Enforcement Decree of the Act on the Designation and Operation of Special Peace Economic Zones
280979 · 2026-01-02
Enforcement Decree of the Act on the Designation and Operation of Special Peace Economic Zones
Article 1 (Purpose)
The purpose of this Decree is to prescribe matters delegated by the Act on the Designation and Operation of Special Peace Economic Zones and matters necessary for its enforcement.
Article 2 (Scope of Adjacent Areas)
(1) The Sis and Guns bordering the southern limit line of the Demilitarized Zone or the Northern Limit Line at sea under subparagraph 1 of Article 2 of the Act on the Designation and Operation of Special Peace Economic Zones (hereinafter referred to as the "Act") shall be the Sis and Guns classified as follows:
1. Incheon Metropolitan City: Ganghwa-gun and Ongjin-gun;
2. Gyeonggi-do: Gimpo-si, Paju-si, and Yeoncheon-gun;
3. Gangwon Special Self-Governing Province: Cheorwon-gun, Hwacheon-gun, Yanggu-gun, Inje-gun, and Goseong-gun.
(2) "Areas prescribed by Presidential Decree" in subparagraph 1 of Article 2 of the Act means the Sis and Guns classified as follows: <Amended on October 21, 2025>
1. Gyeonggi-do: Goyang-si, Yangju-si, Dongducheon-si, Pocheon-si, and Gapyeong-gun;
2. Gangwon Special Self-Governing Province: Chuncheon-si and Sokcho-si.
Article 3 (Hearing Residents' Opinions)
(1) Where a Metropolitan City Mayor, Do Governor, or Special Self-Governing Province Governor having jurisdiction over an area adjacent to North Korea (hereinafter referred to as a "Mayor/Do Governor") intends to hear residents' opinions in advance regarding the designation of a special peace economic zone (hereinafter referred to as a "special peace economic zone") pursuant to the latter part of Article 8 (2) of the Act, the Mayor/Do Governor shall publicly announce the following matters in the official bulletin and on the website of the relevant local government. In such cases, the Mayor/Do Governor shall make the documents available for inspection by residents of the jurisdiction for at least 14 days from the date of the public announcement:
1. The name, location, and area of the special peace economic zone;
2. The principal content of the development plan for the special peace economic zone under Article 10 of the Act (hereinafter referred to as the "special peace economic zone development plan");
3. The period and methods for inspecting relevant documents.
(2) A resident who has an opinion regarding matters publicly announced under paragraph (1) may submit the opinion in writing to the Mayor/Do Governor during the inspection period under paragraph (1) 3.
(3) The Mayor/Do Governor shall examine whether to reflect opinions submitted under paragraph (2) in the special peace economic zone development plan and inform the residents who submitted the opinions of the results within 15 days from the end of the inspection period.
Article 4 (Consultation on Special Peace Economic Zone Development Plans)
The head of a relevant administrative agency requested to engage in consultation by the Minister of Unification and the Minister of Land, Infrastructure and Transport pursuant to the former part of Article 8 (4) of the Act shall reply with an opinion within 20 days from the date of the request: Provided, That, where it is difficult to reply within that period due to unavoidable circumstances, the head shall notify the Minister of Unification and the Minister of Land, Infrastructure and Transport of the reasons and the deadline for the reply and shall reply with an opinion by that deadline.
Article 5 (Phased Development of Special Peace Economic Zones)
"Cases meeting requirements prescribed by Presidential Decree, such as where the land necessary for developing a special peace economic zone has been secured" in Article 8 (9) of the Act means any of the following cases:
1. Where all the land necessary for developing a unit development project district under Article 10 (1) 4 of the Act (hereinafter referred to as a "unit development project district") is owned by the State or local governments;
2. Where all the land necessary for developing a unit development project district is owned by the implementer (hereinafter referred to as the "development project implementer") of the relevant development project for a special peace economic zone (hereinafter referred to as a "development project") or by a person intending to implement the development project;
3. Where all the land necessary for developing a unit development project district is land created by public waters reclamation works under the Public Waters Management and Reclamation Act.
