MARINE USE IMPACT ASSESSMENT ACT
69342 · 2025-01-03
MARINE USE IMPACT ASSESSMENT ACT
Act No. 20369, Feb. 27, 2024
Act No. 20369, Feb. 27, 2024
CHAPTER I GENERAL PROVISIONS
법령보기 화면
Article 1 (Purpose)
The purpose of this Act is to prescribe matters necessary for the prior prediction and assessment of the appropriateness of marine use and the marine environmental impacts of projects involving the use and development of marine areas, and for the management and supervision of such projects, in order to conserve the marine environment and promote the sustainable use of marine areas.
법령보기 화면
Article 2 (Definitions)
The terms used in this Act are defined as follows:
1.
The term "marine area" means marine areas defined in subparagraph 1 of
Article 3 of the Framework Act on Marine Fishery Development
;
2.
The term "marine and fisheries resources" means marine and fisheries resources defined in subparagraph 2 of
Article 3 of the Framework Act on Marine Fishery Development
;
3.
The term "marine use and development project" means an activity or project that affects, or is likely to affect, the marine environment or existing marine uses in the course of using or developing marine and fisheries resources;
4.
The term "consultation on marine use" means a series of procedures in which the head of an administrative agency (hereinafter referred to as "competent authority") who intends to grant a license, permission, consultation, approval, designation, etc. (hereinafter referred to as "license, etc.") for a marine use and development project consults with the Minister of Oceans and Fisheries on the appropriateness of marine use and the marine environmental impact of the relevant act or project;
5.
The term "marine use impact assessment" means a series of procedures that involve the prior investigation, prediction, and assessment of the marine environmental impacts of a marine use and development project that has significant impacts on the marine environment or is likely to cause social conflicts, and the subsequent preparation of measures to mitigate adverse impacts on the marine environment and securing of acceptance from interested parties in the relevant project.
법령보기 화면
Article 3 (Responsibilities of the State)
(1)
The State, local governments, and persons who intend to conduct marine use and development projects (hereinafter referred to as "project operators"), as well as citizens, shall recognize the specificity of marine use and the importance of marine biodiversity and shall endeavor to achieve balance and harmony between the conservation of the marine environment and the sustainable use of marine areas.
(2)
The State, local governments, and project operators shall conduct a prior examination of the potential impacts of marine use and development projects on the marine environment and shall prepare and implement necessary measures to minimize marine environmental pollution and damage to the marine ecosystem.
(3)
The State, local governments, and project operators shall establish procedures to disclose relevant information and ensure opportunities for participation by interested parties, including local residents (hereinafter referred to as "interested parties"), during a marine use impact assessment or consultation on marine use (hereinafter referred to as "marine use impact assessment, etc.") and shall endeavor to facilitate such procedures.
(4)
The Minister of Oceans and Fisheries shall establish relevant procedures, guidelines, and standards to enhance the objectivity, scientific basis, and predictability of marine use impact assessments, etc., and shall endeavor to train professional human resources and to develop and disseminate relevant standards.
(5)
The Minister of Oceans and Fisheries shall comply with international conventions on the marine environment and shall endeavor to promote international cooperation for the conservation of the marine environment and the sustainable use of marine areas.
법령보기 화면
Article 4 (Basic principles)
A marine use impact assessment, etc. shall be conducted in accordance with the following basic principles:
1.
Investigations, predictions, assessments, and other procedures conducted as part of a marine use impact assessment, etc. shall be based on scientific methods and reasonable grounds;
2.
Cumulative impacts on the marine environment resulting from a past, present, or future planned act or project shall be reasonably considered;
3.
Measures for marine environmental conservation and their alternatives shall be prepared from a precautionary perspective, considering marine biodiversity, socio-economic impacts, and other relevant factors, and shall be technically and economically feasible;
4.
Efforts shall be made to incorporate the opinions of interested parties during the process of a marine use impact assessment, etc. and the results thereof shall be transparently disclosed;
5.
A marine use impact assessment, etc. shall be conducted in accordance with prescribed procedures, and the results of consultations shall be faithfully implemented.
법령보기 화면
Article 5 (Scope of application)
This Act shall apply to a marine use impact assessment, etc., conducted in the following sea areas, waters, etc.:
1.
The territorial sea and internal waters (limited to the area between the baseline from which the breadth of the territorial sea is measured and the area registered in the cadastral records under
Article 64 (1) of the Act on the Establishment and Management of Spatial Data
) under the
Territorial Sea and Contiguous Zone Act
;
2.
The exclusive economic zone and continental shelf under
Article 2 of the Act on the Exclusive Economic Zone and Continental Shelf
;
3.
Other waters prescribed by Presidential Decree as requiring a marine use impact assessment, etc. for marine environmental conservation.
CHAPTER II PROJECTS SUBJECT TO MARINE USE IMPACT ASSESSMENTS AND PROCEDURES THEREFOR
SECTION 1 Assessment fields and conservation objectives of marine use impact assessments
법령보기 화면
Article 6 (Assessment fields and items of marine use impact assessments)
(1)
A marine use impact assessment, etc. shall be conducted in the assessment fields of marine use appropriateness and environmental impact (hereinafter referred to as "marine use impact assessment fields") for a marine use and development project.
(2)
An assessment in the field of marine use appropriateness shall be conducted with full consideration of the following matters:
1.
The purpose and feasibility of a marine use and development project;
2.
Compatibility with marine use activities in neighboring sea areas, including fisheries, leisure, tourism, and navigation;
3.
Consistency with regulation prescribed by other statutes or regulations, such as protected areas;
4.
Acceptance by interested parties, including right holders related to the occupancy or use of public waters under
Article 12 (2) of the Public Waters Management and Reclamation Act
;
5.
The reasonableness of establishing and analyzing alternatives and the appropriateness of facility scale;
6.
Other matters that the Minister of Oceans and Fisheries deems necessary to consider for ensuring the appropriateness of marine use.
(3)
An assessment in the field of environmental assessment for marine use shall be conducted with full consideration of the following:
1.
Rationality of determining the target area and scope of impact for marine use impact assessments, etc.;
2.
Regional characteristics of the marine environment and ecosystem for each sea area;
3.
Changes in the physical and chemical marine environment caused by marine use; the prediction of environmental hazards; and the rationality of the assessment of impacts on the marine ecosystem;
4.
Appropriateness of mitigation measures to minimize the impacts on the marine ecosystem;
5.
Other matters that the Minister of Oceans and Fisheries deems necessary to consider due to their impacts on the marine environment.
(4)
The detailed assessment items and methods for each field under paragraph (1) shall be prescribed by Decree of the Ministry of Oceans and Fisheries.
법령보기 화면
Article 7 (Establishment of conservation objectives for each assessment item)
A project operator intending to conduct a marine use impact assessment, etc. shall establish and present marine environment conservation objectives for each assessment item, taking considering the following factors based on the characteristics of the relevant marine use and development project:
1.
Marine environmental standards under
Article 13 of the Act on Conservation and Utilization of the Marine Environment
;
2.
Marine ecology maps under
Article 12 of the Conservation and Management of Marine Ecosystems Act
;
3.
Standards for the disposal of wastes to be discharged into the sea under
Article 7
of the Management of Marine Wastes and Contaminated Marine Sediment Act;
4.
Total pollutant control under
Article 15-2 of the Marine Environment Management Act
;
5.
Other standards established under other statutes for the conservation of the marine environment.
법령보기 화면
Article 8 (Relationship to marine spatial management plans)
(1)
If a project operator intends to conduct a marine use and development project, the relevant project plan shall comply with the marine spatial management plan under
Article 7 of the Act on Marine Spatial Planning and Management
.
(2)
When conducting a marine use impact assessment, etc., on a project plan under paragraph (1), the Minister of Oceans and Fisheries shall review the project plan, considering the results of the marine spatial characteristics evaluation under
Article 13 of the Act on Marine Spatial Planning and Management
or the marine spatial suitability consultation under
Article 15
of that Act (applicable only to projects subject to such consultation).
