ENFORCEMENT DECREE OF THE ACT ON REPAIR OF CULTURAL HERITAGE
40528 · 2016-11-29
ENFORCEMENT DECREE OF THE ACT ON REPAIR OF CULTURAL HERITAGE
Presidential Decree No. 27619, Nov. 29, 2016
Presidential Decree No. 22638, Jan. 26, 2011
Amended by Presidential Decree No. 23488, Jan. 6, 2012
Presidential Decree No. 23759, May 1, 2012
Presidential Decree No. 23943, Jul. 10, 2012
Presidential Decree No. 24676, Jul. 30, 2013
Presidential Decree No. 25050, Dec. 30, 2013
Presidential Decree No. 25711, Nov. 11, 2014
Presidential Decree No. 25854, Dec. 16, 2014
Presidential Decree No. 27115, Apr. 29, 2016
Presidential Decree No. 27619, Nov. 29, 2016
법령보기 화면
Article 1 (Purpose)
The purpose of this Decree is to prescribe matters delegated by the
Act on Cultural Heritage Maintenance, Etc.
and matters necessary for the enforcement thereof.
법령보기 화면
Article 2 (Scope of Repair of Cultural Heritage)
"Public structures and landscape prescribed by Presidential Decree" under subparagraph 1 (c) of
Article 2 of the Act on Cultural Heritage Maintenance, Etc.
(hereinafter referred to as "Act") shall mean any of the following public structures and landscape:
1.
Structures and landscape in a protected area that surround the designated cultural heritage under
Article 2 (2) of the Cultural Heritage Protection Act
(including the provisionally designated cultural heritage under
Article 32 of the same Act
, but excluding the intangible cultural heritage under
Article 2 (1) 2 of the same Act
and the historic sites, scenic spots and natural monuments under
Article 25 of the same Act
; hereafter the same shall apply in this Article);
2.
Structures and landscape necessary for the preservation and utilization of designated cultural heritage in a land (limited to the one managed by the owner under
Article 33 of the Cultural Heritage Protection Act
and the management organization under
Article 34 of the same Act
(including cases in which such provision applies
mutatis mutandis
pursuant to
Article 74 (2) of the same Act
)) surrounding the designated cultural heritage under
Article 2 (2) of the same Act
.
법령보기 화면
Article 3 (Formulation of Master Plan for Repair, etc. of Cultural Heritage)
(1)
The master plan (hereafter referred as "master plan" in this Article) for the repair, on-site survey and design or supervision of cultural heritage (hereinafter referred to as "repair, etc. of cultural heritage") under
Article 4 (1) of the Act
shall include the following matters:
1.
Basic direction-settings for repair, etc. of cultural heritage;
2.
Measures to assure the quality of repair, etc. of cultural heritage;
3.
Matters concerning technological promotion of repair, etc. of cultural heritage;
4.
Other matters necessary for repair, etc. of cultural heritage.
(2)
If needs arise for a formulation of a master plan, the Administrator of the Cultural Heritage Administration may request the Special Metropolitan City Mayor, Metropolitan City Mayors,
Do
Governors or Special Self-Governing Province Governor (hereinafter referred to as "Mayors/
Do
Governors") to submit data on the repair, etc. of cultural heritage located in their jurisdictions.
(3)
Pursuant to
Article 4 (3) of the Act
, Mayors/
Do
Governors shall formulate a detailed implementation plan within one year after they receive notification on a master plan and submit it to the Administrator of the Cultural Heritage Administration.
법령보기 화면
Article 4 (Restrictions on Repair of Cultural Heritage)
(1)
"Minor repairs prescribed by Presidential Decree that do not influence the preservation of relevant cultural heritage" under the proviso to
Article 5 (1) of the Act
shall be as listed in Appendix 1.
(2)
"Structures prescribed by Presidential Decree" under
Article 5 (2) of the Act
are structures the main structure of which is a reinforced concrete structure, steel structure or steel framed reinforced concrete structure.
<Amended by Presidential Decree No. 25854, Dec. 16, 2014>
(3)
"Institutions prescribed by Presidential Decree" under
Article 5 (3) of the Act
shall mean any of the following institutions:
Provided
, That the foregoing shall be applicable to the institutions under subparagraphs 2 through 4 only in cases of repair of movable cultural heritage:
1.
Cultural Heritage Administration;
2.
National Museum of Korea;
3.
National Museum of Modern and Contemporary Art, Korea;
4.
National Folk Museum of Korea.
법령보기 화면
Article 5 (Restrictions on On-Site Survey and Design for Repair of Cultural Heritage)
(1)
"The field of protection of plants or movable cultural heritage, which are prescribed by Presidential Decree" under
Article 5 (5) of the Act
shall mean the following:
1.
Protection of plants:
(a)
Disease and insect control, plant surgery and soil improvement for the conservation and protection of plants;
(b)
Installation of protective facilities and environmental improvement for the conservation and protection of plants;
2.
Movable cultural heritage:
(a)
Taxidermy and specimen production;
(b)
Sculpture;
(c)
Picture mounting;
(d)
Lacquering;
(e)
Plating;
(f)
Mimesis.
(2)
Where an on-site cultural heritage survey and design business entity intends to conduct any of the following on-site cultural heritage survey and design, the business entity shall have a landscape architect under subparagraph 4 of Appendix 2 conduct it:
1.