Article 6 (Public Notice of Designation of Special Peace Economic Zones)
Where the Minister of Unification and the Minister of Land, Infrastructure and Transport designate a special peace economic zone pursuant to Article 8 (4) or (5) of the Act, they shall publicly notify the following matters in the Official Gazette pursuant to paragraph (10) of that Article:
1. The name, location, and area of the special peace economic zone;
2. The development project implementer for the special peace economic zone or the person intending to implement the development project;
3. The date of designation of the special peace economic zone.
Article 7 (Matters to Be Considered in Designating Special Peace Economic Zones)
"Matters prescribed by Presidential Decree" in subparagraph 9 of Article 9 of the Act means the following matters:
1. Demand from enterprises intending to carry out cooperative projects under subparagraph 4 of Article 2 of the Inter-Korean Exchange and Cooperation Act within the special peace economic zone;
2. The feasibility of continued operation and management after the special peace economic zone is established;
3. The degree of contribution to balanced development of the national territory.
Article 8 (Content of Special Peace Economic Zone Development Plans)
"Matters prescribed by Presidential Decree" in Article 10 (1) 15 of the Act means the following matters:
1. Project costs;
2. Plans linking the development project with economic exchanges between South and North Korea;
3. Plans for managing existing buildings, structures, etc. that are to be retained;
4. Demand from enterprises that will locate in the special peace economic zone;
5. Other matters jointly publicly notified by the Minister of Unification and the Minister of Land, Infrastructure and Transport as deemed necessary for formulating the special peace economic zone development plan.
Article 9 (Amendment of Special Peace Economic Zone Development Plans)
(1) Where the Minister of Unification and the Minister of Land, Infrastructure and Transport receive a request to amend a special peace economic zone development plan pursuant to the latter part of Article 11 (1) and paragraph (2) of that Article of the Act, they shall, except where there are special grounds, inform the Mayor/Do Governor or the development project implementer whether the special peace economic zone development plan will be amended within three months from the date of the request.
(2) "Cases where important matters prescribed by Presidential Decree are to be amended" in Article 11 (3) 1 of the Act means any of the following cases:
1. Where the area of the special peace economic zone or a unit development project district is to be changed by at least 10 percent;
2. Where the development method is to be changed to phased development under Article 8 (9) of the Act;
3. Where the project period is extended by at least one year.
(3) "Cases of amending minor matters prescribed by Presidential Decree" in Article 11 (4) of the Act means any of the following cases:
1. Where the area of the special peace economic zone or a unit development project district is changed by less than 10 percent;
2. Where project costs are changed by less than 10 percent;
3. Where the population in the population accommodation plan under Article 10 (1) 8 of the Act is changed by less than 10 percent.
Article 10 (Restrictions on Acts)
(1) “Acts prescribed by Presidential Decree, such as alteration of the form and quality of land, construction of buildings, and installation of structures” in the former part of Article 13(1) of the Act means the following acts:
1. Construction of buildings: Construction of buildings defined in Article 2(1)2 of the Building Act.
2. Installation of structures: Installation of artificially produced facilities (excluding buildings defined in Article 2(1)2 of the Building Act).
3. Alteration of the form and quality of land: Acts of changing the shape of land by cutting (excavating land), filling (piling up soil), leveling (grading land), paving, or similar methods, and reclamation of public waters (excluding alteration of the form and quality of land for cultivation).
4. Extraction of soil and stone: Acts of extracting soil and stone, such as soil, sand, gravel, and rock; provided that extraction for the purpose of altering the form and quality of land is excluded.
5. Subdivision of land: Subdivision of land falling under any of the following (excluding sites with buildings under Article 57 of the Building Act):
(a) Subdivision of land without obtaining permission, authorization, etc. under the relevant statutes and regulations in green areas under Article 36(1)1(d) of the National Land Planning and Utilization Act (hereinafter referred to as “green areas”), management areas under subparagraph 2 of Article 6 of that Act (hereinafter referred to as “management areas”), agricultural and forest areas under subparagraph 3 of that Article, or natural environment conservation areas under subparagraph 4 of that Article (hereinafter referred to as “natural environment conservation areas”);
(b) Subdivision of land into parcels smaller than the minimum area permitted for subdivision under Article 57(1) of the Building Act;
(c) Subdivision of land into parcels with a width of 5 meters or less without obtaining permission, authorization, etc. under the relevant statutes and regulations.
