimated price may not be determined.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 15614, Feb. 2, 1998; Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17019, Dec. 27, 2000>
법령보기 화면
Article 8 (Methods for Determining Projected Price)
(1)
The projected price shall be determined with respect to the total amount of the items for which the contract is to be concluded:
Provided
, That in case of a contract under which the manufacture, construction work, repair, processing, purchase and sale, supply, and renting are performed continually during a certain fixed period, the estimated price may be determined with respect to the unit cost.
(2)
In case of a construction work which takes some years to perform and under which the contents of the whole business are fixed in accordance with the design, etc. (hereinafter referred to as "long-term continuous construction work") and a contract for the manufacture, etc. of goods which takes some years to perform and under which the contents of the object of the contract are fixed in accordance with the design or the specifications, etc. (hereinafter referred to as the "long-term manufacture, etc. of goods"), the projected price shall be determined within the limits of the total amount of the construction work or the total amount of the manufacture, etc. appropriated in the budget.
법령보기 화면
Article 9 (Criteria for Determination of Projected Price)
(1)
The head of each central government agency or the public official in charge of contracts shall determine the projected price by using the price prescribed in the following subparagraphs as the criteria:
1.
In a case where a suitable transaction is executed, an actual example price of that transaction (in a case where the price is determined under to the provisions of Acts and subordinate statutes, an actual price of that transaction within the limit of the determined price);
2.
In case where there is no suitable actual example price of a transaction due to a newly-developed product or to special characteristics of a contract for special goods such as goods of extraordinary dimension, special construction work, or special services, etc., the price calculated by cost accounting. In this case, the price calculated by cost accounting shall be calculated on the basis of the cost of materials, labor cost, overhead expenses, general management expenses, and profits necessary for goods, construction work, and services, etc., which are the object of a contract;
3.
In case of a construction work, the price approved by the head of a central government agency as the construction work performance cost which is accumulated on the basis of the construction work which has been already performed; and
4.
In case where it is impossible to use the price under the provisions of subparagraphs 1 through 3 above, an appraised value, and an actual example price or an estimated cost of transaction of similar goods, similar construction works, and similar services, etc.
(2)
Notwithstanding the provisions of paragraph (1), where it is intended to make localization of the parts of war materials imported from abroad, the projected prices may be determined on the basis of prices acknowledged by the Administrator of the Defense Acquisition Program by taking account of the said import prices.
<Newly Inserted by Presidential Decree No. 18155, Dec. 11, 2003; Presidential Decree No. 19321, Feb. 8, 2006>
(3)
The head of each central government agency or the public official in charge of contracts, in determining the projected price under the provisions of paragraph (1) of this Article, shall take into consideration the volume of contract, duration of performance, supply and demand situation, contractual conditions or other various conditions.
(4)
Matters necessary for the determination of the projected price, except for the matters prescribed in paragraphs (1) through (3) of this Article shall be determined by the Minister of Finance and Economy.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 18155, Dec. 11, 2003>
CHAPTER III METHOD OF CONTRACTING
법령보기 화면
Article 10 (Methods for Competition)
(1)
Competition under the provisions of
Article 7 of the Act
shall be conducted by method of tender.
(2)
The head of each central government agency or the public official in charge of contracts may, if it is deemed necessary for the sale of movables, put such movables to auction, instead of using the method of tender under the provisions of this Decree.
법령보기 화면
Article 11 (Effectuation of Competitive Tender)
A competitive tender shall be effected by a valid tender in which two or more persons participate.
법령보기 화면
Article 12 (Qualifications to Participate in Competitive Tender)
(1)
The head of each central government agency or the public official in charge of contracts shall allow only those persons who satisfy the necessary conditions referred to in the following subparagraphs to participate in a competitive tender:
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 16548, Sep. 9, 1999>
1.
Deleted;
<by Presidential Decree No. 16548, Sep. 9, 1999>
2.
A person who has obtained a permission, authorization, license, or registration, and has filed a report, etc. if such items are required under the provisions of other Acts and subordinate statutes or who has satisfied certain qualifications if such qualifications are required;
3.
A person who has been judged suitable by a related government agency in cases where investigations, such as a security inspection, are required; and
4.
A person who has satisfied any other necessary conditions prescribed by the Ordinance of the Ministry of Finance and Economy.
(2)
In case where the small and medium enterprise cooperatives under the
Small and Medium Enterprise Cooperatives Act
participate in a competitive tender for the manufacture and purchase of goods (limited to the case of having the cooperative members who satisfy the requirements stipulated in paragraph (1) 2 manufacture or purchase the competent goods), the provisions of paragraph (1) 2 shall not apply:
Provided
, That in case of the participation in a competitive tender for the manufacture and purchase of goods falling under any of the following subparagraphs, the same shall not apply:
<Newly Inserted by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 19035, Sep. 8, 2005>
1.
Goods which correspond to the proper business category of the small and medium enterprises under Article 3 of the Act on the Protetion of the Business Sphere of Small and Medium Enterprises and Promotion of Their Cooperation, and which are solely manufactured by the small and medium enterprises under
Article 2 of the Framework Act on Small and Medium Enterprises
; and
2.
Goods under
Article 4 of the Enforcement Decree of the Promotion of Small and Medium Enterprises and Encouragement of Purchase of Their Products Act
, and which are placed to a competitive tender which is solely for the small and medium enterprises.
법령보기 화면
Article 13 (Prequalification to Participate in Tender)
(1)
The head of each central government agency or the public official in charge of contracts, in the case of construction work as prescribed by the Ordinance of the Ministry of Finance and Economy, may examine the qualifications to participate in the tender in advance with respect to an applicant for prequalification to participate in the tender, and may select eligible persons to participate in the competitive tender. In this case, the result of the selection shall be notified to the eligible persons to be selected.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(2)
The head of each central government agency or the public official in charge of contracts, when intending to examine the qualifications of a participant in a tender under paragraph (1) of this Article, shall determine detailed standards for examination on qualification to participate in the tender in accordance with standards for examination determined by the Minister of Finance and Economy, and shall make them available for inspection by the persons who intend to participate in the tender prior to the tender.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(3)
The head of each central government agency or the public official in charge of contracts, if the related Acts and subordinate statutes prescribe the procedures for selection of a businessman with respect to services, etc., may select the eligible persons to participate in the competitive tender according to such procedures, etc.
법령보기 화면
Article 14 (Tender for Construction Work)
(1)
The head of each central government agency or the public official in charge of contracts shall, in case where he intends to place a construction work to the tender, prepare and keep a design, the quantity specifications of objects by the type of work (hereinafter referred to as the "quantity specifications") and other documents for the tender as prescribed by the Ordinance of the Ministry of Finance and Economy (hereinafter referred to as the "documents for the tender"), and shall make them available for an inspection at the request of the persons who intend to participate in the tender from the date of public notice of the tender to the closing day of tender registration:
Provided
, That in the case of construction work of which the estimated price is 5 billion won or more, and where there exists a request from the persons who intend to participate in the tender, he shall deliver these documents.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(2)
In case of the construction work of which the estimated price is 100 million won or more but less than 5 billion won, the design and the quantity specifications from among the documents for the tender under paragraph (1) shall be delivered to the successful bidder.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(3)
The head of each central government agency or the public official in charge of contracts, when intending to put construction work to the tender, shall make in advance an explanation of construction work site before the closing day of the submission of documents for the tender:
Provided
, That if an explanation on construction work site is deemed unnecessary due to the characteristics of construction work, this shall not apply.
(4)
An explanation of construction work site under paragraph (3) shall be made according to the size of construction work and before the period falling under each of the following subparagraphs counting from the day preceding the closing day of the submission of competent bid documents:
Provided
, That if it is given under
Article 35
(4), such period may be shortened:
<Amended by Presidential Decree No. 15614, Feb. 2, 1998; Presidential Decree No. 16548, Sep. 9, 1999>
1.
Where the estimated price is less than one billion won, 10 days;
2.
Where the estimated price is one billion won or more but less than 5 billion won, 20 days; and
3.
Where the estimated price exceeds 5 billion won, 33 days.
(5)
The head of each central government agency or the public official in charge of contracts shall, in case where he makes an explanation of construction work site under paragraphs (3) and (4) for the case of tender for construction work of which the estimated price is 5 billion won or more, allow only those who have taken part in such explanation of construction work site to participate in the tender.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(6)
The head of each central government agency or the public official in charge of contracts shall, in case of a tender for construction work, have the bidders enter the total bid amount in the bid document, and attach, in the case of construction work of which the estimated price is 5 billion won or more, the specifications calculating the bid amount (hereinafter referred to as the "calculation specifications") which carry a unit cost entered in the quantity specifications distributed under paragraph (1) to the bid document, and where the successful bidder is determined by examining the propriety of bidding prices pursuant to the proviso of
Article 42
(1), he shall have the enterprise subject to an examination of bidding prices submit the basic data on a unit cost computation.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 18155, Dec. 11, 2003>
(7)
The successful bidder shall be required to submit the calculation specifications by the time of presenting a report of starting the work in case of the construction work for which the estimated price is less than 5 billion won, and of that for 5 billion won or more which is put to the second tender under
Article 20
(1).
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(8)
In case of long-term continuous construction work, the whole construction work shall be put to tender.
[This Article Wholly Amended by Presidential Decree No. 15186, Dec. 31, 1996]
법령보기 화면
Article 15 (Restriction on Participation in Tender for Continuous Construction Work)
The head of each central government agency or the public official in charge of contracts, in case of construction work for which a negotiated contract may be concluded with an immediately preceding or current person carrying out construction work under the provisions of
Article 26
(1) 4 (a) through (c) (hereinafter referred to as the "continuous construction work"), shall prevent those persons who have not concluded a negotiated contract participating in a competitive tender related to a related construction work.
[This Article Wholly Amended by Presidential Decree No. 15186, Dec. 31, 1996]
법령보기 화면
Article 16 (Tender for Manufacture and Purchase of Goods, and for Services, etc.)
(1)
The head of each central government agency or the public official in charge of contracts, when intending to put the manufacture and purchase of goods, and services, etc. to the tender, shall prepare and keep documents concerning the tender, and if there are requests by those persons who intend to participate in the tender, shall make those documents available for inspection from the date of the public notice for the tender to the closing day of the registration for the tender:
Provided
, That in the case of a tender for the manufacture and purchase of goods, and for services, etc. of which the estimated price is equal to or exceeds the posted amount, if there are requests by those persons who intend to participate in the tender, the head of each central government agency or the public official in charge of contracts shall deliver those documents to such persons.
(2)
The head of each central government agency or the public official in charge of contracts may, if deemed necessary due to the special characteristics of the contract when carrying out software business under the provisions of subparagraph 3 of
Article 2 of the Software Industry Promotion Act
, put goods and services on a package deal basis for a tender.
<Amended by Presidential Decree No. 17019, Dec. 27, 2000; Presidential Decree No. 19035, Sep. 8, 2005>
(3)
The head of each central government agency or the public official in charge of contracts shall, in case where he puts the goods and services for a tender on a package deal under paragraph (2), choose a method from among the methods of deciding a successful bidder under
Articles 42
(1) and
43
which are deemed suitable in view of the characteristics of the contract objects, and clarify it at the time of public notice for the tender.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(4)
A tender for the manufacture and purchase of goods and for services, etc. shall be based on the bid documents in the forms prescribed by the Ordinance of the Ministry of Finance and Economy, and the bid amount shall be indicated by the total amount in case of a tender conducted with respect to the total amount, and by the unit cost in case of a tender conducted with respect to the unit cost, respectively.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(5)
The provisions of
Article 14
(8) of this Decree shall apply
mutatis mutandis
to the long-term manufacture of goods, etc.
[This Article Wholly Amended by Presidential Decree No. 15186, Dec. 31, 1996]
법령보기 화면
Article 17 (Tender for Large Quantity of Goods)
(1)
A general competitive tender may, when selling off a large quantity of goods, be conducted for the quantity of goods which a consumer desires to purchase and for the unit cost of that quantity of goods within the limits of the quantity of goods which will be sold.
(2)
A general competitive tender may, when manufacturing and purchasing a large quantity of required goods, be conducted for the quantity of goods which a supplier desires to supply and for the unit cost of that quantity of goods within the limits of the quantity of goods which will be required.
(3)
The scope of the goods for a competitive tender in a desired quantity under paragraphs (1) and (2) of this Article shall be prescribed by the Ordinance of the Ministry of Finance and Economy.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 18 (Tender by Dual Stage Competition, etc.)
(1)
The head of each central government agency or the public official in charge of contracts, if it is difficult to prepare appropriate specifications in advance or it is deemed necessary in view of the special characteristics of the contract in case of a contract for the manufacture and purchase of goods and for services, may conduct a tender for the price of goods after conducting first a tender for the specifications or the technology.
(2)
In a case of paragraph (1) of this Article, the qualifications to participate in a tender for the price of goods shall be granted only to those persons who have been confirmed as eligible persons after opening the tender for the specifications or the technology.
(3)
The head of each central government agency or the public official in charge of contracts, if it is deemed necessary in view of the special characteristics of the contract, notwithstanding the provisions of paragraphs (1) and (2) of this Article, may conduct a tender for the specifications and the price of the goods or a tender for the technology and the price of the goods at the same time. In this case, a tender for the price of goods shall be open only to those persons who have been confirmed as an eligible person after opening the tender for the specifications or the tender for the technology.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
(4)
The head of each central government agency, when intending to perform a tender under the provisions of paragraphs (1) through (3) of his Article, shall determine the criteria and procedures for evaluation before the tender, and shall make them avaliable for inspection by the person who intends to participate in the tender.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
(5)
Where it is impossible to determine a successful bidder as a result of opening tenders for the price of goods under paragraph (3), and where there are two or more eligible persons for specifications or technology, the head of each central government agency or the public official in charge of contracts may have eligible persons for specifications or technology submit tenders for the price of goods anew.
<Newly Inserted by Presidential Decree No. 15614, Feb. 2, 1998>
법령보기 화면
Article 19 (Incidental Tender)
(1)
The head of each central government agency or the public official in charge of contracts shall, when he intends to place a construction work corresponding to the standards as provided by the Ordinance of the Ministry of Finance and Economy to the tender, make the bidders enter in the calculation specifications the matters concerning the subcontracts, such as the portions to be subcontracted, amount of subcontract and subcontractors, from among the construction works constituting the tender amount and to submit it:
Provided
, That the same shall not apply to a case falling under any of the following subparagraphs:
1.
The case of re-tender under
Article 20
(1);
2.
The case of an urgent construction work tender;
3.
The case of a construction work tender for which there exists no specialized constructor to make a subcontract, due to a necessity of special technology or the local features, etc.; and
4.
The case of a construction work tender for which it is deemed to be inadequate to make any subcontract, in view of the performance of obligations following the defects of construction works, process control, or the needs for security, etc.
(2)
In the case of making the bidders enter the matters concerning the subcontract under paragraph (1), if it is a long-term continued work, an entry of the tender amount for total construction works shall be made:
Provided
, That where deemed necessary in view of the implementation period of works, an entry may be made, limited to the tender amount for the works to be implemented during the first year.
(3)
Procedures for the incidental tender under paragraph (1) and other necessary matters shall be stipulated and publicly notified by the Minister of Finance and Economy.
[This Article Newly Inserted by Presidential Decree No. 17546, Mar. 25, 2002]
법령보기 화면
Article 20 (Re-Tender and Tender by Second Public Notice)
(1)
If there are no two or more valid bidders or there is no successful bidder in the competitive tender, a re-tender may be conducted at the same place as that of the competitive tender. In this case, the re-tender shall not be considered as a new tender, and no limitations on the bidders or on the number of tenders shall be made.
(2)
If there is no bidder or successful bidder, or if a successful bidder does not conclude a contract, a tender by second public notice may be conducted.
(3)
At the time of a re-tender or a tender by second public notice referred to in paragraph (1) or (2), no changes in prices or other conditions determined at the first tender, except for the time limit, shall be made.
<Newly Inserted by Presidential Decree No. 15614, Feb. 2, 1998>
법령보기 화면
Article 21 (Contract to be Subject to Limited Competitive Tender, and Limited Matters, etc.)
(1)
The cases where qualifications of a participant in the competition may be limited under the proviso of
Article 7 of the Act
and the limited matters are specified in the following subparagraphs, and the criteria for limitation of such limited matters as referred to in subparagraphs 1 through 6 and 9 of this Article shall be prescribed by the Ordinance of the Ministry of Finance and Economy:
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 15433, Jul. 10, 1997; Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 19035, Sep. 8, 2005>
1.
In case of a contract for construction work the amount of which is determined by the Ordinance of the Ministry of Finance and Economy, the maximum amount to be contracted, the construction capabilities or the past records of construction performances which belong to the same type as the construction work concerned;
2.
In case of a contract for construction work in which a special technology or a special method of construction is required, the status of possessing the technology necessary for the performance of the construction work concerned, or the past records of construction performances which belong to the same type as the construction work concerned;
3.
In case of a contract for manufacture of goods in which special facilities or a special technology is required, the status of possessing the facilities and technology necessary for the manufacture of the goods concerned, or the past records of manufacture of goods which belong to the same type as the goods concerned;
4.
In case of a contract for purchase of goods in which a special capacity or quality is required, the capability to deliver the goods concerned;
5.
In case of a contract for service in which a special technology is required, the status of possessing the technology necessary for the performance of the service concerned, or the past records of performance of a service which belongs to the same type as the service concerned;
6.
In case of a contract for which the estimated price is less than the amount as prescribed by the Ordinance of the Ministry of Finance and Economy, the location of the principal place of business;
7.
