NEW HARBOR CONSTRUCTION PROMOTION ACT
33107 · 2014-10-15
NEW HARBOR CONSTRUCTION PROMOTION ACT
Act No. 12826, Oct. 15, 2014
Act No. 5251, Dec. 31, 1996
Amended by Act No. 5453, Dec. 13, 1997
Act No. 5454, Dec. 13, 1997
Act No. 5864, Feb. 8, 1999
Act No. 5893, Feb. 8, 1999
Act No. 5911, Feb. 8, 1999
Act No. 5914, Feb. 8, 1999
Act No. 5922, Feb. 8, 1999
Act No. 6095, Dec. 31, 1999
Act No. 6656, Feb. 4, 2002
Act No. 6841, Dec. 30, 2002
Act No. 6842, Dec. 30, 2002
Act No. 6893, May 29, 2003
Act No. 7304, Dec. 31, 2004
Act No. 7386, Jan. 27, 2005
Act No. 7459, Mar. 31, 2005
Act No. 7678, Aug. 4, 2005
Act No. 8042, Oct. 4, 2006
Act No. 8338, Apr. 6, 2007
Act No. 8352, Apr. 11, 2007
Act No. 8369, Apr. 11, 2007
Act No. 8370, Apr. 11, 2007
Act No. 8371, Apr. 11, 2007
Act No. 8404, Apr. 27, 2007
Act No. 8466, May 17, 2007
Act No. 8819, Dec. 27, 2007
Act No. 8820, Dec. 27, 2007
Act No. 8852, Feb. 29, 2008
Act No. 8974, Mar. 21, 2008
Act No. 8976, Mar. 21, 2008
Act No. 9037, Mar. 28, 2008
Act No. 9071, Mar. 28, 2008
Act No. 9313, Dec. 31, 2008
Act No. 9763, Jun. 9, 2009
Act No. 9770, Jun. 9, 2009
Act No. 9773, Jun. 9, 2009
Act No. 10272, Apr. 15, 2010
Act No. 10331, May 31, 2010
Act No. 10599, Apr. 14, 2011
Act No. 10672, May 19, 2011
Act No. 11037, Aug. 4, 2011
Act No. 11690, Mar. 23, 2013
Act No. 11794, May 22, 2013
Act No. 12087, Aug. 13, 2013
Act No. 12248, Jan. 14, 2014
Act No. 12542, Mar. 24, 2014
Act No. 12826, Oct. 15, 2014
법령보기 화면
Article 1 (Purpose)
The purpose of this Act is to meet rapidly increasing demand for harbors and to contribute to developing the national economy by providing for matters necessary for facilitating construction of new harbors, and by efficiently implementing new harbor construction projects.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 2 (Definitions)
The terms used in this Act are defined as follows:
1.
The term "new harbor" means a harbor designated and publicly notified by the Minister of Oceans and Fisheries, that is constructed for efficiently transporting exported and imported cargo, etc.;
2.
The term "new harbor construction project" means any of the following projects necessary for constructing and operating a new harbor:
(a)
A project for constructing harbor facilities, as defined in subparagraph 5 of
Article 2 of the Harbor Act
;
(b)
A project for constructing roads, railroads, or canals connecting a harbor with main arterial roads to transport cargo, passengers, etc. to and from a new harbor;
(c)
A project for developing harbor-related infrastructure, such as goods distribution facilities, information and communications facilities, amenities for harbor users and those engaged in harbor-related business, recreational marine waterfronts;
(d)
A project for developing residential infrastructure for those engaged in harbor-related business and relocated residents;
(e)
A project for reclaiming public waters to develop an area prearranged for constructing a new harbor.
법령보기 화면
Article 3 (Formulation, etc. of Master Plans for Construction of New Harbors)
(1)
Where necessary to construct a new harbor, the Minister of Oceans and Fisheries shall formulate a master plan to construct the new harbor (hereinafter referred to as "master plan"), as prescribed by Presidential Decree.
(2)
When the Minister of Oceans and Fisheries intends to formulate a master plan pursuant to paragraph (1), he/she shall pre-consult thereon with the relevant Metropolitan City Mayor,
Do
Governor, or Governor of a Special Self-Governing Province involved in the master plan (hereinafter referred to as "Mayor/
Do
Governor") and the heads of relevant central administrative agencies.
(3)
Upon formulating a master plan pursuant to paragraph (1), the Minister of Oceans and Fisheries shall give public notification thereof, as prescribed by Presidential Decree, and forward the plan to the relevant Mayor/
Do
Governor to make it available to the public for inspection for at least 14 days.
(4)
Paragraphs (2) and (3) shall apply
mutatis mutandis
where the Minister of Oceans and Fisheries intends to amend a master plan formulated pursuant to paragraph (1):
Provided
, That the foregoing shall not apply to any amendment to minor matters specified by Presidential Decree.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 4 (Contents of Master Plans)
Each master plan shall include:
1.
Basic direction-setting for construction of the relevant new harbor;
2.
An overview of the new harbor construction plan;
3.
A medium to long term development plan;
4.
A land-use plan and an infrastructure plan regarding the relevant new harbor construction project;
5.