Where the proportion of landscape occupies at least 20/100 among the whole survey and design for the repair of cultural heritage;
2.
Where the estimated cost for landscape among the whole survey and design for the repair of cultural heritage is at least five million won.
법령보기 화면
Article 6 (Public Notification of Standards for Repair, etc. of Cultural Heritage)
Where the Administrator of the Cultural Heritage Administration sets, changes or repeals standards necessary for the repair, etc. of cultural heritage under any subparagraph of
Article 7 of the Act
, he/she shall publish the details in the Official Gazette.
법령보기 화면
Article 7 (Implementation of Qualifying Examination for Cultural Heritage Repair Engineers, Public Announcement thereof, etc.)
(1)
The Administrator of the Cultural Heritage Administration shall implement an examination to qualify as a cultural heritage repair engineer under
Article 8 (1) of the Act
at least once a year:
Provided
, That where implementation of an examination is not reasonable in consideration of demand for and supply of cultural heritage repair engineers, etc., he/she may choose not to implement an examination for the relevant year.
(2)
Where the Administrator of the Cultural Heritage Administration intends to implement an examination to qualify as a cultural heritage repair engineer, he/she shall publicly announce the following matters in at least one daily newspaper registered as having nationwide circulation pursuant to
Article 9 (1) of the Act on the Promotion of Newspapers, Etc.
not later than 90 days before the examination:
<Amended by Presidential Decree No. 23759, May 1, 2012>
1.
Eligibility to take a qualifying examination;
2.
Date, time and place of examination;
3.
Examination subjects;
4.
Date, time, method and place of announcement of successful applicants;
5.
Period and place of issuance of application forms, and period and place of acceptance of application forms;
6.
Other matters necessary for the implementation of examination.
(3)
A person (including a person who intends to be exempted from written examination, in full or in part, pursuant to the proviso to
Article 8 (3) of the Act
and
Article 8 (4) of the Act
) who intends to apply for an examination to qualify as a cultural heritage repair engineer shall submit an application form accompanied by necessary documents as prescribed by Ministerial Decree of Culture, Sports and Tourism to the Administrator of the Cultural Heritage Administration.
법령보기 화면
Article 8 (Types of Cultural Heritage Repair Engineer, Scope of Duties and Eligibility to Take Qualifying Examination)
(1)
The types of cultural heritage repair engineers and scope of duties under
Article 8 (2) of the Act
shall be as listed in Appendix 2.
(2)
A person who intends to apply for an examination to qualify as a cultural heritage repair engineer (excluding on-site cultural heritage survey and design engineers) under
Article 8 (5) of the Act
shall meet any of the following requirements:
<Amended by Presidential Decree No. 25854, Dec. 16. 2014>
1.
He/she shall have served in the field of repair of cultural heritage for at least one year;
2.
He/she shall have graduated from a middle school under the
Elementary and Secondary Education Act
or be deemed to have an academic background equivalent thereto or higher;
3.
He/she shall have obtained the qualification of a technician under the
National Technical Qualifications Act
or higher;
4.
He/she shall be a cultural heritage repair technician.
법령보기 화면
Article 9 (Subjects of Qualifying Examination for Cultural Heritage Repair Engineers, Methods thereof, etc.)
(1)
The written examination to qualify as a cultural heritage repair engineer referred to in
Article 8 (3) of the Act
shall consist of multiple-choice objective examination and essay-type subjective examination.
(2)
The subjects of a written examination under paragraph (1) and methods of examination shall be as listed in Appendix 4.
(3)
Part of the subjects of an examination to qualify as a cultural heritage repair engineer that a person under the proviso to
Article 8 (3) of the Act
is exempted from taking shall be as listed in Appendix 5.
(4)
A person who passes a written examination under the main sentence of
Article 8 (3) of the Act
or a person who is exempted from written examination pursuant to
Article 8 (4) of the Act
shall be allowed to take an oral examination.
(5)
The following matters shall be evaluated in an oral examination under the main sentence of
Article 8 (3) of the Act
:
1.
Expert knowledge in the relevant technology and capability of practical application;
2.
Understanding of history and cultural heritage;
3.
Awareness of sense of duty and role as a cultural heritage repair engineer;
4.
Proper vocational ethics.
법령보기 화면
Article 10 (Determination, etc. of Successful Applicants for Cultural Heritage Engineers)
(1)
The perfect score on each subject of a written qualifying examination for cultural heritage repair engineers under the main sentence of
Article 8 (3) of the Act
shall be 100 points, and a successful applicant shall score a minimum of 40 points on each subject and achieve an average mark of at least 60 points on all subjects.
(2)
Each interviewer can award a maximum of 100 points for an oral qualifying examination for cultural heritage repair engineers under the main sentence of
Article 8 (3) of the Act
, and a successful applicant shall score a minimum of 40 points from each interviewer and achieve an average mark of at least 60 points from all interviewers.
(3)
When successful applicants are determined at last, the Administrator of the Cultural Heritage Administration shall notify such fact using a method by which all the applicants know who are successful.
법령보기 화면
Article 11 (Examination to Qualify as Cultural Heritage Repair Technician)
(1)
The Administrator of the Cultural Heritage Administration shall implement an examination to qualify as cultural heritage technician under
Article 11 (1) of the Act
at least once a year:
Provided
, That where implementation of an examination is not reasonable in consideration of demand for and supply of cultural heritage repair technicians, etc., he/she may choose not to implement an examination for the relevant year.