In case where the contract for construction work is concluded on the basis of limitations under
Article 22
, the criteria for such limitations;
8.
Deleted;
<by Presidential Decree No. 19035, Sep. 8, 2005>
9.
In case where the head of each central government agency or the public official in charge of contracts specially deems it necessary to avoid the event of a failure to perform the contract, the financial status of a participant in the competition; and
10.
In case of the manufacture and purchase of any goods or service whose price falls short of the notified amount (excluding any engineering project under subparagraph 4 of
Article 2 of the Engineering Technology Promotion Act
and any construction technology services under subparagraph 3 of
Article 2 of the Construction Technology Management Act
), the small and medium enterpriser under
Article 2 of the Framework Act on Small and Medium Enterprises
.
(2)
The head of each central government agency or the public official in charge of contracts shall, when intending to limit the qualification of participants in the competition under paragraph (1) of this Article, specify the limited matters and the criteria for limitation in the public notice of the tender.
(3)
The head of each central government agency or the public official in charge of contracts may, when it is deemed necessary for construction work in which the qualification of participants in the competition is limited under the provisions of paragraph (1) 6 of this Article, substitute public notice of the tender under the provisions of paragraph (2) of this Article by notifying the persons eligible to participate in the tender of the matters prescribed in each subparagraph of
Article 36
under the provisions of the Ordinance of the Ministry of Finance and Economy.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 22 (Tender by Limitation according to Character and Size of Construction Work)
(1)
The head of each central government agency or the public official in charge of contracts may cause the persons eligible to participate in the tender to apply for registration by categorizing the construction work according to character and size thereof, by determining the criteria for limitation of competition corresponding to each category, and by notifying them publicly by means of publishing the criteria in advance in the information processing apparatus as designated and publicly announced by the Minister of Finance and Economy (hereinafter referred to as the "designated information processing apparatus").
<Amended by Presidential Decree No. 17688, Jul. 30, 2002>
(2)
The head of each central government agency or the public official in charge of contracts may, when receiving an application for registration under the provisions of paragraph (1) of this Article, make the registration by examining the application for registration, by registering persons eligible to participate in the tender after selecting persons eligible to participate in the tender according to the character and size of construction work, and by notifying those eligible persons of the matters prescribed in each subparagraph of
Article 36
every time the tender for construction work is conducted to enable them to participate in the tender.
(3)
The head of each central government agency shall, when intending to determine the criteria for limitation of the competition under the provisions of paragraph (1) of this Article, consult with the Minister of Finance and Economy.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 23 (Contract Subject to Nominated Competitive Tender)
(1)
Cases which may be put to a nominated competitive tender under the proviso of
Article 7 of the Act
shall be as follows:
<Amended by Presidential Decree No. 15614, Feb. 2, 1998; Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17019, Dec. 27, 2000; Presidential Decree No. 18155, Dec. 11, 2003; Presidential Decree No. 19035, Sep. 8, 2005>
1.
A case where not more than 10 persons are expected to participate in the tender since it is difficult to accomplish the purpose of contract judging by the character and purpose of the contract unless the prospective participants possess special facilities, technology, materials, goods, or past records of performances;
2.
A case where any construction work (excluding any specialized work) under the
Framework Act on the Construction Industry
is done with its estimated price not exceeding 300 million, any specialized work under the
Framework Act on the Construction Industry
is done with its estimated price not exceeding 100 million won, any other construction work under other construction-related Acts and subordinate statutes is done with its estimated price not exceeding 100 million won, or any goods are manufactured with their estimated price not exceeding 100 million won;
3.
A case of selling or purchasing properties of which the estimated price is thirty million won or less;
4.
A case of leasing out or hiring articles of which the total amount of the estimated rental charge for hiring or leasing is thirty million won or less;
5.
A case of a contract, other than subcontracts for construction work or manufacture and contracts for selling properties or for leasing out or hiring articles, of which the estimated price is thirty million won or less;
6.
A case of purchasing those articles which bear a certified standard mark under
Article 11 of the Industrial Standardization Act
or those goods which have been manufactured by a person who has obtained certification of a quality management system under
Article 7 of the Quality Management and Safety Control of Industrial Products Act
;
7.
Deleted;
<by Presidential Decree No. 16548, Sep. 9, 1999>
8.
A case where the negotiated contract may be concluded under the proviso of
Article 7 of the Act
and
Article 26
of this Decree;
9.
A case where any recycled goods which conform to the standards under
Article 33 of the Act on the Promotion of Saving and Recycling of Resources
and for which a quality certification under Article 28 (3) of the Enforcement Decree of the Industrial Development Act is granted or any other goods for which an environmental mark certification is granted under
Article 20 of the Development of and Support for Environmental Technology Act
are manufactured or purchased; and
10.
Deleted.
<by Presidential Decree No. 19035, Sep. 8, 2005>
(2)
Where public officials who are entrusted by the head of each central government agency conclude a contract by nominated competitive tender under the provisions of paragraph (1) 1 of this Article, they shall report the contents to the head of the central government agency to which they belong, and the head of each central government agency shall notify the Board of Audit and Inspection thereof.
<Amended by Presidential Decree No. 15614, Feb. 2, 1998>
법령보기 화면
Article 24 (Nomination of Prospective Participants in Nominated Competitive Tender)
(1)
The head of each central government agency or the public official in charge of contracts shall, where he intends to conduct a nominated competitive tender under the provisions of
Article 23
, nominate five or more prospective participants in the tender, and thereafter two or more prospective participants shall apply for participation in the tender:
Provided
, That if the prospective participants to be nominated are less than five persons, he shall nominate all of them.
<Amended by Presidential Decree No. 15614, Feb. 2, 1998>
(2)
In case of paragraph (1) of this Article, the matters referred to in each subparagraph of
Article 36
shall be announced to each prospective participant in the tender.
(3)
The head of each central government agency or the public official in charge of contracts shall, where he intends to nominate prospective participants in the tender under the provisions of paragraph (1) of this Article, notify them thereof under the provisions of the Ordinance of the Ministry of Finance and Economy, and thereafter shall confirm whether the prospective participants will participate in the tender.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 25 (Plural Competition of Similar Goods)
The head of each central government agency or the public official in charge of contracts may, when intending to designate and purchase goods meeting certain requirements for quality, performance, or efficiency, etc. from among similar goods having a different quality, performance, or efficiency, etc., put them to a plural competition. In this case, the bidder presenting the lowest rate of the tendered amount for the projected price set for such similar goods shall become the successful bidder.
법령보기 화면
Article 26 (Cases Allowing Negotiated Contract)
(1)
Cases which allow a negotiated contract to be concluded under the proviso of
Article 7 of the Act
shall be as follows:
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 15614, Feb. 2, 1998; Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 16682, Dec. 31, 1999; Presidential Decree No. 16919, Jul. 27, 2000; Presidential Decree No. 17019, Dec. 27, 2000; Presidential
Decree No. 18155, Dec. 11, 2003; Presidential Decree No. 18359, Apr. 6, 2004; Presidential Decree No. 18903, Jun. 30, 2005; Presidential Decree No. 19035, Sep. 8, 2005; Presidential Decree No. 19321, Feb. 8, 2006>
1.
Cases where there is no time to conduct a competitive tender due to natural disasters, movement of military forces for military operations, urgent events, emergency disasters such as flood damage requiring urgent restoration, sharp rises in raw materials prices, or others similar thereto;
2.
Cases where it is necessary to conduct the activities of State agencies in secret;
3.
Cases where the contract is concluded with other State agencies and local governments;
4.
Cases falling under one of the following items where it is impossible to compete due to the technology and service of a particular person, or a particular location, structure, quality, performance, efficiency, etc.:
(a)
Cases where the contract is concluded with a person having carried out or carrying out construction work at the present time or at the time immediately preceding the present time for whom it is difficult to specify liability for the future defects of the facilities built under construction work;
(b)
Cases where the contract is concluded with a person carrying out construction work at the present time since two or more contractors shall not carry out the construction work in the same place due to disorderly working conditions, etc.;
(c)
Cases where the contract is concluded with a person having carried out or carrying out construction work at the present time or at the time immediately preceding the present time for finishing the work;
(d)
Cases where it is actually impossible to conduct a competitive tender since the construction work is made in a special region such as a region adjacent to an enemy;
(e)
Cases where it is actually impossible to conduct a competitive tender, such as a construction work by a patented construction method, a new technology as designated and noticed under the provisions of
Article 18 of the Construction Technology Management Act
or a new electric technology under
Article 6-2 of the Electric echnology Management Act
(limited to that within the protection period designated under the same Act);
(f)
Cases where a person manufacturing or supplying related articles directly installs, assembles, or maintains them;
(g)
Cases where articles are manufactured or purchased which are patented or registered as a utility model or as a design and where there exist no appropriate substitutes or fungibles therefor;
(h)
Cases where it is impossible to accomplish the purpose of business by having other articles manufactured or purchasing other articles because the said articles are manufactured or held by only one person;
(i)
Cases where parts are purchased for foreign capital facilities, machines, and equipment which may not be substituted by domestic goods but have been already introduced;
(j)
Cases where a service contract is concluded for the examination, design, supervision, special surveying, training, and facilities management which require the technology of a particular person or for academic research with a particular person or where a design service contract is concluded with a person who has won the prize in an open contest for the design;
(k)
Cases where real estate, such as land and buildings, of a particular person is purchased, or where the properties are leased out to or hired from a particular person; and
(l)
Cases where articles are procured to exchange for parts or to expand facilities already procured and their compatibility is lost if they are manufactured or supplied by others than the person who has manufactured and supplied them;
5.
Cases where the construction work (excluding a specialized work) under the
Framework Act on the Construction Industry
with its estimated price not exceeding 100 million won, the specialized work under the
Framework Act on the Construction Industry
with its estimated price not exceeding 70 million won, or other construction work under construction work-related Acts and subordinate statutes with its estimated price not exceeding 50 million won is made, or where the manufacture and purchase of articles with their estimated price (in the case of hiring or leasing out articles, the basis is the annual amount or the total amount) not exceeding 30 million won, services, and other contracts are made;
6.
Cases where a particular entrepreneur is caused to purchase or manufacture special articles and properties, etc. under the provisions of other Acts such as those falling under any of the following items:
(a)
Cases where any goods whose standard mark is certified under
Article 11 of the Industrial Standardization Act
, any articles that are manufactured by anyone who obtains a quality management system certification under
Article 7 of the Quality Management and Safety Control of Industrial Products Act
, any goods that bear a quality certification granted under
Article 11-2 of the Promotion of Small and Medium Enterprises and Encouragement of Purchase of Their Products Act
, any goods that bear an environmental mark certification granted under
Article 20 of the Development of and Support for Environmental Technology Act
, or any recycled goods that conform to the standards under
Article 33 of the Act on the Promotion of Saving and Recycling of Resources
, bear a quality certification granted under Article 28 (3) of the Enforcement Decree of the Industrial Development Act, are purchased from their producer who is only one person, and where any recycled goods that conform to the standards under
Article 33 of the Act on the Promotion of Saving and Recycling of Resources
and bear a quality certification granted under Article 28 (3) of the Enforcement Decree of the Industrial Development Act are manufactured and then immediately used on a construction site for the construction work, which makes it difficult to distinguish the manufacture of such goods from the construction work;
(b)
Cases where a collective negotiated contract is concluded under
Article 9 of the Promotion of Small and Medium Enterprises and Encouragement of Purchase of Their Products Act
;
(c)
Cases where defense equipment and materials are manufactured by an enterprise in the defense industry and they are purchased from the said enterprise under the Defense Acquisition Program Act;
(d)
Cases of the manufacture and purchase of articles which are directly produced by the factories located in an agricultural and industrial complex (including a
Saemaul
factory) under the Rearrangement of Agricultural and Fishing Villages Act;
(e)
Cases of the purchase of articles which are directly produced by the factories located in a special support region for the local small and medium enterprises under
Article 50 of the Balanced Regional Development and Support for Local Small and Medium Enterprises Act
; and
(f)
Cases of the manufacture and purchase from the producers of arcles which are notified as the subject of the preferential purchase by the Administrator of the Small and Medium Business Administration under
Article 14 (2) of the Enforcement Decree of the Promotion of Small and Medium Enterprises and Encouragement of Purchase of Their Products Act
;
7.
Cases where a contract is required to be concluded with a person with a special relationship, a local resident, the producer of particular articles or where other reasons similar thereto exist such as those falling under each of the following items:
(a)
Cases of disposing of certain properties by selling or leasing them for valuable consideration to a person to whom those properties may be transferred or rented free of charge under the provisions of other Acts;
(b)
Cases of selling state-owned materials for reconstruction to persons who have suffered damage due to the occurrence of an emergency or disaster;
(c)
Cases of selling or leasing out a discarded official residence to a person with a special relationship or leasing out forests and fields to a person with a special relationship;
(d)
Cases of selling materials necessary for developing an overseas market to the person who has developed the overseas market;
(e)
Cases of concluding the contract for construction work of which the estimated price is less than twenty million won or the contract for cultivating young trees of which the estimated price is less than twenty million won directly with local residents or representatives thereof designated by the Ordinance of the Ministry of Finance and Economy if the majority of the local residents need to participate therein for the development of a local community;
(f)
Cases of causing a producer to manufacture the articles directly produced by a welfare factory of a self-support collective village by persons with distinguished services to the state as designated by the Minister of Patriots and Veterans Affairs or purchasing them from the producer thereof, or selling or leasing out such articles directly to the producer;
(g)
Cases of causing a producer to manufacture the products based on new technology or products selected for development as recognized or designated by the competent Minister (including a person who has been entrusted by the competent Minister) in order to promote the localization of the products or purchasing them from the producer thereof within two years after confirming that the development thereof has been completed; and
(h)
Cases where the Administrator of the Defense Acquisition Program causes an enterprise engaged in research and development of standardized products for military use or an enterprise mobilized in time of war under the
Emergency Resources Management Act
to manufacture standardized products for military use or purchases such products from them (in the case of an enterprise mobilized in time of war, it is limited to standardized products for military use as designated by the Administrator of the Defense Acquisition Program); and
8.
Cases where other unavoidable reasons in view of the purpose and character of the contract exist as follows:
(a)
Cases of purchasing materials used by overseas diplomatic and consular missions in an overseas location;
(b)
Cases where it is deemed disadvantageous to make any person process, load and unload, transport, or take custody of products under a competitive tender;
(c)
Cases of concluding a contract for the manufacture, purchase, or service of products with juristic persons established under special Acts who produce such products directly by carrying on a line of businesses prescribed by the relevant special Act, or selling or leasing out products directly to such juristic persons;
(d)
Cases of concluding a contract for the manufacture, purchase, or services of products which are directly produced by the juristic persons established under the
Social Welfare Services Act
, or selling or leasing out the goods directly to those persons;
(e)
Cases of concluding a contract for the manufacture, purchase or services of articles which are directly produced by an association which is composed of wounded persons from among associations established under Article 1 of the Act on the Establishment of Associations by Persons, etc. of Distinguished Services to the State, or selling or leasing out the goods directly to those associations;
(f)
Cases of concluding a contract for the manufacture, purchase, or service of products with an organization for the welfare of disabled persons or other organizations for disabled persons established under
Article 53 of the Welfare of Disabled Persons Act
from among the incorporated associations established under the provisions of
Article 32 of the Civil Act
or selling or leasing out products directly to those organizations;
(g)
Cases of manufacturing and purchasing the products are manufactured directly by UNICEF, Korea Commission established under the provisions of
Article 32 of the Civil Act
; and
(h)
Cases of concluding a contract for a relevant project with persons who may be entrusted with a national project or may carry out such project vicariously under the provisions of other Acts and subordinate statutes.
(2)
Where the public official in charge of contracts concludes a negotiated contract under the provisions of paragraphs (1) 4 and 7 (a) through (e), (g), (h), paragraph (1) 8 (b), (c) and (e) through (h) of this Article, he shall report the contents to the head of the central government agency to which the public official in charge of contracts belongs, and the head of such central government agency shall notify the Board of Audit and Inspection of the contract referred to in paragraph (1) 4 from among reported matters.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 15614, Feb. 2, 1998>
법령보기 화면
Article 27 (Tender by Second Public Notice and Negotiated Contract)
(1)
Where it falls under any of the following subparagraphs as a result of a sale by competitive tender, a negotiated contract may be made:
1.
Where there is only one bidder, though a competitive tender has been conducted under
Article 10
, and it is deemed evident that there is only one person qualified to participate in the tender referred to in
Article 12
even if a tender by a second public notice is conducted under
Article 20
(2); and
2.
Where there is no bidder or successful bidder for a tender conducted by second public notice under the provisions of
Article 20
(2).
(2)
In case of a negotiated contract referred to in paragraph (1), no changes in prices and other conditions determined at the first sale by tender shall be made except for the bid bond and time limit.
[This Article Wholly Amended by Presidential Decree No. 15614, Feb. 2, 1998]
법령보기 화면
Article 28 (Negotiated Contract When Successful Bidder Fails to Conclude Contract)
(1)
When a successful bidder fails to conclude the contract, a negotiated contract may be concluded in an amount not less than the lowest tender price:
Provided
, That the price and other conditions determined for the first tender shall not be modified except for the time limit.
(2)
The provisions of paragraph (1) of this Article shall apply
mutatis mutandis
to cases where a successful bidder does not commence to carry out the contract within the prescribed date after concluding the contract or where the contract is cancelled or terminated because the successful bidder fails to fulfill contractual obligations after commencing to carry out the contract.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
법령보기 화면
Article 29 (Divided Negotiated Contract)
In the case of
Articles 26
(1) 6 (c),
27
, and
28
, only if it is possible to divide and calculate the estimated price or the lowest tender price, the contract may be concluded by dividing it among several persons in an amount not less than the estimated price or the lowest tender price.