Other matters specified by Presidential Decree.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 5 (Designation, etc. of Prearranged Areas)
(1)
The Minister of Oceans and Fisheries may designate a specified area of territorial sea or a certain area necessary for implementing a new harbor construction project, as an area prearranged for constructing a new harbor (hereinafter referred to as "prearranged area"), or may alter a prearranged area so designated.
(2)
When the Minister of Oceans and Fisheries intends to designate a prearranged area or alter a prearranged area under paragraph (1), he/she shall pre-consult thereon with the relevant Mayor/
Do
Governor and the heads of relevant central administrative agencies.
(3)
When the Minister of Oceans and Fisheries designates a prearranged area or alter a prearranged area under paragraph (1), he/she shall give public notification thereof, as prescribed by Presidential Decree.
(4)
When the head of a relevant administrative agency intends to grant permission, approval, authorization, licenses, or accept registration (hereafter in this paragraph referred to as "permission or approval") for any activity specified by Presidential Decree, such as changing the form or quality of land, constructing a building, erecting an artificial structure, extracting soil, stones, gravel, or sand, or capturing, gathering, or cultivating aquatic animals and plants, in a prearranged area, he/she shall seek the opinion of the Minister of Oceans and Fisheries thereon. The foregoing shall also apply where he/she intends to grant permission or approval to amend any matter already permitted or approved.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 6 Deleted. <by Act No. 5922, Feb. 8, 1999>
법령보기 화면
Article 7 (Operators of New Harbor Construction Projects)
(1)
A new harbor construction project shall be implemented by the State or a person designated by the Minister of Oceans and Fisheries (hereinafter referred to as "project operator"):
Provided
, That where a new harbor construction project is implemented as a public-private partnership project pursuant to the
Act on Public-Private Partnerships in Infrastructure
, the operator of such project shall be deemed a project operator designated under this Act pursuant to
Article 13 (4) of the said Act
.
(2)
A person who wishes to be designated as a project operator under paragraph (1) shall formulate a project plan to construct a new harbor (hereinafter referred to as "project plan") in accordance with the master plan publicly notified under
Article 3
(3), as prescribed by Presidential Decree, and obtain approval of the project plan from the Minister of Oceans and Fisheries. The foregoing shall also apply where he/she intends to amend an approved project plan.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 8 (Approval of Implementation Plans)
(1)
A project operator shall formulate a plan to implement a new harbor construction project (hereinafter referred to as "implementation plan") within the scope of the relevant project plan, as prescribed by Presidential Decree, and obtain approval of the implementation plan from the Minister of Oceans and Fisheries. In such cases, if the project operator deems it necessary for efficiently implementing the new harbor construction project, it may formulate an implementation plan for each phase or facility within the scope of the relevant project plan.
(2)
The Minister of Oceans and Fisheries shall review the following before approving an implementation plan under paragraph (1):
1.
Whether the contents of the implementation plan conform to the relevant master plan and project plan;
2.
Whether the results of consultation with the heads of relevant administrative agencies under
Article 9
(1) and the results of deliberation by the New Harbor Construction Deliberative Committee under
Article 10
(1) are complied with;
3.
Whether the preparation of design documents for the project, and design supervision, consultation, and review have been performed in compliance with relevant statutes;
4.
Whether financial plans, including annual investment plans and annual financing plans, are feasible;
5.
Whether the plan to purchase and compensate for land, etc. in the project zone, and the resident relocation plan are appropriate;
6.
Whether the results of assessment conducted under the
Environmental Impact Assessment Act
are confirmed;
7.
Whether the results of the traffic impact assessment and of the review of improvement measures, conducted under the
Urban Traffic Improvement Promotion Act
, have been confirmed;
8.
Whether the plan includes details about the survey of direct and indirect damage from the implementation of the relevant harbor project.
(3)
When the Minister of Oceans and Fisheries approves an implementation plan under paragraph (1), he/she shall give public notification thereof, as prescribed by Presidential Decree, and forward copies of relevant documents to the head of the relevant local government.
(4)
Upon receipt of copies of relevant documents under paragraph (3), the head of the relevant local government shall take necessary measures, such as filing an application for approval of a topographic map under
Article 32 of the National Land Planning and Utilization Act
, if such documents contain any matter subject to determination by an urban/
Gun
management plan. In such cases, the relevant project operator shall submit documents required for giving public notification of the topographic map to the head of the local government.
(5)
When the Minister of Oceans and Fisheries formulates or approves an implementation plan that requires expropriation or use of land, etc. under
Article 16
(1), he/she shall give public notification of the name of the relevant project operator, the type of project, the subcategories of land, etc. to be expropriated or used, and inform the owners or right-holder of such land, etc. of the same:
Provided
, That the foregoing shall not apply where a project operator has held pre-consultation with the owners or right-holders of the land, etc. before filing an application for approval of an implementation plan.
(6)
When a project operator intends to amend or rescind any matter specified by Presidential Decree regarding his/her implementation plan approved under paragraph (1), it shall obtain approval thereof from the Minister of Oceans and Fisheries. Paragraphs (1) through (5) (excluding the proviso to paragraph (5)) shall apply
mutatis mutandis
to such cases.
