Article 1 (Purpose)
The purpose of this Act is to simplify the procedures necessary for execution of the project to establish, relocate, and expand the elementary, middle, high, and special school facilities, prescribe special cases relating to building permission, etc., and facilitate the establishment, relocation and expansion of school facilities, thereby contributing to the improvement of the educational environment and the enhancement of the quality of education.
<Amended by Act No. 4881, Jan. 5, 1995; Act No. 5069, Dec. 29, 1995>
법령보기 화면
Article 2 (Definitions)
For the purpose of this Act:
1.
the term “school facilities” means school sites, school buildings, gymnasiums, training ground, and accessory facilities; and
2.
the term “school facilities project” means any project to establish, relocate, and expand school facilities.
법령보기 화면
Article 3 (Scope of Application)
Schools to which this Act applies (hereinafter referred to as the “school”) shall be elementary, middle, high, and special schools.
<Amended by Act No. 5069, Dec. 29, 1995>
법령보기 화면
Article 4 (Approval, etc. of Plan for School Facilities Project)
(1)
The person who intends to undertake a school facilities project (except the State and local government) shall prepare the plan for school facilities project execution (hereinafter referred to as the “execution plan”) including the site of execution, size, and financial resources of the school facilities project as prescribed by the Presidential Decree and obtain approval from the supervisory organ referred to in
Article 84 of the Education Act
(hereinafter referred to as the “supervisory authority”):
Provided
, That this shall not apply to the execution plan when construction, building, large-scale repair or alteration of use (hereinafter referred to as the “construction, etc.”) is intended for school facilities at a school facilities project execution on site that has passed the completion inspection referred to in
Article 13
(2) upon completion of the school facilities project.
(2)
The person who intends to modify the plan approved as referred to in the main text of paragraph (1) shall obtain the supervisory authority‘s approval for change:
Provided
, That the approval shall not be required for trivial change determined by the Presidential Decree.
(3)
In approving the plan or the modification plan under paragraph (1) or (2), the supervisory authority shall, under the conditions as prescribed by the Presidential Decree, consult in advance with the head of the competent administrative agencies that have jurisdiction over the applicable matters of each subparagraph of
Article 5
.
(4)
In executing a school facilities projects, the State or local government shall prepare the execution plan and consult with the heads of the competent administrative agencies that have jurisdiction over the applicable matters of each subparagraph of
Article 5
as prescribed by the Presidential Decree:
Provided
, That this shall not apply with regard to any execution plan for a case in which construction, etc. of school facilities is intended within a school facilities project execution site where the school facilities project has been already completed.
(5)
The matters that shall be included in the execution plan referred to in paragraphs (1) and (4) shall be determined by the Presidential Decree.
(6)
In a case where the supervisory authority intends to approve the plan or the changed plan under paragraph (1) or (2), or where the State or local government intends to prepare the execution plan as prescribed in paragraph (4), it shall hear the opinions of the interested parties about the land ownership, etc. when those parties have, within the execution site, any land, building and other fixtures of land whose expropriation or use is necessary under the provisions of
Article 10
or rights other than the ownership thereof.
(7)
In a case where the supervisory authority approves the plan or the modification plan under paragraph (1) or (2), the consulted administrative agencies and interested persons referred to in paragraph (3) shall be notified, and a public notification of the fact shall be made immediately. The same shall apply when the State or local government completes the consultation referred to in paragraph (4).
(8)
The person who intends to execute a school facilities project may apply simultaneously for the approval or modification approval for the execution plan referred to in paragraph (1) or (2) and the approval for construction, etc. of school facilities referred to in of
Article 5-2
(1).
[This Article Wholly Amended by Act No. 4881, Jan. 5, 1995]
법령보기 화면
Article 5 (Relation with Other Acts)
In a case where the person who intends to execute a school facilities project has obtained the approval or modification approval for the execution plan under of
Article 4
(1) or (2), or has completed a consultation under paragraph (4) of the same Article, he shall be considered to have a permission, authorization, approval, designation, agreement, consultation, report, or cancellation of the applicable matters from among the following subparagraphs:
<Amended by Act No. 4429, Dec. 14, 1991; Act No. 4881, Jan. 5, 1995>
1.
Consultation on or approval of the establishment of public facilities referred to in
Article 20 of the Act on the Utilization and Management of the National Territory
;
2.
Permission for acts referred to in
Article 4 of the Urban Planning Act
, designation of the project undertaker for the urban planning project referred to in
Article 23
of the same Act, and approval of the execution plan for the urban planning project referred to in
Article 40
of the same Act;
3.