(2)
The types of cultural heritage repair technicians and scope of duties under
Article 11 (2) of the Act
shall be as listed in Appendix 6.
(3)
The performance examination to qualify as cultural heritage technician under
Article 11 (3) of the Act
shall be implemented by a method by which competency is examined according to the types of cultural heritage technicians, and each examiner can award a maximum of 100 points for a performance examination to quality as cultural heritage repair technician under
Article 11 (3) of the Act
, and a successful applicant shall score a minimum of 40 points from each examiner and achieve an average mark of at least 60 points from all examiners.
(4)
Each interviewer can award a maximum of 100 points for an oral examination to qualify as cultural heritage repair engineer under
Article 11 (3) of the Act
, and a successful applicant shall score a minimum of 40 points from each interviewer and achieve an average mark of at least 60 points from all interviewers.
(5)
Articles 7
(2) and (3),
9
(5) and
10
(3) shall apply
mutatis mutandis
to the public announcement of an examination to qualify as cultural heritage technician under
Article 11 (4) of the Act
, application forms, evaluation of an oral examination and public announcement of successful applicants, respectively.
법령보기 화면
Article 12 (Requirements for Registration of Cultural Heritage Repair Business, etc.)
(1)
The requirements for registration of cultural heritage repair business, on-site cultural heritage survey and design business or cultural heritage supervision business (hereinafter referred to as "cultural heritage repair business, etc.") shall be as listed in the following:
<Amended by Presidential Decree No. 24676, Jul. 30, 2013; Presidential Decree No. 25854, Dec. 16. 2014>
1.
It shall have the technological capabilities, capital (referring to the appraised value of asset provided to the cultural heritage repair business, etc. in cases of an individual; hereinafter the same shall apply) and facilities prescribed in Appendix 7;
2.
A confirmation document evidencing that a security worth of at least 20/100 of the base amount of the capital prescribed in subparagraph 1 is provided or cash equivalent thereto is deposited or contributed, which is verified and issued by any of the following institutions, shall be submitted:
(a)
The Cultural Heritage Conservation Committee under
Article 42 of the Act
;
(b)
Banks designated by the Administrator of the Cultural Heritage Administration from among banks defined in the
Banking Act
;
(c)
Insurance companies designated by the Administrator of the Cultural Heritage Administration from among insurance companies defined in the
Insurance Business Act
;
(d)
Mutual-aid associations under
Article 54 of the Framework Act on the Construction Industry
(limited to where an entity intending to register cultural heritage repair business, etc. is a member);
3.
Where it is designated as an inappropriate business pursuant to the
Act on Contracts to which the State Is a Party
or the
Act on Contracts to which a Local Government Is a Party
and thus its qualification for participation in a bidding is restricted, the period of restriction shall have ended;
4.
Where it is issued disposition of suspension of business pursuant to
Article 49 (1) of the Act
, the period of suspension of business shall have ended;
5.
In cases of an on-site cultural heritage survey and design business entity (referring to the representative in cases of a corporation), it shall be the person who is an on-site cultural heritage survey and design engineer from among cultural heritage repair engineers and has reported the establishment of an architectural firm pursuant to
Article 23 of the Certified Architects Act
.
(2)
"Important matters prescribed by Presidential Decree" under
Article 14 (2) of the Act
shall mean the following:
1.
Company name;
2.
Representative;
3.
Address of main business office;
4.
Current state of cultural heritage repair engineers and cultural heritage repair technicians on the payroll.
법령보기 화면
Article 13 (Types of Cultural Heritage Repair Business and Scope of Duties)
The types of general cultural heritage repair business and special cultural heritage repair business under
Article 16 (2) and (3) of the Act
and the scope of duties shall be as listed in Appendix 8.
법령보기 화면
Article 14 (Scope, etc. of Appurtenant Repair of Cultural Heritage)
"Minor part prescribed by Presidential Decree" under
Article 16 (4) of the Act
shall mean any of the following:
1.
Appurtenant repair of cultural heritage the necessity for which arises as the principal repair of cultural heritage is being or to be implemented;
2.
Where at least two specialized fields of repair of cultural heritage are mixed, and the total estimated amount of which is less than 100 million won, and the estimated amount of repair of cultural heritage for the principal part is at least 1/2 of the estimated amount of whole repair of cultural heritage, the repair of cultural heritage for the rest part.
법령보기 화면
Article 15 (Contents of Contract)
(1)
"Matters prescribed by Presidential Decree" under
Article 24 (2) of the Act
shall mean the following:
1.
Concrete details of the repair, etc. of cultural heritage;
2.
Time to commence the repair, etc. of cultural heritage and time of completion;
3.
Where advance payment of contract amount or progress payment is specified in the contract, the time, method and amount of respective payment;
4.
Matters concerning taking responsibility for loss if the repair, etc. of cultural heritage are suspended, the contract is revoked, or a natural disaster occurs;
5.
Matters concerning change in contract amount or change in the details of repair, etc. of cultural heritage due to change of design, price fluctuation, etc.;
6.
Matters concerning payment of funds for occupational safety and health management under
Article 30 of the Occupational Safety and Health Act
;
7.
Matters concerning industrial accident compensation insurance premiums under the
Industrial Accident Compensation Insurance Act
, employment insurance premiums under the
Employment Insurance Act
, various charges for which a party takes responsibility pursuant to statutes with regard to the repair, etc. of cultural heritage, and methods of taking responsibility therefor;
8.