(7)
Upon receipt of an application for approval of an implementation plan or an application for approval for amendment or rescindment under paragraph (1) or (6), the Minister of Oceans and Fisheries shall notify the relevant applicant of approval or rejection of the application, or grounds for delay in processing such application, within 60 days from the filing date of the application. If he/she fails to give notification of approval or rejection of the application or grounds for delay in processing the application, within such period, the application shall be deemed approved on the date immediately following the expiration of such period.
(8)
When the Minister of Oceans and Fisheries gives notice of grounds for delay in processing an application under paragraph (7), he/she may extend the processing period specified under paragraph (7) by up to 20 days.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 9 (Authorization, Permission, etc. Deemed Granted under other Acts)
(1)
When the Minister of Oceans and Fisheries intends to formulate or approve an implementation plan that includes any of the matters specified in paragraph (2), he/she shall pre-consult with the heads of relevant administrative agencies, along with the relevant documents submitted by a project operator. In such cases, the head of an administrative agency shall present his/her opinion thereon within 20 days after receipt of a request for consultation, but if he/she fails to present his/her opinion within such period, consultation shall be deemed completed.
(2)
When the Minister of Oceans and Fisheries formulates or approves an implementation plan in consultation with the heads of relevant administrative agencies pursuant to paragraph (1), the following approval, permission, authorization, determination, licenses, consultation, consent, cancellation, deliberation, registration, or such (hereinafter referred to a "authorization, permission, etc.”) shall be deemed granted, made, completed, or accepted, and if the approval of the implementation plan is publicly notified, authorization, permission, etc. shall be deemed publicly notified or announced under the following Acts:
<Amended by Act No. 11794, May 22, 2013; Act No. 12248, Jan. 14, 2014; Act No. 12542, Mar. 24, 2014>
1.
Determination of an urban/
Gun
management plan under
Article 30 of the National Land Planning and Utilization Act
(limited to a plan for harbor facilities, among the facilities referred to in subparagraph 6 (a) of
Article 2 of the said Act
); permission for development activities under
Article 56 of the said Act
; designation of the implementer of an urban/
Gun
planning facility project under
Article 86 of the said Act
; formulation and authorization of an implementation plan for an urban/
Gun
planning facility project under
Article 88 of the said Act
;
2.
Authorization for a general waterworks project under
Article 17 (1) of the Water Supply and Waterworks Installation Act
; authorization for a waterworks project for industrial use under
Article 49 of the said Act
; authorization to install a private water supply system under
Article 52 of the said Act
; authorization to install a private water supply system for industrial use under
Article 54 of the said Act
;
3.
Permission to implement a public sewerage project under
Article 16 of the Sewerage Act
; permission to occupy and use a public sewerage system under
Article 24 of the said Act
; reporting on the installation of a private sewerage treatment facility under
Article 34 (2) of the said Act
;
4.
Permission to occupy and use public waters under
Article 8 of the Public Waters Management and Reclamation Act
; approval of, or reporting on an implementation plan to occupy and use public waters under
Article 17 of the said Act
; formulation of, or amendments to, the master plan to reclaim public waters under
Articles 22 or 27 of the said Act
; granting of a license to reclaim public waters under
Article 28 of the said Act
; consultation on, or approval of, reclamation conducted by the State or other entity under
Article 35 of the said Act
; approval of an implementation plan to reclaim public waters under
Article 38 of the said Act
;
5.
Consultation with, or approval from, a river management authority under
Article 6 of the River Act
(limited to consultation or approval regarding permission to implement a river project under
Article 30 of the said Act
, permission to occupy and use a river under
Article 33 of the said Act
; permission to use water from a river under
Article 50 of the said Act
);
6.
Permission to fell trees, or extract soil or stone under
Article 14 of the Erosion Control Work Act
; cancellation of the designation of an erosion control area under
Article 20 of the said Act
;
7.
Permission for, or consultation on, conversion of farmland under
Article 34 of the Farmland Act
;
8.
Consultation with, or approval from, a road management authority under
Article 107 of the Road Act
(limited to consultation or approval regarding designation or public notification of a road route under
Article 19 of the said Act
; determination of a road zone under
Article 25 of the said Act
; permission to implement a road project, granted to a person who is not a road management authority under
Article 36 of the said Act
; permission to occupy and use a road under
Article 61 of the said Act
;
9.
Permission for, or reporting on, conversion of a mountainous district under
Articles 14
or
15 of the Mountainous Districts Management Act
; permission for, or reporting on, temporary use of a mountainous district under
Article 15-2 of the said Act
; permission for, or reporting on, felling standing trees under
Article 36 (1) or (4) of the Creation and Management of Forest Resources Act
; permission for, or reporting on, activities in a reserved forest (excluding conservation zones for forest gene resources) under
Article 9 (1) or (2) 1 or 2 of the Forest Protection Act
; cancellation of designation of a reserved forest under
Article 11 (1) 1 of the said Act
;
10.
Consent to a building permit under
Article 7 (1) of the Installation, Maintenance, and Safety Control of Fire-Fighting Systems Act
; reporting on installation of a fire-fighting system under
Article 13 (1) of the Fire-Fighting System Installation Business Act
; permission to build or alter a factory, etc. under
Article 6 (1) of the Safety Control of Dangerous Substances Act
;
11.
Approval of an implementation plan for a railroad construction project, or approval to amend such implementation plan under
Article 9 of the Railroad Construction Act
;
12.