SECTION 2 Projects subject to consultation on marine use, preparation of written consultation, and consultation
법령보기 화면
Article 9 (Projects subject to consultation on marine use)
(1)
The head of the competent authority shall consult with the Minister of Oceans and Fisheries on marine use before granting a license, etc., to a project operator intending to conduct a marine use and development project that requires any of the following licenses, etc. (hereinafter referred to as "project subject to consultation"):
1.
Designation of prospective areas for extraction of aggregate under
Article 21-2 of the Aggregate Extraction Act
;
2.
Permission to occupy or use public waters under
Article 8 of the Public Waters Management and Reclamation Act
;
3.
Consultation on, or approval for, the occupancy or use of public waters under
Article 10 of the Public Waters Management and Reclamation Act
;
4.
A reclamation license under
Article 28 of the Public Waters Management and Reclamation Act
;
5.
Consultation on, or approval for, the reclamation of public waters under
Article 35 or 36 of the Public Waters Management and Reclamation Act
;
6.
A license for fishery business under
Article 7 of the Fisheries Act
or a license for aquaculture business under
Article 10 of the Aquaculture Industry Development Act
; provided, this shall apply only to licenses for fishery business or aquaculture business in sea areas prescribed by Presidential Decree.
(2)
In applying paragraph (1) 2 through 5, if a single project subject to consultation involves at least 2 cases of the occupancy or use of public waters, the Minister of Oceans and Fisheries may conduct a collective consultation on marine use.
(3)
Even if other statutes provide that any license, etc., specified in paragraph (1) 2 through 5 of are deemed to have been granted, consultation on marine use shall be conducted.
(4)
Notwithstanding paragraphs (1) and (3), if a project subject to consultation falls under any of the following categories, it shall be excluded from the scope of projects subject to consultation on marine use:
1.
A project for emergency measures under
Article 37 of the Framework Act on the Management of Disasters and Safety
;
2.
A project that the Minister of National Defense deems to require the protection of military confidential information or to be necessary for the urgent performance of military operations, and on which the Minister consults with the Minister of Oceans and Fisheries;
3.
A project that the Director of the National Intelligence Service deems to require a high degree of protection of confidential information for national security, and on which the Director consults with the Minister of Oceans and Fisheries;
4.
A project prescribed by Presidential Decree as an act for the conservation of the marine environment and the safety of marine traffic;
5.
A project subject to marine use impact assessment under
Article 13
.
(5)
The specific types and scope of projects subject to consultation shall be prescribed by Presidential Decree.
법령보기 화면
Article 10 (Preparation of written consultation on marine use)
(1)
A project operator shall prepare a written consultation on marine use (hereafter in this Section referred to as "written consultation") before filing an application for a license, etc. for a project subject to consultation and shall submit it to the head of the competent authority.
(2)
Matters necessary for the details and methods of preparing a written consultation, the procedures for submitting such written consultation, etc. shall be prescribed by Decree of the Ministry of Oceans and Fisheries.
법령보기 화면
Article 11 (Request for consultation)
(1)
Before granting a license, etc., for a project subject to consultation to a project operator, the head of the competent authority shall submit a written consultation to the Minister of Oceans and Fisheries and request consultation, as prescribed by Presidential Decree.
(2)
When requesting consultation under paragraph (1), the head of the competent authority may attach opinions on the written consultation; provided, if the head of the competent authority is not a management agency of public waters under
Article 4 of the Public Waters Management and Reclamation Act
or a reclamation license agency under
Article 28
of that Act (hereinafter referred to as "management agency, etc. of public waters"), the opinions of the relevant management agency, etc. of public waters shall be attached.
(3)
If a project subject to consultation is classified as a project subject to environmental impact assessment under
Article 22 of the Environmental Impact Assessment Act
, the head of the competent authority shall conduct consultation on marine use before requesting consultation on the environmental impact assessment report under
Article 27
(1) of that Act.
법령보기 화면
Article 12 (Review of written consultation)
(1)
Upon receipt of a request for consultation under
Article 11
(1), the Minister of Oceans and Fisheries shall review whether the project is subject to consultation, the validity of the details of the written consultation, and other relevant matters.
(2)
When reviewing a written consultation under paragraph (1), the Minister of Oceans and Fisheries shall seek the opinions of an institution with expertise in the marine use impact assessment fields, which is prescribed by Presidential Decree (hereinafter referred to as “marine use impact review agency”); provided, this shall not apply to a project subject to consultation that has minor impacts on the marine environment and that is prescribed by Decree of the Ministry of Oceans and Fisheries.
(3)
The Minister of Oceans and Fisheries may request a project operator or the head of the competent authority to submit relevant materials for reviewing the written consultation and may, if necessary, seek the opinions of relevant experts or request on-site investigations.
(4)
If the results of the review of a written consultation under paragraph (1) fall under any of the following categories, the Minister of Oceans and Fisheries may request the head of the competent authority to supplement or adjust the written consultation or project plan. In such cases, such requests for supplementation or adjustment may be made only twice, and the head of the competent authority in receipt of the requests shall comply therewith unless there is a compelling reason not to do so:
1.
If the surveys on the current status of the marine environment and the analysis of relevant data are insufficient;
2.
If the analysis of the impact on the marine environment is omitted or insufficient;
3.
If the prediction or assessment of the impact on the marine environment and the measures to mitigate adverse impacts are inappropriate;
4.
Where it is deemed necessary to supplement or adjust the project plan in terms of the appropriateness of marine use.
(5)
The Minister of Oceans and Fisheries may return a written consultation, in any of the following cases:
1.
Where the relevant project is not classified as a project subject to consultation;
2.
Where it is deemed impracticable to proceed with consultations because the written consultation or the relevant project plan is not properly prepared, such as omitting requested important details, despite a request for supplementation or adjustment under paragraph (4);
3.
Where the written consultation is deemed to have been prepared with false details.
(6)
Matters necessary for the details and methods of reviewing written consultations under paragraph (1), the supplementation and adjustment of written consultations under paragraph (4), the return of written consultations under paragraph (5), and other relevant measures shall be prescribed by Decree of the Ministry of Oceans and Fisheries.
SECTION 3 Projects subject to marine use impact assessment, preparation of assessment reports, and consultation
법령보기 화면
Article 13 (Projects subject to marine use impact assessment)
(1)
A project operator intending to undertake any of the following marine use and development projects (hereinafter referred to as "projects subject to assessment") shall conduct a marine use impact assessment before obtaining a license, etc. from the head of the competent authority; provided, projects prescribed by Presidential Decree, among those subject to environmental impact assessment under
Article 22 of the Environmental Impact Assessment Act
, shall be excluded:
1.
A marine aggregate extraction project among aggregate extraction projects under
Article 22 of the Aggregate Extraction Act
, or a project requiring designation of marine aggregate extraction complexes under
Article 34
of that Act;
2.
A project requiring permission for the occupancy or use of public waters under
Article 8 of the Public Waters Management and Reclamation Act
, or a project requiring consultation on, or approval for, such occupancy or use under
Article 10
of that Act;
3.
A project requiring a reclamation license for public waters under
Article 28 of the Public Waters Management and Reclamation Act
or a project requiring consultation on, or approval for, the reclamation of public waters under
Article 35
of that Act;
4.
A project involving the extraction of minerals defined in subparagraph 1 of
Article 3 of the Mining Industry Act
from public waters;
5.
A project involving the installation of new energy and renewable energy facilities defined in subparagraph 3 of
Article 2 of the Act on the Promotion
of the Development, Use and Diffusion of New and Renewable Energy on public waters;
6.
A project using or developing deep sea water defined in subparagraph 1 of
Article 2 of the Development and Management of Deep Sea Water Act
;
7.
A project involving the disposal of wastes through isolation under
Article 9
(1) 2 of the Management of Marine Wastes and Contaminated Marine Sediment Act, or a project involving the storage of carbon dioxide streams in marine geological structures under
Article 10
(1) of that Act; 8. A project involving the extraction of submarine minerals defined in subparagraph 1 of
Article 2 of the Submarine Mineral Resources Development Act
;
9.
Other projects prescribed by Presidential Decree that have an impact on the marine environment.
(2)
Article 9
(4) 1 through 4 shall apply
mutatis mutandis
to projects excluded from marine use impact assessment.
(3)
The specific types and scope of projects subject to assessment shall be prescribed by Presidential Decree.