6. Piling up goods: Acts of piling up goods for at least one month in green areas, management areas, or natural environment conservation areas on land that is not within the enclosure of a building approved for use under Article 22 of the Building Act (limited to sites developed through lawful procedures).
(2) A Mayor/Do Governor may grant permission under Article 13(1) of the Act to the extent that it does not interfere with a development project. In such cases, the competent Mayor/Do Governor shall hear the views of the development project implementer before granting permission.
(3) “Acts prescribed by Presidential Decree” in Article 13(2)2 of the Act means the following acts:
1. Any of the following alterations of the form and quality of land:
(a) Cutting, filling, leveling, or similar acts not exceeding 50 centimeters in height or 50 centimeters in depth (excluding paving; in areas other than residential areas under Article 36(1)1(a) of the National Land Planning and Utilization Act, commercial areas under item (b) of that subparagraph, and industrial areas under item (c) of that subparagraph, limited to cases not involving a change in land category);
(b) Cutting, filling, leveling, paving, or similar acts not involving a change in land category on land with an area of 660 square meters or less in areas other than urban areas under Article 6 of the National Land Planning and Utilization Act (hereinafter referred to as “urban areas”), natural environment conservation areas, and district unit planning zones under Article 51(1) of that Act (hereinafter referred to as “district unit planning zones”) (the area of alteration of the form and quality of land means the total area of the relevant parcel on which the alteration takes place);
(c) Alteration of the form and quality of land for the installation of buildings or other structures on existing sites whose development has been completed (excluding cutting and filling);
(d) Alteration of the form and quality of land for projects directly implemented by the State or a local government as required in the public interest.
2. Any of the following extraction of soil and stone:
(a) Extraction of soil and stone with a volume of 50 cubic meters or less from land with an extraction area of 25 square meters or less in urban areas or district unit planning zones;
(b) Extraction of soil and stone with a volume of 500 cubic meters or less from land with an extraction area of 250 square meters or less in areas other than urban areas, natural environment conservation areas, and district unit planning zones.
3. Any of the following acts of piling up goods:
(a) Piling up goods with a total weight of 50 tons or less and a total volume of 50 cubic meters or less on land with an area used for piling up goods of 25 square meters or less in green areas or district unit planning zones;
(b) Piling up goods with a total weight of 500 tons or less and a total volume of 500 cubic meters or less on land with an area used for piling up goods of 250 square meters or less in management areas (excluding areas designated as district unit planning zones).
(4) A person who, at the time of designation and public notification of a development project area, has commenced construction work or a project in relation to an act requiring permission under Article 13(1) of the Act, for which permission has already been obtained under the relevant statutes and regulations or for which no permission is required, shall report the plan and progress of the act to the Mayor/Do Governor within three months from the date of such designation and public notification pursuant to Article 13(3) of the Act.
Article 11 (Cancellation of Designation of Special Peace Economic Zones)
(1) “Grounds prescribed by Presidential Decree” in Article 14(1)4 of the Act means a case where the designation of a development area, region, district, etc. under other statutes and regulations is being pursued and, in light of the land use plan, plans to attract enterprises, etc. under those statutes and regulations, there is no need to retain the area as a special peace economic zone.
(2) When canceling the designation of a special peace economic zone pursuant to Article 14 of the Act, the Minister of Unification and the Minister of Land, Infrastructure and Transport shall publish a notice of the following matters in the Official Gazette:
1. The name, location, and area of the special peace economic zone;
2. The development project implementer of the special peace economic zone or the person expected to implement the development project;
3. The grounds for cancellation of the designation of the special peace economic zone and the effective date of the cancellation;
4. Matters concerning the restoration of use zones under Article 14(2) of the Act.
(3) When excluding a unit development project district from a special peace economic zone pursuant to Article 14 of the Act, the Minister of Unification and the Minister of Land, Infrastructure and Transport shall publish a notice of the following matters in the Official Gazette:
1. The names, locations, and areas of the special peace economic zone and the unit development project district;
2. The development project implementers of the special peace economic zone and the unit development project district or the persons expected to implement the development projects;
3. The grounds for excluding the unit development project district from the special peace economic zone and the effective date of the exclusion;