Consultation on or approval of a state project as referred to in
Article 8 of the Road Act
, execution permission for road construction for a person who is not the administrative agency referred to in
Article 34
of the same Act, and permission to occupy a road as referred to in
Article 40
of the same Act;
4.
Deleted.
<by Act No. 4881, Jan. 5, 1995>
5.
Consultation on, approval of, or permission for the public sewerage project or its construction referred to in
Articles 3
and
13 of the Sewerage Act
;
6.
Permission to occupy and use a public park as referred to in
Article 23 of the Natural Parks Act
, permission for activities in the public park protection area as referred to in
Article 25
of the same Act, and consultation on a state project as referred to in
Article 50
(1) of the same Act;
7.
Permission for conversion of farmlands as referred to in Article 4 of the Farmland Preservation and Utilization Act, and consultation, agreement, and approval of the conversion of farmlands as referred to in
Article 5
of the same Act;
8.
Permission for activities in the farmland development promotion area as referred to in
Article 8
of the Farmland Expansion and Development Promotion Act, and permission for the conversion of farmland as referred to in
Article 53
of the same Act;
9.
Permission for, agreement on, and consultation on diversion of a conserved forest referred to in
Article 18 of the Forestry Act
, cancellation of the designation of a reserved forest as referred to in
Article 57
of the same Act, permission for timber-cutting in a reserved forest as referred to in
Article 62
of the same Act, and permission and report for cutting any standing timber as referred to in
Article 90
(1) of the same Act;
10.
Permission for timber-cutting in the erosion control area referred to in Article 14 of the Work against Land Erosion or Collapse Act and cancellation of the designation of the erosion control area as referred to in
Article 20-2
of the same Act;
11.
Permission for changes in the configuration and quality of land as referred to in
Article 39 of the Land Compartmentalization and Rearrangement Projects Act
; and
12.
Permission for utilization of the river usage as referred to in
Article 25 of the River Act
.
법령보기 화면
Article 5-2 (Construction, etc. of School Facilities)
(1)
When the person who has obtained the approval or modification approval for the execution plan under of
Article 4
(1) or (2) intends to construct, etc. school facilities, he shall obtain the approval of or notify it to the supervisory authority as prescribed by the Presidential Decree, notwithstanding the provisions of
Articles 8 and 9 of the Building Act
. The same shall apply to the case where he intends to construct, etc. school facilities under the conditions as prescribed in the proviso of
Article 4
(1).
(2)
When the supervisory authority has granted the approval or received the report under paragraph (1), it shall notify the matters concerning it to the head of
Si
/
Gun
/
Gu
(limited to the head of the autonomous
Gu
; hereinafter in this Article the same shall apply).
(3)
When the State or local government intends to construct, etc. school facilities, it shall notify the matters concerning it to the head of
Si
/
Gun
/
Gu
, notwithstanding the provisions of
Article 25 (1) of the Building Act
.
(4)
When the State, local government, or a supervisory authority has notified the matters concerning the construction, etc. of school facilities to the head of
Si
/
Gun
/
Gu
under paragraph (2) or (3), he shall be considered to have obtained the building permission or the building report referred to in
Article 8
or
9
, or to have consulted with the head of
Si
/
Gun
/
Gu
under
Article 25 (1) of the Building Act
. In a case of paragraph (1), in applying the provisions of
Articles 10, 15 (1) and (2), 16 (1), 17, 26 (2), and 27 (1) of the Building Act
with regard to school facilities, the “head of
Si
/
Gun
/
Gu
” in the same Articles and same paragraphs shall be each considered the “supervisory authorities”.
(5)
In a case where the supervisory authority examines whether or not the school facilities for which it has granted the approval and received the report under paragraphs (1) and (2) violate this Act or the
Building Act
, and considers it necessary, it shall order the necessary measure to correct the situation and notify the result to the head of
Si
/
Gun
/
Ku
.
[This Article Added by Act No. 4881, Jan. 5, 1995]
법령보기 화면
Article 6 (Consultation on Activities within School Facilities)
When administrative agencies of various levels, after approval of the execution plan referred to in
Article 4
(referred to as an agreement in the case of the State or local government; hereinafter the same shall apply) has been obtained, plans to carry out the project falling under one of the following subparagraphs or give an approval for it or other such dispositions in any school facilities (including the scheduled site for school facilities for which the execution plan has been approved under the provisions of
Article 4
), they shall consult with the supervisory authority of the schools concerned:
<Amended by Act No. 4881, Jan. 5, 1995>
1.