법령보기 화면
Article 14 (Determination of assessment items and scope)
(1)
To determine the target area, items, scope, methods, and other relevant matters for a marine use impact assessment (hereinafter referred to as "assessment items, etc."), a project operator shall request deliberation by the Minister of Oceans and Fisheries through the head of the competent authority.
(2)
When a project operator requests deliberation under paragraph (1), the operator shall prepare an assessment preparation document and submit it to the head of the competent authority.
(3)
Upon receipt of a request for deliberation under paragraph (1), the Minister of Oceans and Fisheries shall determine the assessment items, etc., in accordance with the procedures and methods prescribed by Presidential Decree, and shall notify the head of the competent authority and the relevant project operator of such determination.
(4)
The Minister of Oceans and Fisheries shall disclose the assessment items, etc., determined under paragraph (3) in accordance with the methods prescribed by Decree of the Ministry of Oceans and Fisheries and shall seek the opinions of residents, etc.
(5)
Matters necessary for the determination of assessment items, etc. under paragraphs (1) and (3) shall be prescribed by Presidential Decree, and those necessary for the methods of preparing assessment preparation documents and other relevant details under paragraph (2) shall be prescribed by Decree of the Ministry of Oceans and Fisheries.
법령보기 화면
Article 15 (Preparation of draft marine use impact assessment reports)
(1)
A project operator shall prepare a draft marine use impact assessment report (hereafter in this Section referred to as "draft assessment report") incorporating the assessment items, etc., determined under
Article 14
.
(2)
A project operator shall submit the draft assessment report to the heads of the following administrative agencies to seek their opinions:
1.
The head of the competent authority;
2.
The Minister of Oceans and Fisheries;
3.
The relevant management agency, etc. of public waters (applicable only if the head of the competent authority is not a management agency, etc. of public waters);
4.
The heads of other relevant administrative agencies prescribed by Presidential Decree.
(3)
Matters necessary for the preparation and submission of draft assessment reports shall be prescribed by Decree of the Ministry of Oceans and Fisheries.
법령보기 화면
Article 16 (Seeking of opinions on draft assessment reports)
(1)
The head of the competent authority shall publicly announce and make available for public inspection a draft assessment report submitted under
Article 15
and shall seek the opinions of interested parties.
(2)
After the public inspection under paragraph (1) is completed, the project operator shall hold a briefing session for interested parties who may be affected by the implementation of the project; provided, in cases prescribed by Presidential Decree, a public hearing shall be held instead.
(3)
If any grounds prescribed by Presidential Decree exist, such as the failure to properly hold a briefing session or public hearing under paragraph (2) (hereinafter referred to as "briefing session, etc.") due to reasons not attributable to the relevant project operator, the briefing session, etc. need not be held. In such cases, the project operator shall seek the opinions of interested parties, as prescribed by Presidential Decree.
(4)
A project operator shall disclose the results of seeking the opinions of interested parties under paragraphs (1) through (3) and whether such opinions have been incorporated, in accordance with the method prescribed by Presidential Decree.
(5)
Notwithstanding paragraphs (1), (2), and (4), the head of the competent authority need not disclose certain parts of a draft assessment report in any of the following cases; in such cases, the head shall state the reasons for non-disclosure in such report:
1.
Where it is necessary for national security, including the protection of military confidential information;
2.
Where disclosure is restricted in accordance with relevant statutes and regulations.
(6)
Matters necessary for the public announcement and public inspection of draft assessment reports, the holding of briefing sessions, etc., and other procedures for seeking opinions under paragraphs (1) through (4) shall be prescribed by Presidential Decree.
법령보기 화면
Article 17 (Reseeking of opinions)
(1)
If a project operator intends to modify important matters prescribed by Presidential Decree, such as changes in the project scale, after completing the procedure for seeking opinions under
Article 16
but before receiving notification of consultation opinions under
Article 21
, the operator shall reprepare the draft assessment report and reseek the opinions of interested parties under
Articles 15
and 16.
(2)
If an interested party files an application for the reseeking of opinions due to any grounds prescribed by Decree of the Ministry of Oceans and Fisheries, such as defects in the procedures for seeking opinions disclosed under
Article 16
(4), the relevant project operator shall reseek opinions under
Article 16
.
(3)
Matters necessary for the application for reseeking of opinions and other details under paragraph (2) shall be prescribed by Decree of the Ministry of Oceans and Fisheries.
법령보기 화면
Article 18 (Preparation of marine use impact assessment reports)
(1)
A project operator shall prepare a marine use impact assessment report (hereafter in this Section referred to as "assessment report") incorporating the results of hearing the opinions of interested parties under
Article 16
and submit it to the head of the competent authority.
(2)
Matters necessary for the details, preparation, and submission methods, etc. of assessment reports shall be prescribed by Decree of the Ministry of Oceans and Fisheries.
법령보기 화면
Article 19 (Request for consultation)
(1)
Before granting a license, etc., for a project subject to assessment to a project operator, the head of the competent authority shall submit the relevant assessment report to the Minister of Oceans and Fisheries and request consultation.
(2)
When requesting consultation with the Minister of Oceans and Fisheries under paragraph (1), the head of the competent authority may attach opinions on the relevant assessment report; provided, if the head of the competent authority is not a management agency, etc. of public waters, the opinions of the relevant management agency, etc. of public waters shall be attached.
(3)
Matters necessary for the timing of requests for consultation and the submission of opinions by the head of the competent authority under paragraphs (1) and (2) shall be prescribed by Presidential Decree.
법령보기 화면
Article 20 (Review of assessment reports)
(1)
Upon receipt of a request for consultation under
Article 19
(1), the Minister of Oceans and Fisheries shall review whether the results of seeking the opinions of interested parties have been incorporated, the validity of the assessment report, and other relevant factors.
(2)
When reviewing an assessment report under paragraph (1), the Minister of Oceans and Fisheries shall seek the opinions of a marine use impact review agency and may also seek additional opinions from agencies with expertise in the marine use impact assessment fields, which are prescribed by Presidential Decree, if necessary.
(3)
The Minister of Oceans and Fisheries may request a project operator or the head of the competent authority to submit relevant materials for reviewing the assessment report and may, if necessary, seek the opinions of relevant experts or request on-site investigations.
(4)
The Minister of Oceans and Fisheries may request the head of the competent authority to supplement or adjust the relevant assessment report or project plan or may return the assessment report.
(5)
Article 12
(4) and (5) shall apply
mutatis mutandis
to the supplementation and adjustment of an assessment report or project plan and the return of an assessment report under paragraph (4). In such cases, "written consultation" shall be construed as "assessment report", and "project subject to consultation" as "project subject to assessment".
(6)
Matters necessary for the details and methods of reviewing assessment reports under paragraph (1), for the supplementation, adjustment, or return of assessment reports under paragraph (4), and for other relevant measures shall be prescribed by Decree of the Ministry of Oceans and Fisheries.
SECTION 4 Notification, incorporation, and supervision of implementation of consultation opinions
법령보기 화면
Article 21 (Notification of consultation opinions)
(1)
The Minister of Oceans and Fisheries shall notify the head of the competent authority of the consultation opinions within the period prescribed by Presidential Decree from the date of receiving a consultation request under
Article 11
(1) or
Article 19
(1); provided, the period may be extended in unavoidable circumstances.
(2)
When extending the notification period for consultation opinions under the proviso of paragraph (1), the Minister of Oceans and Fisheries shall notify the head of the competent authority of the reasons for the extension and the newly extended period before the original notification period expires.
(3)
Upon receipt of notification of the consultation opinions under paragraph (1) or the extension of the notification period for consultation opinions under paragraph (2), the head of the competent authority shall notify the relevant project operator thereof without delay.
(4)
Upon receipt of notification of the consultation opinions under paragraph (1), the head of the competent authority shall, if the head has granted a license, etc. to the relevant project operator, inform the Minister of Oceans and Fisheries of the details without delay.
법령보기 화면
Article 22 (Filing objections)
(1)
A project operator or the head of the competent authority may file an objection with the Minister of Oceans and Fisheries if they have an objection regarding the consultation opinions notified under
Article 21
. In such cases, the project operator shall file the objection through the head of the competent authority.