4. Matters concerning the restoration of use zones under Article 14(2) of the Act.
Article 12 (Designation of Development Project Implementers)
(1) “Institutions prescribed by Presidential Decree” in Article 15(1)2 of the Act means the following institutions:
1. The Korea Land and Housing Corporation under the Korea Land and Housing Corporation Act;
2. The Korea Expressway Corporation under the Korea Expressway Corporation Act;
3. The Korea Tourism Organization under the Korea Tourism Organization Act;
4. The Korea Water Resources Corporation under the Korea Water Resources Corporation Act;
5. The Korea Rural Community Corporation under the Korea Rural Community Corporation and Farmland Management Fund Act;
6. Port authorities under the Port Authority Act;
7. The Korea Industrial Complex Corporation under Article 45-17 of the Industrial Cluster Development and Factory Establishment Act;
8. The Korea Railroad Corporation under the Korea Railroad Corporation Act;
9. The Korea SMEs and Startups Agency under Article 68 of the Small and Medium Enterprises Promotion Act.
(2) “Persons satisfying the qualifications prescribed by Presidential Decree, such as capital requirements” in Article 15(1)4 of the Act means persons intending to move into a special peace economic zone and engage in a cooperative project under subparagraph 4 of Article 2 of the Inter-Korean Exchange and Cooperation Act who fall under any of the following:
1. A person whose equity capital for the most recent year amounts to at least 10 percent of the total project cost for the relevant unit development project district;
2. A person who owns at least 50 percent of the total land area of the relevant unit development project district.
Article 13 (Implementation Orders to Development Project Implementers)
When issuing an implementation order under Article 16(2) of the Act, a Mayor/Do Governor shall notify the development project implementer in writing, specifying the following matters:
1. The development project area and the development project implementer;
2. The grounds for and details of the implementation order;
3. The deadline for compliance with the implementation order.
Article 14 (Method of Calculating Development Costs)
Development costs under Article 18(3) of the Act shall be the sum of land costs, land charges, relocation measures costs, development work costs, infrastructure installation costs and charges, direct labor costs, general administrative expenses, capital costs, and other related costs. The Minister of Land, Infrastructure and Transport shall determine and publicly notify detailed calculation standards for each component of development costs.
Article 15 (Preparation of and Application for Approval of Implementation Plans)
(1) When preparing an implementation plan for a development project (hereinafter referred to as an “implementation plan”) pursuant to the former part of Article 19(1) of the Act, a development project implementer shall prepare it in conformity with the master plan for special peace economic zones under Article 6 of the Act (hereinafter referred to as the “special peace economic zone master plan”) and the special peace economic zone development plan.
(2) An implementation plan shall include the following matters:
1. The location and area where the development project is to be implemented;
2. The period for implementation of the development project;
3. Plans for securing and using the necessary land;
4. An implementation plan for each phase, where development is undertaken in phases pursuant to Article 8(9) of the Act;
5. Details of any permission, authorization, designation, approval, consultation, report, etc. deemed granted, made, or completed pursuant to Article 21(1) of the Act;
6. The business name and place of business of the development project implementer (or, in the case of an individual, the individual's name and address);
7. Other matters that the Minister of Land, Infrastructure and Transport deems necessary for the implementation of the development project and publicly notifies.
(3) The Minister of Land, Infrastructure and Transport may determine and publicly notify matters necessary for the formulation of implementation plans, including drawings and documents to be attached to an implementation plan for approval of the implementation plan or approval of an amendment thereto.
Article 16 (Implementation Plans Subject to Consultation)
The term “implementation plans meeting the standards prescribed by Presidential Decree” in Article 19 (2) of the Act means implementation plans falling under either of the following subparagraphs:
1. An implementation plan that newly provides for or changes matters concerning State funding support in its financing plan;
2. An implementation plan concerning matters that the Special Peace Economic Zone Committee under Article 31 (1) of the Act (hereinafter referred to as the “Committee”) has deliberated and resolved to add to the special peace economic zone development plan.