Consultation with a park management authority under
Article 71 (1) of the Natural Parks Act
(limited to consultation on permission to engage in activities, other than a park project under
Article 23 of the said Act
);
13.
Review of the traffic impact assessment and improvement measures under
Article 16 of the Urban Traffic Improvement Promotion Act
;
14.
Approval for establishing a factory under
Article 13 of the Industrial Cluster Development and Factory Establishment Act
(limited to factories built during the relevant construction period as facilities for construction works, directly required for a new harbor construction project);
15.
Deliberation, etc. by the Building Committee under
Article 4 of the Building Act
; a building permit under
Article 11 of the said Act
; a building permit for a temporary building under
Article 20 (1) of the said Act
; consultation on a building project under
Article 29 of the same Act
;
16.
Approval of, or reporting on, construction of a waste disposal facility under
Article 29 of the Wastes Control Act
;
17.
Permission for, or reporting on, installation of an emitting or discharging facility under
Article 23 of the Clean Air Conservation Act
,
Article 33 of the Water Quality and Aquatic Ecosystem Conservation Act
, or
Article 8 of the Noise and Vibration Control Act
;
18.
Registration of an integrated logistics terminal business under
Article 7 of the Act on the Development and Management of Logistics Facilities
; authorization for implementing an integrated logistics terminal project or a general logistics terminal project under
Article 9 of the said Act
;
19.
Permission to extract aggregate under
Article 22 of the Aggregate Extraction Act
;
20.
Deliberation by the Construction Technology Deliberative Committee under
Article 5 of the Construction Technology Management Act
;
21.
Designation of the implementer of an industrial complex development project under
Article 16 of the Industrial Sites and Development Act
; approval of an implementation plan under
Article 17 of the said Act
.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 9-2 (Integrated Council for Authorization, Permission, etc. Deemed Granted)
(1)
The Minister of Oceans and Fisheries may hold meetings of an Integrated Council comprised of all relevant administrative agencies, as prescribed by Presidential Decree, in order to consult the heads of the relevant administrative agencies on authorization, permission, etc. deemed granted under the former part of Article 9 (1).
(2)
The head of each relevant administrative agency referred to in
Article 9
(1) shall require subordinate public officials to attend meetings of the Integrated Council under paragraph (1).
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 10 (New Harbor Construction Deliberative Committee)
(1)
A New Harbor Construction Deliberative Committee (hereinafter referred to as the "Deliberative Committee") shall be established under the Ministry of Oceans and Fisheries to deliberate on important matters about new harbor construction projects in terms of architectural technology, construction technology, traffic impact, etc.
(2)
When the Minister of Oceans and Fisheries intends to formulate or approve an implementation plan that includes any matter referred to in
Article 9
(2)
13
,
15
(excluding a building permit for a temporary building under
Article 20 (1) of the Building Act
), or
20
, he/she shall submit the plan to the Deliberative Committee for deliberation.
(3)
The organization, functions, and operation of the Deliberative Committee, and other necessary matters, shall be prescribed by Presidential Decree.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 11 (Special Provisions to Facilitate New Harbor Construction Projects and to Improve Quality of such Projects, etc.)
(1)
If either of the following applies to a harbor facility, none of
Articles 49
,
50
, or
53 of the Building Act
,
Article 5 (4) of the Safety Control of Dangerous Substances Act
, and
Article 9 (1) of the Installation, Maintenance, and Safety Control of Fire-Fighting Systems Act
shall apply to the harbor facility:
1.
Where the harbor facility uses a special technology or special device approved by the Minister of Oceans and Fisheries after deliberation by the Deliberative Committee;
2.
Where the Minister of Oceans and Fisheries verifies that the structure and form of the harbor facility meet or excel the standards for fire-fighting, the prevention of disasters, fire prevention, evacuation, etc. provided for by relevant Acts and subordinate statutes after deliberation by the Deliberative Committee.
(2)
If it is impracticable for a project operator to award a contract for architectural works, electrical works, and telecommunications works separately in terms of the nature or technical management of such works when it intends to award a contract for construction works of a major harbor facility with diverse functions and features, such as a container terminal, it may enter into a turnkey contract, as prescribed by Presidential Decree.
(3)
Notwithstanding
Article 20 of the Industrial Cluster Development and Factory Establishment Act
, a project operator may build new manufacturing facilities that the Minister of Oceans and Fisheries deems necessary directly for manufacturing various building materials required for a new harbor construction project, or extend such facilities in, or adjacent to, the prearranged area, or relocate such facilities to the prearranged area or adjacent area. In such cases, manufacturing facilities of building materials shall be limited to those established for construction purposes during the period of the relevant new harbor construction project.
(4)
The Minister of Oceans and Fisheries may entrust a project operator, other than the State, with the implementation of a project for constructing basic facilities, among harbor facilities referred to in subparagraph 2 (a) of
Article 2
and implemented by the State, as prescribed by Presidential Decree.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 12 (Restrictions, etc. on Disposal of State-Owned or Public Land)
(1)
No parcel of land in a prearranged area owned by the State or a local government and required for a new harbor construction project, shall be sold or otherwise transferred to any third person for any purpose other than the new harbor construction project.