(2)
Upon receipt of an objection under paragraph (1), the Minister of Oceans and Fisheries shall review the validity of the objection and notify the relevant project operator or the head of the competent authority of the results.
(3)
A project operator that has an objection shall file the objection under paragraph (1) before obtaining a license, etc. for the relevant project; and in such cases, the head of the competent authority must not grant a license, etc. until receiving notification under paragraph (2); provided, this shall not apply if the details related to the objection are excluded from the project plan, etc.
(4)
The methods and procedures for filing an objection under paragraphs (1) through (3) and other necessary matters shall be prescribed by Presidential Decree.
법령보기 화면
Article 23 (Incorporation of consultation opinions)
(1)
When a project operator or the head of the competent authority receives the consultation opinions under
Article 21
(including cases where an objection filed under
Article 22
has been processed), they shall take necessary measures to incorporate such opinions into the relevant project plan, etc.
(2)
The head of the competent authority shall verify whether the consultation opinions have been incorporated into the relevant project plan, etc., before granting a license, etc. for the project. In such cases, if the consultation opinions have not been incorporated into the project plan, etc., the head shall ensure that such opinions are incorporated.
(3)
When the head of the competent authority notifies the Minister of Oceans and Fisheries of the details of the license, etc. for the relevant project under
Article 21
(4), the notification shall include the results of the incorporation of the consultation opinions.
(4)
If the consultation opinions are not incorporated into the results notified under paragraph (3), the Minister of Oceans and Fisheries may request the head of the competent authority to ensure such incorporation. In such cases, the head of the competent authority shall comply with the request unless there is a compelling reason not to do so.
(5)
If a project operator conducts construction work without undergoing a marine use impact assessment, etc. (including consultation following modification of the relevant project plan under
Article 24
; hereafter in this Article the same shall apply) or without incorporating the opinions from the assessment, etc., the head of the competent authority shall revoke the relevant license, etc. or order the operator to suspend the project, dismantle or suspend the operation of artificial structures, restore the relevant site to its original state, or take measures to prevent damage to the surrounding marine environment or safety-related accidents, and shall notify the Minister of Oceans and Fisheries of such actions without delay.
(6)
If the head of the competent authority grants a license, etc. without undergoing a marine use impact assessment, etc. or without incorporating the opinions from the assessment, etc., the Minister of Oceans and Fisheries may request the head to revoke the license, etc. or to order the relevant project operator to suspend the project, dismantle or suspend the operation of artificial structures, restore the relevant site to its original state, or take measures to prevent damage to the surrounding marine environment or safety-related accidents. In such cases, the head of the competent authority shall comply with the request unless there is a compelling reason not to do so.
법령보기 화면
Article 24 (Consultation following modification of project plans)
(1)
In any of the following cases where a project operator modifies the relevant project plan, etc., after receiving notification of consultation opinions under
Article 21
, the operator shall request reconsultation with the Minister of Oceans and Fisheries:
1.
Where the operator fails to implement the relevant project within the period prescribed by Presidential Decree from the date of receiving notification of consultation opinions under
Article 21
; provided, this shall not apply where changes in the surrounding conditions during the period of non-implementation are minor and the head of the competent authority has consulted with the Minister of Oceans and Fisheries;
2.
Where the area, length, or other aspects of the project subject to marine use impact assessment, etc. have increased to at least the scale prescribed by Presidential Decree;
3.
Where it is inappropriate to implement a project plan, etc. in accordance with consultation opinions due to reasons prescribed by Presidential Decree, such as changes in project conditions.
(2)
Articles 10
through 12 and 14 through 23 shall apply
mutatis mutandis
to reconsultation under paragraph (1).
(3)
If a project operator intends to modify a consulted project plan, etc. but the relevant case does not fall under any category specified in the subparagraphs of paragraph (1), the operator shall undergo consultation on modification. In such cases, the operator shall prepare marine environment conservation measures following the modification of the project plan, etc. and incorporate such measures into the modified project plan, etc., and shall notify the head of the competent authority and the Minister of Oceans and Fisheries of the details thereof.
(4)
A project operator shall undergo prior review of the marine environment conservation measures under paragraph (3) by the head of the competent authority; provided, this shall not apply to a minor modification prescribed by Presidential Decree.
(5)
When reviewing marine environment conservation measures under paragraph (4), the head of the competent authority shall seek the opinion of the Minister of Oceans and Fisheries if grounds prescribed by Presidential Decree exist.
(6)
Article 23
(2) through (4) shall apply
mutatis mutandis
to the verification and notification as to whether marine environment conservation measures under paragraph (3) have been incorporated. In such cases, "consultation opinions" shall be construed as "marine environment conservation measures".
법령보기 화면
Article 25 (Prohibition of construction work before completion of consultation)
(1)
No project operator shall conduct construction work for the relevant project subject to marine use impact assessment, etc. without undergoing the procedures for consultation or reconsultation on, or consultation on modification of, such assessment, etc. under
Articles 10
through 12 and 14 through 24, or before the procedures are completed; provided, this shall not apply in any of the following cases:
1.
Where the operator obtains a license, etc. after receiving notification of consultation opinions under
Article 21
and conducts any act not related to the details subject to reconsultation or consultation on modification under
Article 24
;
2.
Where the project operator conducts any act involving minor matters prescribed by Decree of the Ministry of Oceans and Fisheries, which are necessary for preparing to commence construction work or for fulfilling obligations under other statutes or regulations.
(2)
The head of the competent authority must not grant a license, etc., for the relevant project (including modification of the details of the previously obtained license, etc.) before completing the procedures for consultation, reconsultation, or consultation on modification under
Articles 10
through 12 and
Articles 14
through 24.
(3)
If a project operator conducts construction work in violation of paragraph (1), the head of the competent authority shall order the operator to suspend all or part of such work, restore the relevant site to its original state, or take measures to prevent damage to the surrounding marine environment or safety-related accidents, and shall notify the Minister of Oceans and Fisheries thereof without delay.
(4)
If a project operator conducts construction work in violation of paragraph (1), the Minister of Oceans and Fisheries may request the head of the competent authority to order the operator to suspend construction work, restore the relevant site to its original state, or take measures to prevent damage to the surrounding marine environment or safety-related accidents. In such cases, the head of the competent authority shall comply with the request unless there is a compelling reason not to do so.
법령보기 화면
Article 26 (Notification of progress of projects)
A project operator shall notify the head of the competent authority and the Minister of Oceans and Fisheries of the details of the commencement or completion of the relevant project, suspension of construction work for at least 3 months, or the resumption of construction work after a suspension of at least 3 months, as prescribed by Decree of the Ministry of Oceans and Fisheries.
법령보기 화면
Article 27 (Compliance with consultation opinions)
(1)
A project operator shall comply with consultation opinions incorporated under
Article 23
, when implementing a project plan, etc.
(2)
A project operator shall designate a person in charge to manage the status of compliance with the consultation opinions and shall record and manage such status in a management ledger, as prescribed by Decree of the Ministry of Oceans and Fisheries; provided, this shall not apply to a project prescribed by Presidential Decree that has minor impacts on the marine environment.
(3)
Matters necessary for the designation of persons in charge, preparation of management ledgers, and other relevant details under paragraph (2) shall be prescribed by Decree of the Ministry of Oceans and Fisheries.
법령보기 화면
Article 28 (Verification of compliance with consultation opinions)
(1)
The head of the competent authority shall verify whether a project operator that has obtained a license, etc. is properly complying with the consultation opinions.
(2)
If the head of the competent authority fails to conduct such verification without good cause or significantly delays it, the Minister of Oceans and Fisheries may directly conduct the verification, notwithstanding paragraph (1). In such cases, the Minister may seek opinions from relevant experts or marine use impact review agencies, request on-site inspections, or require the submission of relevant materials from the head of the competent authority.
(3)
When verifying compliance with consultation opinions under paragraphs (1) and (2), the head of the competent authority or the Minister of Oceans and Fisheries may require the relevant project operator to submit necessary materials or may authorize their officials to enter the place of business for inspection. In such cases, the project operator must not refuse to submit materials or refuse or interfere with the inspection, without good cause.