Article 17 (Completion Inspections)
(1) A development project implementer seeking to undergo a completion inspection pursuant to Article 24 (1) of the Act shall submit the following documents to the Mayor/Do Governor having jurisdiction:
1. A completion report (including as-built design documents and photographs of the completed project);
2. A cadastral survey results map;
3. A statement of land areas by use;
4. A statement and drawings concerning the vesting of public facilities, etc.
(2) Upon receipt of an application for a completion inspection from a development project implementer pursuant to paragraph (1), the Mayor/Do Governor shall inspect whether the relevant development project conforms to the implementation plan and, if the project is found to conform to that plan, shall approve the completion inspection and publicly notify the following matters in the official gazette:
1. The name of the development project;
2. The business name and business address of the development project implementer (in the case of an individual, the individual's name and address);
3. The location, area, and areas by use of the area where the development project is implemented;
4. The date of completion;
5. Matters concerning the management and disposal of major facilities.
Article 18 (Use of Land, etc. before Completion Inspections)
(1) Where a development project implementer intends to use land developed or facilities installed through a development project before a completion inspection pursuant to the proviso of Article 24 (3) of the Act, the development project implementer shall apply to the Mayor/Do Governor for permission to use such land or facilities by attaching the following documents to the use permit form prescribed by Ordinance of the Ministry of Land, Infrastructure and Transport:
1. Materials demonstrating the reasons for, or urgency of, the need to use the land or facilities before the completion inspection;
2. Documents concerning the progress of construction of the land or facilities intended to be used;
3. An opinion of the construction supervisor or the construction supervisory official concerning the usability, safety, etc. of the land or facilities intended to be used;
4. Drawings and photographs of the land or facilities intended to be used at the stage of completion;
5. A boundary demarcation survey of the land intended to be used.
(2) Upon receipt of an application for permission to use land or facilities pursuant to paragraph (1), the Mayor/Do Governor shall determine whether the developed land or installed facilities can be used appropriately for their intended purposes and shall grant or deny permission within 30 days from the date of receipt of the application.
Article 19 (Scope of Facilities to Be Installed)
The term “scope prescribed by Presidential Decree” in Article 25 (2) of the Act shall be as follows, according to the following categories:
1. Roads: Roads meeting both of the following requirements:
(a) The road must have been designated as a road under the National Land Planning and Utilization Act or as a road zone under the Road Act before the designation of the special peace economic zone;
(b) The road must be a local road or a State-supported local road under the Road Act that a local government is required to install;
2. Water supply and sewerage facilities: Water supply and sewerage pipelines that pass through a special peace economic zone without being connected to the water supply and sewerage pipelines within the zone;
3. Electricity facilities: Electricity facilities extending from trunk facilities outside a special peace economic zone to the boundary of an individual lot abutting an urban or Gun planning road at least 6 meters wide under the land-use plan for the special peace economic zone (hereinafter referred to as an “individual lot”): Provided, That where the trunk electricity facilities in a special peace economic zone are installed as underground lines at the request of a development project implementer, the electricity supplier and the person requesting underground installation shall each bear 50 percent of the cost of installing the trunk electricity facilities within the special peace economic zone;
4. Gas supply facilities: Gas supply facilities extending from trunk gas supply facilities outside a special peace economic zone to the boundary of an individual lot [where a pressure regulation room (a room for maintaining and regulating a constant pressure) is installed within an individual lot to supply gas for cooking or individual heating (excluding central heating), to that pressure regulation room];
5. District heating facilities: Heat transmission pipes extending from the branching point of a trunk heat transmission pipe outside a special peace economic zone to the shutoff valve at the entrance of each machinery room on an individual lot;
6. Telecommunications facilities: Conduit facilities extending from trunk facilities outside a special peace economic zone to the boundary of an individual lot, and cable facilities extending from trunk facilities outside a special peace economic zone to the first terminal within an individual lot.
Article 20 (Scope of Resident Enterprises)
(1) The enterprises under Article 28 (1) 1 of the Act shall be the following enterprises:
1. Enterprises engaging in trade under subparagraph 2 of Article 2 of the Inter-Korean Exchange and Cooperation Act;
2. Enterprises carrying out cooperative projects in the economic sector among the cooperative projects under subparagraph 4 of Article 2 of the Inter-Korean Exchange and Cooperation Act that have obtained approval for cooperative projects under Article 17 of that Act.