(2)
Notwithstanding the
State Property Act
, the
Public Property and Commodity Management Act
, and other statutes, any property in a prearranged area owned by the State or a local government, may be sold to a project operator under a negotiated contract. In such cases, the Minister of Oceans and Fisheries shall pre-consult with the heads of relevant administrative agencies on the disuse and sale of such property (limited to administrative property; hereinafter the same shall apply).
(3)
Upon receipt of a request for consultation under the latter part of paragraph (2), the head of a relevant administrative agency shall take measures to disuse or sell the relevant property or other necessary measures within 90 days after receipt of such request.
(4)
Notwithstanding the provisions of other statutes, the Minister of Strategy and Finance shall manage or dispose of property to be sold to a project operator under paragraph (2), if the management authority of such property is unknown.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 13 (Confirmation of Completion)
(1)
Upon completion of construction works for a new harbor construction project, the project operator shall submit a project completion report to the Minister of Oceans and Fisheries to obtain confirmation of completion. Upon receipt of an application for confirmation of completion in such cases, the Minister of Oceans and Fisheries may request the head of the relevant central administrative agency, local government, public institution (referring to a public institution defined under the
Act on the Management of Public Institutions
), research institute, or other specialized institution, to conduct inspections necessary for confirmation of completion.
(2)
Upon receipt of an application for confirmation of completion under paragraph (1), the Minister of Oceans and Fisheries shall conduct inspections, as prescribed by Presidential Decree, and shall issue a certificate of completion to the relevant applicant, if he/she finds that the project has been performed in compliance with approved terms and conditions.
(3)
A certificate of completion issued under paragraph (2) shall be deemed a certificate of final inspection, or approval of completion, of the relevant project conducted following authorization, permission, etc. under
Article 9
(2).
(4)
No project operator shall use any parcel of land or facility developed or built in the course of a new harbor construction project before it accepts a certificate of completion under paragraph (2):
Provided
, That the foregoing shall not apply where a project operator reports on use to the Minister of Oceans and Fisheries, as prescribed by Ministerial Decree of Oceans and Fisheries.
(5)
A project operator may file an application for confirmation of completion for each phase of the project, or for each facility within the scope of the relevant implementation plan, if necessary for efficiently implementing the relevant new harbor construction project.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 14 (Vesting Ownership of Facilities)
(1)
The
Harbor Act
shall apply to vesting ownership of land and facilities developed or built in the course of a new harbor construction project, the calculation of the total project cost, and the use of facilities.
(2)
Notwithstanding paragraph (1), the
Act on Public-Private Partnerships in Infrastructure
shall apply to vesting ownership of land and facilities developed or built in the course of a new harbor construction project, the calculation of the total project cost, and the use of facilities, if the operator of such new harbor construction project is an implementer of a public-private partnership project conducted under said Act.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 15 (Access to, and Use of, Land, etc.)
(1)
If necessary for conducting investigations and surveys to formulate an implementation plan, or for implementing a new harbor construction project, a project implementer may:
1.
Access a third person’ land;
2.
Temporarily use a third person’s land as a storage yard, passage, or temporary road;
3.
Alter or remove bamboo, trees, soil, and stones, and other obstacles, where particularly necessary.
(2)
Article 130
(2) through (7), and
Article 131 of the National Land Planning and Utilization Act
shall apply
mutatis mutandis
to paragraph (1).
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 16 (Expropriation of Land, etc.)
(1)
A project operator may expropriate or use any of the land, goods, or rights specified in
Article 3 of the Act on the Acquisition of and Compensation for Land, etc. for Public Works Projects
(hereinafter referred to as "land or other property"), if necessary for implementing a new harbor construction project.
(2)
The public notification of an implementation plan under
Article 8
(3) shall be deemed project approval and public announcement of project approval under
Articles 20
(1) and
22 of the Act on the Acquisition of and Compensation for Land, etc. for Public Works Projects
.
(3)
Notwithstanding
Articles 23
(1) and
28 (1) of the Act on the Acquisition of and Compensation for Land, etc. for Public Works Projects
, an application for adjudication on expropriation or use of land or other property under paragraph (1) may be filed during the implementation period specified in the relevant implementation plan.
(4)
The Central Land Tribunal shall have jurisdiction over adjudication on expropriation or use of land or other property under paragraph (1).
(5)
Except as otherwise expressly provided for by this Act, the
Act on the Acquisition of and Compensation for Land, etc. for Public Works Projects
shall apply
mutatis mutandis
to expropriation or use of land and other property under paragraph (1).
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 17 (Advance Payments, etc.)
(1)
A project operator may receive advance payments for the full, or part of, the price for the land developed and supplied by implementing a new harbor construction project in accordance with terms and conditions stipulated in the relevant implementation plan from the persons to whom such land are supplied by parcels, as prescribed by Presidential Decree.
(2)
A project operator may issue bonds redeemable for land (hereinafter referred to as "bonds redeemable for land") to persons, to whom the land developed by implementing a new harbor construction project, are to be supplied by parcels in accordance with terms and conditions stipulated in the relevant implementation plan.
(3)
Procedures and methods for, terms and conditions of issuance of bonds redeemable for land, and other necessary matters, shall be prescribed by Presidential Decree.