(4)
When conducting an inspection under paragraph (3), the inspecting authority shall notify the relevant project operator of the inspection plan, including the reason and details of the inspection, at least 7 days prior to the inspection; provided, this shall not apply if urgent action is required or if giving prior notice is deemed to defeat the purpose of the inspection, such as by enabling the destruction of evidence.
(5)
A public official conducts an on-site inspection under paragraph (3) shall carry identification verifying his or her authority and present it to relevant persons.
(6)
If the head of the competent authority intends to conduct a completion inspection of the relevant project, the head shall verify compliance with the consultation opinions and notify the Minister of Oceans and Fisheries of the results.
법령보기 화면
Article 29 (Marine environmental impact surveys)
(1)
A project operator shall conduct a survey on the impact of the relevant project implemented after obtaining a license, etc., on the marine environment (hereinafter referred to as "marine environmental impact survey") and shall submit a marine environmental impact survey report containing the results to the head of the competent authority and the Minister of Oceans and Fisheries.
(2)
If the results of a marine environmental impact survey indicate that measures are necessary to prevent damage to the surrounding environment, the relevant project operator shall take such measures without delay and notify the head of the competent authority and the Minister of Oceans and Fisheries thereof.
(3)
The Minister of Oceans and Fisheries shall review the results of a marine environmental impact survey under paragraph (1) and the results of the measures taken under paragraph (2); and if it is recognized that damage to the marine environment has occurred, the Minister shall direct the head of the competent authority to order the relevant project operator to take measures, such as modifying the construction method or reducing the project scale, as prescribed by Decree of the Ministry of Oceans and Fisheries, to mitigate the damage to the marine environment.
(4)
The head of the competent authority shall notify the Minister of Oceans and Fisheries of the results of the measures taken under paragraph (3).
(5)
If necessary for the review under paragraph (3), the Minister of Oceans and Fisheries may request the relevant project operator or the head of the competent authority to submit relevant materials. In such cases, the operator or the head shall comply with the request unless there is good cause.
(6)
Matters necessary for the projects subject to marine environmental impact surveys, the survey items and periods, and other relevant details shall be prescribed by Decree of the Ministry of Oceans and Fisheries.
법령보기 화면
Article 30 (Order for measures)
(1)
If a project operator fails to comply with consultation opinions, the head of the competent authority shall issue an order to take necessary measures for such compliance.
(2)
If the head of the competent authority deems that the continued implementation of the relevant project by the project operator, without complying with the order for measures under paragraph (1), would have a significant adverse impact on the marine environment, the head shall order the operator to suspend all or part of construction work, restore the relevant site to its original state, or take measures to prevent damage to the surrounding marine environment or safety-related accidents.
(3)
The Minister of Oceans and Fisheries may request the head of the competent authority to order the relevant project operator to suspend construction work, restore the relevant site to its original state, or take measures to prevent damage to the surrounding marine environment or safety-related accidents, in any of the following cases; in such cases, the head shall comply with the request unless there is a compelling reason not to do so:
1.
Where a review of the results of a marine environmental impact survey or the details of the measures taken reveals that damage to the surrounding environment has occurred or is expected;
2.
Where it is deemed necessary for managing the compliance with the consultation opinions.
(4)
If the head of the competent authority issues an order under paragraphs (1) through (3), or if the relevant project operator complies with such order, they shall notify the Minister of Oceans and Fisheries of the details without delay.
CHAPTER III AGENCY SERVICES FOR PREPARATION OF MARINE USE IMPACT ASSESSMENT REPORTS
법령보기 화면
Article 31 (Agency services for preparation of marine use impact assessment reports)
(1)
When a project operator prepares the following documents (hereinafter referred to as "marine use impact assessment report, etc."), the operator may engage a person registered to act as an agency for the preparation of a marine use impact assessment report, etc. under
Article 33
(hereinafter referred to as "assessment agency") to prepare such report, etc.:
1.
A written consultation on marine use;
2.
A draft marine use impact assessment report and a marine use impact assessment report;
3.
Marine environment conservation measures under
Article 24
(3);
4.
A marine environmental impact survey report under
Article 29
(1).
(2)
If a project operator concludes a contract to engage agency services for the preparation of a marine utilization impact assessment report, etc., under paragraph (1), such contract shall be separate from any other contracts related to the design or other matters regarding the construction work for the relevant project.
(3)
If a project operator engages agency services for the preparation of a marine environmental impact survey report under paragraph (1) 4 for a project prescribed by Presidential Decree, such as a project with a significant impact on the marine environment, the operator shall engage a person other than the one who provided agency services for the preparation of a document specified in paragraph (1) 1 or 2, to act as an agency.
(4)
If the head of any of the following institutions or organizations intends to engage an agency to prepare a marine use impact assessment report, etc., under paragraph (1), the head shall evaluate the project performance capabilities of an assessment agency wishing to participate, including its technical and managerial capabilities:
1.
A State agency or a local government;
2.
A public enterprise or quasi-governmental institution under
Article 5 of the Act on the Management of Public Institutions
;
3.
A local government-invested public corporation or local public agency under
Local Public Enterprises Act
;
4.
Other institutions and organizations prescribed by Presidential Decree.
(5)
Necessary matters regarding the agencies subject to project performance capability evaluation, and the criteria, procedures, and other details for such evaluation under paragraph (4) shall be prescribed by Decree of the Ministry of Oceans and Fisheries.
법령보기 화면
Article 32 (Institutions for selecting assessment agencies)
(1)
Notwithstanding
Article 31
, if a project operator conducts a project with a significant impact on the marine environment, as prescribed by Presidential Decree, among projects subject to consultation or assessment, the operator shall request the selection of an assessment agency from an institution with expertise in the marine environment field, as prescribed by Presidential Decree.
(2)
A project operator that requests the selection of an assessment agency under paragraph (1) shall bear the costs necessary for preparing a marine use impact assessment report, etc.
(3)
The Minister of Oceans and Fisheries may, within the budget, subsidize an institution under paragraph (1) to cover the expenses incurred in performing its business affairs.
(4)
Matters necessary for requesting the selection of assessment agencies under paragraphs (1) and (2) shall be prescribed by Presidential Decree.
법령보기 화면
Article 33 (Registration of marine use impact assessment agency services)
(1)
A person who intends to provide agency services for the preparation of marine use impact assessment reports, etc. (hereinafter referred to as “marine use impact assessment agency services”) shall be equipped with technical personnel, facilities, and equipment as prescribed by Decree of the Ministry of Oceans and Fisheries and shall file for registration with the Minister of Oceans and Fisheries.
(2)
If a person intends to modify any important matters prescribed by Decree of the Ministry of Oceans and Fisheries among the matters registered under paragraph (1), the person shall file for registration of such modification.
(3)
Matters necessary for the registration of marine use impact assessment agency services, registration of modification thereof, and other relevant details under paragraphs (1) and (2) shall be prescribed by Decree of the Ministry of Oceans and Fisheries.
법령보기 화면
Article 34 (Grounds for disqualification)
None of the following persons shall file for registration of marine use impact assessment agency services:
1.
A person under adult guardianship or a person under limited guardianship;
2.
A person for whom 2 years (or 6 months for the revocation of registration under
Article 38
(1) 5) have not passed since his or her registration of marine use impact assessment agency services was revoked under
Article 38
(excluding where the registration was revoked on the ground specified in subparagraph 1);
3.
A person for whom 1 year has not passed since the completion of imprisonment with labor declared by a court (including where such sentence is deemed fully executed) or the finalization of the non-execution of the sentence;
4.
A person who has been sentenced to a suspended sentence of imprisonment with labor for violation of this Act and for whom the period of suspension has not yet expired;
5.
A corporation whose representative falls under any of the categories specified in subparagraphs 1 through 4.
법령보기 화면
Article 35 (Compliance requirements for project operators and assessment agencies)
(1)
A project operator shall comply with the following requirements when preparing a marine use impact assessment report, etc.:
1.
The operator must not prepare a marine use impact assessment report, etc., by copying the details of any other such report, etc.;
2.
The operator must not prepare a marine use impact assessment report, etc. and the underlying data for its preparation, with false or deficient details;
3.
