Article 1 (Purpose)
The purpose of this Act is to ensure the smooth execution of contract business affairs by prescribing the basic matters related to the contracts to which the State is a party.
법령보기 화면
Article 2 (Scope of Application)
This Act shall apply to contracts to which the State is a party such as government procurement contracts by means of international tender, contracts entered into by the State with the people of the Republic of Korea (including contracts which become a source of revenue).
법령보기 화면
Article 3 (Relation with Other Acts)
Contracts to which the State is a party shall be governed by the provisions of this Act, except as otherwise prescribed by other Acts.
법령보기 화면
Article 4 (Scope of Government Procurement Contracts by Means of International Tender)
(1)
The scope of government procurement contracts by means of international tender shall include such contracts for commodities, construction works, or services entered into by a government agency as are equal to or exceeding the amount notified by the Minister of Strategy and Finance in accordance with the government procurement agreements and international norms which are bases of such agreements:
Provided
, That the cases falling under one of the following subparagraphs shall be excluded from the government procurement contracts by means of international tender:
<Amended by Act No. 5454, Dec. 13, 1997; Act No. 8852, Feb. 29, 2008>
1.
Cases of procuring commodities and services necessary for production for the purpose of resale or sale;
2.
Cases of manufacturing and purchasing small and medium enterprisemanufactured products in accordance with the Facilitation of Purchase of Small and Medium Enterprise-Manufactured Products Act;
3.
Cases of purchasing agricultural, fishery, and livestock products in accordance with the
Grain Management Act
, the
Act on Distribution and Price Stabilization of Agricultural and Fishery Products
, and the
Livestock Industry Act
; and
4.
Such other matters referred to in the government procurement agreement as prescribed by the Presidential Decree.
(2)
The scope of government agencies and commodities, construction work, and services referred to in the provisions of the main sentence of paragraph (1) of this Article shall be prescribed by the Presidential Decree in accordance with the contents of the government procurement agreement.
(3)
The head of each central government agency (referring to the head of a central government agency as referred to in
Article 6 of the National Finance Act
; hereinafter the same shall apply) or the public official entrusted with the functions related to contracts pursuant to the provisions of
Article 6
of this Act (hereinafter referred to as the "public official in charge of contracts"), if it is deemed necessary in view of the nature and the purpose of the contract, may conduct the procurement by means of international tender under the provisions of the Presidential Decree, even if it does not fall under paragraph (1) of this Article.
<Amended by Act No. 8050, Oct. 4, 2006>
법령보기 화면
Article 5 (Principle of Contracts)
(1)
A contract shall be concluded in accordance with the mutual agreement of the parties concerned in a mutually equal position, and the parties concerned shall perform the contents of a contract in accordance with the principle of faith and trust.
(2)
In case of an international tender as referred to in
Article 4
(1), the head of each central government agency or the public official in charge of contracts, in relation to the people of states which have acceded to the government procurement agreement and commodities or services produced by such states in accordance with the principle of reciprocity, shall not enter into any special agreement or conditions which will favor the people of the Republic of Korea and commodities or services produced in the Republic of Korea.
법령보기 화면
Article 6 (Delegation and Entrustment of Functions Related to Contracts)
(1)
The head of each central government agency, if he deems it necessary for performing the functions related to contracts under his jurisdiction may appoint the public official in charge of functions related to contracts (hereinafter referred to as the "contract official") from among the public officials under its control and delegate the functions related to contracts to the contract official and may ask the public officials under its control to act on behalf of the contract official or take partial charge of such functions.
(2)
The head of each central government agency may entrust the functions of the contract official to the public official of another central government agency pursuant to the provisions of the Presidential Decree.
(3)
The head of each central government agency may entrust the functions related to contracts under its jurisdiction to another central government agency pursuant to the provisions of the Presidential Decree.
(4)
The delegation and entrustment, the acting on behalf of and taking partial charge of the functions of the contract official as referred to in the provisions of paragraphs (1) and (2) of this Article may be replaced by designating a government post established at an organization under the control of each central government agency.
(5)
The contract official may not perform his duties without a financial guarantee prescribed by the Presidential Decree.
법령보기 화면
Article 7 (Method of Contracting)
(1)
When intending to conclude a contract, the head of each central government agency or a public official in charge of contracts shall conclude a contract through competitive bidding:
Provided
, That if it is deemed necessary in view of the purpose, nature, size, etc. of a contract, the head of each central government agency or the public official in charge of contracts may conclude a contract by limiting qualifications of the participants or nominating participants, or conclude a negotiated contract pursuant to the Presidential Decree.