Methods of disposing of and recycling the wastes occurring from the relevant repair, etc. of cultural heritage;
9.
Inspection for the delivery of the object of a contract and time of delivery;
10.
Time to pay contract amount after completion of repair, etc. of cultural heritage;
11.
Matters concerning compensation for loss, such as payment of penalty for breach of a contract, interest for arrears in cases of a delay in the implementation of a contract;
12.
Warranty period and warranty methods;
13.
Other matters to be specified according to statutes or an agreement by both parties.
(2)
To make both parties conclude a fair contract on equal terms, the Administrator of the Cultural Heritage Administration may set and disseminate a standard contract form or a standard subcontract form for the repair, etc. of cultural heritage (referring to a standard subcontract form for the repair of cultural heritage as recommended by the Fair Trade Commission pursuant to the
Fair Transactions in Subcontracting Act
in cases of a subcontract).
법령보기 화면
Article 16 (Notification of Subcontracts)
(1)
The notification under
Article 25 (2) of the Act
shall be made within 30 days from the date a subcontract is concluded, as prescribed by Ministerial Decree of Culture, Sports and Tourism. The same shall apply to the modification or revocation of a subcontract.
(2)
Where a general cultural heritage repair business entity being given a subcontract for the repair of cultural heritage over which a cultural heritage supervision business entity conducts supervision makes notification to a cultural heritage business entity by the deadline under paragraph (1), the notification shall be deemed to be made to the person placing the contract.
법령보기 화면
Article 17 (Request for Change of Subcontractor)
Where a person placing a contract intends to request the change of a subcontractor pursuant to
Article 32 (1) of the Act
, he/she shall make a written request within 15 days from the day he/she perceives the existence of reasons therefor or within 30 from the day reasons begin to exist.
법령보기 화면
Article 18 (Standards, etc. for Posting Cultural Heritage Repair Engineers to Sites)
(1)
Pursuant to
Article 33 (1) of the Act
, a cultural heritage repair business entity shall post a cultural heritage repair engineer conforming to the following standards and corresponding to the type of repair of cultural heritage to the site of repair of cultural heritage simultaneously with the commencement of repair of cultural heritage:
Provided
, That where the parties to a contract set stricter standards for the type, work experience and the number of cultural heritage engineers to be posted to the site of repair of cultural heritage in consideration of the importance and characteristics of the repair of cultural heritage, such standards shall apply:
<Amended by Presidential Decree No. 25854, Dec. 16. 2014>
1.
In cases of repair of cultural heritage falling under subparagraph 1 (a) or (b) of
Article 2 of the Act
the estimated cost for which is at least one billion won: A person in the relevant service for at least seven years after obtaining the qualification of a cultural heritage engineer;
2.
In cases of repair of cultural heritage falling under subparagraph 1 (c) of
Article 2 of the Act
the estimated cost for which is at least three billion won: A person in the relevant service for at least five years after obtaining the qualification of a cultural heritage engineer;
3.
In cases of repair of cultural heritage falling under subparagraph 1 (c) of
Article 2 of the Act
the estimated cost for which is between two and three billion won: A person in the relevant service for at least three years after obtaining the qualification of a cultural heritage engineer;
4.
In cases of repair of cultural heritage other than those prescribed in subparagraphs 1 through 3: A person who has obtained the qualification of a cultural heritage engineer.
(2)
In cases of repair of cultural heritage in which at least two types of specialized fields are mixed, cultural heritage repair engineers in the field that occupies higher proportion among the amount of repair of cultural heritage shall be posted when cultural heritage repair engineers are to be posted pursuant to paragraph (1).
(3)
Pursuant to the proviso to
Article 33 (1) of the Act
, a cultural heritage repair business entity may post one cultural heritage repair engineer to less than three sites of repair of cultural heritage (sites on which repair of cultural heritage is temporarily suspended and sites on which disease and insect control is performed as specified in the duties of a plant protection engineer under subparagraph 6 of Appendix 2 shall be excluded from the calculation of the number of sites) with the consent of the person placing the contract to the extent that no impediment arises to the quality and safety of repair of cultural heritage:
Provided
, That where the repair of cultural heritage under a negotiated contract under
Article 26 (1) 5 (a) of the Enforcement Decree of the Act on Contracts to which the State Is a Party
or under
Article 25 (1) 5 of the Act on Contracts to which a Local Government Is a Party
or the repair of cultural heritage falling under subparagraph 1 (c) of
Article 2 of the Act
, the estimated cost for which is less than 50 million won is included, it may post a cultural heritage repair engineer to less than five sites of repair of cultural heritage (sites on which repair of cultural heritage is temporarily suspended and sites on which disease and insect control is performed as specified in the duties of a plant protection engineer under subparagraph 6 of Appendix 2 shall be excluded from the calculation of the number of sites).
<Amended by Presidential Decree No. 25854, Dec. 16. 2014>
(4)
When a cultural heritage repair business entity posts cultural heritage repair engineers to the site of repair of cultural heritage pursuant to
Article 33 (1) of the Act
, it shall receive confirmation from the person placing the contract on the details of posting as prescribed by Ministerial Decree of Culture, Sports and Tourism.
법령보기 화면
Article 19 (Warranty Period)
The warranty period by types of repair of cultural heritage under
Article 35 (1) of the Act
shall be as listed in Appendix 9.