법령보기 화면
Article 30 (Determination of Price by Estimate)
(1)
If the head of each central government agency or any public official in charge of contracts is to conclude a negotiated contract, he shall receive written estimates from two or more persons:
Provided
, That in the case of a contract under the provisions of the
Articles 26
(1) 4, 6 (a) and (b),
27
, and
28
or in the case of a contract the amount of which is twenty million won or less, the negotiated contract may be concluded by a written estimate received from one person.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 17019, Dec. 27, 2000>
(2)
In the application of the provisions of the main sentence of paragraph (1), the head of each central government agency or the public official in charge of contracts shall allow all persons who intend to submit their written estimates to submit them.
<Newly Inserted by Presidential Decree No. 19035, Sep. 8, 2005>
(3)
If the estimated price stated in a written estimate submitted under paragraph (1) is beyond the scope of the projected price, the contract amount shall be determined through a written estimate to be newly submitted.
<Newly Inserted by Presidential Decree No. 17019, Dec. 27, 2000>
(4)
Notwithstanding the provisions of paragraphs (1) and (3) of this Article, in those cases prescribed by the Ordinance of the Ministry of Finance and Economy, a submission of a written estimate may be dispensed with.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17019, Dec. 27, 2000; Presidential Decree No. 19035, Sep. 8, 2005>
법령보기 화면
Article 31 (Contract Amount of Negotiated Contract for Continuous Construction Work)
In case of continuous construction work, the contract amount, after the relevant construction work has been completed, shall not exceed the amount calculated by multiplying the estimated price by the ratio at which the first construction work has been awarded (referring to the ratio of the successful tender price or the contracted price of the first construction work to the estimated price):
Provided
, That in cases determined by the Minister of Finance and Economy, this shall not apply.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 32 (Application Mutatis Mutandis to Competitive Contracts)
The provisions of
Article 12
shall apply
mutatis mutandis
to the case of a negotiated contract:
Provided
, That in the case of
Article 26
(1) 6 (b), this shall not apply.
CHAPTER IV PROCEDURE FOR TENDER AND SUCCESSFUL TENDER
법령보기 화면
Article 33 (Public Notice of Tender)
(1)
When a competition is to be conducted by method of tender, this shall be notified publicly by utilizing the designated information processing apparatus, unless otherwise prescribed by this Decree:
Provided
, That it may, if deemed necessary, be notified publicly by means of concurrently publishing in the daily newspapers.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17688, Jul. 30, 2002>
(2)
Deleted.
<by Presidential Decree No. 17688, Jul. 30, 2002>
법령보기 화면
Article 34 (Notification for Participation in Tender)
The head of each central government agency or the public official in charge of contracts, if necessary for the maintenance of the security of the State, notwithstanding the provisions of
Article 33
, may give notification of the matters referred to in
Article 36
to the persons eligible to participate in the tender under the provisions of the Ordinance of the Ministry of Finance and Economy and cause them to submit an application for participation in the tender. In this case, with respect to the time for the notification, the provisions of
Article 35
shall apply
mutatis mutandis
.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 35 (Time for Public Notice of Tender)
(1)
Public notice of tender shall be given at least ten days in advance to be calculated from the day preceding the closing day for submission of the tender documents before the tender is conducted.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
(2)
In case of a tender for construction work, notwithstanding the provisions of paragraph (1) of this Article, the public notice of tender shall be given at least seven days in advance to be calculated from the day preceding the day for explanation of the construction work site under the provisions of
Article 14
(4), before the tender is conducted:
Provided
, That in case of a tender for construction work referred to in
Article 13
, the public notice of tender shall be given at least thirty days in advance to be calculated from the date preceding the date for explanation of the construction work site.
<Newly Inserted by Presidential Decree No. 15186, Dec. 31, 1996>
(3)
When an explanation of the construction work site is not conducted under the proviso of
Article 14
(3) in the case of a tender for construction work, notwithstanding the provisions of paragraphs (1) and (2) of this Article, the public notice of tender shall be given at least as many days as prescribed in the following subparagraphs in advance to be calculated from the day preceding the closing day for the submission of the tender documents before the tender is conducted:
<Newly Inserted by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 16548, Sep. 9, 1999>
1.
In case where the estimated price is less than one billion won, 10 days;
2.
In case where the estimated price is one billion won or more, but less than five billion won, 20 days; and
3.
In case where the estimated price is five billion won or more, 40 days.
(4)
Notwithstanding the provisions of paragraphs (1) through (3) of this Article, in case of an emergency and of a tender by second public notice under the provisions of
Article 20
(2), the public notice of tender may be given at least five days in advance to be calculated from the day preceding the closing day for the submission of the tender documents.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
법령보기 화면
Article 36 (Contents of Public Notice for Tender)
Matters prescribed in each of the following subparagraphs shall be specified in the public notice of a tender:
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17546, Mar. 25, 2002; Presidential Decree No. 17688, Jul. 30, 2002>
1.
Matters to be put to the tender;
2.
Place, and date and time of the tender or the opening of the tender;
3.
In case of a tender for construction work, matters concerning the place, and date and time of an explanation of the construction work site, qualifications to participate in the tender, and whether it is obligatory to participate in the tender;
4.
Matters concerning the qualifications for participants in the tender;
5.
Matters concerning a bid bond, and the reversion thereof to the National Treasury;
6.
Methods to decide a successful tender (in case where the successful bidder is decided under the text of
Article 42
(1), the date of submission of documents necessary for deciding the successful bidder and the expected date of notification of the successful bidder shall be included);
7.
Commencement day and completion day of the contract;
8.
Place where the contractual conditions are publicly notified;
9.
Matters concerning the invalidity of a tender under the provisions of
Article 39
(4);
10.
Place where the documents for the tender can be made available for inspection, or delivery as well as the cost for delivery thereof;
11.
Address, etc. of an agency from which additional information may be obtained;
12.
In case of permitting the tender by mail, etc., the address to which the notice to that effect and the documents for the tender to be sent;
12-2. In case of allowing one to submit a tender document by utilizing the designated information processing apparatus under the provisions of
Article 39
(2), the contents thereof;
13.
In case of permitting a joint contract under the provisions of
Article 72
, the fact that a joint contract may be concluded (in case of a joint contract under the provisions of
Article 72
(3) and (4), including matters concerning the limitations on qualifications of the members of a joint supply and demand organization) and methods of performing the joint contract;
14.
In case of an incidental tender under
Article 19
, its purport;
15.
In case of a tender under the provisions of
Article 78
, matters concerning a tender by an alternative proposal or on a package deal; and
16.
Other necessary matters concerning the tender.
[This Article Wholly Amended by Presidential Decree No. 15186, Dec. 31, 1996]
법령보기 화면
Article 37 (Bid Bond)
(1)
The bid bond under the provisions of
Article 9 of the Act
shall be 5/100 or more of the tendered amount (in case of a tender by the unit cost, the amount calculated by multiplying the unit cost by the total estimated quantity of the tender).
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
(2)
The bid bond shall be paid in cash (including a bank check issued by a postal service office or by a financial institution governed by the
Banking Act
; hereinafter the same shall apply) or with a certificate of guarantee prescribed in each of the following subparagraphs:
<Amended by Presidential Decree No. 14973, Apr. 8, 1996; Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 15433, Jul. 10, 1997; Presidential Decree Nos. 15581 & 15582, Dec. 31, 1997; Presidential Decree No. 15614, Feb. 2, 1998; Presidential Decree No. 16308, May 13, 1999; Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 16943, Aug. 5, 2000; Presidential Decree No. 17585, Apr. 20, 2002; Presidential Decree No. 17791, Dec. 5, 2002; Presidential Decree No. 18155, Dec. 11, 2003; Presidential Decree No. 18666, Dec. 31, 2004; Presidential Decree No. 19035, Sep. 8, 2005>
1.
Written payment guarantee issued by the financial institutions under the provisions of
Article 135 of the Enforcement Decree of the Budget and Accounts Act
(hereinafter referred to as "financial institutions") and foreign financial institutions under the
Banking Act
;
2.
Securities referred to in
Article 84-16 of the Enforcement Decree of the Securities and Exchange Act
;
3.
Policy of guarantee insurance issued by an insurance company under the
Insurance Business Act
;
4.
Written guarantee for the payment of the debt amount, etc. that is each issued by the mutual aid association under the
Framework Act on the Construction Industry
, the Electric Contractors' Financial Cooperative under the Electrical Construction Mutual Aid Association Act, the Korea Credit Guarantee Fund under the
Credit Guarantee Fund Act
, the Korea Technology Credit Guarantee Fund under the
Korea Technology Credit Guarantee Fund Act
, the Information and Communication Financial Cooperative under the
Information and Communication Work Business Act
, the Engineering Financial Cooperative under the
Engineering Technology Promotion Act
, the mutual aid association under the
Industrial Development Act
, the Software Financial Cooperative under the
Software Industry Promotion Act
, the Korea Electric Engineers Association (limited to the organization that is published by the Minister of Commerce, Industry and Energy after his consultations thereabout with the Minister of Finance and Economy) under the
Electric Technology Management Act
, the Korea Association of Machinery Industry that performs guarantees for defects of environmental equipment and facilities pursuant to the
Act on the Promotion of the Conversion into Environment-Friendly Industrial Structure
, the mutual aid association under the Construction Waste Recycling Promotion Act, the mutual aid association provided for in the
Aggregate Picking Act
, the credit guarantee foundation under the Regional Credit Guarantee Foundation Act, or the Korea Tourism Association under the
Tourism Promotion Act
;
5.
Certificate of time deposit issued by financial institutions and foreign financial institutions referred to in subparagraph 1 of this paragraph and postal service offices;
6.
Beneficiary certificate issued by a trust company under the
Trust Business Act
; and
7.
Beneficiary certificate issued by a management company under the
Act on Business of Operating Indirect Investment and Assets
.
(3)
Persons who are exempted from paying in whole or in part of the amount of the bid bond under the proviso of
Article 9 (1) of the Act
, shall be as follows:
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 15433, Jul. 10, 1997; Presidential Decree No. 15581, Dec. 31, 1997; Presidential Decree No. 15614, Feb. 2, 1998; Presidential Decree No. 16448, Jun. 30, 1999; Presidential Decree No. 17019, Dec. 27, 2000; Presidential Decree No. 18666, Dec. 31, 2004; Presidential Decree No. 19035, Sep. 8, 2005; Presidential Decree No. 19463, Apr. 28, 2006>
1.
State agencies and local governments;
2.
Government-invested institutions under the
Framework Act on the Management of Government-Invested Institutions
;
3.
Juristic persons to which the Government contributes 50/100 or more of the basic property (including the property reverted to the National Treasury in accordance with the relevant Acts; hereinafter the same shall apply);
4.
Cooperatives and the Federation thereof under the Agricultural Cooperatives Act, fishing village fraternity, fisheries cooperatives and the Federation thereof under the Fisheries Cooperatives Act, forestry associations and the Federation thereof under the Forestry Cooperatives Act, small and medium enterprise cooperatives and the Federation thereof under the
Small and Medium Enterprise Cooperatives Act
, and the Korea Rural Community & Agricultural Corporation under Korea Rural Community & Agricultural Corporation and Farmland Management Fund Act;
5.
Juristic persons who have made registration, etc. under the Acts and subordinate statutes, such as the
Framework Act on the Construction Industry
, the
Electrical Construction Business Act
, the
Information and Communication Work Business Act
, the Construction Waste Recycling Promotion Act, or the
Aggregate Picking Act
, meeting the criteria determined by the Minister of Finance and Economy; and
6.
Other persons who are not feared to evade concluding contracts after they are determined as successful bidders in a competitive bidding.
(4)
The head of each central government agency or the public official in charge of contracts shall, when the events for the reversion to the National Treasury arise under the provisions of
Article 9 (3) of the Act
, ask a person who is exempted from paying in whole or in part of the amount of the bid bond under the provisions of paragraph (3) of this Article to submit the document of undertaking to pay in order to ensure the payment of an amount corresponding to the amount of the bid bond.
법령보기 화면
Article 38 (Reversion of Amount of Bid Bond to National Treasury)
(1)
If the head of each central government agency or the public official in charge of contracts has received the bid bond with the certificates of guarantee, etc. under the provisions of
Article 37
(2), he shall, when the events for the reversion to the National Treasury arise under the provisions of
Article 9 (3) of the Act
, immediately give notification of that fact to the financial institutions or the guarantee institutions which fall under each subparagraph of
Article 37
(2), and the related receipts collectors or the public officials in charge of securities, etc., and shall have the relevant amount of the bid bond collected in cash or converted into securities possessed by the Government under the provisions of the Ordinance of the Ministry of Finance and Economy.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 18155, Dec. 11, 2003>
(2)
The head of each central government agency or the public official in charge of contracts shall, when the events for the reversion to the National Treasury under
Article 9 (3) of the Act
arise to a person who is exempted from paying in whole or in part of the amount of the bid bond under the proviso of
Article 9 (1) of the Act
, give notification of that fact to the related receipts collectors with the document of undertaking to pay under the provisions of
Article 37
(4), and shall ask the said collectors to collect in cash the amount corresponding to the amount of the bid bond from the related successful bidder.
<Amended by Presidential Decree No. 18155, Dec. 11, 2003>
법령보기 화면
Article 39 (Submission and Receipt of Documents for Tender, and Invalidity of Tender)
(1)
The head of each central government agency or any public official in charge of contracts shall, when a bidder submits documents for tender, have him directly do so at the place and time indicated in the public notice for the tender:
Provided
, That in case where deemed necessary, such documents may be allowed to be submitted by mail.
<Amended by Presidential Decree No. 17019, Dec. 27, 2000; Presidential Decree No. 17688, Jul. 30, 2002>
(2)
The head of each central government agency or any public official in charge of contracts may, with regard to the contracts other than those subject to international bidding under the provisions of
Article 4 of the Act
, allow one to submit the tender document by utilizing the designated information processing apparatus, notwithstanding the provisions of paragraph (1):
Provided
, That in case where a consultation has been made in advance with the Minister of Finance and Economy, he may allow one to submit the tender document by utilizing such information processing apparatus as designated and publicly announced by the head of each central government agency other than the designated information processing apparatus.
<Newly Inserted by Presidential Decree No. 17688, Jul. 30, 2002>
(3)
The bidder may not exchange, modify, or cancel the documents for tender which have been already submitted:
Provided
, That in cases prescribed by the Minister of Finance and Economy, this shall not apply.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(4)
A tender performed by a person lacking the qualifications to participate in a competitive tender under the provisions of
Articles 12
and
21
, and a tender falling under reasons prescribed by the Ordinance of the Ministry of Finance and Economy shall be invalidated.
<Amended by Presidential Decree No. 15614, Feb. 2, 1998; Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 40 (Opening of Tender and Declaration of Successful Tender)
(1)
The head of each central government agency or any public official in charge of contracts shall conduct the opening of tender in the presence of bidders at the place and time indicated in the public notice for the tender. In this case, when there is a bidder not present at the opening of the tender, a public official not related to the tender shall be asked to participate in the opening of the tender.
(2)
The head of each central government agency or any public official in charge of contracts shall, when he confirms the documents for tender presented and thus determines a successful bidder by comparing the tendered amounts indicated in effective documents for the tender with the projected price, make without delay the declaration of successful tender:
Provided
, That where it takes him long time to determine a successful bidder such as where he should determine a successful bidder through examination of the capabilities to perform the contract under
Article 42
(1), the declaration of a successful bidder may be made after taking such necessary procedures.
(3)
In the case of submitting the tender document by utilizing the information processing apparatus under the provisions of
Article 39
(2), the opening of tender and the declaration of successful tender shall be conducted in accordance with the procedures and methods indicated in the public notice for the tender, notwithstanding paragraphs (1) and (2).
<Amended by Presidential Decree No. 17688, Jul. 30, 2002>
[This Article Wholly Amended by Presidential Decree No. 17019, Dec. 27, 2000]
법령보기 화면
Article 41 (Determination of Successful Bidder in Competitive Tender Which becomes Source of Revenue)
In a competitive tender which becomes a source of revenue, a bidder participating in the tender with the highest price which is more than the projected price shall become the successful bidder.
법령보기 화면
Article 42 (Determination of Successful Bidder in Competitive Tender Charged to National Treasury)
(1)
The head of each central government agency or the public official in charge of contracts shall, in a public tender which is a charge to the National Treasury, decide the successful bidder by examining the capabilities to perform the contract concerned in the order of the bidder who has bidden with the lowest price which is less than the projected price:
Provided
, That where a contract for goods whose estimated price is less than the notified price, and any tender under the provisions of
Article 18
, the bidder who has bidden with the lowest price which is less than the projected price shall be decided as the successful bidder, and in the case of construction work subject to a prior examination of qualifications for participating in the tender under
Article 13
which is the case of the tender for construction work whose estimated price is not less than 50 billion won, the successful bidder shall be decided starting with the bidder who has bidden with the lowest price which is less than the projected price, by examining the propriety of the bidding price, under the conditions as determined by the Minister of Finance and Economy.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17019, Dec. 27, 2000; Presidential Decree No. 18155, Dec. 11, 2003>
(2)
In examining the capabilities to perform the contract under paragraph (1), whether any bidder is eligible shall be determined on the basis of detailed examination criteria which are prescribed according to the examination criteria established by the Minister of Finance and Economy in comprehensive consideration of the past record of performances, technological capabilities, financial status, sincerity shown in the past performance of contracts, price appropriateness in the supply of materials and manpower, degree of the observation of contractual order, degree of the quality of past construction performances and the tendered price, etc. of the relevant bidders; and the relevant person who is deemed eligible by the results of examination shall be decided as the successful bidder:
Provided
, That if deemed necessary in view of the specific character of construction work or goods, etc., the head of each central government agency may directly determine the examination criteria through consultation with the Minister of Finance and Economy, and the person who holds the past records of having supplied goods, which are as good as or better than the goods of contract objects, to the public agency under
Article 2 of the Promotion of Small and Medium Enterprises and Encouragement of Purchase of Their Products Act
(hereinafter referred to as the "public agency") may be decided as the successful bidder without undergoing an examination of whether that person is eligible.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17019, Dec. 27, 2000; Presidential Decree No. 19035, Sep. 8, 2005>
(3)
through (5) Deleted.