<Amended by Act No. 11377, Mar. 21, 2012>
(2)
In cases where competitive bidding is invited pursuant to the body of paragraph (1), qualifications for participating in the bidding shall be reviewed in advance in accordance with prequalification criteria necessary for evaluating one's ability to perform the given contract, such as difficulty of contract performance, records of contract performance, technical capability, financial status, social reputation and sincerity in performing contract, and in accordance with prequalification procedures and other criteria prescribed by Presidential Decree, and thereafter only qualified persons shall be authorized to participate in the bidding.
<Newly Inserted by Act No. 11377, Mar. 21, 2012>
법령보기 화면
Article 8 (Public Notice of Tender)
(1)
In case of a public tender, the head of each central government agency or the public official in charge of contracts shall give public notice or notification of matters related to the tender.
(2)
The method, contents, time, and other necessary matters for the public notice or notification of the tender pursuant to the provisions of paragraph (1) of this Article shall be prescribed by the Presidential Decree.
법령보기 화면
Article 9 (Deposit for Tender)
(1)
The head of each central government agency or the public official in charge of contracts shall ask the person who intends to participate in the competitive tender to pay the amount of the bid bond:
Provided
, That in cases prescribed by the Presidential Decree, the payment of the bid bond may be exempted in whole or in part.
(2)
The amount, method of payment, and other necessary matters for the bid bond under the provisions of paragraph (1) of this Article shall be prescribed by the Presidential Decree.
(3)
If a successful bidder fails to enter into a contract, the head of each central government agency or the public official in charge of contracts shall have the bid bond concerned revert to the national treasury. In this case, if the payment of the bid bond has been exempted in whole or in part pursuant to the proviso of paragraph (1) of this Article, he shall have the amount corresponding to the bid bond shall be caused to be reverted to the national treasury.
법령보기 화면
Article 10 (Determination of Successful Bidder in Competitive Tender)
(1)
In the competitive tender which becomes a source of annual revenue, the bidder with the highest price shall be the successful bidder:
Provided
, That if criteria for the successful tender are prescribed by the Presidential Decree after taking into consideration the purpose of the contract, the price and volume, etc. of the tender, this shall not apply.
(2)
If the competitive tender becomes a burden on the national treasury, a bidder who meets the criteria falling under one of the following subparagraphs shall become the successful bidder:
1.
A person who is deemed to have sufficient ability to carry out the contract, and has tendered the lowest price;
2.
A person who has made the tender most favorable to the State in compliance with the criteria for evaluation specified in the public notice of the tender or the explanatory note of the tender; and
3.
Any other person who has made a tender which best meets the criteria for the successful tender, if such criteria are specially prescribed by the Presidential Decree in view of the nature and size, etc. of the contract.
법령보기 화면
Article 11 (Preparation of Contract and Conclusion of Contract)
(1)
When intending to enter into a contract, the head of each central government agency or the public official in charge of contracts shall prepare a written contract which specifies the purpose, contract amount, period of performance, deposit for the contract, liability for the risk, compensation for delay, and other necessary matters for the contract:
Provided
, That if it is prescribed by the Presidential Decree, the preparation of a written contract may be dispensed with.
(2)
If a contract is prepared pursuant to the provisions of paragraph (1) of this Article, the contract shall be confirmed by the writing of the name and the seal or signature on the contract by the public official in charge and the other party to the contract.
법령보기 화면
Article 12 (Deposit for Contract)
(1)
The head of each central government agency or the public official in charge of contracts shall ask the person who intends to enter into a contract with the State to pay the deposit for contract:
Provided
, That if it is prescribed by the Presidential Decree, the payment of the deposit for the contract may be exempted in whole or in part.
(2)
The amount, method of payment, and other necessary matters for the deposit for the contract under the provisions of paragraph (1) of this Article shall be prescribed by the Presidential Decree.
(3)
When the other party to the contract fails to fulfill contract obligations, the head of each central government agency or the public official in charge of contracts shall cause the subject deposit for the contract to revert to the national treasury. In this case, if the payment of the deposit for the contract has been exempted in whole or in part under the proviso of paragraph (1) of this Article, he shall have the amount corresponding to the deposit for the contract revert to the national treasury.
법령보기 화면
Article 13 (Supervision)
(1)
If it is deemed necessary to assure the appropriate performance of a contract concluded for construction work, manufacture, services, etc., the head of each central government agency or the public official in charge of contracts shall personally supervise the contract, design drawing and other relevant documents, or shall entrust the functions to the related public official and ask them to supervise the necessary matters thereof:
Provided
, That in case of the contracts prescribed by the Presidential Decree, a specialized agency may be designated separately to supervise the necessary matters.