(4)
If a project operator intends to receive advance payments for the full, or part of, the price for land supplied under paragraph (1), or issue bonds redeemable for land under paragraph (2), it shall formulate a plan thereon and obtain approval thereof from the Minister of Oceans and Fisheries.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 17-2 (Deadline for Processing Applications for Approval of Advance Payments, etc.)
(1)
Upon receipt of an application for approval filed by a project implementer under
Article 17
(4), the Minister of Oceans and Fisheries shall notify the project operator as to whether he/she approves or reject the application by not later than 20 days after the filing date of the application.
(2)
If the circumstances make it impracticable for the Minister of Oceans and Fisheries to decide on approval within the period specified in paragraph (1), he/she may notify the relevant project operator of the grounds for delaying processing the application, and the extended deadline for processing the application. In such cases, no processing period shall be extended by more than 20 days.
(3)
If the Minister of Oceans and Fisheries fails to notify a project operator of approval or rejection of his/her application, or the grounds for delaying processing his/her application within the period specified in paragraph (1), or of approval or rejection of his/her application by the deadline extended under paragraph (2), it shall be deemed that the Minister of Oceans and Fisheries approves the application on the date immediately following the deadline.
[This Article Added by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 18 (Supervision)
(1)
The Minister of Oceans and Fisheries may revoke permission or approval granted under this Act, or issue an order to a project operator to suspend or alter construction works, or rebuild, alter, or relocate a facility or an object if:
1.
the project operator obtained permission or approval under this Act by fraudulent or other illegal means;
2.
the project operator violates this Act or an order or a disposition issued or taken under this Act;
3.
the project operator substantially falls behind the schedule due to its fault;
4.
it is impossible to continue a new harbor construction project due to a change in circumstances.
(2)
When the Minister of Oceans and Fisheries takes a disposition or issues an order under paragraph (1), he/she shall give public notification thereof, as prescribed by Presidential Decree.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 18-2 (Hearings)
The Minister of Oceans and Fisheries shall hold a hearing if he/she intends to revoke permission or approval under
Article 18
(1).
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 19 Deleted. <by Act No. 5922, Feb. 8, 1999>
법령보기 화면
Article 20 (Government Subsidies, etc.)
The Government may fully or partially subsidize a project operator for expenses incurred in implementing a new harbor construction project or may provide loans from government funds to a project operator, within budgetary limits.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 21 (Implementation of Incidental Works)
(1)
A project operator may conduct incidental works that are not included in the scope of a new harbor construction project but becomes necessary as a consequence of, or in order to perform, the new harbor construction project, in addition to the new harbor construction project, deeming such incidental works part of the new harbor construction project.
(2)
The scope of incidental works referred to in paragraph (1) shall be prescribed by Presidential Decree.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 22 (Entrustment of Purchase of Land, etc.)
(1)
A project operator may entrust the head of the relevant local government with the purchase of land, compensation for losses, relocation measures, etc. for a new harbor construction project, as prescribed by Presidential Decree.
(2)
Fees for entrusting purchase of land, compensation for losses, relocation measures, etc. to the head of the relevant local government under paragraph (1) shall be prescribed by Presidential Decree.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 23 (Delegation of Authority)
The Minister of Oceans and Fisheries may delegate part of his/her authority vested under this Act to the head of a Regional Maritime Affairs and Port Administration or a Mayor/
Do
Governor, as prescribed by Presidential Decree.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 24 (Penal Provisions)
Any person who uses land or a facility without reporting before the completion of a project is confirmed, in violation of
Article 13
(4), shall be punished by imprisonment for up to one year, or by a fine not exceeding ten million won. <Amended by Act No. 12826, Oct. 15, 2014>
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 24-2 (Penal Provisions)
Any person who violates an order or a disposition issued or taken under
Article 18
(1) shall be punished by a fine not exceeding three million won.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
법령보기 화면
Article 25 (Joint Penalty Provisions)
When the representative of a juristic person or an agent, employee or other servant of a juristic person or individual commits an offence under
Article 24
or
24-2
in connection with the business of the juristic person or the individual, not only shall such offender be punished, but the juristic person or the individual shall also be punished by a fine under the relevant provisions:
Provided
, That this shall not apply where such juristic person or individual has not been negligent in giving due attention and supervision concerning the relevant duties to prevent such offence.
[This Article Wholly Amended by Act No. 10672, May 19, 2011]
법령보기 화면
Article 26 (Administrative Fines)
The Minister of Oceans and Fisheries shall impose an administrative fine not exceeding three million won on any person who refuses or interferes with activities conducted by a project operator under
Article 15
(1), without just grounds.
[This Article Wholly Amended by Act No. 12542, Mar. 24, 2014]
ADDENDA
(1)
(Enforcement Date) This Act shall enter into force three months after the date of its promulgation.
(2)
(Transitional Measures concerning Harbor Construction Projects in Progress) New construction of harbor facilities in progress under the
Harbor Act
or the
Promotion of Private Capital into Social Overhead Capital Investment Act
or a private investment project for harbor construction which has undergone deliberation by the Steering Committee, at the time this Act enters into force, shall be deemed a new harbor construction project in progress under this Act. In such cases, when a master plan has already been publicized pursuant to the provisions of the relevant statutes, the designation and announcement of a new harbor and the formulation and publication of a master plan shall be deemed to have been made under this Act with regard to the relevant harbor and harbor construction project, and when an action plan has already been approved pursuant to the provisions of the relevant statutes, the action plan shall be deemed to have been approved under this Act.