<by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 43 (Conclusion of Contract by Negotiation)
(1)
If deemed necessary in view of the special nature, technical nature and urgency of the execution of contract, the safety of public installations and other national security purposes, the head of each central government agency or the public official in charge of contracts may, notwithstanding the provisions of
Article 42
, conclude a contract by negotiation with a person deemed to be most favorable to the State after evaluating the written proposals submitted by many suppliers.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 18155, Dec. 11, 2003>
(2)
The head of each central government agency or the public official in charge of contracts shall, when intending to conclude a contract under the provisions of paragraph (1) of this Article, state clearly that the contract is a contract by negotiation at the time of the public notice.
<Newly Inserted by Presidential Decree No. 15186, Dec. 31, 1996>
(3)
The head of each central government agency or the public official in charge of contracts shall issue and deliver the necessary documents such as a written request for proposal, etc. to persons who intend to participate in a contract by negotiation.
<Newly Inserted by Presidential Decree No. 15186, Dec. 31, 1996>
(4)
The head of each central government agency shall determine the criteria and procedures necessary for concluding a contract under the provisions of paragraph (1) of this Article, and shall make them available for inspection by those persons who intend to participate in a contract by negotiation.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
법령보기 화면
Article 43-2 (Methods of Contract for Knowledge-Based Business)
(1)
Where the head of each central government agency or the public official in charge of contracts concludes a contract for the business falling under any of the following subparagraphs (hereinafter referred to as the "knowledge-based business") from among the businesses which create the high added values by utilizing the highly intensive knowledge, such as information science technology, he may preferentially apply the method of concluding contracts through negotiations under the provisions of
Article 43
:
<Amended by Presidential Decree No. 19035, Sep. 8, 2005>
1.
Engineering business under subparagraph 4 of
Article 2 of the Engineering Technology Promotion Act
:
Provided
, That in case of construction technology providing services under subparagraph 3 of
Article 2 of the Construction Technology Management Act
, it shall be limited to the case requiring high level of difficulty and techniques;
2.
Software business under subparagraph 3 of
Article 2 of the Software Industry Promotion Act
;
3.
Business relating to the informatization under subparagraph 2 of Article 2 of the Framework Act on Informatization Promotion;
4.
Business relating to the industrial design under
Article 2 of the Industrial Design Promotion Act
;
5.
Cultural business under subparagraph 1 of Article 2 of the Framework Act on the Promotion of Cultural Industries;
6.
Online digital contents business under subparagraph 3 of Article 2 of the Online Digital Contents Industry Development Act;
7.
Scientific research service relating to the basic science and applied science; and
8.
Other businesses deemed by the head of each central government agency to be corresponding thereto.
(2)
Where the head of each central government agency or the public official in charge of contracts intends to conclude the contract through negotiations under paragraph (1), he shall set the detailed criteria pursuant to the evaluation method of written proposals and negotiation procedures set by the Minister of Finance and Economy, and conclude the competent contract.
[This Article Newly Inserted by Presidential Decree No. 18155, Dec. 11, 2003]
법령보기 화면
Article 44 (Determination of Successful Bidder according to Quality, etc.)
(1)
If deemed necessary for a contract for the manufacture and purchase of goods, the head of each central government agency or the public official in charge of contracts shall, notwithstanding the provisions of
Article 42
, determine the participant in the tender who has quoted the price which is most economical within the range of the projected price as the successful bidder by taking into consideration comprehensively not only the tendered price but also the quality, etc. of the related goods.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17019, Dec. 27, 2000>
(2)
The head of each central government agency or a public official in charge of contracts shall, when intending to determine the successful bidder under the provisions of paragraph (1) of this Article, determine the criteria for evaluation of the quality, etc. concerning related goods, and shall make them available for inspection by the participants in the tender.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17019, Dec. 27, 2000>
법령보기 화면
Article 45 (Determination of Successful Bidder When Selling Off Large Quantity of Goods)
When intending to sell off a large quantity of goods by dividing them according to the desired quantity to be sold under the provisions of
Article 17
(1), notwithstanding the provisions of
Article 41
, the successful bidders shall be determined according to the order of the bidders who have quoted the highest price from among the participants in the tender who have quoted a unit price which is more than the projected price until the required quantity is reached.
법령보기 화면
Article 46 (Determination of Successful Bidder When Manufacturing and Purchasing Large Quantity of Goods)
When intending to manufacture and purchase a large quantity of goods by dividing them according to the desired quantity to be manufactured or purchased under the provisions of
Article 17
(2), notwithstanding the provisions of
Article 42
, the successful bidders shall be determined according to the order of the bidders who have quoted the lowest price from among the participants in the tender who have quoted a unit price which is less than the projected price until the required quantity is reached.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 18155, Dec. 11, 2003>
법령보기 화면
Article 47 (Determination of Successful Bidder in Case of Tender with Equal Price)
(1)
The head of each central government agency or the public official in charge of contracts, when there are more than two persons who have quoted the same price which may be the successful price, shall determine immediately the successful bidder by means of drawing lots:
Provided
, That in case of a tender by 2-stage competitive tender, etc. under the provisions of
Article 18
, a person who has excellent specifications and technology shall be determined as the successful bidder, and in case of determining the successful bidder under the text of
Article 42
(1), the participant who has obtained the best marks as a result of examining the capability to perform the contract shall be determined as the successful bidder.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 16548, Sep. 9, 1999>
(2)
In case of paragraph (1) of this Article, when there are persons not present or persons not drawing lots from among the bidders, the public officials not related to the tender may be asked to draw lots instead of those persons.
(3)
If there are more than two persons who have quoted the same price for a general competitive tender according to a desired quantity under the provisions of
Article 17
(1) or (2), the participant who has tendered for more quantity than other participants shall be determined as the successful bidder.
CHAPTER V CONCLUSION AND PERFORMANCE OF CONTRACT
법령보기 화면
Article 48 (Preparation of Written Contract)
(1)
The form of the contract which the head of each central government agency or the public official in charge of contracts prepares under the provisions of the main text of
Article 11 (1) of the Act
and other necessary matters shall be prescribed by the Ordinance of the Ministry of Finance and Economy.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(2)
The public official in charge of contracts shall write the name and seal the written contract:
Provided
, That if the contract is concluded with a foreigner or where there are special reasons, the signature may take the place of writing the name and of the seal.
법령보기 화면
Article 49 (Ommission of Preparation of Written Contract)
Cases where preparation of a written contract may be omitted under the proviso of
Article 11
(1) shall be specified in each of the following subparagraphs:
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
1.
Cases of concluding a contract of which the amount is less than 30 million won;
2.
Cases of conducting an auction;
3.
Cases where a buyer instantly pays the price and acquires the goods when related goods are sold;
4.
Cases where each government agency and a local government conclude a contract each other; and
5.
Cases where the preparation of a written contract is not required due to the characteristics of the contract such as a contract for the supply of electricity, gas, and piped water, etc.
법령보기 화면
Article 50 (Deposit for Contract)
(1)
The head of each central government agency or the public official in charge of contracts shall cause the deposit for the contract under the provisions of
Article 12 of the Act
to be paid for 10/100 or more of the contract amount.
(2)
In case of a unit-cost contract to be performed by being divided into several stages, notwithstanding the provisions of paragraph (1) of this Article 10/1000 or more of the amount calculated by multiplying the maximum quantity out of the estimated quantities which shall be performed at each stage by the contractual unit cost shall be made to be paid as the deposit for the contract.
(3)
In case of a continuous long-term contract, 10/100 or more of the amount of whole construction work or whole manufacture, etc., which is additionally entered at the time of concluding the first contract, shall be made to be paid as a contract deposit. In this case, the relevant contract deposit shall be deemed as the contract deposit for whole construction work or whole manufacture, etc.; and in case where the contract by annual basis is completed, 10/100 of the amount of contracts by annual basis of which the work is completed from among the initial contract deposit shall be refunded.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 19035, Sep. 8, 2005>
(4)
and (5) Deleted.
<by Presidential Decree No. 16548, Sep. 9, 1999>
(6)
Cases where one may be exempted from paying whole or part of the contract deposit under the proviso of
Article 12 (1) of the Act
shall be as follows:
<Amended by Presidential Decree No. 15614, Feb. 2, 1998; Presidential Decree No. 19035, Sep. 8, 2005>
1.
Cases of concluding a contract with a person referred to in
Article 37
(3) 1 through 4;
2.
Cases of concluding a collective negotiated contract with small and medium enterprises cooperatives under the provisions of
Article 9 of the Promotion of Small and Medium Enterprises and Encouragement of Purchase of Their Products Act
;
3.
Cases of concluding the contract of which the contract amount is not more than thirty million won;
4.
Cases where the collection of the deposit is not appropriate in view of contractual customs generally recognized to be fair and reasonable; and
5.
Cases of purchasing parts of already introduced foreign capital facilities, machinery, equipment and of having difficulty purchasing the parts unless the supplier concerned purchases them.
(7)
The deposit shall be made to be paid in cash or with the certificates of guarantee, etc. prescribed in each subparagraph of
Article 37
(2).
<Amended by Presidential Decree No. 15614, Feb. 2, 1998>
(8)
If the other party to the contract due to special reasons has made a request to replace the contract deposit paid in cash or with securities prescribed in
Article 84-16 of the Enforcement Decree of the Securities and Exchange Act
by a certificate of guarantee, etc. prescribed in the
Article 37
(2) 1 through 5, it may be paid with such certificate of guarantee, etc. in an amount corresponding to or more the said cash or securities.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 19035, Sep. 8, 2005>
(9)
Deleted.
<by Presidential Decree No. 15614, Feb. 2, 1998>
(10)
The provisions of
Article 37
(4) shall apply
mutatis mutandis
to the cases where the payment of the whole or part of the deposit for the contract may be exempted under the provisions of paragraph (6) 1 through 3 and 5 of this Article.
<Amended by Presidential Decree No. 18155, Dec. 11, 2003>
(11)
Deleted.
<by Presidential Decree No. 17019, Dec. 27, 2000>
[This Article Wholly Amended by Presidential Decree No. 15186, Dec. 31, 1996]
법령보기 화면
Article 51 (Reversion of Deposit for Contract to National Treasury)
(1)
The head of each central government agency and the public official in charge of contracts shall, when the other party to the contract fails to fulfill contractual obligations without justifiable reasons, revert the contract deposit under
Article 50
(including an amount guaranteed under
Article 52
(1) 2 and 3; hereinafter the same shall apply) to the National Treasury under
Article 12 (3) of the Act
. In this case, the provisions of
Article 75
(1) shall apply
mutatis mutandis
.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 15614, Feb. 2, 1998; Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17019, Dec. 27, 2000>
(2)
The provisions of paragraph (1) of this Article shall apply
mutatis mutandis
to cases where the other party to a continuous long-term contract fails to conclude the contract for construction work or manufacture, etc. after the second stage under the provisions of the latter part of
Article 69
(2) and the provisions of
Article 69
(3).
<Newly Inserted by Presidential Decree No. 15186, Dec. 31, 1996>
(3)
In reverting the deposit for the contract to the National Treasury under the provisions of paragraphs (1) and (2) of this Article, that deposit may not be offset by any unpaid amount for the completed parts.
<Newly Inserted by Presidential Decree No. 15186, Dec. 31, 1996>
(4)
The provisions of
Article 38
(1) and (2) shall apply
mutatis mutandis
to cases of reversion of the deposit for the contract to the National Treasury.
법령보기 화면
Article 52 (Performance Bond for Contract for Construction Work)
(1)
The head of each central government agency or the public official in charge of contracts shall, in case where he intends to conclude a contract for construction work, have the counter party of contract guarantee the performance of relevant contract by selecting one of the methods falling under the following subparagraphs:
Provided
, That where the head of each central government agency or the public official in charge of contracts deems it necessary in consideration of the character of the contract for construction work, he may limit the methods of guaranteeing the performance of the contract to the methods under subparagraph 3, and with respect to the contract for construction work under the proviso of
Article 42
(1), he shall have such counter party guarantee the performance of the contract only by the methods under subparagraph 3:
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17019, Dec. 27, 2000>
1.
The method of paying the contract deposit under
Article 50
(1) through (3), and put up one or more joint and several sureties who guarantee the performance of the work obligations in the relevant construction contract (including an execution of repair of defects);
2.
The method of paying the contract deposit of more than 20/100 of the contract amount without putting up the joint and several sureties under item 1; and
3.
The method of submitting a performance bond (it shall be the one which guarantees that the agency, which has guaranteed the execution of contractual obligations of the relevant construction works, shall pay on behalf of the counter party of contract the amount of more than 40/100 of the contract amount in the event of failure to execute the said contractual obligations) without paying the contract deposit under
Article 50
(1) through (3).
(2)
A joint and several surety shall be the person who has qualifications equal to or superior than those requested in the public notice of tender, etc. under
Article 36
; and other matters necessary for a joint and several surety shall be prescribed by the Ordinance of the Ministry of Finance and Economy.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(3)
The Minister of Finance and Economy may determine the matters necessary for the submission, etc. of the performance bond under paragraph (1).
<Newly Inserted by Presidential Decree No. 16548, Sep. 9, 1999>
(4)
The provisions of paragraphs (1) through (3) may apply
mutatis mutandis
to the case of a service contract.
<Newly Inserted by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 53 (Insuring of Non-life Insurance)
(1)
The head of each central government agency or the public official in charge of contracts may, if it is deemed necessary in concluding a contract, have objects under the related contract insured non-life insurance, or ask the other party to the contract to insure them non-life insurance.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
(2)
The Minister of Finance and Economy may determine the necessary matters concerning effecting the non-life insurance under the provisions of paragraph (1).
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 54 (Supervision)
(1)
The term "contract prescribed by the Presidential Decree" in the proviso of
Article 13 (1) of the Act
means a contract falling under one of the following subparagraphs:
<Amended by Presidential Decree No. 19035, Sep. 8, 2005>
1.
A contract for construction work for which the responsible supervision is executed under the provisions of
Article 27 of the Construction Technology Management Act
; and
2.
A contract for manufacture and any other contract for work for which the supervision prescribed in the main sentence of
Article 13 (1) of the Act
may not be executed due to the need for expert knowledge or technology or due to other unavoidable reasons.
(2)
In the case of the construction work contract concluded by a successful bid of less than 70/100 of the projected prices, the head of each central government agency or the public official in charge of contracts may add the number of supervisory officials (referring to the number of supervisory officers as referred to in the
Construction Technology Management Act
, etc. in the case of construction work contract from among the contracts under paragraph (1)) within the limit of 50/100 of the relevant criteria for posting in order to prevent the unconscientious works.
<Newly Inserted by Presidential Decree No. 18155, Dec. 11, 2003; Presidential Decree No. 19035, Sep. 8, 2005>
(3)
Expenses for supervision or superintendence additionally required pursuant to paragraph (2) may be appropriated by the difference in price of successful bid from among the relevant construction work budgets (referring to the difference between the projected price and the price of successful bid).
<Newly Inserted by Presidential Decree No. 18155, Dec. 11, 2003>
법령보기 화면
Article 55 (Inspection)
(1)
An inspection under the provisions of
Article 14 (1) of the Act
shall be completed within 14 days from the date on which the notice has been received from the other party to the related party to the effect that the performance of the related contract has been completed:
Provided
, That if it is prescribed by the Minister of Finance and Economy, the inspection period may be extended within the limit of seven days.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(2)
When executing the inspection under paragraph (1) of this Article, in case of a research and design service contract, the question of whether the other party to the related service contract has calculated reasonably the total costs of the project shall be also examined.
(3)
The term "contract as prescribed by the Presidential Decree" referred to in the proviso of
Article 14 (1) of the Act
means a contract falling under any of the following subparagraphs of
Article 54
(1).
<Amended by Presidential Decree No. 18155, Dec. 11, 2003>
(4)
In case of concluding contracts by separating the basic design (including a feasibility study; the same shall apply to the following provisions) from the shop design, when inspecting the performance of the shop design service under paragraph (1) of this Article, the question of whether the calculation of the total costs of the project under the shop design is reasonable shall be examined by comparing the total costs under the basic design with the total costs under the shop design. In this case, if there is a difference between the total costs under the basic design and the total costs under the shop design, the other party to the contract for the shop design service shall be asked to present the materials and data which explain the reasons therefor.
(5)
In case the inspection has failed to be completed due to
force majeure
such as natural disasters during the prescribed period under paragraph (1) of this Article, the inspection shall be completed within 3 days from the date on which such
force majeure
has disappeared.