(2)
The supervisor as referred to in the provisions of paragraph (1) of this Article shall prepare a protocol of supervision.
법령보기 화면
Article 14 (Inspection)
(1)
When the other party to the contract has completed the performance of the contract in whole or in part, the head of each central government agency or the public official in charge of contracts shall inspect the contract, design drawing, and other related documents for the purpose of confirmation, or shall entrust the tasks to the related public official and ask him to inspect the necessary matters thereof:
Provided
, That in case of contracts prescribed by the Presidential Decree, a specialized agency may be designated separately and be asked to inspect the necessary matters.
(2)
The inspector as referred to in the provisions of paragraph (1) of this Article shall prepare a protocol of inspection:
Provided
, That if it is prescribed by the Presidential Decree, the preparation of a protocol of inspection may be dispensed with.
법령보기 화면
Article 15 (Payment of Price)
(1)
In case of a contract for construction work, manufacture, purchase, service, etc. which becomes a burden on the national treasury the head of each central government agency or the public official in charge of contracts shall pay the price after completing the inspection thereof and preparing the protocol of inspection:
Provided
, That if any unavoidable reasons such as international usage, etc., exist, this shall not apply.
(2)
The price as referred to in the provisions of paragraph (1) of this Article shall be paid within the period prescribed by the Presidential Decree from the date on which the request for the payment of the price is received from the other party to the contract. If the price shall not be paid within the prescribed period, the interest for the overdue days shall be paid pursuant to the provisions of the Presidential Decree.
(3)
For the same contract, the interest as referred to in the provisions of paragraph (2) of this Article may be offset the arrears as referred to in the provisions of
Article 26
of this Act.
법령보기 화면
Article 16 (Advance Payment of Price)
In case of the sale or the loan of property, or supply of services, or of other contracts which become a source of revenue, the head of each central government agency or the public official in charge of contracts shall make the other party to the contract pay the price in advance, unless otherwise prescribed in other Acts and subordinate statutes.
법령보기 화면
Article 17 (Liability for Security in Case of Contract for Construction Work)
When entering into a contract for construction work, the head of each central government agency or the public official in charge of contracts shall determine the duration of the liability for security. In this case, the duration of the liability for security may not exceed the period prescribed in
Article 671 of the Civil Act
.
법령보기 화면
Article 18 (Deposit for Repair of Defects)
(1)
The head of each central government agency or the public official in charge of contracts shall ask the other party to the contract, in the case of a contract for construction work, to provide the deposit for repair of defects for the purpose of guaranteeing the repair of defects of that construction work:
Provided
, That if it is prescribed by the Presidential Decree, the provision of the deposit for repair of defects may be exempted in whole or in part.
(2)
The amount, payment time, method of payment, deposit period, and other necessary matters for the deposit for repair of defects as prescribed in paragraph (1) of this Article shall be prescribed by the Presidential Decree.
(3)
The provisions of
Article 12
(3)shall apply
mutatis mutandis
to the deposit for repair of defects:
Provided
, That if the budget is unavailable or insufficient for repairing such defect, the deposit for repair of defects may be used directly for the purpose of repairing such defect.
(4)
In case of the provisions of paragraph (3) of this Article, the balance of the deposit, if any, after being used shall be paid to the national treasury.
법령보기 화면
Article 19 (Adjustment of Contract Amount Due to Price Fluctuation, etc.)
If it is necessary to adjust the contract amount due to price fluctuation, design modifications, or other modifications to the contents of the contract, after concluding the contract for construction work, manufacture, service, etc. which becomes a burden on the national treasure, the head of each central government agency or the public official in charge of contracts shall adjust the contract amount pursuant to the provisions of the Presidential Decree.
법령보기 화면
Article 20 (Conclusion of Contract before Commencement of Fiscal Year)
In case of a contract which may not be suspended due to the characteristics of the contract such as lease, transport, or custody, notwithstanding the provisions of
Article 20 of the Management of the National Funds Act
, the head of each central government agency or the public official in charge of contracts may conclude the contract beforehand within the limit of the budget which has been finalized for the corresponding year before the commencement of the fiscal year pursuant to the provisions of the Presidential Decree.
<Amended by Act No. 6836, Dec. 30, 2002>
법령보기 화면
Article 21 (Continuing Expenditure and Long-Term Permanent Contract)
(1)
With respect to any project involving continuing expenditure pursuant to
Article 23 of the National Finance Act
, the head of each central government agency or a public official in charge of contracts shall make the total amount of expenditure and annual installment disbursements clear before entering into a contract for such project.