(3)
Omitted.
ADDENDA <Act No. 5453, Dec. 13, 1997>
Article 1 (Enforcement Date)
This Act shall enter into force on January 1, 1998. (Proviso Omitted).
Article 2 Omitted.
ADDENDUM <Act No. 5454, Dec. 13, 1997>
This Act shall enter into force on March 1, 1998. (Proviso Omitted).
ADDENDA <Act No. 5864, Feb. 8, 1999>
Article 1 (Enforcement Date)
(1)
This Act shall enter into force six months after the date of its promulgation.
(2)
through (4) Omitted.
Articles 2 through 10 Omitted.
ADDENDA <Act No. 5893, Feb. 8, 1999>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation.
Articles 2 through 6 Omitted.
ADDENDA <Act No. 5911, Feb. 8, 1999>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation.
Articles 2 through 8 Omitted.
ADDENDA <Act No. 5914, Feb. 8, 1999>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation.
Articles 2 through 5 Omitted.
ADDENDA <Act No. 5922, Feb. 8, 1999>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation:
Provided
, That the amended provisions of
Article 19
shall enter into force on the date of its promulgation.
Article 2 (Applicability for Confirmation of Completion)
The amended provisions of
Article 13
(2) shall apply to applications for confirmation of completion filed on or after the date this Act enters into force.
Article 3 (Transitional Measures concerning Orders for Reinstatement and Vicarious Execution)
The previous provisions shall apply to an order for reinstatement and the vicarious execution thereof with regard to a person who has violated the previous Article 6 (1) at the time this Act enters into force.
Article 4 (Transitional Measures concerning Permission for Use Before Completion)
A person who has obtained or applied for permission for use before completion pursuant to the proviso to previous Article 13 (4) at the time this Act enters into force shall be deemed a person who has filed a report of use before completion or a person who has obtained or applied for permission before completion pursuant to the amended provisions of the proviso to the same paragraph of the same Article.
Article 5 (Transitional Measures concerning Penalty Provisions)
The previous provisions shall apply to the penalty provisions applicable to acts committed before this Act enters into force.
ADDENDA <Act No. 6095, Dec. 31, 1999>
Article 1 (Enforcement Date)
This Act shall enter into force on January 1, 2001.
Articles 2 through 10 Omitted.
ADDENDA <Act No. 6656, Feb. 4, 2002>
Article 1 (Enforcement Date)
This Act shall enter into force on January 1, 2003.
Articles 2 through 12 Omitted.
ADDENDA <Act No. 6841, Dec. 30, 2002>
Article 1 (Enforcement Date)
This Act shall enter into force nine months after the date of its promulgation.
Articles 2 through 12 Omitted.
ADDENDA <Act No. 6842, Dec. 30, 2002>
Article 1 (Enforcement Date)
This Act shall enter into force on July 1, 2003.
Articles 2 through 8 Omitted.
ADDENDA <Act No. 6893, May 29, 2003>
Article 1 (Enforcement Date)
This Act shall enter into force one year after the date of its promulgation.
Articles 2 through 6 Omitted.
ADDENDA <Act No. 7304, Dec. 31, 2004>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation.
Articles 2 through 10 Omitted.
ADDENDA <Act No. 7386, Jan. 27, 2005>
Article 1 (Enforcement Date)
This Act shall enter into force on the date of its promulgation. (Proviso Omitted.)
Articles 2 through 6 Omitted.
ADDENDA <Act No. 7459, Mar. 31, 2005>
Article 1 (Enforcement Date)
This Act shall enter into force one year after the date of its promulgation.
Articles 2 through 6 Omitted.
ADDENDA <Act No. 7678, Aug. 4, 2005>
Article 1 (Enforcement Date)
This Act shall enter into force one year after the date of its promulgation.
Articles 2 through 12 Omitted.
ADDENDA <Act No. 8042, Oct. 4, 2006>
(1)
(Enforcement Date) This Act shall enter into force three months after the date of its promulgation.
(2)
(Transitional Measures concerning Penalty Provisions) The previous provisions shall apply to the penalty provisions applicable to acts committed before this Act enters into force.
ADDENDA <Act No. 8338, Apr. 6, 2007>
Article 1 (Enforcement Date)
This Act shall enter into force one year after the date of its promulgation.
Articles 2 through 17 Omitted.
ADDENDA <Act No. 8352, Apr. 11, 2007>
Article 1 (Enforcement Date)
This Act shall enter into force on the date of its promulgation. (Proviso Omitted.)
Articles 2 through 16 Omitted.
ADDENDA <Act No. 8369, Apr. 11, 2007>
Article 1 (Enforcement Date)
This Act shall enter into force on the date of its promulgation. (Proviso Omitted.)
Articles 2 through 16 Omitted.
ADDENDA <Act No. 8370, Apr. 11, 2007>
Article 1 (Enforcement Date)
This Act shall enter into force on the date of its promulgation. (Proviso Omitted.)
Articles 2 through 20 Omitted.
ADDENDA <Act No. 8371, Apr. 11, 2007>
Article 1 (Enforcement Date)
This Act shall enter into force on the date of its promulgation. (Proviso Omitted.)