The operator shall register a marine use impact assessment report, etc. and the underlying data for its preparation in the information support system under
Article 45
(2) as prescribed by the Decree of the Ministry of Oceans and Fisheries;
4.
When an assessment agency provides agency services for the preparation of a marine use impact assessment report, etc. under
Article 31
or 32 (hereinafter referred to as "agency services"), the operator shall provide the agency with sufficient information and data regarding the relevant project subject to assessment;
5.
When concluding a contract with an assessment agency, the operator shall provide reasonable compensation in accordance with the cost calculation standards under
Article 42
to ensure the proper performance of the agency services;
6.
The operator must not require an assessment agency to prepare a marine use impact assessment report etc. and the underlying data for its preparation, with false or deficient details;
7.
The operator must not offer to or accept from an assessment agency any unjust solicitation, money, valuables, or entertainment in connection with the agency services.
(2)
An assessment agency shall comply with the following requirements when providing agency services:
1.
The agency must not prepare a marine use impact assessment report, etc., by copying the details of any other such report, etc.;
2.
The agency must not prepare a marine use impact assessment report, etc. and the underlying data for its preparation, with false or deficient details;
3.
The agency shall register a marine use impact assessment report, etc. and the underlying data for its preparation in the information support system under
Article 45
(2) as prescribed by the Decree of the Ministry of Oceans and Fisheries;
4.
The agency must not lend its registration certificate or name to another person;
5.
The agency must not subcontract its services to another person; provided, this shall not apply if the agency obtains approval from the contracting party, as prescribed by the Decree of the Ministry of Oceans and Fisheries;
6.
The agency must not offer to or accept from the relevant project operator any unjust solicitation, money, valuables, or entertainment in connection with the agency services.
(3)
The detailed criteria for determining preparation with false or deficient details under paragraphs (1) 2 and 6 and (2) 2 shall be prescribed by Decree of the Ministry of Oceans and Fisheries.
법령보기 화면
Article 36 (Succession of rights and obligations)
(1)
When an assessment agency dies or transfers his or her business or a corporate assessment agency merges with another corporation, the heir, the transferee, or the surviving or newly established corporation resulting from the merger shall succeed to the rights and obligations of the previous assessment agency under the registration.
(2)
A person who succeeds to the rights and obligations of the former assessment agency under paragraph (1) shall file a report thereon with the Minister of Oceans and Fisheries within 1 month, as prescribed by the Decree of the Ministry of Oceans and Fisheries.
(3)
A person who has filed a report on the succession of rights and obligations under paragraph (2) shall also succeed to the previous performance records of agency services.
법령보기 화면
Article 37 (Closure or suspension of business)
If an assessment agency intends to close or suspend its business, the agency shall file a report thereon with the Minister of Oceans and Fisheries, as prescribed by Decree of the Ministry of Oceans and Fisheries. In such cases, the period of business suspension shall not exceed 2 years.
법령보기 화면
Article 38 (Revocation of registration or business suspension of assessment agencies)
(1)
If an assessment agency falls under any of the following categories, the Minister of Oceans and Fisheries may revoke its registration or order the suspension of all or part of its business for a fixed period of up to 6 months; provided, if the agency falls under any category specified in subparagraph 1, 4, 6, or 7, the Minister shall revoke the registration:
1.
If the agency has filed for registration or registration of modification by fraud or other improper means;
2.
If the agency no longer satisfies the requirements for technical personnel, facilities, or equipment under
Article 33
(1);
3.
If the agency fails to file for registration of modification under
Article 33
(2);
4.
Where the agency falls under any of the subparagraphs of
Article 34
; provided, this shall not apply if a corporation specified in subparagraph 5 of that Article appoints a new representative director within 6 months;
5.
If the agency fails to commence its agency services within 2 years of registration or has no record of providing agency services for at least 2 consecutive years;
6.
If the agency, having been subject to 2 business suspension dispositions within the most recent year, commits another act subject to such disposition;
7.
If the agency provides agency services (including the conclusion of contracts) during a period of business suspension;
8.
If the agency violates any of the compliance requirements under the subparagraphs of
Article 35
(2).
(2)
The detailed standards for administrative dispositions under paragraph (1) shall be prescribed by Decree of the Ministry of Oceans and Fisheries, taking into account the type, severity, and other relevant aspects of the violations.
법령보기 화면
Article 39 (Continuation of business by assessment agencies subject to registration revocation or business suspension)
(1)
A person who has been subject to a disposition of registration revocation or business suspension under
Article 38
may continue to perform only those agency services contracted before such disposition.
(2)
An assessment agency that continues to perform agency services under paragraph (1) shall be deemed as an assessment agency under this Act until the completion of such services.
(3)
An assessment agency that continues to perform agency services under paragraph (1) must not conclude a new contract for agency services other than those contracted before the relevant disposition.
(4)
If the Minister of Oceans and Fisheries deems that a person who has been subject to a disposition of registration revocation under
Article 38
(1) 1 or 2 is unable to perform appropriate agency services, the Minister may restrict the performance of all or part of the agency service contracts concluded before the relevant disposition, notwithstanding paragraph (1).
법령보기 화면
Article 40 (Succession to effects of administrative dispositions)
Where an assessment agency transfers his or her business or where a corporate assessment agency merges with another corporation, the effect of an administrative disposition under
Article 38
imposed on the former assessment agency shall be succeeded to the transferee or the surviving or newly established corporation resulting from the merger for 1 year from the date the period of such disposition expires, and where procedures for such administrative disposition are in progress, such procedures may continue for the transferee or such corporation; provided, this shall not apply if it proves that the transferee or such corporation was not aware of the disposition or violation at the time of the transfer or merger.
법령보기 화면
Article 41 (Reporting of agency service performance)
(1)
An assessment agency shall report to the Minister of Oceans and Fisheries its agency service performance prescribed by Decree of the Ministry of Oceans and Fisheries, including the conclusion of agency service contracts, within 30 days from the date of such conclusion or other relevant events, as prescribed by Decree of the Ministry of Oceans and Fisheries.
(2)
The Minister of Oceans and Fisheries shall manage the current status of assessment agencies and the agency service performance reported under paragraph (1).
(3)
The Minister of Oceans and Fisheries shall publicly announce the agency service performance and the details of administrative dispositions at least once every year, as prescribed by Decree of the Ministry of Oceans and Fisheries.
(4)
If an assessment agency fails to file a report under paragraph (1), or if it is necessary to verify whether the marine use impact assessment services are being properly performed, the Minister of Oceans and Fisheries may require the agency to submit necessary materials or authorize a public official under his or her control to enter the place of business for inspection. In such cases, the agency must not refuse to submit materials or refuse or interfere with the inspection, without good cause.
(5)
Article 28
(4) and (5) shall apply
mutatis mutandis
to an inspection under paragraph (4).
(6)
If a person performing agency services intends to obtain recognition of agency service performance, the person shall file an application therefor with the Minister of Oceans and Fisheries, along with information regarding his or her workplace, career experience, and other relevant details; and if the Minister recognizes the details of such application, he or she may issue a certificate of such performance. In such cases, if necessary to verify the details of the application, the Minister may request the head of a relevant agency, such as a central administrative agency, a local government, or an institution or enterprise to which the person currently belongs or previously belonged, to submit relevant materials.
(7)
Matters necessary for the application for the recognition of agency service performance and the issuance of certificates under paragraph (6) shall be prescribed by Decree of the Ministry of Oceans and Fisheries.
법령보기 화면
Article 42 (Standards for calculating costs of agency services)
The Minister of Oceans and Fisheries shall determine and publicly notify the standards for calculating the costs necessary for agency services.
CHAPTER IV SUPPLEMENTARY PROVISIONS
법령보기 화면
Article 43 (Implementation of international conventions and strengthening of international cooperation)
(1)
The Minister of Oceans and Fisheries shall establish the necessary measures for assessing the potential impacts on the marine environment of activities planned under the jurisdiction or control of the State, in accordance with the United Nations Convention on the Law of the Sea.
(2)
The Minister of Oceans and Fisheries shall endeavor to ensure domestic implementation of international conventions related to the marine environment, including the United Nations Convention on the Law of the Sea, and to strengthen international cooperation.