(6)
The head of each central government agency and the public official in charge of contracts, when discovering the fact that in whole or in part of the contract performed by the other party to the contract violates the original contract or is inappropriate in course of the inspection under
Article 14 (1) of the Act
, shall take corrective actions without delay. In this case, the period under paragraph (1) of this Article shall be calculated from the date on which the notice has been received from the other party to the contract to the effect that such corrective actions have been completed.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
(7)
In case where the inspection of the completed parts at the time of paying the costs for the completed parts under
Article 58
(3) may be replaced by the verification of the protocol of supervision prepared by the person executing the supervision under
Article 13 of the Act
:
Provided
, That every three times such an inspection is executed, the inspection under
Article 14
shall be executed once.
<Newly Inserted by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 56 (Ommission of Preparation of Protocol of Inspection)
Cases where preparation of a protocol of inspection may be omitted under to the proviso of
Article 14 (2) of the Act
shall be specified in each of the following subparagraphs:
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
1.
Cases of a contract whose contract amount is less than 30 million won;
2.
Cases of a contract for sale; and
3.
Cases of a contract not requiring the preparation of a protocol of inspection due to the characteristics of the contract such as the contract for supply of electricity, gas, and piped water, etc.
법령보기 화면
Article 57 (Concurrent Performance of Supervision Duty and Inspection Duty by Same Person)
The duty for supervision under
Article 54
and the duty for inspection under
Article 55
may not be concurrently performed by the same person:
Provided
, That in cases falling under any of the following subparagraphs this shall not apply:
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 18155, Dec. 11, 2003>
1.
Cases where it is extremely difficult to ask a person other than the one who executes the supervision to execute the inspection if the inspection requires a special technology;
2.
Cases where it is difficult to confirm the performance without inspecting the performance of a related contract immediately after the completion of the performance of the contract such as a contract for construction work for the repair and maintenance;
3.
Cases of a contract for the manufacture of goods or construction work of which the contract amount is less than three hundred million won;
4.
Cases of a contract for construction work prescribed in
Article 54
(1) 1; and
5.
Cases of a substitution of the inspection of completed parts for a verification of the protocol of supervision under the text of
Article 55
(7).
법령보기 화면
Article 58 (Payment of Cost)
(1)
The cost of a contract which becomes a burden on the national treasury under
Article 15 (2) of the Act
shall be paid within 14 days from the date on which a request of the other party to the contract has been received after the inspection under
Article 55
has been completed. In this case, a special agreement which may postpone the time limit for payment of the cost may within a limit not exceeding 14 days be concluded.
(2)
If it is impossible to make the payment of the cost due to
force majeure
such as natural disasters within the time limit of payment, the cost shall be paid within 3 days from the date on which that
force majeure
has disappeared.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
(3)
In case of paying the cost for completed parts or supplied parts under to
Article 15 of the Act
, notwithstanding paragraph (1) of this Article, the cost for the completed parts or the supplied parts shall be paid at least every 30 days by taking into consideration the contract volume, the prospect for performance, and the period of performance, etc.
<Newly Inserted by Presidential Decree No. 15186, Dec. 31, 1996>
(4)
For the payment of the cost under paragraph (3) of this Article, the other party to the contract may be asked to request the payment of the cost before the date on which the inspection under
Article 55
is completed, and the cost shall be finalized and paid according to the inspected contents within 7 days from the date on which the inspection is completed:
Provided
, That when the other party to the contract requests the payment of the cost after the date on which the inspection is completed, the cost shall be paid within 7 days from the date on which such request has been received.
<Newly Inserted by Presidential Decree No. 15186, Dec. 31, 1996>
(5)
The head of each central government agency or the public official in charge of contracts, when discovering the fact that in whole or in part of the contents of the request is inappropriate after the request for the payment of the cost under paragraph (1) or (4) of this Article has been received, may return the related request to the other party to the contract by clearly stating the reasons therefor. In this case, the period from the date on which the request is returned to the date on which the re-request has been received shall not be included in the payment period under paragraph (1) or (4) of this Article.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
법령보기 화면
Article 59 (Interest for Delayed Payment of Cost)
If the head of each central government agency or the public official in charge of contracts fails to pay the cost by the time limit for the payment period of the cost under
Article 58
(in case of a contract by an action of the National Treasury to bear the liability, 20 days from the date on which the related budget is allocated under the
Budget and Accounts Act
after the next fiscal year has started) after having received the request for the payment of the cost under
Article 15 (2) of the Act
, the unpaid amount plus the interest on such unpaid amount calculated by multiplying the number of days from the day following the time limit for the payment to the day on which the payment has been made (hereinafter referred to as the "number of days of the delayed payment of the cost") by the interest rate for the overdue payment applicable to general loans by financial institutions shall be paid.
<Amended by Presidential Decree No. 19035, Sep. 8, 2005>
법령보기 화면
Article 60 (Defect Security Liability Period of Contract for Construction Work)
(1)
The head of each central government agency or the public official in charge of contracts shall, when concluding a contract for construction work, determine the defect security liability period in order to guarantee the repair of defect in the related construction work during the period prescribed by the Ordinance of the Ministry of Finance and Economy within the limit of 1 year to 10 years from the earlier one of either the first date on which whole objects have been delivered or the date on which the inspection on the completion of the construction work has been finished:
Provided
, That if it is not required to repair the defect in view of the nature of the construction work under the provisions of the Ordinance of the Ministry of Finance and Economy, this shall not apply.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(2)
The defect deposit liability period under paragraph (1) shall, in case of a continuous long-term construction, be determined by annual contract:
Provided
, That the defect security liability period shall, in case where it is the construction work for which the defect security liability cannot be divided by annual contract, be determined for the entire construction works at the time of concluding the first contract.
<Newly Inserted by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 61 (Inspection of Defects)
(1)
The head of each central government agency or the public official in charge of contracts shall inspect the defects periodically twice or more a year or entrust the inspection affairs to the public official under its control to ask him to inspect the said defects periodically twice or more a year during the defect security liability period under the provisions of
Article 60
of this Decree.
(2)
If the inspection of defects under paragraph (1) of this Article requires an expert knowledge or technology or is executed with respect to construction work awarded in the amount of less than 86/100 of the projected price which is made for the installation under subparagraph 1 of Article 2 of the Special Act on the Safety Control of Public Structures, the head of each central government agency or the public official in charge of contracts shall request a specialized organization to perform the said inspection.
<Amended by Presidential Decree No. 18155, Dec. 11, 2003; Presidential Decree No. 19035, Sep. 8, 2005>
(3)
The person who inspects the defects under the provisions of paragraphs (1) and (2) shall prepare a protocol of defect inspection:
Provided
, That in case of a contract for construction work of which the contract amount is not more than 30 million won, the preparation of the said protocol may be omitted.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 62 (Deposit for Repair of Defects)
(1)
The deposit for the repair of defects under
Article 18 of the Act
shall be between 2/100 or more and 10/100 or less of the contract amount under the conditions as prescribed by the Ordinance of the Ministry of Finance and Economy:
Provided
, That if it is not required to repair the defects due to the nature of the construction work under the Ordinance of the Ministry of Finance and Economy, the deposit for the repair of defects may not be paid.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(2)
The head of each central government agency or the public official in charge of contracts shall cause the deposit for the repair of defects under paragraph (1) to be paid before paying the cost for construction work after the inspection on completion of the relevant construction work, and shall keep it during the defect security liability period under
Article 60
.
(3)
The deposit for repair of defects under paragraphs (1) and (2) shall, in case of the continuous long-term construction, be paid by annual contract:
Provided
, That the deposit for repair of defects shall, in case where it is the construction work for which the defect security liability cannot be divided by annual contract, be paid after the inspection of completion of whole construction.
<Newly Inserted by Presidential Decree No. 16548, Sep. 9, 1999>
(4)
Cases where the payment of deposit for the repair of defects may be exempted under the proviso of
Article 18 (1) of the Act
shall be specified in each of the following subparagraphs:
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
1.
Cases of concluding a contract under the provisions of
Article 26
(1) 7 (e); and
2.
Cases of concluding a contract with a person referred to in the provisions of
Article 37
(3) 1 through 4.
(5)
The provisions of
Articles 37
(2) and (4) and
38
shall apply
mutatis mutandis
to the payment of deposit for the repair of defects and to the reversion thereof to the National Treasury.
<Amended by Presidential Decree No. 15614, Feb. 2, 1998>
법령보기 화면
Article 63 (Direct Use of Deposit for Repair of Defects)
(1)
In case of intending to use directly the deposit for the repair of the defects under the proviso of
Article 18 (3) of the Act
, the related deposit for the repair of defects shall not be paid into the revenue account but shall be entered separately under the title of accounts other than revenue and expenditure.
(2)
Procedures for the direct use of the deposit for the repair of defects under the provisions of paragraph (1) of this Article shall be prescribed by the Ordinance of the Ministry of Finance and Economy.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 64 (Adjustment of Contract Amount Due to Price Fluctuations)
(1)
The head of each central government agency or the public official in charge of contracts shall, in case where 90 days or more have passed since the date on which a contract forming a burden on the National Treasury was concluded under
Article 19 of the Act
(referring to the conclusion of a first-stage contract in the case of a continuous long-term construction and a long-term manufacture of goods, etc.) and where at the same time it falls under any of the following subparagraphs, adjust the contract amount (referring to the amount of whole construction works and whole manufacture, etc. entered additionally at the time of concluding the first-stage contract in the case of a continuous longterm construction work and a long-term manufacture of goods, etc.; hereafter in this Chapter the same shall apply) under the conditions as prescribed by the Ordinance of the Ministry of Finance and Economy. In this case, the contract amount shall not be adjusted again within 90 days from the base day of adjustments (referring to the date on which the grounds of adjustments have occurred; hereafter the same shall apply in this Article):
<Amended by Presidential Decree No. 15661, Feb. 24, 1998; Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 18359, Apr. 6, 2004; Presidential Decree No. 19035, Sep. 8, 2005>
1.
When the adjustment rate of the goods that is calculated under the conditions as prescribed by the Ordinance of the Ministry of Finance and Economy on the base date that is the bidding date (referring to the date on which a negotiated contract is concluded in the case of negotiated contract and the immediately preceding adjustment base date in the adjustment of contract amount after the second bidding; hereafter in this paragraph the same shall apply) increases or decreases by not less than 3/100; and
2.
When the adjustment rate of the index number that is calculated under the conditions as prescribed by the Ordinance of the Ministry of Finance and Economy on the base date that is the bidding date increases or decreases by not less than 3/100.
(2)
The head of each central government agency or public official in charge of contracts shall, in case where he adjusts the contract amount under paragraph (1), be based on one of the methods from among those falling under each subparagraph of paragraph (1) for the identical contracts, and indicate clearly that the contract amount shall be adjusted by the method of paragraph (1) 1, except a case where a counter party of the contract wants the method of paragraph (1) 2, on the contract at the time of concluding the contract.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 19035, Sep. 8, 2005>
(3)
If any advance payment has been made to a relevant counter party of the contract under Article 40 of the Enforcement Decree of the Management of the National Funds Act, the amount calculated under the Ordinance of the Ministry of Finance and Economy shall be deducted from the increased amount calculated under paragraph (1).
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17824, Dec. 30, 2002; Presidential Decree No. 19035, Sep. 8, 2005>
(4)
The head of each central government agency or public official in charge of contracts may, in case where he purchases the goods for which the maximum selling price is publicly notified under the relevant Acts and subordinate statutes, and where it is difficult to procure the goods under the provisions of paragraph (1), determine on the adjustment of contract amount, when the contract is concluded, in a way different from the provisions of paragraph (1).
<Newly Inserted by Presidential Decree No. 16548, Sep. 9, 1999>
(5)
If it is deemed difficult to execute a contract without adjusting the contract amount within the relevant adjustment restriction period due to natural disasters or sharp rises in raw materials prices, etc. in applying the provisions of paragraph (1), the contract amount may be adjusted within sixty days from the date on which the contract is concluded or the immediately preceding base date of adjustment, notwithstanding the provisions of the same paragraph.
<Newly Inserted by Presidential Decree No. 18359, Apr. 6, 2004; Presidential Decree No. 19035, Sep. 8, 2005>
법령보기 화면
Article 65 (Adjustment of Contract Amount Due to Modification of Design)
(1)
The head of each central government agency or the public official in charge of contracts shall, if the construction volume increases or decreases due to a modification of design in the case of a contract for construction work, adjust the said contract amount under the provisions of
Article 19 of the Act
.
(2)
When intending to increase the contract amount of the construction work awarded successfully in the amount of less than 86/100 of the projected price by adjustment under the provisions of paragraph (1) of this Article, if the contract amount increased by adjustment (referring to all of the amount obtained by adding up the amount that is decreased or increased by a change in the design or the amount that is increased by adjustment and the amount to be increased by adjustment in the adjustment of the contract amount on and after the second contract) is not less than 10/100 of the original contract amount, the public official in charge of contracts shall obtain approval therefor from the head of the central government agency to which he belongs after going through the deliberation thereof of the Contract Council under
Article 94
, the Budget Expenditure Council under
Article 162 of the Enforcement Decree of the Budget and Accounts Act
, or the Design Advisory Committee under Article 21 of the Enforcement Decree of the Construction Technology Management Act (hereinafter referred to as the "Design Advisory Committee").
<Amended by Presidential Decree No. 18155, Dec. 11, 2003; Presidential Decree No. 19035, Sep. 8, 2005>
(3)
When adjusting the contract amount under the provisions of paragraph (1) of this Article, the criteria prescribed in each of the following subparagraphs shall be applied:
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 19035, Sep. 8, 2005>
1.
The unit cost for the increased or decreased volume of construction shall be the unit cost indicated in the statement of particulars concerning calculation which is submitted under the provisions of
Article 14
(6) or (7) (hereinafter referred to as the "contractual unit cost"):
Provided
, That if the contractual unit cost is more than the unit cost of the projected price under the provisions of
Article 9
(hereinafter referred to as the "unit cost of the projected price") and if the volume is increased, the unit cost applicable to the increased volume shall be the unit cost of the projected price;
2.
The unit cost for the new item in the absence of a contractual unit cost shall be the amount calculated by multiplying the unit cost calculated as of the time of modifying the design by the ratio of the successful tender; and
3.
If the Government requests a change in the design (including a case where any contracting party is not responsible for such change), notwithstanding the provisions of subparagraphs 1 and 2 of this paragraph, the unit cost for the increased volume and the unit cost for the new items shall be determined by consultation between the contracting parties within the limits of the unit cost calculated as of the time of the modification of design and of the amount calculated by multiplying the said unit cost by the ratio of the successful tender:
Provided
, That in case where no agreement is reached between the contracting parties, the unit cost shall be 50/100 of the amount obtained by adding up the unit cost that is calculated at the time when the design is changed to the unit cost that is obtained by multiplying the successful tender rate by the unit cost.
(4)
If the head of each central government agency or the public official in charge of contracts has conducted the necessary modification of design at the request of the other party to the contract because the use of the new technology and a new method of construction by the other party is deemed to have a remarkable effect on saving the costs of construction and shortening the construction period, etc. (including technology, method of construction, and equipment and materials, etc. equal to or superior to those of a design chosen by the Government in terms of functions and effectiveness; hereinafter the same shall apply), he shall, in the adjustment of contract amount, reduce the amount equivalent to 30/100 of the relevant savings.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 18155, Dec. 11, 2003>
(5)
In case of paragraph (4) of this Article, when objections are raised against the scope and limit of the new technology and method of construction, the head of each central government agency or the public official in charge of contracts shall request the Design Advisory Committee to examine the said objections:
Provided
, That if the Design Advisory Committee is not established, the head of each central government agency or the public official in charge of contracts shall request the examination by the construction technology deliberation committee under the provisions of
Article 5 of the Construction Technology Management Act
.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 17019, Dec. 27, 2000; Presidential Decree No. 19035, Sep. 8, 2005>
(6)
The general and administrative expenses and profits, etc. to be incurred or to be accrued in connection with the increased or decreased portion of the contract amount shall be based on the rate of general and administrative expenses and the rate of profits, etc. specified in the statement of particulars concerning calculation submitted under the provisions of
Article 14
(6) or (7), but shall not exceed the rate prescribed by the Ordinance of the Ministry of Finance and Economy.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 16548, Sep. 9, 1999>
(7)
The provisions of paragraphs (1) through (6) may apply
mutatis mutandis
to an adjustment of the contract amount in the case of a contract for manufacture and service, etc.
법령보기 화면
Article 66 (Adjustment of Contract Amount Due to Modification of Other Contents of Contract)
(1)
The head of each central government agency or the public official in charge of contracts shall, if it is necessary to adjust the contract amount in the case of a contract for construction work and manufacture, etc. under the provisions of
Article 19 of the Act
except for the cases under the provisions of
Articles 64
and
65
, due to modifications of the contents of the contract, such as construction period and the transport distance, adjust the contract amount within a limit not exceeding the actual expenses incurred according to the modified contents of the contract.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
(2)
The provisions of
Article 65
(6) shall apply
mutatis mutandis
to paragraph (1) of this Article.
법령보기 화면
Article 67 (Contract Prior to Commencement of Fiscal Year)
The head of each central government agency or the public official in charge of contracts shall, when he intends to conclude any contract before the fiscal year commences pursuant to the provisions of
Article 20 of the Act
, get such contract to take its effect after the date on which the relevant fiscal year commences.
[This Article Wholly Amended by Presidential Decree No. 19035, Sep. 8, 2005]
법령보기 화면
Article 68 (Prohibition of Contract for Divided Construction Work)
The head of each central government agency or the public official in charge of contracts may not conclude a contract by dividing it in terms of either the period or the volume of construction work on the same structure and the single construction work prescribed by the Minister of Finance and Economy of which the whole contents are finalized by design, etc.:
Provided
, That the same shall not apply to the case where the construction work falls under any of the following subparagraphs:
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17688, Jul. 30, 2002>
1.