Articles 2 through 10 Omitted.
ADDENDA <Act No. 8404, Apr. 27, 2007>
Article 1 (Enforcement Date)
This Act shall enter into force on the date of its promulgation. (Proviso Omitted.)
Articles 2 through 14 Omitted.
ADDENDA <Act No. 8466, May 17, 2007>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation.
Articles 2 through 5 Omitted.
ADDENDA <Act No. 8819, Dec. 27, 2007>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation. (Proviso Omitted.)
Articles 2 through 9 Omitted.
ADDENDA <Act No. 8820, Dec. 27, 2007>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation. (Proviso Omitted.)
Articles 2 through 9 Omitted.
ADDENDA <Act No. 8852, Feb. 29, 2008>
Article 1 (Enforcement Date)
This Act shall enter into force on the date of its promulgation. (Proviso Omitted.)
Articles 2 through 7 Omitted.
ADDENDA <Act No. 8974, Mar. 21, 2008>
Article 1 (Enforcement Date)
This Act shall enter into force on the date of its promulgation. (Proviso Omitted.)
Articles 2 through 14 Omitted.
ADDENDA <Act No. 8976, Mar. 21, 2008>
Article 1 (Enforcement Date)
This Act shall enter into force on the date of its promulgation. (Proviso Omitted.)
Articles 2 through 10 Omitted.
ADDENDA <Act No. 9037, Mar. 28, 2008>
Article 1 (Enforcement Date)
This Act shall enter into force on January 1, 2009.
Articles 2 through 19 Omitted.
ADDENDA <Act No. 9071, Mar. 28, 2008>
Article 1 (Enforcement Date)
This Act shall enter into force on January 1, 2009. (Proviso Omitted.)
Articles 2 through 11 Omitted.
ADDENDA <Act No. 9313, Dec. 31, 2008>
Article 1 (Enforcement Date)
This Act shall enter into force on the date of its promulgation.
Articles 2 and 3 Omitted.
ADDENDA <Act No. 9763, Jun. 9, 2009>
Article 1 (Enforcement Date)
This Act shall enter into force nine months after the date of its promulgation. (Proviso Omitted.)
Articles 2 through 8 Omitted.
ADDENDA <Act No. 9770, Jun. 9, 2009>
Article 1 (Enforcement Date)
This Act shall enter into force nine months after the date of its promulgation. (Proviso Omitted.)
Articles 2 through 7 Omitted.
ADDENDA <Act No. 9773, Jun. 9, 2009>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation. (Proviso Omitted.)
Articles 2 through 10 Omitted.
ADDENDA <Act No. 10272, Apr. 15, 2010>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation. (Proviso Omitted.)
Articles 2 through 14 Omitted.
ADDENDA <Act No. 10331, May 31, 2010>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation. (Proviso Omitted.)
Articles 2 through 13 Omitted.
ADDENDA <Act No. 10599, Apr. 14, 2011>
Article 1 (Enforcement Date)
This Act shall enter into force one year after the date of its promulgation. (Proviso Omitted.)
Articles 2 through 9 Omitted.
ADDENDA <Act No. 10672, May 19, 2011>
(1)
(Enforcement Date) This Act shall enter into force on the date of its promulgation.
(2)
(Applicability to Approval of Action Plans) The amended provisions of
Article 8
(7) and (8) shall apply beginning from the first action plans for new harbor construction projects filed for approval after this Act enters into force.
(3)
(Period of Validity) The amended provisions of the proviso to
Article 18
(1) shall be effective until December 31, 2012.
ADDENDA <Act No. 11037, Aug. 4, 2011>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation. (Proviso Omitted.)
Articles 2 through 6 Omitted.
ADDENDA <Act No. 11690, Mar. 23, 2013>
Article 1 (Enforcement Date)
(1)
This Act shall enter into force on the date of its promulgation.
(2)
Omitted.
Articles 2 through 7 Omitted.
ADDENDA <Act No. 11794, May 22, 2013>
Article 1 (Enforcement Date)
This Act shall enter into force one year after the date of its promulgation.
Articles 2 through 26 Omitted.
ADDENDA <Act No. 12087, Aug. 13, 2013>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation.
Article 2 (Applicability to Authorization, Permission, etc. Deemed Granted)
The amended provisions of the latter part of
Article 9
(1) shall apply, beginning from the first request for consultation made to formulate or approve an implementation plan after this Act enters into force.
ADDENDA <Act No. 12248, Jan. 14, 2014>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation.
Articles 2 through 25 Omitted.
ADDENDA <Act No. 12542, Mar. 24, 2014>
Article 1 (Enforcement Date)
This Act shall enter into force on the date of its promulgation. (Proviso Omitted.)
Article 2 (Applicability to Deadline for Processing Applications for Approval to Make Advance Payments or to Issue Bonds Redeemable for Land)
The amended provisions of
Article 17-2
shall apply, beginning from the first application to approve a plan to receive advance payments or to issue bonds redeemable for land, filed by a project operator with the Minister of Oceans and Fisheries, after this Act enters into force.
Article 3 Omitted.
ADDENDUM <Act No. 12826, Oct. 15, 2014>
This Act shall enter into force on the date of its promulgation.
Last updated : 2016-03-24