(2) The enterprises under Article 28 (1) 2 and 3 of the Act mean enterprises engaging in industries in the sectors of materials and equipment, finance, education and training, distribution and services, tourism, and other sectors publicly notified by the Minister of Unification in consideration of inter-industry linkage effects, the potential for generating added value through convergence and integration, etc.
Article 21 (Financial Support for Local Governments)
Where the State provides financial support to a local government pursuant to Article 29 (3) of the Act, it shall comprehensively consider the following matters:
1. The extent of the local government's contribution to attracting enterprises locating in or investing in a special peace economic zone (hereinafter referred to as “resident or investing enterprises”);
2. The scale of job creation by resident or investing enterprises supported by the local government;
3. The effects of resident or investing enterprises supported by the local government on inter-Korean trade and economic cooperation;
4. Whether financial support is provided under other statutes or regulations.
Article 22 (Support for Infrastructure)
The State and local governments may, pursuant to the main clause of Article 30 of the Act, provide support within their budgets for the costs necessary to install infrastructure under subparagraph 6 of Article 2 of the National Land Planning and Utilization Act.
Article 23 (Matters for Deliberation and Resolution by the Committee)
The term “matters prescribed by Presidential Decree” in Article 31 (2) 8 of the Act means the following matters:
1. Matters concerning development and operation in connection with special zones related to the economy designated by North Korea;
2. In the case of special peace economic zones for tourism purposes, matters concerning the coordinated operation of tourism between South and North Korea;
3. Matters concerning the prevention of illegal circulation of foreign currencies within special peace economic zones;
4. Matters concerning the prevention of uncontrolled development in special peace economic zones and measures to stabilize real estate prices;
5. Other matters that the chairperson of the Committee (hereinafter referred to as the “chairperson”) deems necessary for the effective functioning and smooth management of special peace economic zones.
Article 24 (Composition of the Committee)
(1) The term “persons prescribed by Presidential Decree” in Article 31 (5) of the Act means the Vice Minister of Finance and Economy; the Vice Minister of Science and ICT; the Vice Minister of Justice; the Vice Minister of National Defense; the Vice Minister of the Interior and Safety; the Vice Minister of Culture, Sports and Tourism; the Vice Minister of Agriculture, Food and Rural Affairs; the Vice Minister of Trade and Industry; the Vice Minister of Health and Welfare; the Vice Minister of Climate, Energy and Environment; the Vice Minister of Employment and Labor; the Vice Minister of Oceans and Fisheries; the Vice Minister of SMEs and Startups; and the Vice Minister of Planning and Budget. In this case, for an agency with more than one vice minister, the term means the vice minister designated by the head of that agency. <Amended on October 1, 2025; December 30, 2025>
(2) The term of office of commissioned members under Article 31 (6) of the Act (hereinafter referred to as “commissioned members”) shall be 2 years, and they may be recommissioned consecutively no more than twice.
Article 25 (Exclusion, Challenge, and Recusal of Members)
(1) A member of the Committee shall be excluded from the Committee's deliberations and resolutions in any of the following cases:
1. Where the member or the member's spouse or former spouse is a party to the relevant agenda item (where a party is a corporation, organization, etc., including its officers; hereinafter the same shall apply in this subparagraph and subparagraph 2), or is a joint holder of rights or a joint obligor with a party to that agenda item;
2. Where the member is or was a relative of a party to the relevant agenda item;
3. Where the member has given testimony, made a statement, provided advice, conducted research, rendered services, or performed an appraisal concerning the relevant agenda item;
4. Where the member or the corporation, organization, etc. to which the member belongs is or was an agent of a party to the relevant agenda item.
(2) Where there are circumstances that make it difficult to expect impartial deliberation and resolution from a member, a party to the relevant agenda item may file a challenge against that member with the Committee, and the Committee shall determine by resolution whether to uphold the challenge. In such cases, the member subject to the challenge shall not participate in that resolution.
(3) Where a member falls under any of the grounds for exclusion specified in the subparagraphs of paragraph (1), the member shall recuse himself or herself from the deliberation and resolution of the relevant agenda item.