Installation of roads, water-supply systems, sewer systems, waterways, and fixtures thereon; and
2.
Excavation of the ground, reclamation, and other changes in the configuration and quality of the land.
법령보기 화면
Article 7 (Priority Given to Construction of Public Facilities)
When the execution plan as referred to in
Article 4
has been approved, the administrative agency in charge of the public facilities determined by the Presidential Decree such as roads, water-supply systems, sewerages, etc. shall make efforts to give priority to the installation of the public facilities related to the school facilities project within the limit of its budget so as to allow a smooth execution of the school facilities project.
법령보기 화면
Article 8 (Entry to and Exit from Land, etc.)
(1)
The party who obtained the approval of the execution plan as referred to in
Article 4
(hereinafter referred to as the “project undertaker”) may enter others’ land or use it temporarily in order to execute the school facilities project and, if necessary, may change or eliminate the standing trees, earth and rocks, or other obstacles.
(2)
The provisions of
Article 5 of the Urban Planning Act
shall apply
mutatis mutandis
to paragraph (1).
법령보기 화면
Article 9 (Compensation)
(1)
When there exists any person who has suffered a loss through the activities referred to in
Article 8
, the project undertaker shall compensate him for the loss.
(2)
The provisions of
Article 6 of the Urban Planning Act
shall apply
mutatis mutandis
with regard to the compensation referred to in paragraph (1).
법령보기 화면
Article 10 (Expropriation and Utilization)
(1)
In a case where the project undertaker needs rights besides the ownership of the specific land, buildings, and other fixtures on the land within the execution site in order to execute the school facilities project, he may expropriate or use those rights besides the ownership of the land, buildings, and other fixtures on the land.
(2)
With regard to the land expropriation or utilization referred to in paragraph (1), the
Land Expropriation Act
shall apply, except when there are specific provisions in this Act.
(3)
In applying the
Land Expropriation Act
under paragraph (2), the approval of the execution plan shall be considered the approval of project referred to in
Article 14
, and the public notification referred to in
Article 4
(7) shall be considered the notification referred to in of
Article 16 (1) of the Land Expropriation Act
, notwithstanding the provisions of
Articles 17 and 25 (2) of the Land Expropriation Act
, the application for adjudication shall be completed within the school facilities project execution period determined while approving the execution plan.
<Amended by Act No. 4881, Jan. 5, 1995>
[This Article Added by Act No. 3740, Aug. 2, 1984]
법령보기 화면
Article 11 (Cancellation, etc. of Approval of Execution Plan)
(1)
When the project undertaker (excluding the project undertaker who is the State or local government; hereinafter the same shall apply within
Articles 12
(1) and
13
(1)) falls under one of the following subparagraphs, the supervisory authority may cancel the approval referred to in this Act or order the modification of the execution on plan or other necessary measures:
<Amended by Act No. 4881, Jan. 5, 1995>
1.
When one has obtained the approval referred to in this Act by using unjust means; and
2.
When the continued execution of the school facilities project is deemed difficult, or when there is a possibility for considerable delay.
(2)
When the supervisory authority intends to make the dispositions referred to in paragraph (1), it shall provide the relevant party subject to disposition or his agent with an opportunity to state his opinion in advance as prescribed by the Presidential Decree:
Provided
, That in case the party concerned who is subject to the disposition or his agent does not conform to it without any justifiable reason, or in case the supervisory authority can not give such an opportunity to the party concerned because of his incorrect address, it shall not apply.
<Added by Act No. 4881, Jan. 5, 1995>
법령보기 화면
Article 12 (Supervision, etc.)
(1)
If the supervisory authority deems it necessary in supervising, it may ask the party in charge of the construction, etc. of school facilities under the conditions as prescribed in the proviso of
Article 4
(1) to file necessary report or order him to submit material, or make the official affiliated with the supervisory authority inspect the school facilities project.
(2)
The official who performs his inspection under paragraph (1) shall present the identification card that indicates his powers to the party concerned.
[This Article Wholly Amended by Act No. 4881, Jan. 5, 1995]
법령보기 화면
Article 13 (Completion Inspection, etc.)
(1)
When the project undertaker completes the school facilities project, he shall report it to the supervisory authority and receive the inspection of his completed project under the conditions as prescribed by the Presidential Decree. The same shall apply also to the case where the person constructing, etc. school facilities under the proviso of
Article 4
(1) has completed them.