법령보기 화면
Article 20 (Repair of Cultural Heritage Subject to Supervision, etc.)
The repair of cultural heritage subject to supervision by a cultural heritage supervision business entity under
Article 38 (2) of the Act
shall be as listed hereunder:
<Amended by Presidential Decree No. 25854, Dec. 16. 2014>
1.
In cases falling under subparagraph 1 (a) or (b) of
Article 2 of the Act
: Repair of cultural heritage, the estimated amount of which is at least 300 million won:
Provided
, That movable cultural heritage shall be excluded;
2.
In cases falling under subparagraph 1 (c) of
Article 2 of the Act
: Repair of cultural heritage the estimated cost for which is at least 500 million won;
3.
Repair of cultural heritage in addition to the cultural heritage under subparagraphs 1 and 2, which is separately determined and publicly notified by the Administrator of the Cultural Heritage Administration deeming supervision of the cultural heritage is necessary as it has significance in historical, academic, scenic, or architectural values.
법령보기 화면
Article 21 (Scope of Duties of Cultural Heritage Supervisors)
(1)
Cultural heritage supervisors shall conduct supervision over the repair of relevant cultural heritage pursuant to
Article 38 (3) of the Act
, and they are classified into resident supervisors and non-resident supervisors as listed hereunder:
<Amended by Presidential Decree No. 25854, Dec. 16. 2014>
1.
Resident supervisor: A cultural heritage supervisor who resides in and conducts supervision over one site of repair of cultural heritage;
2.
Non-resident supervisor: A cultural heritage supervisor who conducts supervision over a site of repair of cultural heritage occasionally or when needs arise, but does not reside in the site. In such case, a non-resident supervisor may conduct supervision over not more than five sites of repair of cultural heritage as he/she does not reside in such sites.
(2)
The scope of duties of a cultural heritage supervisor shall be as listed in Appendix 10.
(3)
The Administrator of the Cultural Heritage Administration may determine and publicly notify detailed standards necessary for the methods of implementation of supervision, procedures therefor, etc. so that cultural heritage supervision entities and cultural heritage supervisors may perform such duties efficiently.
법령보기 화면
Article 22 (Posting, etc. of Cultural Heritage Supervisors)
(1)
The standards for posting cultural heritage supervisors to the sites of repair of cultural heritage by a cultural heritage supervision business entity pursuant to
Article 38 (3) of the Act
shall be as listed in Appendix 11.
(2)
In cases of supervision over the repair of cultural heritage conducted in a site of repair of cultural heritage in which at least two types of specialized fields are mixed, a cultural heritage supervisor in the field of repair of cultural heritage that occupies higher proportion out of the amount of repair of cultural heritage shall be posted.
(3)
Where a person placing a contract deems that a cultural heritage supervisor already posted or to be posted is not appropriate for the performance of supervision over the repair of relevant cultural heritage, he/she may clearly state the reason and request the cultural heritage supervision business entity to change the cultural heritage supervisor, and where a cultural heritage supervision entity voluntarily changes a cultural heritage supervisor, it shall obtain approval from the person placing the contract in advance.
(4)
Where a cultural heritage supervisor leaves the site of repair of cultural heritage as he/she receives supplemental education prescribed in
Article 53 of the Act
or education prescribed in the
Framework Act on Civil Defense
or the
Reserve Forces Act
while he/she conducts supervision over the repair of cultural heritage or is on a paid leave, the cultural heritage supervision business entity shall take measures so that the supervision of repair of cultural heritage is not obstructed, and the person placing the contract shall pay the cost for supervision for the period during which the cultural heritage supervisor receives the education.
<Amended by Presidential Decree No. 27619, Nov. 29, 2016>
(5)
A cultural heritage supervisor posted to a site of repair of cultural heritage shall record and preserve a supervision journal, as prescribed by Ministerial Decree of Culture, Sports and Tourism.
(6)
The Administrator of the Cultural Heritage Administration may determine and publicly notify detailed standards necessary for posting cultural heritage supervisors.
법령보기 화면
Article 23 (Orders, etc. of Reimplementation by Cultural Heritage Supervisors)
(1)
Where a person placing a contract is notified of a reimplementation order, suspension order, etc. issued by a cultural heritage supervisor pursuant to
Article 39 (4) of the Act
, he/she shall examine the details, and take necessary measures, such as verification whether to make rectification, instruction to resume the repair of cultural heritage, etc.
(2)
For reasons of issuing a reimplementation order, suspension order, etc. by a cultural heritage supervisor under
Article 39 of the Act
, the person placing the contract shall not change the cultural heritage supervisor, refuse the cultural heritage supervisor to be posted to the site all the time, refuse to pay or delay in making payment for supervision or issue unfavorable disposition to the cultural heritage supervisor.
법령보기 화면
Article 24 (Restrictions on Supervision)
"Where the relationship between the two of them is as that of a parent company and a subsidiary, which is prescribed by Presidential Decree" under subparagraph 1 of
Article 41 of the Act
shall mean a case falling under subparagraph 2 of
Article 2 of the Monopoly Regulation and Fair Trade Act
.
법령보기 화면
Article 25 (Matters to be Specified in Articles of Association of Cultural Heritage Conservation Association)
The following matters shall be specified in the articles of association of the Cultural Heritage Conservation Association (hereinafter referred to as "Cultural Heritage Conservation Association") under
Article 42 (1) of the Act
:
1.