Article 26 (Dismissal of Commissioned Members)
The chairperson may dismiss a commissioned member if the member falls under any of the following subparagraphs:
1. Where the member becomes unable to perform his or her duties due to prolonged physical or mental infirmity;
2. Where the member has committed misconduct in connection with his or her duties;
3. Where the member is deemed unsuitable to serve as a member due to neglect of duties, impairment of dignity, or any other reason;
4. Where the member fails to refrain from participation despite falling under any of the subparagraphs of Article 25 (1);
5. Where the member expresses his or her own view that it is difficult to perform his or her duties.
Article 27 (Operation of the Committee)
(1) The chairperson shall represent the Committee and exercise overall control over its affairs.
(2) The vice chairperson shall assist the chairperson and act on behalf of the chairperson when the chairperson is unable to perform his or her duties due to unavoidable circumstances.
(3) The chairperson shall convene meetings of the Committee and preside over them.
(4) When convening a meeting of the Committee, the chairperson shall notify the members in writing of the date, time, place, purpose, and other particulars of the meeting no later than three days before the meeting is held: Provided, That where it is necessary to convene a meeting urgently, notification may be given no later than the day before the meeting is held.
(5) A meeting of the Committee shall be convened with the attendance of a majority of all incumbent members, and resolutions shall be adopted with the affirmative votes of a majority of the members present.
(6) The Committee shall have one secretary to handle its affairs, and the Minister of Unification shall designate the secretary from among public officials of the Ministry of Unification who belong to the Senior Civil Service or are Grade III public officials.
(7) Matters necessary for the operation of the Committee and other details, other than those prescribed in paragraphs (1) through (6), shall be determined by the chairperson following a resolution of the Committee.
Article 28 (Hearing of Opinions)
Where the chairperson deems it necessary for deliberation, the chairperson may have public officials of relevant central administrative agencies and local governments, relevant experts, and other relevant persons attend a meeting to hear their opinions.
Article 29 (Allowances)
Allowances may be paid, within the budget, to members attending a meeting of the Committee or persons attending a meeting pursuant to Article 28: Provided, That this shall not apply where a public official attends in direct connection with his or her duties.
Article 30 (Subcommittees)
(1) Subcommittees established under the Committee pursuant to Article 31 (7) of the Act (hereinafter referred to as "subcommittees") may be established by specialized field.
(2) Each subcommittee shall consist of not more than 10 members, including one subcommittee chairperson, and the chairperson of the Committee shall designate the subcommittee chairperson from among the members of the subcommittee.
(3) The chairperson shall designate the members of a subcommittee from among the members of the Committee, taking into account their expertise, experience, and other relevant factors.
(4) Matters necessary for the establishment and operation of subcommittees shall be determined by the chairperson following a resolution of the Committee.
Article 31 (Requests for Secondment)
Where the Minister of Unification deems it necessary to perform duties concerning the designation and operation of special peace economic zones, the Minister may request the secondment of public officials of relevant administrative agencies or local governments, or officers or employees of related organizations.
Article 32 (Improvement of the Investment Environment)
The scope of improvement of the investment environment, living conditions, and provision of related services within special peace economic zones under Article 34 (2) of the Act shall be as follows:
1. Improvement of relevant laws and institutional systems;
2. Establishment of a cooperative framework among relevant institutions to promote research and development;
3. Formulation of measures to disseminate operational outcomes;
4. Creation of a living environment for attracting investment from domestic and foreign persons and facilitating their settlement.
Article 33 (Types and Scope of Tourism Businesses)
The tourism businesses to be fostered by the State and local governments within special peace economic zones pursuant to Article 35 (2) of the Act shall be as follows: <Amended on August 26, 2025>
1. Travel business, tourist accommodation business, tourist-use facility business, and international conference business under Article 3 (1) 1 through 4 of the Tourism Promotion Act;
2. Theme park business under Article 3 (1) 6 of the Tourism Promotion Act (excluding other theme park business under subparagraph 5 (c) of Article 2 of the Enforcement Decree of that Act);
3. Tourist convenience facility business under Article 3 (1) 7 of the Tourism Promotion Act (excluding those falling under subparagraph 6 (a) through (c) of Article 2 of the Enforcement Decree of that Act).