(2)
When the supervisory authority receives the report under paragraph (1), it shall perform the inspection of the completed construction; with respect to the school facilities which passed the inspection, it shall notify the result of the inspection to each of the head of the administrative agency that has the jurisdiction over the applicable matters of each subparagraph of
Article 5
as well as the head of
Si
/
Gun
/
Gu
and give a public notification of the fact.
(3)
When the State or local government has completed a school facilities project, it shall notify the matters concerning it to each of the head of the administrative agency that has the jurisdiction over the applicable matters of each subparagraph of
Article 5
as well as the head of
Si
/
Gun
/
Gu
concerned and give a public notification of the fact.
(4)
When the supervisory authority has given a public notification of the result of its inspection of the completed construction under paragraph (2), the school facilities concerned shall be considered to have passed the usability test as referred to in
Article 18 of the Building Act
, when the State or local government has notified the matters concerning the completion of the school facilities project to the head of
Si
/
Gun
/
Gu
under paragraph (3), the notice shall be considered the one served under the proviso of
Article 25 (3) of the Building Act
.
(5)
When the head of
Si
/
Gun
/
Gu
has received notification under paragraph (2) or (3), he shall record it without delay in the building register or building control register referred to in the Acts and subordinate statutes related to building.
[This Article Wholly Amended by Act No. 4881, Jan. 5, 1995]
법령보기 화면
Article 14 (Rearrangement of Graves)
(1)
If the supervisory authority deems it necessary for the execution of the school facilities project, (in case the State or local government is the undertaker of the school facilities project, it refers to the project undertaker concerned; hereinafter in this Article the same shall apply) it may order the burier, owner or manager of the grave, or the relatives of the buried (hereinafter referred to as the “relatives, etc.”) to change the burial site or remove graves, tombstones, and their accessory facilities (hereinafter as referred to as the “graves, etc.”) within the execution site of the school facilities.
(2)
When the relatives, etc. of the graves, etc. do not conform to the order to change or move the burial site as referred to in paragraph (1), the supervisory authority may execute it by proxy as prescribed by the
Administrative Vicarious Execution Act
.
(3)
In case of paragraph (1), when the relatives, etc. of the graves, etc. are unknown, the supervisory authority shall put a notice, for a given period of time, ordering the change or removal of the graves, etc., and if graves, etc. are not changed or removed within the time period, the supervisory authority may change or remove them.
(4)
The supervisory authority shall pay the person, who has changed or removed the graves, etc. according to the change or removal of the graves, and etc. order referred to in paragraph (1), for the expenses associated with the action.
(5)
The cost of the execution by proxy as referred to in paragraph (2), the cost of the changing or removal of the burial site as referred to in paragraph (3), and the expenses referred to in paragraph (4) shall be born by the project undertaker.
(6)
The project undertaker shall include the plans for rearrangement of the graves, etc. in the execution plan.
[This Article Added by Act No. 3740, Aug. 2, 1984]
법령보기 화면
Article 15 (Delegation of Authority)
(1)
The Minister of Education may delegate part of his authority referred to in this Act to the superintendent of the board of education as prescribed by the Presidential Decree.
(2)
The superintendent of the board of education may redelegate part of the authority delegated to him under paragraph (1) to the educational superintendent, after he obtains the approval from the Minister of Education.
(3)
The superintendent of the board of education may delegate part of his authority referred to in this Act to the educational superintendent as prescribed by the Presidential Decree.
[This Article Wholly Amended by Act No. 4881, Jan. 5, 1995]
법령보기 화면
Article 16 (Enforcement Decree)
Necessary matters concerning the Enforcement Decree shall be determined by the Presidential Decree.
ADDENDA
(1)
(Enforcement Date) This Act shall enter into force 3 months after its promulgation.
(2)
(Special Cases for Application of
Urban Planning Act
to Existing Schools) Among the facilities of elementary, middle, high schools, and special schools that have been established under the
Education Act
before the enforcement of this Act, the school facilities established without obtaining the decision for urban planning referred to in
Article 12 of the Urban Planning Act
, the permission for urban planning project execution by any urban planning project undertaker who is not an administrative agency referred to in
Article 24
of the same Act, and the authorization of urban planning project execution plan referred to in
Article 25
of the same Act and conforming to the standards determined by the Presidential Decree shall be considered the facilities established with the decision for urban planning, the permission for urban planning project execution on and the authorization for urban planning project execution on plan referred to in
Articles 12
,
24
and
25
, respectively, of the
Urban Planning Act
:
Provided
, That if the land register for the facilities is uncertain, it shall be established by the public notification of the land register referred to in
Article 13 of the Urban Planning Act
. In this case, a copy of the land registration map may substitute for the application draft for the public notification of land register.