Objectives;
2.
Name;
3.
Address of main office;
4.
Matters concerning qualification of members, entry and withdrawal, rights and duties;
5.
Matters concerning plenary meetings;
6.
Matters concerning directors' meetings, chapters, branches and committees;
7.
Matters concerning executives;
8.
Matters concerning asset and accounting;
9.
Matters concerning amendment of articles of association;
10.
Matters concerning dissolution and handling of remaining property;
11.
Matters concerning duties and execution thereof;
12.
Other matters necessary for repair, etc. of cultural heritage, operation of the Cultural Heritage Conservation Association, etc.
법령보기 화면
Article 26 (Mutual-Aid Projects, etc. of Cultural Heritage Conservation Association)
(1)
The scope of mutual-aid projects of the Cultural Heritage Conservation Association under
Article 42 (5) of the Act
shall be as listed hereunder:
1.
Bid guarantee, contract guarantee (including performance guarantee), indemnity, advance payment guarantee and security deposit for defects for implementation of duties by members;
2.
Mutual-aid projects for financing for members.
(2)
Where the Cultural Heritage Conservation Association intends to perform mutual-aid projects under paragraph (1), it shall enact mutual-aid regulations and obtain approval from the Administrator of the Cultural Heritage Administration. The same shall apply to the amendment of mutual-aid regulations.
(3)
The mutual-aid regulations referred to in paragraph (2) shall include matters necessary for the operation of mutual-aid projects, such as the details of mutual-aid contracts, mutual-aid benefits, fees for mutual-aid, etc.
(4)
Where the Administrator of the Cultural Heritage Administration intends to grant approval for mutual-aid regulations pursuant to paragraph (2) or to prescribe standards for the supervision of mutual-aid projects, he/she shall consult with the Financial Services Commission in advance.
(5)
The Administrator of the Cultural Heritage Administration may request the Governor of the Financial Supervisory Service defined in the
Act on the Establishment, etc. of Financial Services Commission
to examine mutual aid projects under paragraph (1).
(6)
The Cultural Heritage Conservation Association shall submit a project plan and an income and expenditure budget before each fiscal year begins.
법령보기 화면
Article 26-2 (Temporarily Falling Short of Requirements for Registration)
"Cases prescribed by Presidential Decree, such as where capital temporarily falls short of the requirements for registration, etc." under the proviso to
Article 49 (1) 4 of the Act
shall mean any of the following cases:
<Amended by Presidential Decree No. 27115, Apr. 29, 2016>
1.
Where any of the following is applicable when capital requirements under Appendix 7 are not met:
(a)
Where a court decides on the commencement of rehabilitation procedures pursuant to the
Debtor Rehabilitation and Bankruptcy Act
and the procedures are in progress;
(b)
Where, pursuant to the
Debtor Rehabilitation and Bankruptcy Act
, a court deems that the implementation of a rehabilitation plan is not impeded, and thus decides to terminate rehabilitation procedures on the relevant cultural heritage repair business entity or cultural heritage supervision business entity and the rehabilitation plan is being implemented;
(c)
Where a council of financial creditors resolves to commence a joint administrative proceeding implemented by the financial creditor association pursuant to the
Corporate Restructuring Promotion Act
, and the proceeding is in progress;
2.
Where a corporation to which the proviso to
Article 542-8 (1) of the Commercial Act
is applicable falls below requirements for registration due to reduction of capital as at the end of the most recent business year, and the period is no more than 50 days.
[This Article Added by Presidential Decree No. 25711, Nov. 11, 2014]
법령보기 화면
Article 27 (Methods, etc. of Calculating Wages Excluded from Seizure)
(1)
An amount equivalent to the wages under
Article 50 (1) of the Act
shall be calculated by aggregating the wages specified in the calculation statement among the contract amount of repair of relevant cultural heritage (including subcontract for the repair of cultural heritage).
(2)
A person placing a contract (referring to a contractor in cases of a subcontract) shall specify the wages under paragraph (1) in the contract sheet (referring to a subcontract sheet in cases of a subcontract).
법령보기 화면
Article 28 (Supplemental Education of Cultural Heritage Repair Engineers and Cultural Heritage Supervisors)
(1)
Cultural heritage repair engineers affiliated with a cultural heritage repair business entity or an on-site cultural heritage survey and design business entity and cultural heritage supervisors affiliate with a cultural heritage supervision business entity shall receive supplemental education under
Article 53 (1) of the Act
.
(2)
The details of supplemental education under
Article 53 (1) of the Act
shall be as listed hereunder:
1.
Education to increase understanding of knowledge that cultural heritage repair engineers and cultural heritage supervisors are required to possess, and understanding of knowledge in the relevant statutes, system, etc.;
2.
Education to increase specialized capabilities in the relevant fields.
(3)
Cultural heritage repair engineers and cultural heritage supervisors under paragraph (1) shall receive supplemental education according to the following classifications:
1.
Cultural heritage repair engineers:
(a)
They shall receive supplemental education before the period of actual service becomes three years from the day they are affiliated with a cultural heritage repair business entity or an on-site cultural heritage survey and design business entity;
(b)
After they receive the education under item (a), they shall receive supplemental education within six months before or after the fifth anniversary of the day they are affiliated with a cultural heritage repair business entity or an on-site cultural heritage survey and design business entity and have actually performed the relevant duties;
2.