(2)
In case of a contract which needs to be continuously maintained due to the characteristics of the contract, such as lease, transport, custody, supply of electricity, gas, and waterworks, or a contract which takes several years for the completion thereof, the head of each central government agency or a public official in charge of contracts may conclude a long-term permanent contract pursuant to the Presidential Decree. In such cases, the relevant contract shall be implemented within budget limit for each fiscal year.
[This Article Wholly Amended by Act No. 11377, Mar. 21, 2012]
법령보기 화면
Article 22 (Contract by Unit Cost)
If it is necessary to maintain a contract continuously for a fixed period for the purpose of manufacture, repair, processing, sale and purchase, supply, and use, etc., the head of each central government agency or the public official in charge of contracts may conclude a contract based on the unit cost within the limit of the budget for the corresponding year.
법령보기 화면
Article 23 (Contract by Rough Estimate)
If it is impossible to determine the price in advance for a contract for the manufacture of prototypes for development, a service contract for testing, inspection, or research, or a contract for entrustment or vicarious execution as prescribed in Acts and subordinate statutes which is entered into with a government-invested institution or government-contributed institution, the head of each central government agency or the public official in charge of contracts may conclude a contract by rough estimate pursuant to the provisions of the Presidential Decree.
법령보기 화면
Article 24 (Integrated Contract)
(1)
The head of each central government agency or the public official in charge of contracts may conclude a contract jointly with the related institutions for construction work, etc. to which other government agencies, local governments, or government-invested institutions are related at the same location.
(2)
The heads of institutions related to the conclusion of the contract as referred to in the provisions of paragraph (1) of this Article shall cooperate on matters necessary for the conclusion of such contract.
법령보기 화면
Article 25 (Joint Contract)
(1)
If it is deemed necessary for a contract for construction work, manufacture, etc., the head of each central government agency or the public official in charge of contracts may conclude a joint contract with two or more parties to the contract.
(2)
In case of preparing a contract pursuant to the provisions of paragraph (1) of this Article, the contract shall be concluded when both the public official in charge of contracts and the other parties thereto write their names and put their seals or signature on it.
법령보기 화면
Article 26 (Compensation for Delay)
(1)
The head of each central government agency or the public official in charge of contracts shall have the other party to the contract who delayed performing the contract without justifiable grounds pay compensation for delay.
(2)
The amount, method of payment, and other necessary matters of the compensation for delay as referred to in paragraph (1) of this Article shall be prescribed by the Presidential Decree.
(3)
The provisions of the proviso of
Article 18
(3) shall apply
mutatis mutandis
to the compensation for delay as referred to in paragraph (1) of this Article.
법령보기 화면
Article 27 (Limitation on Qualifications of Unjust Businessmen to Participate in Tender)
(1)
If the head of each central government agency judges that any person is feared to hinder the fair execution of competition or appropriate performance of a contract, or is not eligible for the participation in a tender, he shall limit the qualification of such person to participate in the tender under the conditions as prescribed by the Presidential Decree within the scope of two years and shall notify without delay another central government agency thereof. In this case, the head of other central government agency who has received such notification shall limit the qualifications of such person to participate in the tender under the provisions of the Presidential Decree.
<Amended by Act No. 7722, Dec. 14, 2005>
(2)
Deleted.
<by Act No. 5453, Dec. 13, 1997>
(3)
The head of each central government agency or public officials in charge of contract shall not conclude any negotiated contract with the person subjected to a restriction of the qualification for participating in a tender under the provisions of paragraph (1):
Provided
, That the same shall not apply to the cases where there exists inevitable reasons such as there exists no adequate work executor or manufacturer except the persons subjected to a restriction of qualification for participating in a tender under the provisions of paragraph (1).
<Newly Inserted by Act No. 7722, Dec. 14, 2005>
법령보기 화면
Article 28 (Formal Objection)
(1)
If any person has suffered the damage because the head of the related central government agency or the public official in charge of contracts, in the process of a government procurement contract by means of international tender, has committed the acts falling under one of the following subparagraphs, he may file an objection for the purpose of cancelling or correcting such acts:
1.
Matters related to the scope of a government procurement contract by means of international tender as referred to in
Article 4
(1);
2.
Matters related to the qualifications to participate in the tender as referred to in
Article 7
;
3.
Matters related to the public notice for the tender as referred to in
Article 8
;
4.
Matters related to the determination of the successful bidder as referred to in
Article 10
(2); and
5.
Other matters as prescribed by the Presidential Decree.