(3)
The Minister of Oceans and Fisheries shall strive to cooperate with international organizations and other countries in relation to environmental impact assessments to promote the exchange of technology, information, and other resources for the conservation of the marine environment.
법령보기 화면
Article 44 (Research and surveys)
(1)
The Minister of Oceans and Fisheries may conduct or support research and surveys on the following to enhance the expertise and reliability of marine use impact assessment, etc.:
1.
Development of assessment criteria and indicators necessary for marine use impact assessments, etc.;
2.
Development of methodologies for marine use impact assessments, etc.;
3.
Surveys of the current status of the marine environment and the state of conservation and use by sea area;
4.
Investigation of marine use and development projects in which the Government or citizens of the Republic of Korea participate in accordance with international laws and regulations, and assessment of their impact on the marine environment;
5.
Analysis of the effects of marine use impact assessment, etc.;
6.
Other matters necessary for the efficient implementation of marine use impact assessments, etc.
(2)
When conducting research and surveys under paragraph (1), the Minister of Oceans and Fisheries may request the head of a relevant administrative agency or a related institution or organization to submit necessary materials. In such cases, a person so requested shall comply with the request unless there is a compelling reason not to do so.
(3)
The Minister of Oceans and Fisheries may collect a usage fee from a project operator, an assessment agency, or any other relevant person who intends to utilize the materials from the research and surveys under paragraph (1), as prescribed by Decree of the Ministry of Oceans and Fisheries.
(4)
Matters necessary for research and surveys under paragraph (1) shall be prescribed by Decree of the Ministry of Oceans and Fisheries.
법령보기 화면
Article 45 (Establishment and operation of information support system)
(1)
The Minister of Oceans and Fisheries shall collect and disseminate information on marine use impact assessments, etc. to enhance expertise, objectivity, predictability, and other relevant qualities of such assessments, etc.
(2)
The Minister of Oceans and Fisheries may establish and operate an information support system for marine use impact assessments, etc. (hereinafter referred to as "information support system") to perform the following tasks, as prescribed by Decree of the Ministry of Oceans and Fisheries:
1.
Collection and Dissemination of Information under paragraph (1);
2.
Registration of marine use impact assessment reports, etc., and the underlying data for their preparation under
Article 35
(1) 3 and (2) 3;
3.
Management of the current status of assessment agencies and their performance of agency services under
Article 41
(2);
4.
Other matters prescribed by Decree of the Ministry of Oceans and Fisheries.
(3)
The Minister of Oceans and Fisheries may entrust tasks regarding the establishment and operation of the information support system to an institution prescribed by Presidential Decree.
(4)
Matters necessary for the establishment and operation of the information support system shall be prescribed by Presidential Decree.
법령보기 화면
Article 46 (Training of professional human resources)
(1)
The Minister of Oceans and Fisheries may designate an institution or organization that meets the requirements for appropriate personnel, facilities, and other relevant conditions as an institution for training professional human resources, as prescribed by Presidential Decree, to enhance the expertise of human resources conducting marine use impact assessments, etc. and to strengthen the competitiveness thereof.
(2)
An institution for training professional human resources shall conduct the following projects:
1.
Analysis of the supply of, and demand for, professional human resources and the development of human resources;
2.
Development and operation of assessment methodologies and educational programs for professional human resources;
3.
Cooperation with academia, industry, and public institutions for training professional human resources;
4.
Other projects necessary for training and educating professional human resources for marine use impact assessments, etc.
(3)
The Minister of Oceans and Fisheries may fully or partially subsidize a designated institution for training professional human resources to cover the expenses incurred in training such human resources, within the budget.
(4)
If an institution for training professional human resources falls under any of the following categories, the Minister of Oceans and Fisheries may revoke its designation or order it to suspend its business operations for a fixed period of up to 6 months; provided, in the case of subparagraph (1), the Minister shall revoke the designation:
1.
If the institution has obtained the designation by fraud or other improper means;
2.
If the institution no longer meets the designation requirements under paragraph (1);
3.
If the institution fails to commence or delays the training of professional human resources, without good cause;
4.
If the institution fails to train professional human resources for a consecutive period of at least 1 year, without good cause.
(5)
The specific designation requirements for an institution for training professional human resources under paragraph (1), the detailed criteria and procedures for dispositions under paragraph (4), and other necessary matters shall be prescribed by Decree of the Ministry of Oceans and Fisheries.
법령보기 화면
Article 47 (Association on marine use impact assessments)
(1)
Assessment agencies and persons conducting business affairs regarding marine use impact assessments, etc. may establish an association on marine use impact assessments, etc. (hereinafter referred to as the "Association") to promote the sound development of surveys, research, education, public relations, and other business affairs regarding marine use impact assessments, etc.
(2)
The Association shall be a corporation.
(3)
To establish the Association, its articles of incorporation shall be prepared and permission therefor shall be obtained from the Minister of Oceans and Fisheries; and the same shall also apply to any amendment to the articles of incorporation.
(4)
The Association shall be duly established upon completing its incorporation registration at the registry office having jurisdiction over the location of its principal office, after obtaining permission for incorporation under paragraph (3).
(5)
If the Minister of Oceans and Fisheries deems that the operation of the Association violates any statute or regulation or its articles of incorporation, the Minister may order the Association to amend its articles of incorporation or business plan, or to replace its executive officers.
(6)
Except as provided in this Act, the provisions of the
Civil Act
governing incorporated associations shall apply
mutatis mutandis
to matters regarding the Association.
법령보기 화면
Article 48 (Duty of confidentiality)
An assessment agency, a relevant current or former expert involved in the review process of marine use impact assessment reports, etc. or a current or former executive officer or employee of a relevant specialized institution must not disclose or misappropriate any confidential information acquired in the course of their duties related to marine use impact assessments, etc.
법령보기 화면
Article 49 (Hearings)
If the Minister of Oceans and Fisheries intends to make any of the following dispositions, the Minister shall hold a hearing:
1.
Revocation of the registration of an assessment agency under
Article 38
(1);
2.
Revocation of the designation of an institution for training professional human resources under
Article 46
(4).
법령보기 화면
Article 50 (Delegation and entrustment of authority)
(1)
Part of the authority of the Minister of Oceans and Fisheries under this Act may be delegated to the head of an affiliated agency, as prescribed by Presidential Decree.
(2)
Part of the duties of the Minister of Oceans and Fisheries under this Act may be entrusted to the Association or the head of a relevant specialized institution, as prescribed by Presidential Decree.
(3)
The Minister of Oceans and Fisheries may provide full or partial subsidies to cover the expenses incurred in performing the duties entrusted under paragraph (2), within the budget.
법령보기 화면
Article 51 (Legal fiction as public officials for purposes of applying penalty provisions)
Any of the following persons shall be deemed a public official for purposes of applying penalty provisions under
Articles 129 through 132 of the Criminal Act
:
1.
An executive officer or employee of a marine use impact review agency who performs business affairs under
Article 12
(2), 20 (2), or 28 (2);
2.
An executive officer or employee of an institution that selects an assessment agency under
Article 32
(1);
3.
A person who belongs to an association or a relevant specialized institution entrusted with duties under
Article 50
(2) and performs such entrusted duties.
CHAPTER V PENALTY PROVISIONS
법령보기 화면
Article 52 (Penalty provisions)
(1)
Any of the following persons shall be punished by imprisonment with labor for up to 5 years or by a fine not exceeding 50 million won:
1.
A project operator that fails to comply with an order to suspend the relevant project, dismantle or suspend the operation of artificial structures, or restore the relevant site to its original state under
Article 23
(5) or (6);
2.
A project operator that fails to comply with an order to suspend the relevant construction work or restore the relevant site to its original state under
Article 25
(3) or 30 (2);
3.
A project operator that fails to comply with an order to suspend the relevant construction work or restore the relevant site to its original state under
Article 25
(4) or 30 (3).
(2)
Any of the following persons shall be punished by imprisonment with labor for up to 2 years or by a fine not exceeding 20 million won:
1.
A project operator that fails to conduct a marine environmental impact survey under
Article 29
(1);
2.
An assessment agency that provides agency services for the preparation of a marine use impact assessment report, etc. without filing for registration under
Article 33
(1);
3.