Construction work which shall be ordered separately from other types of construction work under other Acts;
2.
Construction work which can be efficiently carried out by being divided in view of the nature or the size, etc. thereof; and
3.
Construction work in which a separation of liability for defects is easy and no hindrance exists in process control, and which is deemed to be efficient if it is done by a separate working.
법령보기 화면
Article 69 (Long-Term Continuous Contract and Contract by Continuing Expenditure)
(1)
In the case of a contract falling under one of the following subparagraphs when a long-term continuous contract under the provisions of
Article 21 of the Act
is to be concluded, a contract by unit cost may be concluded with the approval of the head of each competent central government agency:
1.
A contract for service related to transport, custody, experiment, investigation, research, measurement, and facilities management, etc., or the lease contract;
2.
A contract for the supply of electricity, gas, and piped water, etc.; and
3.
A contract for the maintenance and repair of equipment.
(2)
Long-term continuous construction work shall be concluded in such a way that the amount of the whole construction work determined by the successful bidding, etc. may be recorded in a book and the first stage construction work may be executed within the limit of the budget of the corresponding year. In this case, a contract concerning the second-stage construction work shall stipulate additional clauses that the contract shall be concluded within the limit of the amount calculated by deducting the amount already contracted from the total amount of the construction work recorded in the book (in case the adjustment of the contract amount under to the provisions of
Articles 64 through 66
is performed, it means the total amount of the adjusted construction work).
(3)
With respect to methods for the conclusion of contracts for longterm manufacture of goods, the provisions of paragraph (2) of this Article shall be applied
mutatis mutandis
.
(4)
The contract amount following the first stage or the second stage construction work under the provisions of paragraphs (2) and (3) of this Article shall be determined in accordance with the contractual unit cost of the whole construction work and whole manufacture, etc.
(5)
In case of construction work executed by continuing expenditure, the contract shall be concluded after specifying matters related to the whole construction work and the annual construction work.
법령보기 화면
Article 70 (Contract by Rough Estimate)
(1)
The head of each central government agency or the public official in charge of contracts, when intending to conclude a contract by rough estimate under the provisions of
Article 23 of the Act
, shall determine in advance the price roughly estimated.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
(2)
The head of each central government agency, when intending to conclude a contract by rough estimate under the provisions of paragraph (1) of this Article, shall determine the criteria and procedures, etc. necessary for the examination of the cost by taking into consideration the special characteristics of the objects of the contract, contracted volume, and performance period of the contract, etc. before the tender, and shall make them available for inspection by the persons who intend to participate in the tender.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
(3)
The public official in charge of contracts, when intending to conclude a contract by rough estimate under the provisions of paragraph (1) of this Article, shall inform the Board of Audit and Inspection thereof, and shall keep an accurate account according to the criteria, etc. under the provisions of
Article 9
(2) of this Article and obtain the approval of the head of the competent central government agency after the performance of the contract has been completed.
<Newly Inserted by Presidential Decree No. 15186, Dec. 31, 1996>
법령보기 화면
Article 71 (Integrated Contract)
The Minister of Finance and Economy may, if he deems it necessary to conclude an integrated contract under the provisions of
Article 24 of the Act
, determine the methods to conclude the integrated contract and other necessary matters.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 72 (Joint Contract)
(1)
The Minister of Finance and Economy may determine the methods to conclude a joint contract under the provisions of
Article 25 of the Act
and other necessary matters.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(2)
The head of each central government agency or the public official in charge of contracts shall, when intending to conclude a contract by competition, conclude a joint contract as far as possible, unless the joint contract is deemed inappropriate in light of the purpose and characteristics of the contract.
(3)
The head of each central government agency or the public official in charge of contracts shall, in case of a joint contract under paragraph (2) of which the estimated price is less than 5 billion won (less than 7.8 billion won, not later than December 31, 2003), and where deemed necessary for the balanced development of the construction industry, etc., assign one or more persons as the members of a joint supply and demand organization from among the persons whose principal business places are located in the Special Metropolitan City, Metropolitan Cities, and Dos which exercise jurisdiction over the site of construction work:
Provided
, That if the persons who have the qualifications necessary for the execution of construction work in the relevant area are less than 10, this shall not apply.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17546, Mar. 25, 2002>
(4)
The relationship between the businesses of the relevant area and those of other areas from among the members of a joint supply and demand organization shall, in case of a joint contract under paragraph (3), not be the same as that between the affiliated firms under the
Monopoly Regulation and Fair Trade Act
.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 19035, Sep. 8, 2005>
법령보기 화면
Article 72-2 (Joint Contract for Knowledge-Based Business)
Where the participants to a bidding intend to make a joint participation in the complex business requiring several professional fields from among the knowledge-based business, the head of each central government agency or the public official in charge of contracts shall permit it unless he has any special grounds.
[This Article Newly Inserted by Presidential Decree No. 18155, Dec. 11, 2003]
법령보기 화면
Article 73 (Contract Subject to Condition of Ex Post Facto Examination of Prime Cost)
(1)
The head of each central government agency or the public official in charge of contracts, if he is unable to determine a part of the amount because of items having an the estimated price before the tender, may conclude the contract subject to an
ex post facto
examination of the prime cost.
(2)
The head of each central government agency, when intending to conclude a contract under the provisions of paragraph (1) of this Article, shall determine the criteria and procedures, etc. necessary for the
ex post facto
examination of the prime cost by taking into consideration the special characteristics of the objects of the contract, contracted volume, and performance period of the contract, etc. before the tender, and shall make them available for inspection by a persons who intend to participate in the tender.
(3)
The prime cost shall be examined and the accounts shall be settled according to the criteria, etc. under the provisions of
Article 9
and paragraph (2) of this Article after the performance of the contract has been completed.
[This Article Wholly Amended by Presidential Decree No. 15186, Dec. 31, 1996]
법령보기 화면
Article 74 (Compensation for Delay)
(1)
The head of each central government agency or the public official in charge of contracts shall, in case where the counterpart of the contract (excluding government agencies and local governments) delays the performance of contractual obligations, have the said other party pay in cash an amount calculated by multiplying the contract amount by the rate prescribed by the Ordinance of the Ministry of Finance and Economy and the number of days delayed as the compensation for delay. In this case, if the execution of contract is deemed to be delayed due to the events not attributable to the counter party of the contract, the number of relevant days shall not be included in the number of days delayed.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(2)
In case of paragraph (1), and where the completed part or the supplied part is accepted through inspection (including the cases where the relevant part is not accepted but only managed or used; hereinafter in this Article the same apply), the compensation for delay shall be calculated on the basis of the amount calculated by deducting the amount corresponding to the said part from the contract amount. In this case, the acceptance of the completed part or the supplied part shall be limited to the cases where it is accepted as the completed part of the construction work, goods or services, etc. which may be divided as to the characteristics thereof.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 75 (Cancellation and Termination of Contract)
(1)
When reverting the deposit for the contract to the National Treasury under the provisions of
Article 12 (3) of the Act
, unless otherwise provided in the contract, the head of each central government agency or the public official in charge of contracts shall cancel or terminate the related contract and shall notify the other party to the contract of the reasons therefor.
(2)
If events to collect the compensation for delay under the provisions of
Article 74
(1) have arisen and the amount of such compensation for delay has reached an amount corresponding to the deposit for the contract (including the deposit for the contract which is exempted) under the provisions of
Article 50
(1), and it is deemed clearly impossible to perform the contract due to the cause imputable to the other party to the contract, the head of each central government agency or the public official in charge of contracts may revert the deposit for the contract to the National Treasury under the provisions of
Article 12 (3) of the Act
and may cancel or terminate the related contract.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
법령보기 화면
Article 76 (Limitation of Qualification of Unjust Persons to Participate in Tender)
(1)
The head of each central government agency shall set restrictions on the qualification of the other party to the contract or the bidder falling under any of the following subparagraphs (including an agent, manager or any other employee of the other party to a contract or the bidder) to participate in a tender up to a period between one month or more and two years or less without delay thereafter under the provisions of
Article 27 of the Act
:
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 15581, Dec. 31, 1997; Presidential Decree No. 15614, Feb. 2, 1998; Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17019, Dec. 27, 2000; Presidential Decree No. 18155, Dec. 11, 2003; Presidential Decree No. 19035, Sep. 8, 2005>
1.
A person who has, in the execution of contractual obligations, performed deficiently, crudely or unreasonably, or committed a malpractice;
2.
A person who has concluded a subcontract in violation of the provisions concerning the limitation of the subcontract (excluding the case of violating the liability for notification of the subcontract) under the
Framework Act on the Construction Industry
, the
Electrical Construction Business Act
, the
Information and Communication Work Business Act
, or other Acts and subordinate statutes, and a person who has concluded a subcontract without the approval of the government agency which has placed the order or has modified the conditions of the subcontract approved by the said government agency;
3.
A person for whom a request for a limitation of qualifications to participate in the tender is made by the Fair Trade Commission due to the violation of the
Monopoly Regulation and Fair Trade Act
or the
Fair Transactions in Subcontracting Act
;
4.
A person who has, in the contract of survey and design services or of cost accounting services, failed to appropriately calculate the amount of survey and design or cost accounting by intent or material fault;
5.
A person who has inflicted an injury on the general public by neglecting safety measures while fulfilling any contract or a person who has inflicted a serious injury, such as death, on employees, etc. by neglecting safety and health measures at a work place under the
Industrial Safety and Health Act
;
6.
A person who has, without any just cause, failed to conclude or execute a contract (including the execution of the matters concerning an incidental tender under
Article 19
and a joint contract under
Articles 72
and
72-2
);
7.
A person who has agreed upon the tendered price in advance by having discussed it between bidders or has committed a collusion for the purpose of successful tender by a specific person in the competitive tender;
8.
A person who has forged or altered the document concerning tender or contract (including any written public certification provided for in the provisions of subparagraph 8 of
Article 2 of the Digital Signature Act
in case where the documents for the tender are submitted in use of the designated information processing apparatus) or uttered it unjustly, or a person who has produced the false document;
9.
A person who has executed an invalid tender by intent;
10.
A person who has, in relation to a bid, successful bid, or conclusion of a contract and execution thereof, offered a bribe to the relevant public official (including members of the International Contract Dispute Conciliation Committee under
Article 29 of the Act
, the Contract Council under
Article 94
of this Decree, the Central Construction Technology Deliberation Committee and the Special Construction Technology Deliberation Committee and the Design Advisory Committee under the
Construction Technology Management Act
);
11.
A person who has failed to participate in the tender three times or more during the corresponding fiscal year without justifiable reasons even after having submitted a written application for participation in the tender or a written consent to participation in the tender;
12.
A person who has interfered with participation in the tender or hinders a successful bidder from concluding the contract and executing it;
13.
A person who has interfered with the performance of duties in the course of supervision or inspection;
14.
A person who has, without just cause, failed to submit the documents in full or part which are required for an inspection of capabilities to execute the contract under the text of
Article 42
(1); and
15.
Where a successful bidder is determined for the alternative tender or package deal tender under
Article 86
or
87
, a person who has failed to submit a written shop design within the time limit without any justifiable reasons after being selected as the person suitable for the shop design.
(2)
The detailed criteria for limitation of qualification to participate in a tender under the provisions of paragraph (1) of this Article shall be prescribed by the Ordinance of the Ministry of Finance and Economy.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(3)
In case of the joint contract, the provisions of paragraph (1) of this Article shall apply to a person who is responsible for the causes of limitation of qualification to participate in the tender.
<Amended by Presidential Decree No. 17019, Dec. 27, 2000>
(4)
If a person who is subject to limitation of the qualification to participate in the tender under the provisions of paragraphs (1) through (3) of this Article is a juristic person or another organization, the provisions of paragraph (1) of this Article shall apply to a representative of such juristic person or organization, and in case of a Small and Medium Enterprise Cooperative, the provisions of paragraph (1) of this Article shall apply to a member of such a cooperative who is directly responsible for the causes of limitation of qualification to participate in the tender:
Provided
, That if there are several representatives of such juristic person or organization, this shall not apply to the representatives who do not perform any duties related to the related tender or contract.
(5)
The head of each government agency, if an original representative is involved in the tender by using a person who is subject to limitation of qualification under the provisions of paragraphs (1) through (4) of this Article as a representative, shall apply paragraph (1) of this Article to the person who has used such representative.
(6)
The head of each central government agency, when limiting the qualification to participate in the tender, shall specify the matters falling under each of the following subparagraphs and shall notify the Minister of Finance and Economy thereof under the conditions as determined by the Ordinance of the Ministry of Finance and Economy, and publish them in the designated information processing apparatus:
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17688, Jul. 30, 2002>
1.
Business(trade) name, address, name (in case of a juristic person, name of the representative, corporation registration number, etc.), resident registration number, trader's registration number, license or registration number under related Acts and subordinate statutes;
2.
Period of limitation of qualification to participate in the tender; and
3.
Specific reasons for limiting the qualification to participate in the tender.
(7)
The head of each central government agency shall prevent a person, who has been subjected to the limitation of qualification to participate in a tender under paragraphs (1) through (5), from participating in a ll tenders executed by the said government agency during the competent period of limitation.
<Amended by Presidential Decree No. 17688, Jul. 30, 2002>
(8)
The head of each central government agency may prevent a person, who has received a notification of the fact that a limitation of qualification to participate in a tender has been made or who has been so published in the designated information processing apparatus under the
Local Finance Act
or the
Framework Act on the Management of Government-Invested Institutions
, from participating in a tender:
Provided
, That a person who has been subjected to the limitation of qualification to participate in a tender on account of the causes under paragraph (1) 1 through 5, 7 and 8, shall be prevented without fail from participating in the tender.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17688, Jul. 30, 2002; Presidential Decree No. 19035, Sep. 8, 2005>
(9)
The head of each central government agency shall identify the resident registration number, corporation registration number, licence or registration number under related Acts and subordinate statutes, etc. in order to prevent a person whose qualification is limited under the provisions of paragraphs (1) through (4) of this Article from participating in a tender during the period of limitation by means of changing its trade name and its representative, etc.
(10)
The head of each central government agency or the public official in charge of contracts shall not, unless unavoidable reason exists, conclude a negotiated contract with a person who has been subjected to the limitation of qualification to participate in a tender under paragraph (1).
<Newly Inserted by Presidential Decree No. 16548, Sep. 9, 1999>
(11)
The matters necessary for the procedures for the notification of limitation of qualification to participate in a tender, etc. under paragraphs (6) and (7) shall be determined by the Ordinance of the Ministry of Finance and Economy.
<Newly Inserted by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 77 Deleted.<by Presidential Decree No. 15614, Feb. 2, 1998>
CHAPTER VI CONTRACT FOR LARGE CONSTRUCTION WORK
법령보기 화면
Article 78 (Applicable Objects, etc.)
A contract by an alternative plan tender or a package deal tender from among the contracts for large construction work shall be based on the provisions of this Chapter, however the matters which are not specially prescribed in this Chapter shall be based on the provisions of other Chapters of this Decree.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 79 (Definitions)
(1)
For the purpose of this Chapter, the definitions of the terms shall be as follows:
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
1.
The term "large construction work" means a construction work of new compound type of which the estimated price of whole construction cost is 10 billion won or more;
2.
The term "specified construction work" means a construction work for which the head of each central government agency deems it advantageous to execute it by an alternative plan tender or a package deal tender from among the construction works of new compound type of which the estimated price of whole construction cost is 10 billion won or more;
3.
The term "alternative plan" means the plan which is capable of executing the works by the methods, for which the cost on the competent plan is lower than that on the plan prepared by the Government and its work period is not exceeding that on the plan prepared by the Government (in case of a reduction of work period, limited to a period shorter than that on the plan prepared by the Government), with respect to the work type capable of a replacement from among the types on the plan prepared by the Government (refers to a basic plan and an execution plan for whole works), and the plan which reflects a new technology and a reduction of construction period, etc. carrying the equal or superior functions and effects capable of substituting the plan prepared by the Government without changing a basic policy;
4.
The term "tender by alternative plan" means a tender for construction work in which an alternative plan under the provisions of subparagraph 3 of this paragraph is permitted according to the separate intention of the bidders together with a tender by original design;
5.
The term "tender on a package deal" means a tender of the combined plan and construction under which a plan of construction work and other necessary drawings and documents in carrying out the construction work (hereinafter referred to as the "drawings and documents") shall be prepared and submitted together with the documents for tender at the time of the tender in accordance with the basic plan and guidelines of the tender for construction on a package deal presented by the Government;
6.
The term "tender by basic design" means a tender under which a basic design, and drawings and documents thereof shall be prepared and submitted together with the documents for tender prior to the shop design in accordance with the government's basic plan and guidelines for a tender on a package deal basis;
7.
The term "guide to competitive tender" means the document including the scope, size, plan, construction standards, control of quality and process and other basic plans and guidelines for the tender or the execution of contract, which a person intending to participate in a tender under items 4 and 6 shall know well prior to a participation in the tender of relevant construction;
8.
The term "execution plan" means a plan necessary for a construction work (including a literature attached to the plan) which is prepared in detail in accordance with the basic plans, guidelines and the basic design;
9.
The term "large construction work by a continuous expenditure" means a large construction work of which the construction cost is earmarked in the budget as a continuous expenditure; and
10.
The term "general large construction work" means a large construction work of which the construction cost is not earmarked in the budget as a continuous expenditure.