(2)
An objection shall be filed with the head of the related central government agency within 15 days from the date on which such acts constituting the cause of objection are committed or within 10 days from the date on which the existence of such acts becomes known.
(3)
The head of the related central government agency shall investigate and take the necessary measures such as correction, and shall give notice of the results to the person who has raised an objection within 10 days from the date on which the objection has been filed with him.
(4)
A person having an objection against the measures under the provisions of paragraph (3) may request a re-examination for the purpose of conciliation by the International Contract Dispute Conciliation Committee under
Article 29
within 15 days from the date on which the notification has been received.
법령보기 화면
Article 29 (Establishment of International Contract Dispute Conciliation Committee)
(1)
The International Contract Dispute Conciliation Committee (hereinafter referred to as the "Committee") shall be established in the Ministry of Strategy and Finance for the purpose of examining and conciliating the request for the re-examination as referred to in
Article 28
(4).
<Amended by Act No. 5454, Dec. 13, 1997; Act No. 8852, Feb. 29, 2008>
(2)
The organization, operation, procedures, and other necessary matters for the Committee shall be prescribed by the Presidential Decree.
법령보기 화면
Article 30 (Suspension of Procedures for Contracts)
(1)
In case of commencing the examination and conciliation, the Committee shall give notice of that fact to the person who has made the request and the head of the related central government agency.
(2)
If it is deemed necessary in consideration of the opinion of the head of the related central government agency, the Committee may order that the related tender procedures be postponed or that the conclusion of the contract be suspended until the conciliation is completed.
법령보기 화면
Article 31 (Examination and Conciliation)
(1)
The Committee shall examine and conciliate the case within 50 days from the date on which the request for the re-examination has been received unless there exist other special reasons.
(2)
Unless the person who has made the request and the head of the related central government agency raise an objection against the conciliation within 15 days after completion of the conciliation, the provisions of paragraph (1) shall have the same effect as a settlement in court.
법령보기 화면
Article 32 (Training of Public Official in Charge of Contracts)
The Government may conduct training for the purpose of upgrading the quality of the public official in charge of contracts.
법령보기 화면
Article 33 (Report of Contractual Performances)
The head of each central government agency shall submit a written report on contractual performances to the Minister of Strategy and Finance under the conditions as prescribed by Presidential Decree.
<Amended by Act No. 5454, Dec. 13, 1997; Act No. 8852, Feb. 29, 2008>
법령보기 화면
Article 34 (Consultation for Acts and Subordinate Statutes concerning Contracts)
When drafting Acts and subordinate statutes concerning contracts, the head of each central government agency shall consult in advance with the Minister of Strategy and Finance.
<Amended by Act No. 5454, Dec. 13, 1997; Act No. 8852, Feb. 29, 2008>
ADDENDA
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation:
Provided
, That the provisions of
Articles 4
(1) and (2),
5
(2), and
28 through 31
shall enter into force on January 1, 1997.
Article 2 (Transitional Measures)
The contracts concluded pursuant to the
Budget and Accounts Act
prior to the enforcement of this Act shall be regarded as the contracts concluded under this Act.
Article 3 Omitted.
Article 4 (Relation to Other Acts)
If Chapter Ⅵ of the
Budget and Accounts Act
or any provisions of the said Chapter of the said Act have been cited in other Acts, at the time when this Act enters into force, this Act or the corresponding provisions thereof shall be considered to have been cited therein.
ADDENDA<Act No. 5453, Dec. 13, 1997>
Article 1 (Enforcement Date)
This Act shall enter into force on January 1, 1998. (Proviso Omitted.)
Article 2 Omitted.
ADDENDUM<Act No. 5454, Dec. 13, 1997>
This Act shall enter into force on January 1, 1998. (Proviso Omitted.)
ADDENDA<Act No. 6836, Dec. 30, 2002>
Article 1 (Enforcement Date)
This Act shall enter into force on January 1, 2003.
Articles 2 through 7 Omitted.
ADDENDUM<Act No. 7722, Dec. 14, 2005>
This Act shall enter into force three months after the date of its promulgation.
ADDENDA<Act No. 8050, Oct. 4, 2006>
Article 1 (Enforcement Date)
This Act shall enter into force on January 1, 2007. (Proviso Omitted.)
Articles 2 through 12 Omitted.
ADDENDA<Act No. 8852, Feb. 29, 2008>
Article 1 (Enforcement Date)
This Act shall enter into force on the date of its promulgation. (Proviso Omitted.)
Articles 2 through 7 Omitted.
ADDENDUM<Act No. 11377, Mar. 21, 2012>
This Act shall enter into force on the date of its promulgation.