ADDENDA<Act No. 3740, Aug. 2, 1984>
(1)
(Enforcement Date) This Act shall enter into force 30 days after its promulgation.
(2)
(Transitional Measures) The public notification of the execution plan for any school facilities project and approval of that execution on plan that has been approved or passed through consultation under the previous provisions before the enforcement of this Act shall be regarded as the public notice of the execution plan for school facilities project and approval of that execution plan referred to in the amended provisions of
Article 10
.
ADDENDA<Act No. 4268, Dec. 27, 1990>
Article 1 (Enforcement Date)
This Act shall enter into force on the date of its promulgation. (Proviso is Omitted.)
Articles 2 through 10 Omitted.
ADDENDA<Act No. 4429, Dec. 14, 1991>
Article 1 (Enforcement Date)
This Act shall enter into force one year after the date of its promulgation.
Articles 2 through 6 Omitted.
ADDENDA<Act No.. 4881, Jan. 5, 1995>
Article 1 (Enforcement Date)
This Act shall enter into force 6 months after the date of its promulgation.
Article 2 (Special Cases for Application of Urban Planning Act and Building Act to Existing School Facilities)
(1)
Among the school facilities subject to this Act at the time of this Act enters into force, the school facilities established or constructed, etc. without the permission for any action referred to in
Article 4 of the Urban Planning Act
, without the approval of the urban planning project execution plan referred to in
Article 25
of the same Act obtained by the project undertaker referred to in
Article 23
of the same Act, or without the construction permission, construction report, usability inspection, or agreement referred to in
Articles 8
,
9
,
18
, or
25
, respectively, that have been confirmed under the provisions of paragraphs (2) through (4) to conform to the standards of the following subparagraphs shall be regarded as the facilities that have been established or constructed, etc. in accordance with the applicable provisions of the
Urban Planning Act
and
Building Act
. In such cases, when the land register of the facilities is uncertain, it shall be established by the public notification of the land register referred to in
Article 13 of the Urban Planning Act
, and a copy of the land registration map may substitute for the application draft for public notification of the land register:
1.
Facilities installed or constructed, etc. on a lot owned by the installer or manager of the school concerned (including land under another party’s ownership for which approval of use has been obtained);
2.
Facilities in accordance with the provisions of
Articles 33, 37, and 45 of the Building Act
;
3.
Facilities in accordance with the provisions on structural safety, sanitation, and fire-resistance of buildings; and
4.
Facilities that are not any considerable obstacle to execution of the urban planning project.
(2)
The school founder or operator who owns the school facilities (except the State or local government who establishes and manages facilities) falling under paragraph (1), shall apply to the supervisory authority for the confirmation of their suitability by submitting the application form for suitability confirmation determined by the Minister of Education, together with the blueprint and on the spot inspection record of the school facilities concerned.
(3)
When the school facilities for which application was presented for the confirmation of its suitability under paragraph (2) satisfy the criteria of each subparagraph of paragraph (1), the supervisory authority shall notify the matters concerning it to the head of the administrative agency that has jurisdiction over the applicable matters of each subparagraph of
Article 5
and the head of
Si
/
Gun
/
Gu
, with the draft for the placement of facilities, the protocol of the building list, the draft for the progress of constructions and the materials that may prove the land ownership or right of use attached, and give a public notification of the fact.
(4)
When the school facilities falling under paragraph (1) are confirmed to conform to the standards of each subparagraph of paragraph (1), the State or local government who owns them shall notify the matters concerning it to each of the head of the administrative agency that has jurisdiction over the applicable matters of each subparagraph of
Article 5
and the head of
Si
/
Gun
/
Gu
, with the materials referred to in paragraph (3) attached, and give a public notification of the fact.
(5)
When there has been a public notification referred to in paragraph (3), the school facilities concerned shall be considered to have passed the usability inspection referred to in
Article 18 of the Building Act
, notwithstanding the provisions of the
Urban Planning Act
and
Building Act
, and when the State or local government notify the head of
Si
/
Gun
/
Gu
as prescribed in paragraph (4), it shall be considered to have been notified under the proviso of
Article 25 (3) of the Building Act
.
Article 3 (Amendment of Other Acts)
ADDENDA<Act No. 5069, Dec. 29, 1995>
Article 1 (Enforcement Date)
This Act shall enter into force on March 1, 1996.
Articles 2 through 4 Omitted.
Last updated : 2009-07-26