Cultural heritage supervisors:
(a)
They shall receive supplemental education before the period of actual service becomes three years from the day they are affiliated with a cultural heritage supervision business entity;
(b)
After they receive the education under item (a), they shall receive supplemental education within six months before or after the fifth anniversary of the day they become affiliated with a cultural heritage supervision business entity and have actually performed the cultural heritage supervision duties.
(4)
The hours of supplemental education under paragraph (3) shall be at least 32 hours, respectively.
(5)
As prescribed by Ministerial Decree of Culture, Sports and Tourism, the Administrator of the Cultural Heritage Administration shall issue an education completion certificate to cultural heritage repair engineers and cultural heritage supervisors who complete the supplemental education under paragraph (1), and record and confirm the completion of supplemental education on the certificates of cultural heritage repair engineers.
(6)
Where the Administrator of the Cultural Heritage Administration intends to implement supplemental education, he/she shall publicly announce matters necessary for the implementation of education, such as the date and time of education, place of education, etc. on the website of the Cultural Heritage Administration not later than 60 days before education is implemented.
법령보기 화면
Article 29 (Evaluation, etc. of Cultural Heritage Repair Business Entities)
(1)
"Standards prescribed by Presidential Decree" under
Article 54 (1) of the Act
shall mean the standards according to the following classifications:
1.
Repair of cultural heritage:
Repair of cultural heritage the cost for which is at least 500 million won in cases of designated cultural heritage prescribed in
Article 2 (2) of the Cultural Heritage Protection Act
and provisionally designated cultural heritage prescribed in
Article 32 of the same Act
;
2.
On-site survey and design:
On-site cultural heritage survey and design the cost for which is at least 30 million won in cases of designated cultural heritage prescribed in
Article 2 (2) of the Cultural Heritage Protection Act
and provisionally designated cultural heritage prescribed in
Article 32 of the same Act
.
(2)
Where the Administrator of the Cultural Heritage Administration or the heads of local governments designate an exemplary cultural heritage repair business entity or an exemplary on-site cultural heritage survey and design business entity pursuant to
Article 54 (2) of the Act
, they shall publicly announce the following matters in the Official Gazette:
1.
A person placing a contract;
2.
The name of an exemplary cultural heritage repair business entity or an exemplary on-site cultural heritage survey and design business entity, name of representative, registration number and address of workplace;
3.
Date of designation and period of validity.
법령보기 화면
Article 30 (Delegation and Entrustment of Authorities)
(1)
Pursuant to
Article 56 (1) of the Act
, the Administrator of the Cultural Heritage Administration shall delegate the authorities on the supplemental education of cultural heritage repair engineers and cultural heritage supervisors under
Article 53 of the Act
to the head of the Korea National University of Cultural Heritage established under the
Act on the Establishment of the Korea National University of Cultural Heritage
.
<Amended by Presidential Decree No. 23943, Jul. 10, 2012>
(2)
Pursuant to
Article 56 (2) of the Act
, the Administrator of the Cultural Heritage Administration shall entrust the following duties to the Human Resources Development Service of Korea under the
Human Resources Development Service of Korea Act
:
1.
Examinations to qualify as cultural heritage repair engineer under
Article 8 of the Act
;
2.
Examinations to qualify as cultural heritage repair technician under
Article 11 of the Act
.
법령보기 화면
Article 30-2 (Handling of Personally Identifiable Information)
Where unavoidable circumstances arise in the course of performing the following duties, the Administrator of the Cultural Heritage Administration (including the Human Resources Development Service of Korea entrusted with the authorities of the Administrator of the Cultural Heritage Administration) or Mayors/
Do
Governors may handle data including resident registration numbers referred to in subparagraph 1 of
Article 19 of the Enforcement Decree of the Personal Information Protection Act
:
1.
Duties concerning the examination to qualify as cultural heritage repair engineer and the issuance of a certificate under
Articles 8 and 10 of the Act
;
2.
Duties concerning the examination to qualify as cultural heritage repair technician and the issuance of certificates under
Articles 11 and 12 of the Act
;
3.
Duties concerning the registration of cultural heritage repair business entities, etc. under
Article 14 of the Act
;
4.
Duties concerning filing a report on the transfer, etc. of cultural heritage repair business, etc. under
Article 17 of the Act
;
5.
Duties concerning filing a report on the inheritance of cultural heritage repair business, etc. under
Article 20 of the Act
.
[This Article Added by Presidential Decree No. 23488, Jan. 6, 2012]
법령보기 화면
Article 30-3 (Re-Examination of Regulations)
The Administrator of the Cultural Heritage Administration shall, every three years (referring to the day before the third anniversary of the base date), examine the appropriateness of the following matters on the basis of the following base dates, and take improvement measures, etc.:
1.
Restrictions on the repair of cultural heritage under
Article 4
: January 1, 2015;
2.
Requirements for registration of cultural heritage repair business, etc. under
Article 12
: January 1, 2014;
3.
Standards, etc. for posting cultural heritage repair engineers on site under
Article 20
: January 1, 2015;
4.
Repair of cultural heritage subject to supervision, etc. under
Article 20
: January 1, 2015;
5.
Scope of duties of cultural heritage supervisors under
Article 21
and Appendix 10: January 1, 2015.