(2)
If any objections are raised against the scope and limit of design which can be replaced as referred to in paragraph (1) 3 of this Article, the head of each central government agency shall determine such scope and limit by undergoing the deliberation of the Central Construction Technology Deliberation Committee under the
Construction Technology Management Act
(hereinafter referred to as the "Central Construction Technology Deliberation Committee"):
Provided
, That the head of each central government agency who has established and operated the Design Advisory Committee (including the heads under his jurisdiction; hereinafter the same shall apply) may determine the scope and limit via a deliberation by the Design Advisory Committee.
<Amended by Presidential Decree No. 15614, Feb. 2, 1998; Presidential Decree No. 19035, Sep. 8, 2005>
법령보기 화면
Article 80 (Deliberation of Bidding Methods for Large Scale Constructions)
(1)
The head of each central government agency shall, in case of the bidding methods for large scale constructions and specific constructions (hereafter in this Article referred to as "large scale constructions, etc."), go through the deliberation by the Central Construction Technology Deliberation Committee in regard to the method of tender:
Provided
, That in case where he establishes and operates the Design Advisory Committee, he may determine the bidding methods through a deliberation by the Design Advisory Committee in accordance with the standards provided by the Central Construction Technology Deliberation Committee.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(2)
The head of each central government agency shall, in case where he intends to receive the deliberation by the Central Construction Technology Deliberation Committee under the main sentence of paragraph (1), submit the basic plans for the execution of large scale construction works, etc. to be executed after the current year to the Minister of Construction and Transportation under the Ordinance of the Ministry of Finance and Economy before preparing the basic design:
Provided
, That in case where the deliberation is difficult without relying on the basic design, he shall submit without delay the plan for execution to the Minister of Construction and Transportation after the preparation of basic design.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(3)
The Minister of Construction and Transportation shall, in case where he has gone through the deliberation by the Central Construction Technology Deliberation Committee with respect to the basic plans for executing the large construction works, etc. or the plans for execution submitted under paragraph (2), give a public notice of the large construction works, etc. to be executed by the method of an alternative plan tender or a package deal tender in accordance with the results of deliberation.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(4)
The head of each central government agency shall, in case where he has gone through the deliberation by the Design Advisory Committee under the proviso of paragraph (1), give a public notice of the large construction works, etc. to be executed by the method of an alternative plan tender or a package deal tender in accordance with the results of deliberation.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(5)
The head of each central government agency shall, in case of the large construction works, etc., make a tender by the methods publicly announced under paragraph (3) or (4) unless there exist no special causes.
[This Article Wholly Amended by Presidential Decree No. 15614, Feb. 2, 1998]
법령보기 화면
Articles 81 through 83 Deleted.<by Presidential Decree No. 15186, Dec. 31, 1996>
법령보기 화면
Article 84 (Qualification to Participate in Package Deal Tender)
The head of each central government agency or the public official in charge of contracts shall allow only those who satisfy the requirement falling under each of the following subparagraphs to participate in a package deal tender:
Provided
, That in case where the persons, who satisfy only one from among the requirements under subparagraphs 1 and 2, intend to jointly participate in the package deal tender, he shall allow their participation in the tender:
<Amended by Presidential Decree No. 15433, Jul. 10, 1997; Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17019, Dec. 27, 2000; Presidential Decree No. 19035, Sep. 8, 2005>
1.
A person shall be the one who has registered a construction business under
Article 9 of the Framework Act on the Construction Industry
which is necessary for executing the relevant construction work; and
2.
A person shall be the businessman of services for design, etc. under
Article 20-2 of the Construction Technology Management Act
, or a person who has reported on his business as a certified architect under
Article 23 of the Certified Architects Act
.
법령보기 화면
Article 85 (Procedures for Tender on Package Deal Basis, etc.)
(1)
Under a tender on a package deal basis, only a person who is selected as a person eligible for the shop design under the provisions of
Article 87
(1) after having executed the tender by basic design shall be allowed to submit the shop design document.
(2)
If the participant in the alternative tender submits an alternative together with the original tender, then the drawings and documents prescribed in each of the following subparagraphs shall be submitted accompanied by the documents for the tender:
Provided
, That two or more alternative tenders may not be submitted at the same time:
<Amended by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 19035, Sep. 8, 2005>
1.
A particular explanatory note concerning the alternative design;
2.
Related documents under Article 13 of the Enforcement Decree of the Construction Technology Management Act;
3.
A calculation statement of particulars specifying the unit cost and quantity of the original tender and alternative tender:
Provided
, That in case where the basic design is submitted as an alternative tender, a calculation statement of particulars concerning the construction work may be omitted;
4.
Documents in which the advantages derived from the adoption of an alternative tender, and other reference matters are specified; and
5.
Execution design document prepared by a person eligible for the execution design under
Article 86
(3) in accordance with the guidelines as determined in the guide to a tender.
(3)
A bidder on a package deal basis shall submit the documents for tender by basic design or shop design documents accompanied by the drawings and documents thereto classified according to each of the following subparagraphs:
<Amended by Presidential Decree No. 19035, Sep. 8, 2005>
1.
In case of the documents for tender by basic design:
(a)
An explanatory note concerning the basic design;
(b)
Related documents under the provisions of Article 13 of the Enforcement Decree of the Construction Technology Management Act; and
(c)
Other matters required by public notice;
2.
In case of shop design documents:
(a)
A concrete explanatory note concerning the shop design;
(b)
Related documents under the provisions of Article 13 of the Enforcement Decree of the Construction Technology Management Act;
(c)
A statement of particulars concerning calculation in which the unit cost and quantity are specified; and
(d)
Documents in which other reference matters are specified.
(4)
Deleted.
<by Presidential Decree No. 16548, Sep. 9, 1999>
(5)
The head of each central government agency or the public official in charge of contracts shall, in case where it falls under any of the following subparagraphs, request the Central Construction Technology Deliberation Committee to deliberate on the eligibility of the relevant design and make an assessment of a design score. In this case, the Construction Technology Deliberation Committee shall examine the technical feasibility and notify the relevant head of each central government agency or the public official in charge of contracts of the document specifying the eligibility of design (excluding the case of original tender) and the marks scored by the design:
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
1.
In case where the original design (including the basic design and the execution design) and the alternative bid (including the basic design and the execution design; hereinafter the same) selected under
Article 86
(1) from among the bids eligible for a successful tender are submitted in the case of an alternative tender; and
2.
In case where the basic design bid or the execution design under paragraph (3) is submitted in the case of a package deal tender.
(6)
The head of each central government agency or the public official in charge of contracts may replace a deliberation of the design under the provisions of paragraph (5) of this Article with a deliberation by the Design Advisory Committee on the shop design:
Provided
, That if the Design Advisory Committee is not established, this shall not apply.
<Newly Inserted by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 15614, Feb. 2, 1998>
(7)
The Central Construction Technology Deliberation Committee or the Design Advisory Committee may, in case where it deliberates on the design under paragraph (5) or (6), request, in case where the literature attached to an alternative tender, a tender by basic design or an execution design is insufficient or vague in its content in the light of the contents of the basic plans and guidelines for the tender or the contents of the basic design, the complement to them.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 86 (Selection of Successful Bidder in Alternative Tender)
(1)
The head of each central government agency or the public official in charge of contracts shall, in case where an alternative tender has been submitted under
Article 85
(2), select all alternative tenders as the one eligible for the successful tender, of which the alternative tender amount is less than the estimated price for whole construction works and the tender amount for the alternative construction type is less than the estimated price for the alternative construction style:
Provided
, That the alternative tender amount shall be excluded in case where they are higher than the bidder's own original tender amount.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(2)
The head of each central government agency or the public official in charge of contracts shall, in case where he has received the notification under
Article 85
(5), select 4 tenders in the order of the highest marks scored for their designs from among the alternative tenders notified as eligible and decide whether they are adoptable.
<Newly Inserted by Presidential Decree No. 16548, Sep. 9, 1999>
(3)
The head of each central government agency or the public official in charge of contracts shall, in case where he has received a basic design as an alternative, determine the person who has satisfied the criteria for examination of the eligibility under
Article 42
(2) as the preparer of execution design from among the persons who submitted the original tenders and those who submitted the alternative design adopted under paragraph (1). In case where he has received an execution design as an alternative, the person who has satisfied the criteria for examination of the eligibility under
Article 42
(2) shall be decided as a successful bidder from among the persons who submitted the original tenders and the persons who submitted the alternative design adopted under paragraph (1). In this case, the provisions of
Articles 85
(5) and
87
(2) and (5) shall apply
mutatis mutandis
with respect to the determination of the person eligible for an execution design as a successful bidder.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(4)
If no persons have submitted an alternative proposal in the alternative tender or there exists no successful bidder under paragraph (3), the person whose tendered amount of an original design is less than the estimated price and is of the lowest amount and who has satisfied the criteria for examination of the eligibility under
Article 42
(2) shall be determined as a successful bidder.
(5)
The determination of a successful bidder under paragraphs (1) through (4) shall be completed within 80 days from the date of the tender unless unavoidable reasons exist.
법령보기 화면
Article 87 (Selection of Successful Bidder in Package Deal Tender)
(1)
The head of each central government agency or the public official in charge of contracts, when receiving the notification under the provisions of
Article 85
(5) in respect of a tender by basic design, shall select four persons whose design has scored high marks from among participants in the tender and shall determine the persons eligible for the execution design who have met the criteria for examination on eligibility provided in
Article 42
(2).
(2)
The head of each central government agency or the public official in charge of contracts, when receiving the notification on the eligibility of related execution design from the Central Construction Technology Deliberation Committee or the Design Advisory Committee under the provisions of
Article 85
(5) and (6) shall determine a person who has submitted the related execution design as the successful bidder.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996>
(3)
The head of each central government agency or the public official in charge of contracts shall, in case where the tendered amount of a bidder determined as the person eligible for the execution design under paragraph (1) exceeds the budget of continuing expenditure in the case of large scale construction work by continuing expenditure and that of the whole construction works in the case of general large scale construction work respectively, consult with the bidder in order to adjust the tendered amount to the budget limit, and conduct the tender by a second public notice in case where the consultation is not succeeded.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(4)
The determination of a successful bidder under paragraphs (1) and (2) of this Article shall be completed within 60 days from the date on which the execution design has been submitted unless unavoidable reasons exist.
(5)
The head of each central government agency or the public official in charge of contracts may, with respect to the determination of a successful bidder under paragraph (2), have the person eligible for the execution design under paragraph (1) to prepare the execution design by classifying the relevant construction work in the order of priority by work stage, in case where he deems it necessary due to the urgency of construction and other special circumstances; and in case where he has received the notification on the eligibility of relevant execution design from the Central Construction Technology Deliberation Committee or the Design Advisory Committee, the said person eligible for the execution design may be determined as a successful bidder and may execute the construction work in the order of priority.
<Newly Inserted by Presidential Decree No. 16548, Sep. 9, 1999>
(6)
The head of each central government agency or the public official in charge of contracts shall have the person who has been determined as a successful bidder under paragraph (5) submit, prior to an execution of construction works, the statement of particulars of calculation with respect to whole construction works and the work which has received a notification of the eligibility for the execution design, and conclude a contract with him in accordance with the said statement.
<Newly Inserted by Presidential Decree No. 16548, Sep. 9, 1999>
(7)
The head of each central government agency or the public official in charge of contracts shall, in case where there exists a notification of the eligibility for the final execution design of whole construction works, have the person who has concluded the contract under paragraph (6) reprepare a statement of particulars of calculation and substitute it for the initial statement of particulars of calculation. In this case, the initial contract amount shall not be increased.
<Newly Inserted by Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 17019, Dec. 27, 2000>
(8)
The head of each central government agency or the public official in charge of contracts shall, in case where he intends to determine a successful bidder under paragraphs (5) and (6) or conclude a contract, specify the scope of work types and the submission period under which the execution design shall be submitted in preference and the matters for the preparation and submission of the statement of particulars of calculation, etc. on the guide to competitive tender so that the persons who intend to participate in a tender shall know them prior to the tender.
<Newly Inserted by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 88 Deleted.<by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 89 (Compensation for Design Cost)
(1)
The head of each central government agency or the public official in charge of contracts may compensate, within the limit of budget, the person who has not been determined as a successful bidder from among those selected under
Articles 86
(2) and
87
for a part of design costs.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
(2)
Necessary matters related to the criteria and procedures, etc. for the payment of compensation for design cost under the provisions of paragraph (1) shall be prescribed by the Minister of Finance and Economy.
<Amended by Presidential Decree No. 16548, Sep. 9, 1999>
법령보기 화면
Article 90 (Adoption of Alternative Tender)
(1)
The head of each central government agency or the public official in charge of contracts, when intending to determine the adoption of an alternative tender under the provisions of
Article 86
(3), shall determine first the adoption of the alternative tender by types of work, and if there are types of work which are not adopted as an alternative, the head of each central government agency or the public official in charge of contracts shall determine as the successful bidder a persons who meet the criteria for examination on eligibility provided in
Article 42
(2) as the successful bidder, after adjusting the tendered amount by replacing it with the tendered amount of related types of work specified in the statement of particulars concerning calculation submitted by the related alternative bidder when he submitted the original tender. In this case, the adjusted tendered amount of the alternative tender shall be equal to the tendered amount eligible for a successful tender under the provisions of
Article 86
(1).
(2)
The head of each central government agency or the public official in charge of contracts, even when modifying a part of the alternative tender concerning types of work adopted from among alternative tenders adjusted under the provisions of paragraph (1) of this Article, may not increase the tendered amount of the related type of work.
(3)
The adjustment or modification under the provisions of paragraphs (1) and (2) of this Article shall be preceded by the deliberation of the Central Construction Technology Deliberation Committee.
(4)
The head of each central administrative government agency or the public official in charge of contracts may replace a deliberation referred to in paragraph (3) with that by the Design Advisory Committee:
Provided
, That this shall not apply where the Design Advisory Committee is not established.
<Newly Inserted by Presidential Decree No. 15614, Feb. 2, 1998>
법령보기 화면
Article 91 (Restriction of Adjustment of Contract Amount Due to Change of Design)
(1)
In case where the content of a contract for large scale construction work is changed due to a design change in the alternative tender or the package deal tender, the contract amount shall not be increased unless such change is due to the causes attributable to the Government or
force majeure
such as natural disasters.
<Amended by Presidential Decree No. 15186, Dec. 31, 1996; Presidential Decree No. 16548, Sep. 9, 1999>
(2)
In case where he intends to adjust the contract amount in case of paragraph (1), it shall be based on the criteria falling under each of the following subparagraphs:
<Amended by Presidential Decree No. 15614, Feb. 2, 1998; Presidential Decree No. 16548, Sep. 9, 1999; Presidential Decree No. 19035, Sep. 8, 2005>
1.
The unit cost of a decreased quantity of construction work: The unit cost on the statement of particulars of calculation which has been submitted under
Article 85
(2) and (3);
2.
The unit cost of increased quantity of construction work: The unit cost determined by mutual agreement between parties to a contract within the limit of the unit cost calculated at the time of change of design and unit cost specified in a statement of particulars concerning calculation referred to in subparagraph 1:
Provided
, That in case where no agreement is reached between the parties to a contract, the unit cost shall be 50/100 of the amount obtained by adding the unit cost calculated at the time when the design is changed to the unit cost specified in a statement of particulars concerning calculation referred to in subparagraph 1; and
3.
The unit cost of a new item which is not listed on the statement of particulars of calculation under subparagraph 1: The unit cost calculated on the basis of the time of a design change.
법령보기 화면
Article 91-2 (Construction Project Management Contract)
(1)
The head of each central government agency or the public official in charge of contracts may, in case where he concludes a contract for construction work under the
Framework Act on the Construction Industry
from among the large scale construction, and where he deems it necessary in consideration of the characteristics, size and execution period of the contract objects, conclude a contract for the construction project management task with the person who, with respect to the planning, feasibility study, design, work execution, supervision, repair and management, etc. for the said construction, conducts the task of comprehensive management, in all or part (hereinafter referred to as the "construction project management task").
<Amended by Presidential Decree No. 19035, Sep. 8, 2005>
(2)
The method of a contract conclusion under paragraph (1) and other necessary matters shall be determined by the Minister of Finance and Economy.
[This Article Newly Inserted by Presidential Decree No. 16548, Sep. 9, 1999]
법령보기 화면
Article 92 (Evaluation)
The head of each central government agency or the public official in charge of contracts may organize a group for evaluation and conduct an evaluation with respect to a business plan, construction process, performance, and effects of the related construction work after the inspection of completion of large scale construction.
CHAPTER VII PUBLICATION OF CONTRACT INFORMATION, ETC.
법령보기 화면
Article 92-2 (Publication of Information Pertaining to Contracts)
(1)
The head of each central government agency or the public official in charge of contracts shall publish matters concerning the quarterly plan to place orders, to conclude contracts and to change contracts, which are prescribed by the Ordinance of the Ministry of Finance and Economy, in the designated information processing apparatus or the information processing apparatus that is designated and published by the head of each central government agency pursuant to the provisions of the proviso of
Article 39
(2):
Provided
, That the same shall not apply to a case where any negotiated contract is concluded on the grounds of the movement of troops for military operations in
Article 26
(1) 1 and on the grounds provided for in the provisions of
Article 26
(1) 2 and 6 (c).
(2)
The head of each central government agency concerned or the public official in charge of contracts shall, in case where any change is made in the contents published pursuant to the provisions of the main sentence of paragraph (1), publish without delay the fact of such change.