Article 34 (Evaluation of Project Performance)
(1) Where the Minister of Unification intends to evaluate the project performance of each special peace economic zone pursuant to Article 37 (1) of the Act, the Minister shall notify the relevant persons of the evaluation indicators, direction, schedule, and other particulars three months before conducting the evaluation.
(2) Where necessary to evaluate the project performance of each special peace economic zone, the Minister of Unification may conduct on-site inspections, interviews with relevant persons, and other necessary activities.
(3) To finalize the results of an evaluation of the project performance of a special peace economic zone, the Minister of Unification shall undergo deliberation and resolution by the Committee.
(4) Matters necessary for evaluating the project performance of each special peace economic zone, other than those prescribed in paragraphs (1) through (3), shall be prescribed and publicly notified by the Minister of Unification.
Article 35 (Delegation of Authority)
A Mayor/Do Governor shall delegate the following authority to the head of a Si/Gun pursuant to Article 41 of the Act:
1. Granting permission, processing reports, ordering restoration to the original state, and conducting vicarious execution in relation to restrictions on acts under Article 13 (1) through (4) of the Act;
2. Conducting completion inspections, granting permission for use before a completion inspection, and managing districts in which development projects have been completed under Article 24 (1) through (4) of the Act.
Article 36 (Review of Regulations)
The Minister of Unification and the Minister of Land, Infrastructure and Transport shall review the appropriateness of the qualification requirements for development project implementers under Article 12 (2) every three years, using January 1, 2024 as the base date (meaning before January 1 of every third year), and take measures such as making improvements.
Article 37 (Criteria for Imposing Administrative Fines)
The criteria for imposing administrative fines under Article 44 (2) of the Act shall be as specified in the Annex.
ADDENDA <No. 33916, December 12, 2023>
This Decree shall enter into force on December 14, 2023.
ADDENDA (Enforcement Decree of the Tourism Promotion Act) <No. 35716, August 26, 2025>
Article 1 (Enforcement Date)
This Decree shall enter into force on August 28, 2025.
Article 2 (Amendments to Other Statutes and Regulations)
(1) through (28) Omitted.
(29) The Enforcement Decree of the Act on the Designation and Operation of Special Peace Economic Zones shall be partially amended as follows:
In subparagraph 2 of Article 33, "amusement facility business (other amusement facility business under subparagraph 5 (c) of Article 2 of the Enforcement Decree of that Act" shall be replaced with "theme park business (other theme park business under subparagraph 5 (c) of Article 2 of the Enforcement Decree of that Act".
(30) Omitted.
ADDENDA (Presidential Decree on the Partial Amendment of 306 Statutes and Regulations to Reflect the Reorganization of the Government) <No. 35811, October 1, 2025>
This Decree shall enter into force on the date of its promulgation: Provided, That among the Presidential Decrees amended by this Decree, the provisions amending Presidential Decrees that were promulgated before this Decree enters into force but whose enforcement dates have not yet arrived shall enter into force on the respective enforcement dates of those Presidential Decrees.
ADDENDA <No. 35817, October 21, 2025>
This Decree shall enter into force on the date of its promulgation.
ADDENDA (Organization of the Ministry of Finance and Economy) <No. 35947, December 30, 2025>
Article 1 (Enforcement Date)
This Decree shall enter into force on January 2, 2026: Provided, That among the Presidential Decrees amended pursuant to Article 6 of the Addenda, the provisions amending Presidential Decrees that were promulgated before this Decree enters into force but whose enforcement dates have not yet arrived shall enter into force on the respective enforcement dates of those Presidential Decrees.
Articles 2 through 5 Omitted.
Article 6 (Amendments to Other Statutes and Regulations)
(1) through (100) Omitted.
(101) The Enforcement Decree of the Act on the Designation and Operation of Special Peace Economic Zones shall be partially amended as follows:
In the former part of Article 24 (1), "Vice Minister of Economy and Finance" shall be replaced with "Vice Minister of Finance and Economy", and "Vice Minister of Oceans and Fisheries and Vice Minister of SMEs and Startups" shall be replaced with "Vice Minister of Oceans and Fisheries, Vice Minister of SMEs and Startups, and Vice Minister of Planning and Budget".
(102) through (313) Omitted.