[This Article Wholly Amended by Presidential Decree No. 25854, Dec. 16. 2014]
법령보기 화면
Article 31 (Standards for Imposition of Administrative Fines)
(1)
The standards for imposition of administrative fines under
Article 62 (2) of the Act
shall be as listed in Appendix 12.
(2)
The Administrator of the Cultural Heritage Administration, Mayors/
Do
Governors or the heads of Sis/Guns/Gus may increase or decrease an administrative fine under Appendix 12 by up to 1/2 of the amount of fine, considering the degree of seriousness of a violation, violation frequency, motive, result, etc.
ADDENDA
Article 1 (Enforcement Date)
This Decree shall enter into force on February 5, 2011:
Provided
, That
Articles 20 through 23
and
28
shall enter into force on February 5, 2012, Appendix 3 on February 5, 2015, and subparagraphs 19 and 20 of Appendix 6 on February 5, 2014.
Article 2 (Transitional Measures concerning Registration of Cultural Heritage Repair Business, etc.)
An entity deemed a lawful cultural heritage repair business entity, etc. pursuant to Article 4 of the Addenda of the Act shall meet the requirements for registration under
Article 12
by August 31, 2012.
Article 3 (Transitional Measures concerning Supplemental Education of Cultural Heritage Repair Engineers)
A person who performs the repair of cultural heritage as a cultural heritage repair engineer pursuant to previous provisions as at February 5, 2012 shall be deemed to have received supplemental education under
Article 28
(3) 1 (a) on February 5, 2012. In such case, he/she shall receive the first supplemental education under
Article 28
(3) 1 (b) within one year before or after the fifth anniversary of the day he/she becomes affiliated with a repair business entity or an on-site cultural heritage survey and design business entity and actually performs the duties after February 5, 2012, notwithstanding
Article 28
(3) 1 (b).
<Amended by Presidential Decree No. 24676, Jul. 30, 2013>
Article 4 Omitted.
Article 5 (Relationship with other Statutes)
Where the former
Enforcement Decree of the Act on Cultural Heritage Maintenance, Etc.
or provisions thereof are cited by other statutes as at the time this Decree enters into force, and where this Decree includes provisions corresponding thereto, this Decree or relevant provisions of this Decree shall be deemed to be cited in place of the former
Enforcement Decree of the Act on Cultural Heritage Maintenance, Etc.
or provisions thereof.
ADDENDA <Presidential Decree No. 23488, Jan. 6, 2012>
Article 1 (Enforcement Date)
This Decree shall enter into force on the date of its promulgation. (Proviso omitted.)
Article 2 Omitted.
ADDENDA <Presidential Decree No. 23759, May 1, 2012>
Article 1 (Enforcement Date)
This Decree shall enter into force on the date of its promulgation. (Proviso omitted.)
Article 2 (Applicability to Public Announcement of Examinations)
Amendments to the deadline for public announcement of examinations in this Decree shall begin to apply from examinations to be implemented on or after January 1, 2013.
ADDENDA <Presidential Decree No. 23943, Jul. 10, 2012>
Article 1 (Enforcement Date)
This Decree shall enter into force on July 15, 2012.
Articles 2 and 3 Omitted.
ADDENDUM <Presidential Decree No. 24676, Jul. 30, 2013>
This Decree shall enter into force on the date of its promulgation.
ADDENDUM <Presidential Decree No. 25050, Dec. 30, 2013>
This Decree shall enter into force on January 1, 2014. (Proviso omitted.)
ADDENDUM <Presidential Decree No. 25711, Nov. 11, 2014>
This Decree shall enter into force on November 29, 2014.
ADDENDA <Presidential Decree No. 25854, Dec. 16, 2014>
Article 1 (Enforcement Date)
This Decree shall enter into force on the date of its promulgation:
Provided
, That the amended provisions of
Article 8
(2) and Appendix 3 shall enter into force on February 5, 2015, and the amended provisions of subparagraphs 1 and 2 of
Article 20
,
Article 21
(1) 2 and subparagraph 2 of Appendix 11 two years after the date of their promulgations.
Article 2 (Transitional Measures concerning Restrictions on Repair of Cultural Heritage)
Notwithstanding the amended provision of
Article 4
(2), the former provisions shall apply to cases in which a contract for the repair of cultural heritage is concluded with regard to a structure that is with a building area of less than 660 square meters and with less than three floors, and the main frame of which is reinforced concrete structure, steel frame structure or steel frame reinforced concrete structure.
Article 3 (Transitional Measures concerning Posting of Cultural Heritage Repair Engineers to Sites)
Where a contract for the repair of cultural heritage is concluded before this Decree enters into force, the former provisions shall have effect, notwithstanding the amended provisions of
Article 18
(1) and (3).
Article 4 (Transitional Measures concerning Supervision of Repair of Cultural Heritage)
Where a contract for repair of cultural heritage is concluded before this Decree enters into force, the former provisions shall have effect, notwithstanding the amended provisions of
Articles 20
and
21
and subparagraph 2 of Appendix 11.
ADDENDA <Presidential Decree No. 27115, Apr. 29, 2016>
Article 1 (Enforcement Date)
This Decree shall enter into force on the date of its promulgation.
Articles 2 through 5 Omitted.
ADDENDA <Presidential Decree No. 27619, Nov. 29, 2016>
Article 1 (Enforcement Date)
This Decree shall enter into force on the date of its promulgation. (Proviso omitted.)
Articles 2 through 4 Omitted.
Last updated : 2017-04-27