[This Article Newly Inserted by Presidential Decree No. 19035, Sep. 8, 2005]
법령보기 화면
Article 93 (Report on Contract Records)
The head of each central government agency and the public official in charge of contracts shall submit the matters concerning the conclusion of contracts and changes in such contracts, which are prescribed by the Ordinance of the Ministry of Finance and Economy, to the Minister of Finance and Economy within 30 days from the date on which such contracts are concluded and such changes are made in contracts:
Provided
, That the same shall not apply to a case where any negotiated contract is concluded on the grounds of the movement of troops for military operations in
Article 26
(1) 1 and on the grounds provided for in the provisions of
Article 26
(1) 2 and 6 (c).
[This Article Wholly Amended by Presidential Decree No. 19035, Sep. 8, 2005]
법령보기 화면
Article 94 (Establishment of Contract Council)
(1)
The head of each central government agency or the head of an institution under his jurisdiction may establish and operate the Contract Council to provide advice and suggestions concerning the qualification requirements for participating in a tender for goods, construction works, or services, etc. and other contract-related matters.
<Amended by Presidential Decree No. 19035, Sep. 8, 2005>
(2)
The Contract Council under paragraph (1) shall consist of public officials of such agency or institution, persons with extensive learning and experience in the field of contracts, persons recommended by civic organizations (referring to nonprofit non-governmental organizations under Article 2 of the Assistance for Nonprofit Non-Governmental Organizations Act), etc.
<Amended by Presidential Decree No. 19035, Sep. 8, 2005>
(3)
Detailed matters necessary for the composition and operation of the Contract Council under paragraph (1) shall be determined by the head of each central government agency.
[This Article Newly Inserted by Presidential Decree No. 17019, Dec. 27, 2000]
법령보기 화면
Article 95 Deleted.<by Presidential Decree No. 19035, Sep. 8, 2005>
법령보기 화면
Article 96 (Utilization of Designated Information Processing Apparatus)
(1)
The Minister of Finance and Economy may designate the persons who manage and operate the designated information processing apparatus. In this case, the Minister of Finance and Economy shall publicly announce them.
(2)
The head of each central government agency or the public official in charge of contracts and the persons who manage and operate the designated information processing apparatus under the provisions of paragraph (1), shall not use such information as related to the limitation on qualification of unjust persons to participate in a tender under the provisions of
Article 76
, to the report on performances of contract under the provisions of
Article 93
, and to other contracts, for other usages than the purpose of competent duties.
[This Article Newly Inserted by Presidential Decree No. 17688, Jul. 30, 2002]
ADDENDA
Article 1 (Enforcement Date)
This Decree shall enter into force on July 6, 1995:
Provided
, That the provisions of
Article 9
(1) 3 shall enter into force on January 1, 1996.
Article 2 Deleted.
Article 3 (Transitional Measures concerning Conclusion of Contract, etc.)
With respect to a tender, the determination of a successful bidder, and the conclusion of contracts which are executed after the enforcement of this Decree where public notice of the tender has been made before the enforcement of this Decree, and with respect to contracts concluded after the enforcement of this Decree after being selected as the successful tender in a tender conducted before the enforcement of this Decree, the previous provisions shall apply.
Article 4 (Repeal and Amendment of Other Acts and Subordinate Statutes)
(1)
The Special Regulations of the Enforcement Decree of the Act on the Budget and Accounts Related to Contracts for Large Scale Construction Work shall be repealed.
(2)
through (6) Omitted.
Article 5 (Relation to Other Acts and Subordinate Statutes)
If Chapter VI of the
Enforcement Decree of the Budget and Accounts Act
or the provision of the said Chapter of the said Decree have been cited in other Acts and subordinate statutes at the time when this Decree enters into force, or if the Special Regulations of the Enforcement Decree of the Act on Budget and Accounts Related to Contracts for Large Scale Construction Work or the provisions of the said Special Regulations have been cited in other Acts and subordinate statutes, this Decree and Chapter VI of this Decree, or the corresponding provisions of this Decree shall be deemed to have been cited therein.
ADDENDA<Presidential Decree No. 14973, Apr. 8, 1996>
Article 1 (Enforcement Date)
This Decree shall enter into force on the date of its promulgation.
Article 2 Omitted.
ADDENDA<Presidential Decree No. 15186, Dec. 31, 1996>
Article 1 (Enforcement Date)
This Decree shall enter into force on January 1, 1997.
Article 2 (Examples of Application concerning Replacement of Guarantee Certificate of Deposit for Difference to be Paid in Cash)
(1)
The head of each central government agency or the public official in charge of contracts may have, for construction work of which the deposit for the difference is paid in cash under the proviso of Article 123 (1) of the
Enforcement Decree of the Budget and Accounts Act
amended under Presidential Decree No. 14295 (hereinafter referred to as the "former Enforcement Decree of the Budget and Accounts Act"), cash amount in all paid replaced by a guarantee certificate in an amount equivalent to the cash:
Provided
, That this shall not apply to those whose qualifications have been restricted to participation in the tender and who are under such restriction for a cause under
Articles 76
(1) 1 through 5, 7 and 8.
<Amended by Presidential Decree No. 15661, Feb. 24, 1998>
(2)
The head of each central government agency or the public official in charge of contracts may have a guarantee certificate submitted under the purview of Article 123 (1) of the former Enforcement Decree of the Budget and Accounts Act replaced by a certificate guaranteeing an equal amount where the deposit of the difference is paid in cash.
(3)
The necessary matters on the replacement methods and procedures for a guarantee certificate referred to in paragraphs (1) and (2) shall be determined by the Minister of Finance and Economy.
<Amended by Presidential Decree No. 15661, Feb. 24, 1998>
[This Article Wholly Amended by Presidential Decree No. 15614, Feb. 2, 1998]
Article 3 (Examples of Application concerning Treatment of Deposit for Difference Paid in Cash at Time of Prolongation of Contract Period)
If the head of each central government agency or the public official in charge of contracts has received the deposit in cash under the proviso of Article 123 (1) of the
Enforcement Decree of the Budget and Accounts Act
amended by Presidential Decree No. 14295, he may allow the other party to the contract to replace the cash with a guarantee certificate in an amount equal to or exceeding the said cash to be paid after the expiration of the original period of the contract upon the request of the other party to the contract when the period of the contract is extended due to causes not attributable to the other party.
Article 4 (Transitional Measures concerning Conclusion of Contract)
With respect to the tender, of which the public notice has been made before the enforcement of this Decree, the determination of successful bidder, and the conclusion of the contract, which are executed after the enforcement of this Decree, and with respect to contracts concluded after the enforcement of this Decree after being selected as a successful tender in a tender executed before the enforcement of this Decree, the previous provisions shall apply.
ADDENDA<Presidential Decree No. 15433, Jul. 10, 1997>
Article 1 (Enforcement Date)
This Decree shall enter into force on the date of its promulgation. (Proviso Omitted.)
Articles 2 through 10 Omitted.
ADDENDA<Presidential Decree No. 15581, Dec. 31, 1997>
Article 1 (Enforcement Date)
This Decree shall enter into force on January 1, 1998. (Proviso Omitted.)
Articles 2 through 7 Omitted.
ADDENDA<Presidential Decree No. 15582, Dec. 31, 1997>
(1)
(Enforcement Date) This Decree shall enter into force on January 1, 1998.
(2)
Omitted.
ADDENDA<Presidential Decree No. 15614, Feb. 2, 1998>
Article 1 (Enforcement Date)
This Decree shall enter into force on the date of its promulgation:
Provided
, That an amendments to
Article 42
shall enter into force one year following the date of its promulgation.
Article 2 (Abolition of Other Regulations)
The Contract Deliberation Committee Regulations shall be hereby abolished.
Article 3 (Examples of Applications concerning Replacement of Guarantee Certificate of Deposit for Difference to be Paid in Cash)
(1)
An amendment to Article 2 (1) of the Addenda of the Presidential Decree No. 15186 shall apply to bids submitted under the previous provisions.
(2)
An amendment to Article 2 (1) and (3) and Article 3 of the Addenda of the Presidential Decree No. 15186 shall apply
mutatis mutandis
to contract deposits paid in cash under the proviso of the previous Article 50 (7).
Article 4 (Transitional Measures concerning Conclusion of Contracts)
Tenders, determination of successful bidders, and conclusion of contracts conducted after the entry into force of this Decree after announcing invitation for bids prior to the entry into force of this Decree, and contracts concluded after the entry into force of this Decree after succeeding in tenders conducted prior to the entry into force of this Decree shall be governed by the previous provisions.
Article 5 Omitted.
ADDENDA<Presidential Decree No. 15661, Feb. 24, 1998>
(1)
(Enforcement Date) This Decree shall enter into force on the date of its promulgation.
(2)
(Examples of Application) An amendment to
Article 64
shall also apply to contracts concluded prior to the entry into force of this Decree.
ADDENDA<Presidential Decree No. 16308, May 13, 1999>
Article 1 (Enforcement Date)
This Decree shall enter into force on the date of its promulgation.
Articles 2 through 10 Omitted.
ADDENDA<Presidential Decree No. 16448, Jun. 30, 1999>
Article 1 (Enforcement Date)
This Decree shall enter into force on July 1, 1999.
Articles 2 through 5 Omitted.
ADDENDA<Presidential Decree No. 16548, Sep. 9, 1999>
(1)
(Enforcement Date) This Decree shall enter into force on the date of its promulgation:
Provided
, That the amendments to
Article 19
, subparagraph 14 of
Article 36
, and
Article 72
(3) shall enter into force on January 1, 2002.
<Amended by Presidential Decree No. 17019, Dec. 27, 2000>
(2)
(Transitional Measures concerning Conclusion of Contracts, etc.) The previous provisions shall be applied to the tenders, determination of a successful bidder, and conclusion of contracts which are made after the entry into force of this Decree and after the announcement of invitation to bids prior to the entry into force of this Decree, and the contracts which are concluded after the entry into force of this Decree after a successful bidding at a tender conducted prior to the entry into force of this Decree.
(3)
(Transitional Measures concerning Orders for Large Scale Construction to be Executed under Means of Execution Design and Construction Work Tender) The previous provisions shall be applied to the large scale constructions which have been publicly notified to be executed by means of an execution design and construction work tender under
Article 80
prior to the entry into force of this Decree.
(4)
(Transitional Measures concerning the Korea Association of Electrical Engineers) The Korea Association of Electrical Engineers under paragraph (2) of the Addenda of the
Electric Technology Management Act
amended by Act No. 5784, shall be deemed as an organization of electrical engineers which has been publicly notified by the Minister of Commerce, Industry and Energy under the amendments of
Article 37
(2) 4.
ADDENDA<Presidential Decree No. 16682, Dec. 31, 1999>
Article 1 (Enforcement Date)
This Decree shall enter into force on January 1, 2000.
Articles 2 through 4 Omitted.
ADDENDA<Presidential Decree No. 16919, Jul. 27, 2000>
Article 1 (Enforcement Date)
This Decree shall enter into force on July 29, 2000.
Articles 2 through 6 Omitted.
ADDENDA<Presidential Decree No. 16943, Aug. 5, 2000>
(1)
(Enforcement Date) This Decree shall enter into force on the date of its promulgation.
(2)
and (3) Omitted.
ADDENDA<Presidential Decree No. 17019, Dec. 27, 2000>
(1)
(Enforcement Date) This Decree shall enter into force on the date of its promulgation:
Provided
, That the amended provisions of the proviso of
Article 42
(1) and the proviso of
Article 52
(1) excluding the subparagraphs thereof shall enter into force on January 1, 2001.
(2)
(Applicable Cases concerning Limitation of Qualification of Unjust Persons to Participate in Tender) The amended provisions of
Article 76
(1) 10 shall apply to those on which any cause for limitation occurs on or after the enforcement date of this Decree.
(3)
(Transitional Measures concerning Conclusion, etc. of Contracts) With respect to a tender the public notice of which is made before the enforcement of this Decree and which is conducted after the enforcement thereof, the determination of a successful bidder therefor, and the conclusion of a contract therefor, and with respect to a contract for which a successful tender is made in the tender conducted before the enforcement of this Decree and which is concluded after the enforcement thereof, the previous provisions shall apply.
ADDENDA<Presidential Decree No. 17344, Aug. 25, 2001>
Article 1 (Enforcement Date)
This Decree shall enter into force on the date of its promulgation.
Articles 2 and 3 Omitted.
ADDENDA<Presidential Decree No. 17546, Mar. 25, 2002>
(1)
(Enforcement Date) This Decree shall enter into force on the date of its promulgation.
(2)
(Validity Term) The amended provisions of
Article 19
and subparagraph 14 of
Article 36
shall hold their validity not later than December 31, 2003.
(3)
(Transitional Measures for Conclusion of Contracts, etc.) The previous provisions shall govern in the cases of a tender, a decision on successful bidder, and a conclusion of contract which are to be executed after the enforcement of this Decree in the wake of a tender notification made prior to the enforcement of this Decree, and the case of a contract to be concluded after the enforcement of this Decree in the wake of a successful bid achieved prior to the enforcement of this Decree.
ADDENDA<Presidential Decree No. 17585, Apr. 20, 2002>
(1)
(Enforcement Date) This Decree shall enter into force on the date of its promulgation.
(2)
through (4) Omitted.
ADDENDA<Presidential Decree No. 17688, Jul. 30, 2002>
(1)
(Enforcement Date) This Decree shall enter into force on September 30, 2002:
Provided
, That the amended provisions of
Article 68
shall enter into force on the date of its promulgation.
(2)
(Transitional Measures for Designated Information Processing Apparatus) The head of each central government agency or the public official in charge of contracts may follow the previous provisions not later than December, 31, 2002, in case where it is difficult to utilize the designated information processing apparatus due to inevitable reasons, notwithstanding the amended provisions of
Articles 22
and
33
, subparagraph 12-2 of
Article 36
, and
Articles 39
,
40
(3) and
76
(6) through (8).
(3)
(Transitional Measures for Conclusion of Contracts, etc.) The previous provisions shall govern the bidding, decision on a successful bidder and conclusion of contracts, which are effected after the enforcement of this Decree subsequent to the public notice of bidding before the enforcement of this Decree, and the contracts to be concluded after the enforcement of this Decree subsequent to a successful bid in the bidding executed before the enforcement of this Decree.
ADDENDA<Presidential Decree No. 17791, Dec. 5, 2002>
Article 1 (Enforcement Date)
This Decree shall enter into force on the date of its promulgation.
Articles 2 and 3 Omitted.
ADDENDA<Presidential Decree No. 17824, Dec. 30, 2002>
Article 1 (Enforcement Date)
This Decree shall enter into force on January 1, 2003. (Proviso Omitted.)
Articles 2 through 6 Omitted.
ADDENDA<Presidential Decree No. 18155, Dec. 11, 2003>
(1)
(Enforcement Date) This Decree shall enter into force on the date of its promulgation:
Provided
, That the amended provisons of
Article 37
(2) 7 shall enter into force on January 5, 2004.
(2)
(Example of Application to Restrictions on Qualification for Participation in Tender by Unjust Business Operator) The amended provisons of
Article 76
(1) 15 shall apply starting with the portion of causes for relevant restrictions occurring after the enforcement of this Decree.
(3)
(Transitional Measures for Contract Conclusions, etc.) The previous provisions shall govern the tender which a public notice of tender was made for prior to the enforcement of this Decree and is executed after the enforcement of this Decree, the decisions on successful bidders and the contract conclusions, and the contract concluded after the enforcement of this Decree for the successful bidder in the tender executed prior to the enforcement of this Decree.
ADDENDA<Presidential Decree No. 18359, Apr. 6, 2004>
(1)
(Enforcement Date) This Decree shall enter into force on the date of its promulgation.
(2)
(Transitional Measures regarding Adjustment of Contract Amount Due to Price Fluctuations) The amended provisions of
Article 64
shall also apply to a contract concluded before the enforcement of this Decree.
ADDENDA<Presidential Decree No. 18666, Dec. 31, 2004>
(1)
(Enforcement Date) This Decree shall enter into force on January 1, 2005. (Proviso Omitted.)
(2)
and (3) Omitted.
ADDENDA<Presidential Decree No. 18903, Jun. 30, 2005>
Article 1 (Enforcement Date)
This Decree shall enter into force on July 1, 2005.
Article 2 Omitted.
ADDENDA<Presidential Decree No. 19035, Sep. 8, 2005>
(1)
(Enforcement Date) This Decree shall enter into force on the date of its promulgation:
Provided
, That the amended provisions of
Articles 21
(1) 8 and
23
(1) 10 shall enter into force on January 1, 2006.
(2)
(Applicable Examples concerning Ways of Payment of Bid Bond and Exception Thereof) The amended provisions of
Article 37
(2) 4 and (3) 5 shall apply to the bidding for which the closing date for submitting the documents for the tender arrives after the enforcement of this Decree.
(3)
(Transitional Measures concerning Adjustment of Contract Amount on Grounds of Price Fluctuation or Design Change) The amended provisions of
Articles 64
(1) and (5),
65
(2) and (3) 3 and
91
(2) 2 (proviso) shall also apply to any contract that is concluded prior to the enforcement of this Decree.
ADDENDA<Presidential Decree No. 19321, Feb. 8, 2006>
Article 1 (Enforcement Date)
This Decree shall enter into force on the date of its promulgation.
Articles 2 through 5 Omitted.
ADDENDA<Presidential Decree No. 19463, Apr. 28, 2006>
Article 1 (Enforcement Date)
This Decree shall enter into force on April 30, 2006.
Articles 2 through 3 Omitted.
Last updated : 2009-07-26