An assessment agency that has filed for registration under
Article 33
(1) by fraud or other improper means;
4.
A person who prepares a marine use impact assessment report, etc., by copying the details of any other such report, etc., in violation of
Article 35
(1) 1 or (2) 1;
5.
A person who prepares a marine use impact assessment report, etc. with false details, in violation of
Article 35
(1) 2 or (2) 2;
6.
A person who requires an assessment agency to prepare a marine use impact assessment report etc. and the underlying data for its preparation, with false or deficient details, in violation of
Article 35
(1) 6; provided, this shall not apply where a project subject to consultation is subject to an environmental impact assessment under
Article 22 of the Environmental Impact Assessment Act
or a small-scale environmental impact assessment under
Article 43
of that Act;
7.
A person who offers to or accepts from an assessment agency any unjust solicitation, money, valuables, or entertainment in connection with the relevant agency services, in violation of
Article 35
(1) 7;
8.
A person who offers to or accepts from a project operator any unjust solicitation, money, valuables, or entertainment in connection with the performance of the relevant agency services, in violation of
Article 35
(2) 6;
9.
An assessment agency that concludes a new contract for agency services following the revocation of its registration or during a business suspension period, in violation of
Article 39
(3).
(3)
Any of the following persons shall be punished by imprisonment with labor for up to 1 year or by a fine not exceeding 10 million won:
1.
A project operator that commences construction work without undergoing the consultation or reconsultation process or before its completion, in violation of
Article 25
(1);
2.
A person who refuses to submit materials or refuses or interferes with entry or inspection without good cause, in violation of the latter part of
Article 28
(3) or the latter part of
Article 41
(4);
3.
A project operator that fails to submit materials without good cause, in violation of the latter part of
Article 29
(5);
4.
An assessment agency that lends its certificate of registration or name to another person, in violation of
Article 35
(2) 4;
5.
An assessment agency that subcontracts its agency services to another person, in violation of
Article 35
(2) 5;
6.
A person who discloses or misappropriates confidential information, in violation of
Article 48
.
법령보기 화면
Article 53 (Joint penalty provisions)
If the representative of a corporation or an agent or employee of, or any other person employed by, the corporation or an individual commits any violation described in
Article 52
in conducting the business affairs of the corporation or individual, the corporation or individual shall be punished by a fine prescribed in that Article in addition to punishing the violator accordingly; provided, this shall not apply where the corporation or individual has not been negligent in giving due attention and supervision regarding the business affairs to prevent such violation.
법령보기 화면
Article 54 (Administrative fines)
(1)
Any of the following persons shall be subject to an administrative fine not exceeding 50 million won:
1.
A project operator that fails to implement measures to prevent damage to the surrounding marine environment or safety-related accidents under
Article 23
(5) or (6);
2.
A project operator that fails to implement measures to prevent damage to the surrounding marine environment or safety-related accidents under
Article 25
(3) or (4);
3.
A project operator that fails to comply with an order to take measures for damage mitigation under
Article 29
(3);
4.
A project operator that fails to comply with an order to take measures under
Article 30
(1);
5.
A project operator that fails to implement measures to prevent damage to the surrounding marine environment or safety-related accidents under
Article 30
(2) or (3).
(2)
An administrative fine not exceeding 20 million won shall be imposed on a project operator that commences construction work without undergoing the consultation or reconsultation process or before its completion, in violation of
Article 25
(1); provided, this shall not apply where a project subject to consultation is subject to an environmental impact assessment under
Article 22 of the Environmental Impact Assessment Act
or a small-scale environmental impact assessment under
Article 43
of that Act.
(3)
Any of the following persons shall be subject to an administrative fine not exceeding 10 million won:
1.
A project operator that fails to notify marine environment conservation measures following the modification of the relevant project plan, etc. in violation of the latter part of
Article 24
(3);
2.
A project operator that fails to conduct part of a marine environmental impact survey, in violation of
Article 29
(1);
3.
A project operator that fails to take necessary measures or give notification, in violation of
Article 29
(2); provided, this shall not apply where a project subject to consultation is subject to an environmental impact assessment under
Article 22 of the Environmental Impact Assessment Act
or a small-scale environmental impact assessment under
Article 43
of that Act;
4.
A project operator that fails to conclude a separate contract for the agency services for the preparation of a marine use impact assessment report, etc., independent of other contracts, in violation of
Article 31
(2);
5.
A project operator that engages a person who has provided agency services for preparation under
Article 31
(1) 1 or 2 to also provide agency services for the preparation of a marine environmental impact survey report, in violation of paragraph (3) of that Article;
6.
A person who prepares a marine use impact assessment report, etc. with deficient details, in violation of
Article 35
(1) 2 or (2) 2;
7.
A person who fails to register a marine use impact assessment report, etc., and underlying data for its preparation in the information support system, in violation of
Article 35
(1) 3 or (2) 3.
(4)
Any of the following persons shall be subject to an administrative fine not exceeding 5 million won:
1.
A project operator that fails to notify the commencement, completion, suspension, or resumption of a project, in violation of
Article 26
; provided, this shall not apply where a project subject to consultation is subject to an environmental impact assessment under
Article 22 of the Environmental Impact Assessment Act
or a small-scale environmental impact assessment under
Article 43
of that Act;
2.
A project operator that fails to designate a person in charge or to record and manage the status of compliance with the consultation opinions in a management ledger, in violation of
Article 27
(2); provided, this shall not apply where a project subject to consultation is subject to an environmental impact assessment under
Article 22 of the Environmental Impact Assessment Act
or a small-scale environmental impact assessment under
Article 43
of that Act;
3.
A project operator that fails to notify the results of a marine environmental impact survey, in violation of
Article 29
(1);
4.
An assessment agency that modifies an important matter without filing for registration of such modification, in violation of
Article 33
(2);
5.
A person who fails to file a report on the succession of rights and obligations, in violation of
Article 36
(2);
6.
An assessment agency that fails to report its agency service performance, in violation of
Article 41
(1).
(5)
Administrative fines under paragraphs (1) through (4) shall be imposed and collected by the Minister of Oceans and Fisheries, as prescribed by Presidential Decree.
ADDENDA <Act No. 19910, Jan. 2, 2024>
Article 1 (Enforcement date)
This Act shall enter into force 1 year after the date of its promulgation.
Article 2 (Applicability to consultation on marine use)
Article 9
shall begin to apply to the first submission of a written consultation under
Article 10
to the head of the competent authority by a project operator that intends to obtain any license specified in the subparagraphs of paragraph (1) of that Article.
Article 3 (Applicability to marine use impact assessments)
Article 13
shall begin to apply to the first request for deliberation under
Article 14
made to the head of the competent authority by a project operator that intends to conduct any marine use and development project specified in the subparagraphs of paragraph (1) of that Article.
Article 4 (General transitional measures)
Acts performed by or toward administrative agencies under the previous
Marine Environment Management Act
as at the time this Act enters into force shall be deemed those performed by or toward administrative agencies under this Act which correspond thereto.
Article 5 (Transitional measures regarding assessment agencies)
A person registered as an assessment agency under the previous
Marine Environment Management Act
as at the time this Act enters into force shall be deemed registered as an assessment agency under
Article 33
.
Article 6 (Transitional measures regarding administrative dispositions)
For purposes of imposing an administrative disposition for any violation committed before this Act enters into force, the previous
Marine Environment Management Act
shall apply.
Article 7 (Transitional measures regarding penalty provisions)
For purposes of applying penalty provisions or provisions regarding administrative fines to an act committed before this Act enters into force, the previous
Maritime Safety Act
shall govern.
Article 8
Omitted.
Article 9 (Relationship to other statutes or regulations)
A citation of the previous
Marine Environment Management Act
or any provision thereof by other statutes or regulations in force as at the time this Act enters into force shall be deemed a citation of this Act or the relevant provision hereof, if any, in lieu of such previous provision.
ADDENDA <Act No. 20369, Feb. 27, 2024>
Article 1 (Enforcement date)
This Act shall enter into force on the date of its promulgation; provided, ... <omitted>... paragraph (4) of that Article shall enter into force ... <omitted>... on January 3, 2025.
Article 2
Omitted.
Last updated : - -